research administrators forum › ora › wp-content › uploads › raf-201… · extramural...
TRANSCRIPT
Research Administrators Forum
Sponsored by the Office of Research
Administration
Marcia SmithAssociate Vice Chancellor
May 10th, 2011
Agenda Welcome and Announcements - Marcia Smith RAPID Effort Reporting Workgroup Status Report
– Maurice Taylor and Shannon McGarry• Current Deadline and Metrics
Research Policy and Compliance Update – Ann Pollack• PHS COI Regulations
OCGA Initiatives and Updates – Patti Manheim• Intake Team Metrics • EPASS – Extramural Proposal Approval and Submission Summary
• Award Snapshot
RAPID Proposal and Award Tracking System (PATS) Project Update and Go-Live
– Michelle Leonard and Gloria Su RAPID Post Award Management System (PAMS)
Project Update and Demonstration-- Raellen Man, Jennifer Aguilar, Jessica Lee, Allison Philabaum
Effort Reporting Metrics
As of the 4/13/12 Certification Deadline
On-time Completion Rates for Service Period:
Spring 2011 & Summer 2011 74 Percent & 73 Percent
Open Reports 5,253 open reports out of 131,202
On-time Completion Rates for Prior Service Period:
Fall 2010 & Winter 2011 73 Percent & 68 Percent
1
Effort Reporting Metrics
As of 5/09/12 Completion Rates at UCLA
89% certification rate on Campus Open Reports
16,989 open reports out of 156,641
Fall 2011 and Winter 2012 are available!Certification is due July 30th, 2012
2
Ann PollackAssistant Vice Chancellor – Research
May 10, 2012
Revised Public Health Service Regulations
Quick review: • Intended to increase accountability, add
transparency, enhance regulatory compliance and effective management of financial conflicts of interest and strengthen governmental compliance oversight
• Increases disclosure, review and reporting requirements
• Requires an initial disclosure that must be updated within 30 days of acquiring or discovering any new significant financial interest, and at least annually
Revised Public Health Service Regulations
• Adds an education/training requirement
• Expands reporting requirements
• Adds a new public accessibility requirement
• Adds new monitoring requirements
Revised Public Health Service Regulations
• Require that investigators disclose SFIs that are related to their institutional responsibilities
• Require that UCLA engage in a two-step review of disclosed financial interests to determine: if any disclosed significant financial interest is related
to the PHS research (could be affected by the research or is in an entity that whose financial interest could be affected by the research), and then
if any disclosed significant financial interest constitutes a financial conflict of interest
What Are Significant Financial Interests?
• Anything of monetary value related to the investigator’s institutional responsibilities including but not limited to:
Salary or other payment for services and the value of equity in a publicly traded entity >$5,000 over the past 12 months
Salary or other payment for services >$5,000 or any equity in a privately held entity over the past 12 months
Intellectual property rights (e.g. license fees or royalties) paid by any entity, other than UC, upon receipt of income related to such rights (>$5,000 in the past 12 months)
Travel of any $ value paid for, or reimbursed by, an outside entity
Institutional Responsibilities
“For the purposes of this policy, the term institutional responsibilities is defined as teaching/education, research, outreach, clinical service, and University and public service, on behalf of the University of California performed in the course and scope of the investigator’s UC appointment”
(UC and UCLA definition)
What Is a Financial Conflict of Interest?
“ …a significant financial interest that could directly and significantly affect the design, conduct, or reporting of PHS-funded research.”
(PHS regulations)
Review Process
Progress Since March• PHS contracts and grants will be phased in:
• The regulations will affect PHS awards made on or after August 24, 2012
• The regulations will affect proposals submitted on or after August 24, 2012
• Ongoing awards will become subject to the revised regulations as progress reports, competing renewal applications, proposals for supplemental funding or requests for no-cost time extensions are made on, or after August 24, 2012
Progress Since March (continued)
• UCLA Policy 926 “Public Health Service Regulations on Objectivity in Research” drafted
• Developing content for a short education/training program that briefs PHS investigators on: UCLA’s Policy Investigators’ Disclosure Responsibility The PHS COI regulations
• Planning to embed the training/educational program into the web-based disclosure system
Development of an E-Solution
• Working with Huron's Click™ Portal to customize the Conflict of Interest Module starter site
• Designing smart forms for initial disclosure and required updates
• Working with OCGA and OIP-ISR to develop processes for exchanging critical information
Naming the E-Solution
• Considered (and rejected)
eCOI Financial Interest Disclosure System (eFIND) eGAD or eGADs Styx
• We need your good ideas
Contact Information
Ann PollackAssistant Vice Chancellor – Research 310-794-0387 or [email protected]
Claudia ModlinCoordinator, Research Policy and Compliance310-794-2642 or [email protected]
Patti Manheim, DirectorMay 10, 2012
Today’s Updates
• EPASS • Award Snapshot• Award Intake Team Metrics
• Fillable PDF• Drop-down Menus for
Ease and Consistency of Data Entry
• Hyperlinks to Policies, Procedures, Additional Forms, and Responsible Offices/Contacts
• Electronic/Email Signatures Accepted
EXTRAMURAL PROPOSAL APPROVAL AND SUBMISSION SUMMARY “EPASS”
• Logical data groupings with Major Headings
EXTRAMURAL PROPOSAL APPROVAL AND SUBMISSION SUMMARY “EPASS”
EPASS SectionsExpanded Data Elements Provide Better Reporting Capabilities Back to the Campus Research Community:
• Affiliations with Centers and/or ORUs, Employee ID
EPASS SectionsExpanded Data Elements:
• New Categories Added for Actions Related to Existing Awards
• Award, Program and Proposal Type Drop-downs Updated to Match PATS System
• Added Special Program Types (i.e., Limited Submission and Non-monetary Agreements
EPASS SectionsExpanded Data Elements:
• FOA/RFA/RFP# - search Parent R01s• Prime FOA# and Sponsor Name for Incoming Subawards• Deadline Type (postmark, receipt, electronic) and Time
EPASS SectionsExpanded Data Elements:
• International Collaborators• Cost Sharing/Matching• Information Technology Summary
EPASS Sections
New/Updated Compliance Information: • Biohazard• HESC Research• Biological Materials
EPASS Sections
New/Updated Compliance Information: • Foreign Involvement Related to Export Control
Regulations
EPASS Sections• Excluded Direct Costs ($)
EPASS Sections• Signature Certification Clause – Allows for
Elimination of Separate PHS PI Signature Form
PI/Co-PI CertificationThe Investigator(s) certifies to the following: (1) that the information submitted within this application is true, complete and accurate to the best of their knowledge; (2) that any false, fictitious, or fraudulent statements or claims may subject the Investigator(s) to criminal, civil or administrative penalties; (3) agrees to accept responsibility for the scientific conduct of the project and to provide the required progress reports if a grant is awarded as a result of the application; and (4) that you are not currently debarred, suspended or ineligible to receive federal or non-federal funds. When multiple Investigators are proposed in an application this assurance must be obtained by all named Investigators.
• Available on ORA Online Resource Center and OCGA Website by June 1, 2012.
• Electronic Signature(s) Acceptable.• Send as an Attachment PI/Chair/ORU
Director/Dean as cc on Email.• Mandatory with All Proposal Applications
September 1, 2012.
EPASS Form
Award Snapshot• Sleek, Organized Format• PI Information Displayed First• Immediate Actions Required Listed Prominently
• Award Demographics Show Current Status of All Award Years
• Subawards – Both Proposed and Awarded Listed
Award Snapshot
Award Snapshot• Protocol Information Grouped Together• All Financial and Non-financial Deliverables Listed
Together
Award Snapshot
• Central Contact Information Listed at the Bottom
Award Snapshot
• Advantages: User friendly Information and Format Single Page Expedited Processing Sleek look and feel
• Available beginning June 18, 2012
Award Intake Process
Benefits of Expedited Award Process:• Quicker Access to Funds.• Timely and Consistent Communication at Key
Process Points: Award Received Award Set-up Complete
• Accountability• Key Data to Understand: Where an Award is in the Process? What is Holding up Activation?
• Reduction of Retroactive Transactions due to Late Account Set-up.
• Intake Team has Processed Over 1,000 Awards to Date.• The Turnaround Time for Expedited Awards has
Improved by Over 70% When Compared with Pre-Intake Team Levels.
18 Business Days
5 Business Days
0
2
4
6
8
10
12
14
16
18
20
Expedited Unilateral Awards
Non-Pilot Awards Processing Timelines
Pilot Awards Processing Timelines
Award Intake Process
Award Intake Process• Awards are Processed About 6 Days Faster When All
Documents are Present.
10 Business Days
3.9 Business Days
0
2
4
6
8
10
12
Expedited Awards
Awards with Missing Documents
Awards without Missing Documents
Award Intake Process• The Most Common Documents that are Missing From the
File are Conflict of Interest Forms and a Fully-Authorized Goldenrod.
• 20% of Expedited Awards Currently in Process Have Been Outstanding Over 30 Days – 3 Have Been Outstanding Over 80 days.
QUESTIONS?
Thank You for Helping Us to Help You!
1
Proposal and Award Tracking System (PATS)Project Update
Research Administrators ForumMay 10, 2012
Project Objectives
Improve usability of UCLA’s proposal and award tracking system Address current system limitations and challenges Expand data collection Implement a new data structure to improve
reporting capabilities Clean up data to address inconsistencies created
by changes in functionality over years of use
2
Project Team
ORA: Marcia Smith, Dan Newbower OCGA: Patti Manheim, Cindy Gilbert ORDM: Rory Constancio ORIS: Jackson Jeng, Gloria Su, Michelle Leonard,
Igor Castellanos, Linda Suryani, Wai Fok Huron Consulting Group: Jenna Lee, Phil Infurna Leadership Involvement/Policy Enforcement (LIPE) and
Faculty Advisory Committee (FAC)
3
What’s in it for me?
4
QDB: Other UCLA Systems (FS, Payroll)
What’s in it for me?
5
Expanded and
improved reporting
capabilities
Consistent, streamlined
business processes
Expedited award set-up
New and improved
Award Snapshot
Where are we?
May, 2012 Issues resolution Training Downstream systems development and testing Preparing for Production implementation
6
Project Update & Sneak PeekJessica Lee, ORISJennifer Aguilar, EFMRaellen Man, Dept of MedicineAllison Philabaum, PAMS Business Analyst
5/10/2012 1May RAF PAMS Update & Sneak Peek
Agenda
PAMS Update−What is PAMS?−How PAMS Improves the Current Process−Is PAMS Duplicating Functionality?−Is PAMS the Financial System of Record?−PAMS Accomplishments, Current Activities, Next Steps
PAMS Sneak Peek
Q&A
5/10/2012 2May RAF PAMS Update & Sneak Peek
What is PAMS?
Post Award Management System A web-based system Used by Departments and EFM To efficiently review expenses, develop invoices and
reports, and interact in REAL TIME. Replace shadow systems and manual processes
5/10/2012 3May RAF PAMS Update & Sneak Peek
DEPTS EFM
SPONSOR
How PAMS Improves the Current Process
Automate
Standardize
Digitize
5/10/2012 4May RAF PAMS Update & Sneak Peek
Improve the Current Process: Automate Review process used by depts and EFM: −Expenses outside the budget/project period for salary−Salary over the cap−Administrative salaries (new with PAMS)
F&A reconciliation for depts and EFM in real time and projects F&A expenses for journals
Workload report: prioritizes by financial report & invoice due dates to improve dept and EFM accountability
Auto-populate fields for journal creation (e.g., unallowable or unsupported transactions)
5/10/2012 5May RAF PAMS Update & Sneak Peek
Eliminates multiple department shadow systems and manual processes
Facilitates standardization across dept and EFM business processes- workflow, thresholds, transactions requiring review
Facilitates electronic approvals and workflow within and between depts and EFM
5/10/2012 6May RAF PAMS Update & Sneak Peek
Improve the Current Process: Standardize
Provides depts and EFM real time status information which increases transparency
Online mgmt reports for depts/schools
Online document storage & retrieval in an “eFile” resulting in improved efficiencies, data protection, audit trail, and paper reduction
5/10/2012 7May RAF PAMS Update & Sneak Peek
Improve the Current Process: Digitize
Is PAMS Duplicating Functionality?
Q: Is PAMS functionality already available in the current Financial System or will it be made available with FSRP?
5/10/2012 8May RAF PAMS Update & Sneak Peek
A: No. Much functionality is not and will not be available in a financial system (existing FS or after replacement). Some major functions customized to UCLA including:
− Automated Department and EFM worklists− Unlimited number of easily customized UCLA invoice
templates− Routing and Approvals− Consolidated view per budget period of unallowables,
expenses outside the budget period, & admin salaries
Is PAMS the financial system of record?
No. The UCLA Financial System will continue to be the system of record for all transactions.
PAMS will − Facilitate entry of information into FS
(or other systems such as NPEAR)
− Maintain information/documentation currently retained in EFM and dept files.
5/10/2012 9May RAF PAMS Update & Sneak Peek
PAMS Accomplishments: Collaborate
Collaborated with over 50 depts and EFM participants to analyze & develop business process and system design
Gathered requirements & feedback in 25+ working sessions with the depts and EFM
Defined & implemented standardized workflow
5/10/2012 10May RAF PAMS Update & Sneak Peek
PAMS Accomplishments cont.
Accommodated for policy/procedure changes to ensure compliance − Single Fund Number, PI Approval
Thresholds, Dept/EFM Thresholds, and Admin Salary Unallowables
Developed approximately 60 screens to date based on the above
5/10/2012 11May RAF PAMS Update & Sneak Peek
PAMS Current Activities
Developing remaining screens
Developing business logic
Integrating with other systems and services such as PATS & FS
Preparing testing tools
5/10/2012 12May RAF PAMS Update & Sneak Peek
2013: PAMS GO LIVE!
SUMMER 2012
FUNCTIONAL TEAM DEMOS & SCREEN
FEEDBACK
FALL 2012 2013
FUNCTIONAL TEST
PAMS Next Steps
PAMS Sneak Peek Agenda
5/10/2012 May RAF PAMS Update & Sneak Peek 14
Dept workload
Provisions
Closeout Packet− Overview− PPE non-payroll− Transfer− Justify− F&A reconciliation
− Fund balance and approvals
Dept workload
Provisions
Closeout Packet− Overview− PPE non-payroll− Transfer− Justify− F&A reconciliation
− Fund balance and approvals
5/10/2012 May RAF PAMS Update & Sneak Peek 15
PAMS Sneak Peek Agenda
5/10/2012 16May RAF PAMS Update & Sneak Peek
Thank You!