resource management i
TRANSCRIPT
![Page 1: Resource Management I](https://reader030.vdocuments.us/reader030/viewer/2022021119/577d23ae1a28ab4e1e9a797c/html5/thumbnails/1.jpg)
8/3/2019 Resource Management I
http://slidepdf.com/reader/full/resource-management-i 1/21
RESOURCE MANAGEMNT
Activity-Based ResourceAssignment (ABRA)
![Page 2: Resource Management I](https://reader030.vdocuments.us/reader030/viewer/2022021119/577d23ae1a28ab4e1e9a797c/html5/thumbnails/2.jpg)
8/3/2019 Resource Management I
http://slidepdf.com/reader/full/resource-management-i 2/21
INTRODUCTION
In order to meet the proposed schedule, we
have to know if the resources that we need areavailable
We need to determine the impact of resource
availability on project schedule
Ideas of when the resource would be neededfor each activity is known from the CPM
We need to determine areas of resourceshortages and the impact of such shortages willhave in delaying the schedule
![Page 3: Resource Management I](https://reader030.vdocuments.us/reader030/viewer/2022021119/577d23ae1a28ab4e1e9a797c/html5/thumbnails/3.jpg)
8/3/2019 Resource Management I
http://slidepdf.com/reader/full/resource-management-i 3/21
INTRODUCTION
Organization with multiple projects is inabsolute need to maintain an up-to-dateresource availability database by the
functional manager TPC shows how assigning resources to
project activities can benefits the
organization, the PM and the functionalmanagers
![Page 4: Resource Management I](https://reader030.vdocuments.us/reader030/viewer/2022021119/577d23ae1a28ab4e1e9a797c/html5/thumbnails/4.jpg)
8/3/2019 Resource Management I
http://slidepdf.com/reader/full/resource-management-i 4/21
ABRA AND ABC
Activity-based resource assignments(ABRA): It is the first step in resourcescheduling with an objective to determinewhat resources will be needed for eachactivity
Activity-based costing (ABC): It is thefoundation for an important technique incost accounting where the cost of doingwork must be assembled and tracked atthe level of each activity
![Page 5: Resource Management I](https://reader030.vdocuments.us/reader030/viewer/2022021119/577d23ae1a28ab4e1e9a797c/html5/thumbnails/5.jpg)
8/3/2019 Resource Management I
http://slidepdf.com/reader/full/resource-management-i 5/21
ABRA ITEMS
What resourcesare needed?
How much ofeach resource is
needed in orderto complete itwithin itsestimated
durations? When will each
resource beneeded?
![Page 6: Resource Management I](https://reader030.vdocuments.us/reader030/viewer/2022021119/577d23ae1a28ab4e1e9a797c/html5/thumbnails/6.jpg)
8/3/2019 Resource Management I
http://slidepdf.com/reader/full/resource-management-i 6/21
STEPS
Assign resources at the lower level of theWBS
Determine how much of these resources
would be needed to complete of theseactivities in the estimated amount of time
Match them against the resources within
the organization which is located in thedepartments that comprise the OBS
The OBS should contain the cost
information about each resource
![Page 7: Resource Management I](https://reader030.vdocuments.us/reader030/viewer/2022021119/577d23ae1a28ab4e1e9a797c/html5/thumbnails/7.jpg)
8/3/2019 Resource Management I
http://slidepdf.com/reader/full/resource-management-i 7/21
ABC ITEMS
Fairly accurate budget for each resource
being used, for each activity and for thewhole project, for a comparisons anddecision making both within a project and
across projects A schedule that shows how the cost of a
resource changes over time
A schedule that shows the availability of aresource changes over time, allows us tosee what and when resources are available
![Page 8: Resource Management I](https://reader030.vdocuments.us/reader030/viewer/2022021119/577d23ae1a28ab4e1e9a797c/html5/thumbnails/8.jpg)
8/3/2019 Resource Management I
http://slidepdf.com/reader/full/resource-management-i 8/21
RESOURCE LIBRARY
Resource database incorporated in almost allthe project management software packages
Time consuming to be regularly maintained
Their target is to justify additional resources bycontrasting the cost of these resources versusthe impact of resource shortages on project
schedules and EMV Without resource library, this is all but
impossible
![Page 9: Resource Management I](https://reader030.vdocuments.us/reader030/viewer/2022021119/577d23ae1a28ab4e1e9a797c/html5/thumbnails/9.jpg)
8/3/2019 Resource Management I
http://slidepdf.com/reader/full/resource-management-i 9/21
PROJECT BUDGETS
As the resources areassigned, the costdata come with them
Accurate costingrequires all types ofresources beassigned to activities
The budget for eachactivity is therefore,will be determined
![Page 10: Resource Management I](https://reader030.vdocuments.us/reader030/viewer/2022021119/577d23ae1a28ab4e1e9a797c/html5/thumbnails/10.jpg)
8/3/2019 Resource Management I
http://slidepdf.com/reader/full/resource-management-i 10/21
PROJECT BUDGETS
And so wecansummarizethe budget
numbers allthe way tothe top forthe entireproject
![Page 11: Resource Management I](https://reader030.vdocuments.us/reader030/viewer/2022021119/577d23ae1a28ab4e1e9a797c/html5/thumbnails/11.jpg)
8/3/2019 Resource Management I
http://slidepdf.com/reader/full/resource-management-i 11/21
CALCULATING THEPROJECT DIPP
The results of cost analysis is a projectbudget of $3,876,783 which, if it’scompleted in 30 weeks, has an EMV of$10 million. Therefore,
DIPP = EMV / ETC
= $10,000,000 / $3,876,783 = 2.58
The current schedule claims 34 weeks atan EMV of $2 million. Therefore,
DIPP = $2,000,000 / $3,876,783 = 0.52
![Page 12: Resource Management I](https://reader030.vdocuments.us/reader030/viewer/2022021119/577d23ae1a28ab4e1e9a797c/html5/thumbnails/12.jpg)
8/3/2019 Resource Management I
http://slidepdf.com/reader/full/resource-management-i 12/21
ALTERNATIVES
Cut cost drastically
Reduce the duration
Increase scope to increase expectedvalue
Cancel the project
![Page 13: Resource Management I](https://reader030.vdocuments.us/reader030/viewer/2022021119/577d23ae1a28ab4e1e9a797c/html5/thumbnails/13.jpg)
8/3/2019 Resource Management I
http://slidepdf.com/reader/full/resource-management-i 13/21
ANALYSING ANDIMPLEMENTING THE DRED
DRED give the PM a sense of what might be
the effect of adding resources to an activity Adding 50% more resources to an activity with
a duration estimate of 12w and DRED of 10 w
might reduce activity duration to 11w We have to find out whether such resource
would be available and the cost and weight ofthe additional resource
Therefore, DRED comes with a costcomponent determining the reason forimplementing such factor
![Page 14: Resource Management I](https://reader030.vdocuments.us/reader030/viewer/2022021119/577d23ae1a28ab4e1e9a797c/html5/thumbnails/14.jpg)
8/3/2019 Resource Management I
http://slidepdf.com/reader/full/resource-management-i 14/21
DRED COMPUTATION
DRED budget = 2 (activity budget) * (DRED / by
duration) For the activity, Develop advertising, with 6w
duration, activity budget of $101,250 and DRED5w DRED budget = 2 ($101,250) * (5 / 6) =$168.075
DRED cost = DRED budget – Activity Budget =$168.075 - $101,250 = $66,825
Doubling the cost on Develop advertising willcost $66,825 and it is off the critical path withDRAG of zero, but if it was on the critical paththe 1w saved at $2 million would be easily
worth the cost
![Page 15: Resource Management I](https://reader030.vdocuments.us/reader030/viewer/2022021119/577d23ae1a28ab4e1e9a797c/html5/thumbnails/15.jpg)
8/3/2019 Resource Management I
http://slidepdf.com/reader/full/resource-management-i 15/21
DRED COMPUTATION
The biggestdifficulties is indetermining wherethe additional
resources will do: Any good
The most good
This is precisely the analysis that the TPCmetrics DRAG, DRAG cost, DRED and DRED
cost are designed to facilitate
![Page 16: Resource Management I](https://reader030.vdocuments.us/reader030/viewer/2022021119/577d23ae1a28ab4e1e9a797c/html5/thumbnails/16.jpg)
8/3/2019 Resource Management I
http://slidepdf.com/reader/full/resource-management-i 16/21
DECISION MAKING
TPC provides PM with data on which project
decisions can be based DRED data needs to be applied to the actual
details of the project schedule
A conference with activity managers of all theresource-elastic critical path activities should takeplace
PM start displaying the current network scheduleshowing the EMV and DRED potential inimproving the current scenario
![Page 17: Resource Management I](https://reader030.vdocuments.us/reader030/viewer/2022021119/577d23ae1a28ab4e1e9a797c/html5/thumbnails/17.jpg)
8/3/2019 Resource Management I
http://slidepdf.com/reader/full/resource-management-i 17/21
DECISION MAKING
![Page 18: Resource Management I](https://reader030.vdocuments.us/reader030/viewer/2022021119/577d23ae1a28ab4e1e9a797c/html5/thumbnails/18.jpg)
8/3/2019 Resource Management I
http://slidepdf.com/reader/full/resource-management-i 18/21
DECISION MAKING
Time might be saved on the critical
activities path via: Adding resource realizing resource elasticity and
activity DRAG on critical path
Changing relationships on and off critical activities Reducing lag on critical path
The saved time will have the following
impact: Increasing the project EMV
Adding contingency time or managementreserves in case of variance
![Page 19: Resource Management I](https://reader030.vdocuments.us/reader030/viewer/2022021119/577d23ae1a28ab4e1e9a797c/html5/thumbnails/19.jpg)
8/3/2019 Resource Management I
http://slidepdf.com/reader/full/resource-management-i 19/21
DECISION MAKING
Two separate critical paths emerged,the DRAG of almost all the activities is zero,
and the total float have also shrunk
![Page 20: Resource Management I](https://reader030.vdocuments.us/reader030/viewer/2022021119/577d23ae1a28ab4e1e9a797c/html5/thumbnails/20.jpg)
8/3/2019 Resource Management I
http://slidepdf.com/reader/full/resource-management-i 20/21
DECISION MAKING
Further compressing made after discussion with activity
manager of the compressed activity
![Page 21: Resource Management I](https://reader030.vdocuments.us/reader030/viewer/2022021119/577d23ae1a28ab4e1e9a797c/html5/thumbnails/21.jpg)
8/3/2019 Resource Management I
http://slidepdf.com/reader/full/resource-management-i 21/21
DECISION MAKING
Total budget increasedby $160,000 to$4,036,783
while the projected
duration has gone from34w to 28w and the EMV from $2
million to $10.8 million.
The DIPP analysis nowlooks much healthier:DIPP = $10.800,000 / $4,036,783 = 2.68