reserves provided by distributed generation
TRANSCRIPT
![Page 1: Reserves provided by distributed generation](https://reader030.vdocuments.us/reader030/viewer/2022021214/577d2aea1a28ab4e1eaa703f/html5/thumbnails/1.jpg)
8/7/2019 Reserves provided by distributed generation
http://slidepdf.com/reader/full/reserves-provided-by-distributed-generation 1/9
Operating Reserves Provided by Distributed Generation
FRANCISCO D MOYA CH(a)
, DUVIER BEDOYA BEDOYA(b)
, Dr GILBERTO DE MARTINO
JANNUZZI(c)
, Dr LUIZ CARLOS PEREIRA DA SILVA(d)
,
FEM, FEEC, UNICAMP
Cidade Universitária "Zeferino Vaz", Campinas, São Paulo
BRAZIL(a)
[email protected] http://lattes.cnpq.br/6867376592649835(b) [email protected] http://lattes.cnpq.br/0918270598381687
(c) [email protected] http://www.fem.unicamp.br/~jannuzzi/index.html
(d)[email protected] http://www.dsee.fee.unicamp.br/~lui
Abstract: - Among the ancillary services, the operating reserves are important researching aspects, which deal with supplying way and selling-buying prices. Currently, distributed generation (DG) rises as a new participant
in providing ancillary services, therefore, it is of main importance in operating reserves subject. This work shows some advantages and technical drawbacks by using DG when operating reserves are supplied. Different
sceneries were computed where the electric generation was performed in a centralized and non-centralized way
respectively. A methodology for identifying the maximum DG, which can be allocated, is proposed; this
maximum level can be assessed without carrying out a negative impact in the network. Diverse DG technologies,which present better performance in supplying such reserves, are also presented.
Key-Words: - Distributed Generation, Operating reserves, Ancillary services.
1 IntroductionThe reliability concept deals with different elements
in electric power systems: security and sufficiency.Security is described as the capacity of the system to
face different disturbs, this is used combined with protection devices, power dispatch and other
auxiliary services. Sufficiency represents the
capability of the system for attending the demandrequirements in any time.
In economical terms, security concept can be defined
as a public good. Transit systems, national defense
infrastructure, laws, etc, are considered as publicgoods also. Some authors consider the system
security as a public good [1], being operating reserves
of an electric system a key security element.
As other public goods, power system security has noclear indications of its cost per user. Some users can
disagree paying the operating reserves when they
don’t utilize such reserves and also if they are payingfor extra security which is provided for other users.
The difficulty is defining the optimal acquisition levelfor every user and develops a methodology for carrying out this acquisition as well as its costs.
The electricity markets in different countries arediscriminated mainly in the methodologies or
procedures in the operative reserve management. For
instance, in Britain the reserves are obtained by long-
term contracts. In the Nord Pool market, the energyutilities, are required to supply specific auxiliary
services, when they take part into the electricity
market. In California there is a reserve marketindependent and parallel to the electricity market. In
New England, there is a capacity market, similar to
an operative reserve market. In Brazil, the regulatoryagency establishes an operating reserve total for the
whole system, equal to the capacity of the major
generator unit. Thus the Itaipu power plant with 6,3GW sets up the maximum level of the operating
reserves. The current capacity of the Brazilian Power
System is 91,17 GW, being the operative reserve
6,7% of the total installed capacity.Currently, electric systems are changing and with the
distributed generation (DG) growing up, the
distribution systems are turning into from passive to
active entities [2]. The new and future DG schemesare allowing a wide possibility of new energy
suppliers and complementary services such as
auxiliary services in which the operating reservestakes part into. DG is a new participant in the current
and future electric systems related to programmingand the operating reserves dispatch [3], [4].Dispatch of centralized units requires a higher
generation level, which should supply energy to all
the network points, including all the load power andthe network losses in the whole system, the
transmission system and the final points related to the
distribution system [5].
On the other hand, delivering active power by thegenerators in the distribution system, close to the
![Page 2: Reserves provided by distributed generation](https://reader030.vdocuments.us/reader030/viewer/2022021214/577d2aea1a28ab4e1eaa703f/html5/thumbnails/2.jpg)
8/7/2019 Reserves provided by distributed generation
http://slidepdf.com/reader/full/reserves-provided-by-distributed-generation 2/9
load, reduces the losses and consequently, improves
the voltage levels and increases the system security.This work shows some technical advantages when
DG is used in the dispatch of active and reactive power reserves. In the following section, the
formulation of the problem is described. Afterwards,
it is showed and explanation of the methodology
used. It is also proposed a methodology for establishing the maximum DG level that can be
installed and at the same time, caring of the negativeimpacts in the network and consequently the
maximum DG level that can be provided for the
supply of operating reserves.An application is also showed; it is presented an
analysis when DG is used for supplying operating
reserves. Furthermore, the DG technologies that
attend more efficiently the reserves management is
described. Finally the conclusions of this work are
presented.
2 Problem FormulationThe connection of energy supplies to the distributionsystems modifies the traditional hierarchical
generation way before known. The energy injection
in the distribution networks modifies the power flow
and can develop several impacts such as: losses,investments, voltage profile, maintenance people
security, power quality, short circuit power, and
system operation. This work analyzes the impact on
the active and reactive power losses, and the voltage profile impact on the network.
2.1 Loses modification when DG is usedThe problematic associated to the DG impact has
several implications (economic, technical andenvironmental). For this reason, in the last years
researchers have began to take it into account.Currently due to the multiple studies, it is known that
DG presents limited advantages related to the losses
reduction. In [6] and [7] it is known the importance of
the active and reactive energy supplied by the DG. Inthese works it is also demonstrated that with higher
levels of DG the losses may increase. Thus it isnecessary known the DG capacity that can be
installed without increasing the losses and not
affecting the voltage profile. It is required to know
the energy generation limits through DG, it makes
essential to know the maximum DG capacity for supplying the operating reserves.
In the first part of this work, a methodology for
determining the DG installation limits is presented. It
is also studied the influence on the losses in the
transmission, sub transmission and distribution
systems.
2.1 The DG and its role with the Operating
reservesAfter presenting the DG advantages and drawbacks,
it is possible to note that the operating reserves withDG present different implications; therefore, it is also
necessary assessing the advantages anddisadvantages. With this aim, in the second part of
this work is presented an analysis related to the active
and reactive energy supplied by DG when centralized
generators outages occur.
3 MethodologyThe development of a methodology that lets know the
DG energy production limits, allows assessing
directly the DG maximum capacity for providingoperating reserves. In some works such as [8] and [9],
it is described the importance of the DG allocation
and establishing the necessary capacity for DG
installation in order to reduce the distribution systemlosses. However, its neglects the analysis of possible
impacts like overvoltages produced by DG
installation.
For knowing the effects on determined electricsystem when DG is studied, it is convenient to know
the electric parameters of such system whencentralized generators are used. For instance, when a
load flow is computed it is possible to know some of
the most important electric parameters (such as:voltage profile and the losses level) without using DGon the system. After that, it is possible obtaining the
base case for comparing with the alterations in the presence of generators connected to the distribution
system. The base case allows also verifying the
buses, which presents greater voltage drops and theareas and branches where the losses are more critical.
This buses and areas are the best locations for the DG
installation. After the DG installation in such
sceneries, the possible presence of overvoltages is
lower and the losses reduction is more effective.
This section is based on the procedure presented in
[8]. After assessing the DG units to be installed in thedistribution system, it is necessary to compute loadflows by increasing the generators capacity and
assessing the new electric parameters in order to
evaluate the overvoltage levels produced.This methodology is presented in Fig. 1.
![Page 3: Reserves provided by distributed generation](https://reader030.vdocuments.us/reader030/viewer/2022021214/577d2aea1a28ab4e1eaa703f/html5/thumbnails/3.jpg)
8/7/2019 Reserves provided by distributed generation
http://slidepdf.com/reader/full/reserves-provided-by-distributed-generation 3/9
Fig. 1 Methodology for establishing the
maximum DG installation level.
This methodology allows computing the maximum
DG installation level without damaging the network.
It is also possible to establish the maximum DG levelfor the operating reserves. Some works such as [10]
and [11] have presented a methodology for
computing the amount of operating reserves which
can be established for an electric system, but
currently there are no studies related to the evaluationof such reserves in DG. The methodology proposed
in this work arises in response to the necessity of determining the maximum DG admissible level for
supplying operating reserves.
3.1 Study CaseIn this work it is implemented a simulation for different sceneries with the aim of comparing
technical centralized generation aspects and non-
centralized generation when DG is involved.
These sceneries were computed by using a load flow(static model) for an electric system which takes into
account voltage levels for transmission, sub
transmission and distribution in order to assess the
DG impact in every voltage level. The IEEE30 bussystem was used [12] for carrying out the study. Two
buses on the medium voltage level were separated for
generating the distribution network (low voltagelevel). At the buses 30 and 24 it was connected a
distribution system of 70 buses TS2 [13] that is
presented in Fig. (2).
For computing the optimal flow the Newton-Raphsonand Fast-Decoupled Newton methods were used. In
order to develop the simulations, the program for
power system analysis MATPOWER [14] was
utilized.
Fig. 2 Distribution circuit used.
Below the process for the sceneries studied is presented as follows:
Phase I: Load flow without DG (base case): for this
case the active energy generation (P) and the reactive(Q) were delivered in a centralized way without DG.
In this case it is considered that the centralized
generators supply all the active and reactive demand,supposing that the generators are delivering the
operating reserves scheduled previously. In this work
the reserves classified in accordance with theresponse were not considered.
Phase II: Losses and voltage profile analysis: After
computing the base case, it is possible to obtain the
areas where the higher losses level is presented. Theresults for the case analyzed in this work, in only one
of the distribution circuits and determined areas that
are represented with the gross line Fig. (2).In addition, Fig. (3) shows losses level in the
distribution circuit circuit which has more losses. It is
important to emphasize that only one distributioncircuit presents the higher losses level
Fig. (4) shows the voltage profile (V) for each
voltage level: transmission, sub transmission and
distribution (gross line) at base case. The load flowresults show that the voltage levels decrease from the
transmission level until the more distant buses in the
distribution system. These areas are represented withcircles and they are named V1 to V7 Fig. (2).
Phase III: Selection of the more appropriate buses for
the DG installation: After obtaining the areas with
major losses, it is possible to establish the areaswhere the generators can be allocated in the
distribution system.Phase IV: For determining the possible DG impacts
affecting the voltage level, the smaller generators
should be connected only to one of the distribution
![Page 4: Reserves provided by distributed generation](https://reader030.vdocuments.us/reader030/viewer/2022021214/577d2aea1a28ab4e1eaa703f/html5/thumbnails/4.jpg)
8/7/2019 Reserves provided by distributed generation
http://slidepdf.com/reader/full/reserves-provided-by-distributed-generation 4/9
circuits and assess the impact when compared with
the distribution circuit without DG presence. For thecase studied, four generators in the first distribution
system were installed. The first distribution systemcorresponds to the areas V5, V4 and V7 (allocated in
the bus 30) Fig. (2).
Table 1 shows all the generators of the system with
their basic features.
Fig. 3 Losses level in the distributionsystem
Fig. 4 Voltage profile at base case
Generator TypeP max
(MW)
Power
Factor
G1 Centralized 200 Free
G2 Centralized 80 Free
G3 Centralized 50 FreeG4 Centralized 40 Free
G5 Centralized 30 Free
G6 Centralized 40 Free
G7 Distributed 2,53 0,9
G8 Distributed 2,53 0,9
G9 Distributed 2,53 0,9
G10 Distributed 2,53 0,9
Table 1 Generators features
Phase V: After installing the generators, several load
flows were computed increasing the DG installedcapacity, with the aim of obtaining the impact on the
different voltage levels of the system that is beingstudied.
The generators selected were allocated for a operation
with a power factor of 0,9 in capacitive or inductive
way.Phase VI: Verification of the electric parameters
after DG installation: in this part of the procedure it iscompared the voltage level and the losses presented
when DG is used related to the base case.
a) Losses analysis: in Fig. (5), it is possible to analyzethe losses behavior in the transmission, sub
transmission and distribution branches by increasing
the DG from zero up to 3,73 % of the total system
load. This is known as DG Penetration Level
(DGPL).
Fig. 5 Losses increasing the DG
penetration
In this case, the active losses level of the transmission
system decreases by 14% and for the sub
transmission system the losses where reduced by 29%when the DGPL is 10%.
In relation to the distribution system, the losses
decrease up to determined level, after this DGLP
level the losses rises highly. At the base case, whenthe DGLP is 0,78%, a limit for the reduction of the
active losses is obtained. For the reactive limit, it is
presented a DGLP different of the active one due tothe reduction of active energy. Table 2 shows the
numerical results that the load flow provided for threeDGPL levels. Thus, DG presents more advantages inthe active and reactive losses reduction in
transmission and sub transmission levels and with a
limit in through the distribution levels. However, it is possible to reduce the losses in a greater rate in the
distribution circuit than in the other circuits.
For instance, at base case, it was possible to reducethe losses in the distribution system by 33% with only
a 0,78 DGPL level.
![Page 5: Reserves provided by distributed generation](https://reader030.vdocuments.us/reader030/viewer/2022021214/577d2aea1a28ab4e1eaa703f/html5/thumbnails/5.jpg)
8/7/2019 Reserves provided by distributed generation
http://slidepdf.com/reader/full/reserves-provided-by-distributed-generation 5/9
Net Power 0 0,38 1,23
P (MW) 2,65 2,57 2,28
Q(MVAr) 9,41 9,14 8,12
P (MW) 1,33 1,19 0,95
Q(MVAr) 10,44 9,85 8,68
P (MW) 0,12 0,08 0,60
Q(MVAr) 0,23 0,15 0,47Distribution
Sub transmission
DGPL(%)
Transmission
Table 2 Losses in different system
levels
For analyzing the possible impact that DG can
develop in other distributed systems where initially
DG was not installed, it is necessary assessing thelosses behavior, they are showed in Fig. (6).
The losses in the distribution system where DG has
no been installed, present a similar behavior in the
transmission and distribution systems. The reductionlosses curve presents a linear behavior in the
distribution system, whereas, the reduction losses for the transmission system is concave. This feature for
distribution systems is also shown in [7].
In a persuasive way, the DG decreases the active and
reactive losses in distribution systems where DG isnot intall. As was explained earlier (see Phase IV),
four generators in the first distribution system only
were installed. In addition, when the DGPL is 0.78%,
in the second distribution circuit a losses reduction of 0,36% is obtained, see Fig. (6). The DG presents also
advantages in the active and reactive losses reduction
in others distribution circuits of electrical system.The total losses reduction in the system can be to
measure and compensate economy to DG for thiscontributions.
Fig. 6 losses in the distribution system
b) Voltage analysis:The DG energy production in the distribution system
carries out an increase in the voltage profile of the
system [15], [16]. This impact is due to the localenergy supplied and to the injection or consumption
of energy in the system. In the first place, the active
demand reduction that the generator delivers is lower
than when DG is not used, producing a minor voltage
drop. In addition, the active and reactive power injection increase the voltage profile. In Fig. (4) is
showed a voltage profile for the base case and whenthe DGPL is 1,23%. In Brazil, the technical
regulation establishes that the minimum and
maximum values for systems with voltages level up
to 231 kV should not be minor and major than 95%and 105% respectively.
Fig. (6) shows that the voltage levels in the base casedon’t infringe the limits, however, the upper limits
are infringed when the DGPL is greater than 1,23%.
After increasing the active and reactive power outputin the distribution network, overvoltages can occur,
mainly in the distribution system, and with less
importance in the sub transmission and transmission
systems. An alternative for avoiding such violations
is increase the number of smaller generators in the
distribution networks, this is known as an augment inthe DG dispersion level of lower power, it is shown
in [7] and [16].The methodology proposed in this work recommends
increasing the DGPL and verifying at which values
the generation be on the voltage network limit. Fig.(4) shows that the maximum voltage values are
presented exactly in the distribution system where the
DG has been installed. In this case, when the DGPLis 1,23 % the maximum value is obtained when the
voltage limits are not violated (in Brazil for systemsup to 231 kV).
The penetration value is showed in Fig. (6) for GD3,
this means that respecting the maximum voltage
limit, the maximum losses reduction value is notreached, however, the advantage is obtained with a
major losses reduction in other branches of thesystem (transmission, sub transmission and other
distribution networks). All the results are shown in
Table 2.Phase VII) With the identification of the maximum
penetration level, the electric parameters establishedare respected so, it is possible to obtain the maximum
DG value without carrying out a negative impact on
the system, as was explained earlier, in this case
when the DGPL is 1,23 %. Therefore, with thismethodology it is also possible to obtain the
maximum level that DG can deliver in relation to theoperating reserves.
4 DG as an Operating Reserve SupplierWith the aim of verifying the DG performance and its
impacts in operating reserves deliver, it is necessary
analyzing situations for possible outages of
centralized generators. For this analysis it is studiedthe base case where all the centralized generators are
![Page 6: Reserves provided by distributed generation](https://reader030.vdocuments.us/reader030/viewer/2022021214/577d2aea1a28ab4e1eaa703f/html5/thumbnails/6.jpg)
8/7/2019 Reserves provided by distributed generation
http://slidepdf.com/reader/full/reserves-provided-by-distributed-generation 6/9
supplying active and reactive power for all the
system.In the second part of this work, other cases were
simulated turning off a centralized generator in eachcase and the DG deliver operating reserves. The
DGPL is also increased with the aim of assessing the
electric parameters in the system with the output of a
centralized generator and the entry of DG.
4.1 Voltage AnalysisFor the analyzed system, the results showed that the
voltage profiles in every one of the subsystems were
not modified in an important way with the outage of the centralized generators at base case. This means,
without the DG presence, the centralized generators
supplied in an effective way the active and reactive
power demand with the outage of any centralizedgenerator.
The load flow results showed also that the voltage profiles are not modified seriously when DGPL isincrease, being almost the same voltage profiles as
showed in Fig. (4) Section (3.1 b.)
4.2 Losses AnalysisFig. (7) shows the losses level in the transmission andsub transmission branches when compared with the
base case in the worst case, which is when G3 is out
operation. In this case, for the transmission system
the losses increase up to 261% for active power and254% for reactive power.
The impact in the sub transmission and distributionnetworks is minor when G3 is out, the total losses
increases by 2,7% and by 0,7% for active and
reactive power respectively.
Fig. 7 Transmission and subtransmission losses increasing the DG
penetration and with G3 out of operation
Fig. (7) also shows the losses behavior when DGPLis increased form zero up to 3,73%. This is done with
the objective of analyzing the DG impact in the worst
scenery, this happens when the generator G3 is out,
as mentioned before.It is possible to prove that by using DG a minor
losses level is presented when a centralized generator is out. For the studied case, the losses reduction
related to the base case where G3 is out and there is
no DG, the losses level decreased by 7,45% for active
power and by 7,33% for reactive power. In the subtransmission area, the reduction was by 14,7% and by
7,48% for active and reactive power respectively. Inthe distribution system, there are major advantages;
the losses reduction is 23% for active power and
42.3% for reactive power. These results are illustratedin Table 2.
Net Power 0* 0** 1,23
P(MW) 2,646 6,90 6,70
Q(MVAr) 9,407 23,92 23,23
P(MW) 1,334 1,37 1,17
Q(MVAr) 10,44 10,49 9,71
P(MW) 0,123 0,12 0,09
Q(MVAr) 0,229 0,23 0,13
Transmission
Sub transmission
Distribution
DGPL(%)
Table 3 Losses in different DG levels
* base case, all centralized generators on
** base case and G3 is out
Fig. (8) illustrates the curves for the active losses for
the distribution circuits in each case when the
generators are out of operation.
Curves PLC21, PLC22, PLC23 and PLC24, representwhen the generators G1, G2, G3, y G4 are out
respectively. It is observed that for the distribuitedcircuit (1) where DG is installed, there are no changes
in the losses level when the centralized generators are
out.
Fig. 8 Distribution losses increasing the
DG penetration when G3 is out of operation
As explained before (Section 3.1. a.), the losses in the
distribution circuit where DG is not installed present
a linear behavior. Whereas, the curve for the other distribution circuit presents a concave behavior, a
![Page 7: Reserves provided by distributed generation](https://reader030.vdocuments.us/reader030/viewer/2022021214/577d2aea1a28ab4e1eaa703f/html5/thumbnails/7.jpg)
8/7/2019 Reserves provided by distributed generation
http://slidepdf.com/reader/full/reserves-provided-by-distributed-generation 7/9
feature of the distribution systems where DG is
installed. In Fig. (8) the area under the curve PLC23
between 0 and GD3 represents the maximum losses
reduction that the DG installation can obtain whenG3 is out. In Section 3.1. b. it was explained that
GD3 represents the maximum DGPL where there are
no violations on the voltage limits, that means, this
point represents the maximum penetration value andtherefore the maximum operating reserves value. This
is the maximum operating reserves value that DG cancontribute without originating negative impacts on
the system. This work shows a individual case, is
necessary to apply this methodoly for peak hours, lowhours and for summer and winter period.
4.3 DG Technologies for providing operating
reserves
There are different technologies that can be used for
DG applications (wind generation, photovoltaic, co-generation, etc). Every technology presents a
different production profile, therefore, the load flows
and losses impact depends on each technology.
Generally, the DG profile varies constantly. Thisvariation can be produced by the primary resource
(wind, sun, water, etc) or due to the process features
(e.g. co-generation process).As the DG production profile is adapted to the
demand profile of the buses where the DG is
installed, the electric parameters will be better or
worse. For instance, if the DG production in each busis exactly equal to the demand in each bus, the losses
will be annulated since all the demand is suppliedlocally and there are no flows in the network.
Therefore, the GD more appropriate technologies for
supplying operating reserves are with constant
production profiles.In this category can be classified the generators
which supply almost constant power all the time
(higher utilization factor, generally classified from 0
up to 1, where 1 is the maximum value). In somecases the DG production can be practically constant,
which is the case of combustible-cells, biomass plants
and the gas micro-turbines. These technologies arewell conditioned to the demand profile. In [7] was
shown that the wind and photovoltaic generation areill conditioned for the demand profile. Table 4 showsthe technologies behavior related to the demand and
the operating reserves delivery.
As was explained earlier, the electricity markets in
different countries are discriminated mainly in the
methodologies or procedures in the operative reservemanagement. In general, the maximum level of
operating reserves and the time for the entry
operating reserve difference each electricity markets.
Normally, Spinning Reserve (also is known as primary reserves) is the use of generating equipment
that is online and synchronized to the grid such thatthe generating equipment can begin to increase output
delivery immediately in response to changes to
interconnection frequency, and be fully utilized
within seconds to <10 minutes to correct for generation/load imbalances caused by generation or
transmission outages. Most on-line DG could performspinning reserve and respond in less than 10 seconds.
Supplemental reserve (non-spinning also is known as
secundary and third reserves) differs from spinningreserve because supplemental does not need to
respond to an outage immediately. Traditional non-
spinning reserve needs to be available within 10
minutes.
Supply
Technologies
Natural Gas Turbine øøø øøø
Micro-turbine øøø øøø
Steam Turbine øøø øøø
Combined Cycle øøø øøø
Electrochemical Devices øøø øøø
Small hydro ▲▲▲ ▲
Wind turbines ▲▲▲ ▲▲▲
Mini-Wind ▲▲▲ ▲▲▲
PhotoVoltaic ▲▲▲ ▲▲▲
PhotoThermal øø ▲
Fuel Cell øø ▲▲
Demand
following
Operating
Reserves
Table 4 DG technologies behaviors for
operating reserves supplying [17] øøø: very good
øø: good
▲: normal
▲▲: bad▲▲▲: very bad
5 ConclusionProviding operating reserves by DG makes that the
large centralized generators reduces the scheduleenergy for delivering reserves. Therefore, these large
generators can have more available power for the basic energy supplied to the system.
By using DG, overvoltage levels can appear, mainly
in the distribution network and with less impact in the
sub transmission and transmission systems. Analternative for avoiding these overvoltages is
increasing the DG penetration level with low power
generators, it means with a greater DG dispersion.The DG contribution to the operating reserves
presents more advantages related with losses in sub
![Page 8: Reserves provided by distributed generation](https://reader030.vdocuments.us/reader030/viewer/2022021214/577d2aea1a28ab4e1eaa703f/html5/thumbnails/8.jpg)
8/7/2019 Reserves provided by distributed generation
http://slidepdf.com/reader/full/reserves-provided-by-distributed-generation 8/9
transmission and sub transmission systems, in the
distribution systems the losses reduction is moreconservative since it depends on the technical system
variables and can be manage with a major DGdispersion.
The DG impact on the system depends generally on
the production profile and how it is adaptable to the
demand profile. The DG technologies that canaccomplish a better role in the operating reserves
delivery are those with a constant production profileand also those that can begin to increase output
delivery immediately in response to changes to
interconnection frequency to correct for generation/load imbalances caused by generation or
transmission outages.
References:
[1] L. Wang, C.W. Yu, F.S. Wen, Economic Theory
And The Aplication Of Incentive Contracts To
Procure Operation Reserves”, Copyright
Material Electric Power Systems Research, 2007,
N°77, pp. 518-526.[2] Bayegan, M., A Vision of the Future Grid , IEEE
Power Engineering Review, Vol. 21, pp. 10-12,
December 2001.[3] Fang Z, Editorial Special Issue on Distributed
Power Generation, IEEE Transactions on Power Electronics, V 19, N° 5, September 2004.
[4] Y. Xiaoyan, T. Leon, Ancillary Services Provided
from DER with Power Electronics Interface,
IEEE Power Engineering Review, Vol. 21,December 2006, pp. 10-12.
[5] Pepermans G., Driesen J., Haeseldonckx D.,Belmans R., D’haeseleer W., Distributed generation: definition, benefits and issues,
Energy Policy, N° 33, 2005.[6] S. Persaud, B. Fox and D. Flynn, Impact of
Remotely Connected Wind Turbines on SteadyState Operation of Radial Distribution Networks,
IEE Proceedings. Generation, Transmission and
Distribution, Vol. 147, No. 3; pp. 157-163; 2000.
[7] V.H. Méndez, J. River, J.I. de la Fuente, T.Gómez, Assessment of Energy Distribution
Losses for Increasing Penetration of Distributed Generation, IEEE Transactions on Power
Electronics, V 21, N° 2, May 2006, pp. 533-540.
[8] T. Griffin, K. Tomsovic, D. Secrest and A. Law,
Placement of Dispersed Generations Systems for Reduced Losses, 33rd Hawaii International
Conference on System Sciences; 2000.
[9] A. Naesh, M. Pukar, N. Mithulananthan, Ananalytical approach for DG allocation in primary
distribution network , N° 28, 2006, pp. 669-678
[10] C.W. Yu, X.S. Zhao, F.S. Wen, C.Y. Chung,
T.S. Chung, M.X. Huang, Princing and procurement of operating reserves in competitive
pool-based electricity markets, Electrical Power Systems Research, N° 73, 2005, pp. 37-43.
[11] Kun-Yuan Huang, Yann-Chang Huang, Integrating Direct Load Control With
Interruptible Load Management to Provide Instantaneous Reserves for Ancillary services,
IEEE Transactions on Power Systems, Vol. 19, No. 3, pp. 1626-1634, August 2004
[12] Power Systems, Test Case Archive,
http://www.ee.washington.edu/research/pstca/pf30/pg_tca30bus.htm
[13] Mesut E. Baran, Felix F. Wu, Optimal
Capacitor Placement On Radial Distribution
Systems, Copyright Material IEEE Transactions
on Power Delivery, Vol4, N°1, pp. 725-734.
[14] PSERC, Matpowe, A Matlab Power SystemSimulation Packege, V 3,
www.pserc.edu/matpower/[15] S. Conti, S. Raiti and G. Tina, Small-scale
embedded generation effect on voltage profile: ananalytical method , IEE Proceedings Generation,Transmission and Distribution, Vol. 150, No. 1,
2003, pp. 78-86.
[16] C.L. Masters, Voltage rise, the big issue
when connecting embedded generation to long 11
kV overhead lines, Power Engineering Journal,February 2002, pp. 5-12
[17] V.H. Méndez, J. River, J.I. de la Fuente, T.
Gómez, J. Arceluz, J. Marín, Amadurga, Impac
of distributed generation on distributioninvestment deferral ", Electrical Power and
Energy Systems, N° 28, 2006, pp. 244-252
BiographiesFrancisco D. Moya Ch received the P.E. in Electrical
Engineering from the National University of
Colombia and the M.S. in electrical Engineeringfrom University Los Andes, Colombia, in 2000 and
2005, respectively. He presently is a Ph.D. student inelectrical engineering at UNICAMP (University of
Campinas), Brazil. His main research interests are in
power quality, distributed energy systems, energyefficiency and conservation, renewables, energy andenvironmental policy.
Duvier B. Bedoya areceived the P.E. in ElectricalEngineering with first class honours from the
National University of Colombia, Manizales,
Colombia, in 2004, the M.S. in Electrical Engineering
from UNICAMP (University of Campinas), in 2007,where he is currently researcher. His main research
![Page 9: Reserves provided by distributed generation](https://reader030.vdocuments.us/reader030/viewer/2022021214/577d2aea1a28ab4e1eaa703f/html5/thumbnails/9.jpg)
8/7/2019 Reserves provided by distributed generation
http://slidepdf.com/reader/full/reserves-provided-by-distributed-generation 9/9
interests are in voltage stability, high voltaje and
embedded generation studies.
Gilberto de Martino Jannuzzi received Ph.D. degreefrom Cambridge University, U.K. (Energy Research
Group, Cavendish Laboratory). He is an Associate
Professor of Energy Systems at the Department of
Energy, Mechanical Engineering Faculty, UNICAMP(University of Campinas), He is Executive Director
of the International Energy Initiative , a Southern-conceived, Southern-led and Southern-located South-
South-North partnership. My interests are related to
energy planning, with special emphasis on energyefficiency and conservation, renewables, energy and
environmental policy, and technology transfer issues.
Luiz Carlos P. Silva received the B.S. degree in
Electrical Engineering from Goias Federal University
(UFG), Goiania, Brazil, in 1995, and the M.S. andPh.D. degrees from UNICAMP, in 1997 and 2001,
respectively. Currently, he is an Assistant Professor atUNICAMP (University of Campinas), where he has
been with since 2002. His research interests include
dynamic and static voltage stability analysis andgeneration distribution systems.