request for quotation (rfq) - bharat petroleumrequest for quotation (rfq) rfq no.:...

176
Page 1 of 5 Sector 16, Gurgaon 122001 (Haryana), INDIA REQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED Project: LPG IMPORT TERMINAL FACILITIES PROJECT AT HALDIA MR No.: A872-030-XB-MR-0600 REV. A Item: HV SYSTEM PACKAGE Due Date & Time: 09.02.2017; Up to 1200 Hrs. (IST) UNPRICED BID OPENING: At 1400 Hours (IST) on 10.02.2017 PRE-BID QUERIES Last date for submission of Pre Bid Queries will be 19.01.2017 PRE-BID MEETING : A Pre-bid conference will be held on 20.01.2017 at 10:00 Hrs. (IST) at Conference Room, Engineers India Limited 1, Bhikaji Cama Place N.Delhi-110066, India. PRICED BID OPENING: TIME & VENUE SHALL BE INTIMATED LATER. POST BID MEETING: Shall be conducted within 10 days from the date of opening of un-priced bids, if required. GENTLEMEN, 1. Online electronic Bids are requested on behalf of our Client M/s BHARAT PETROLEUM CORPORATION LIMITED under International Competitive Bidding Basis from competent agencies fulfilling Qualification Criteria as per Detailed Notice Inviting Bid (NIB) for the subject item in complete accordance with RFQ Documents/ attachments. 2. Bidders interested to submit their offer can download the complete enquiry document from NIC Portal/ Central Public Procurement Portal (CPPP) i.e. http://eprocure.gov.in/eprocure/app. Also, Bidders are required to upload their bid along with all supporting documents & priced part on the e-tendering website (http://eprocure.gov.in/eprocure/app) only, on or before the due date and time for submission of bid. Bidders are required to register themselves at http://eprocure.gov.in/eprocure/app. No registration fee would be charged from the bidders. 3. Please submit your Acknowledgement against the RFQ on EIL’s website http:tenders.eil.co.in within the due date & time, with reasons(s) of not participating in the bidding in case of regret/negative acknowledgment.In case there is no response, the bidder shall be liable for suitable action including review of their enlistment with EIL for the subject item. 4. The bidders are requested to submit any questions by courier/e-mail in the enclosed Form-A to EIL on or before the date indicated above.

Upload: others

Post on 13-Sep-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 1 of 5

Sector 16, Gurgaon – 122001 (Haryana), INDIA

REQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017

To, M/s

Client : BHARAT PETROLEUM CORPORATION LIMITED

Project: LPG IMPORT TERMINAL FACILITIES PROJECT AT HALDIA

MR No.: A872-030-XB-MR-0600 REV. A

Item: HV SYSTEM PACKAGE

Due Date & Time: 09.02.2017; Up to 1200 Hrs. (IST)

UNPRICED BID OPENING: At 1400 Hours (IST) on 10.02.2017

PRE-BID QUERIES Last date for submission of Pre Bid Queries will be 19.01.2017

PRE-BID MEETING : A Pre-bid conference will be held on 20.01.2017 at 10:00 Hrs. (IST) at Conference Room, Engineers India Limited 1, Bhikaji Cama Place N.Delhi-110066, India.

PRICED BID OPENING: TIME & VENUE SHALL BE INTIMATED LATER.

POST BID MEETING: Shall be conducted within 10 days from the date of opening of un-priced bids, if required.

GENTLEMEN,

1. Online electronic Bids are requested on behalf of our Client M/s BHARAT PETROLEUM CORPORATION LIMITED under International Competitive Bidding Basis from competent agencies fulfilling Qualification Criteria as per Detailed Notice Inviting Bid (NIB) for the subject item in complete accordance with RFQ Documents/ attachments.

2. Bidders interested to submit their offer can download the complete enquiry document from NIC Portal/ Central Public Procurement Portal (CPPP) i.e. http://eprocure.gov.in/eprocure/app. Also, Bidders are required to upload their bid along with all supporting documents & priced part on the e-tendering website (http://eprocure.gov.in/eprocure/app) only, on or before the due date and time for submission of bid. Bidders are required to register themselves at http://eprocure.gov.in/eprocure/app. No registration fee would be charged from the bidders.

3. Please submit your Acknowledgement against the RFQ on EIL’s website http:tenders.eil.co.in within the

due date & time, with reasons(s) of not participating in the bidding in case of regret/negative acknowledgment.In case there is no response, the bidder shall be liable for suitable action including review of their enlistment with EIL for the subject item.

4. The bidders are requested to submit any questions by courier/e-mail in the enclosed Form-A to EIL on

or before the date indicated above.

Page 2: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 2 of 5

5. Bidders are required to upload the bid along with all supporting documents including priced part only on the e-tendering website (http://eprocure.gov.in/cppp.), on or before the due date and time for submission of bid. Bidders are required to register themselves at http://eprocure.gov.in/cppp.. No registration fee would be charged from the bidders.

6. Bidders to refer E-Tendering methodology enclosed with this RFQ cover letter. Various links such as

“Help for Contractor”, “Information about DSC”, “FAQ”, “Resources Required”, “Bidders Manual Kit” etc. are available on home page of http://eprocure.gov.in/cppp. facilitating vendors to participate in the bidding process. Bidder are advised to download & utilize the available information/documents under these links for activities like Registration in CPPP, obtaining User ID & Password, uploading & submission of e-bids etc. Bidders are advised in their own interest to carefully go through Instructions for E-tendering and other related document available against various help links so as to ensure that bids are uploaded in E-tendering website well before the closing date and time of bid submission.

7. NIC Portal mandates that the bidders are to be registered on the portal before any enquiry can be

issued to them. In order to expedite issue of enquiries, the enquiry is being issued through EIL Tender Portal and also being published on Central Public Procurement Portal. The enquiry shall be issued to the bidders on the NIC e-Procurement Portal as soon as their registration is completed in the NIC Portal (http://eprocure.gov.in/cppp).

8. All those vendors who have still not registered on the NIC Portal are required to register on the same

(immediately after issue of enquiry on EIL portal but not later than Ten days before the bid due date) for facilitating issue of enquiry to them on the NIC Portal failing which it will not be possible for them to upload their bids. Pursuant to registration, the vendors are also required to login in EIL tender portal and update NIC’s registration details and inform the undersigned regarding the same for the subject enquiry.

In any case, the enquiry shall be issued on NIC portal to NIC registered vendors about Seven days before the bid due date. Therefore, all those bidders who have not complied with the above registration requirements will not be issued this enquiry on NIC portal and will not be eligible to bid. Request for extension in due date of submission of bids due to non-registration or delayed registration in NIC portal shall not be entertained.

9. The bid has to be necessarily submitted on the NIC Portal and only those bidders who are issued the

enquiry through NIC Portal will be eligible to submit their bids. In case a bidder does not register on the NIC Portal and as a consequence, cannot be issued the enquiry through NIC Portal, it shall be deemed that he is not interested in bidding against this enquiry and no further correspondence will be entertained.

10. In future, EIL shall be issuing all enquiries through NIC Portal alone and bidders who do not register with NIC Portal may not be able to submit their bids. Therefore, it is in the interest of the bidders that they register on the NIC Portal at the earliest.

11. The vendor registration on NIC Portal is a very user friendly process. However, in case of any doubt,

the vendor may contact the undersigned.

12. In the event of failure in bidder’s connectivity with EIL/NIC Portal during the last few hours on account of problem on bidders account, they are likely to miss the deadline for bid submission. Due date extension request due to this reason will not be entertained. In view of the same, bidders are advised to upload their bid in advance.

13. Bidders to upload the Un-priced and Priced part of their bids strictly in the respective designated folders in the NIC Portal.

14. Commercial requirements are specified in the attached General Purchase Conditions, Special Purchase Conditions, Instructions to Bidders, Terms & Conditions for Site Work (applicable if MR calls for Scope of Site Work), Terms & Conditions for Supervision of Erection, Testing & Commissioning

Page 3: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 3 of 5

(applicable if MR calls for supervision), Terms & Conditions for Hazop Study (applicable if MR calls for Hazop Study), Agreed Terms & Conditions (ATC) questionnaire etc. The ATC should be duly filled in, signed & stamped, scanned and uploaded with your bid.

15. Bidders are advised to submit bids strictly based on the specifications, terms & conditions contained in the RFQ Documents and should not stipulate any deviation.

16. Addendum / corrigendum to the RFQ Documents if issued must be signed and submitted along with the bid.

17. The order, if any, will be issued by our above-mentioned client.

18. Delivery Period: -

For Indian Bidders:

Supply: within 08 (Eight) months on FOT site basis from the date of Letter of Award (LOA). Date of receipt of all material at site shall be considered as the date of delivery. Site Work: within 04 (Four) months from the date of site readiness. A 15 (Fifteen) days advance intimation prior to the date of site readiness shall be given to vendor. Date of handing over the equipment at site to owner after successful completion of entire scope of site work as per MR shall be considered as the date of completion.

19. The offer should be valid for 4 (Four) months from final bid due date.

20. Payment Terms: For Indian Bidders:

Supply: As per Clause No. A-1.3 & Notes (as applicable) of Annexure-I to Special Purchase Conditions (SPC).

Site Work: As per Clause No. A-3 & Notes (as applicable) of Annexure-I to Special Purchase Conditions (SPC).

Training: As per Clause No. A-4, A-5 & Notes (as applicable) of Annexure-I to Special Purchase Conditions (SPC).

21. Part Order: Not Applicable.

22. Repeat Order: Not Applicable.

23. The financial net worth of the Bidder as per the latest audited annual report shall be positive.

Networth means paid up share capital, Share Application Money pending allotment* and reserves# less accumulated losses and deferred expenditure to the extent not written off.

# Reserves to be considered for the purpose of networth shall be all reserves created out of the profits and securities premium account but shall not include reserves created out of revaluation of assets, write back of depreciation and amalgamation.

*Share Application Money pending allotment will be considered only in respect of share to be allotted.

Accordingly, the definition of Networth shall be as follows:

Paid up share capital XXXX Add : Share Application Money pending allotment

XXX

Page 4: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 4 of 5

Add : Reserves (As defined Above) XXXX Less : Accumulated Losses XX Less : Deferred Revenue Expenditure to the extent not written off

XX

Networth XXXX

24. Where any portion of Instructions to Bidders, Special Purchase Conditions and General Purchase Conditions is repugnant or at variance with any provisions of RFQ Cover Letter, RFQ Cover Letter shall be deemed to over-ride the provision(s) of Instructions to Bidders, Special Purchase Conditions and General Purchase Conditions only to the extent applicable.

25. Purchase preference shall be applicable for this RFQ. Subject to meeting terms and conditions stated in the RFQ document , in present RFQ, items cannot be split (i.e. minimum 20% to MSEs), all groups shall be awarded on MSE bidder within the price range of L1 bidder’s evaluated price+15% subject to their matching L1 bidder’s price. First, the MSE Bidder next to the price of L1 Bidder shall be considered for purchase preference. In case that MSE Bidder, does not match the price, next MSE Bidder (within the price range of L1 Bidder + 15%) shall be considered for matching the L1 Bidder prices and so on. Accordingly, the MSE Bidder who matches the price of L1 Bidder, shall be considered for award of contract. No separate preference will be given to MSE owned by Scheduled Caste & Scheduled Tribe entrepreneurs over MSE owned by general person as quantity cannot be split in subject Bidding Document.

26. EMD & Bid Document fee is not applicable for this RFQ.

27. As Purchaser intends to contract directly with suppliers of the goods for which bids are invited, the bids should be prepared by the suppliers and submitted directly. Purchaser reserves the right to reject offers made by intermediaries.

28. Bidders to note that price changes against Technical / commercial clarifications, in line with terms & conditions of enquiry documents are not allowed. In case any bidder gives revised prices / price implications against such clarifications, their bid shall be liable for rejection.

29. EIL reserves the right to use in-house information for assessment of bidder’s capability for consideration of bid.

30. In case any bidder is found to be involved in cartel formation, his bid will not be considered for evaluation / placement of order. Such bidder will also be debarred from bidding in future.

31. The bidder shall bear all costs associated with the preparation and submission of its bid, and the Purchaser/Consultant shall in no case be responsible or liable for these costs regardless of the conduct or outcome of the bidding process.

32. Canvassing in any form by the Bidder or by any other agency on their behalf may lead to disqualification of their bid.

33. Consortium/ Joint/ Multiple/ alternative bids shall not be acceptable.

34. Purchaser reserve the right to make any changes in the terms and conditions of purchase and to reject any or all the bids.

35. Contact Persons for this RFQ are:

Mr. Sunita Mitra, DGM (C&P), Contact No. 011-2676 3504 & email: [email protected]

Mr. Vivek Dixit, Dy.MGR (C&P), Contact No. 011-2676 3209 & email: [email protected]

*Please specify Ref. No. (SM/A872-030-XB-MR-0600/1004) in all Correspondence. THIS IS NOT AN ORDER

Very truly yours, For & On Behalf of BPCL

Page 5: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 5 of 5

(SUNITA MITRA) DGM (C&P) ENGINEERS INDIA LIMITED Enclosure: As per List Attached

LIST OF ENCLOSURES

DOCUMENT

1. Price Schedule Format (For Indian Bidders)

2. Price Schedule Format (For Foreign Bidders)

3. Terms and conditions of erection, testing and commissioning (applicable for training charges quoted per diem basis)

4. Form-A (Format for Pre Bid Queries)

5. Agreed Terms & Conditions (For Indian Bidders)

6. Agreed Terms & Conditions (For Foreign Bidders)

7. Instructions To Bidders (ITB)

8. Special Purchase Conditions (SPC) + Annexure-I & II to SPC

9. General Purchase Conditions (GPC)

10. General Conditions of Contracts (GCC)

11. Integrity Pact

12. E-Tendering Methodology

13. Technical document: Material Requisition (MR) No. : A872-030-XB-MR-0600 REV. A

Page 6: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Total Freight Charges upto Project site

excluding Service Tax, Swachh Bharat

Cess & Krishi Kalyan cess

UNIT RATE TOTAL AMOUNT

01.00

01.01 01-HT-20133KV,630A, 40KA(1 sec) HV switchboard as

per datasheet nos.DS -0600,DS-060801 NOS

01.01.01 [01-HT-201.01] Earthing Truck for bus side earthing 01 NOS

01.01.02 [01-HT-201.02] Earthing truck for cable side earthing 01 NOS

01.01.03 [01-HT-201.03]

Lifting truck and accessoies for

withdrawl of circuit breaker from

switchboard panel (if applicable)

01 NOS

01.02 01-HT-2026.6KV, 1250A, 40KA(1 sec) HV switchboard

as per datsheet nos.DS-0600,DS-060901 NOS

01.02.01 [01-HT-202.01] Earthing truck for bus side earthing 01 NOS

01.02.02 [01-HT-202.02] Earthing truckk for cable side earthing 01 NOS

01.02.03 [01-HT-202.03]

Lifting truck and accessories for

withdrawl of Circuit breaker from

switchboard panel(if applicable)

01 NOS

01.03 TR-201

33/6.9 KV , 10/12.5 MVA ONAN/ONAF,with

OLTC&RTCC, power transformer as per

datasheet no.DS-0603

01 NOS

01.04 01-NGR-2016.6kV/Root 3,250A(for 10 sec.),15.935 ohm

NGRs as per DS-060401 NOS

01.05 01-VCB-101

33 KV, 40kA, 3sec TP, Indoor type VCB

Isolator breaker panel as per data sheet,

job specification

01 NOS

01.06 01-CAP-201 6.6 kV, 3 Phase, 1400 kVAR as per DS-0602 01 NOS

01.07 01-CAP-202 6.6 kV, 3 Phase, 1400 kVAR as per DS-0602 01 NOS

01.08 BD-201 A6.6KV,1250A,40kA (1 sec.), Busduct as per

enclosed datasheet,doc. no.01 NOS

PRICE SCHEDULE FOR INDIAN BIDDERS

RFQ No.: SM/A872-030-XB-MR-0600/1004

ITEM: HV SYSTEM PACKAGE

NAME OF BIDDER : M/S

OFFER REFERENCE NO.:

(SUPPLY & TRANSPORTATION)

Design, engineering, manufacture, procurement of materials and bought out components, assembly at shop, inspection, testing at manufacturer's works, packing, delivery & commissioning of

the following, including supply of commissioning spares, special tools and tackles, first fill of consumables, erection material & documentation as per the enclosed standard specifications,

job specifications, data sheets etc. and other codes and standards attached or referred IN MR. NO. A872-030-XB-MR-0600 REV. A COMPLETE IN ALL RESPECTS.

All amount in Indian Rupees (INR)Description

Qty

Prices on FOT Despatch Point Basis including P&F

charges

Sr. No. as per MRItem Code / Tag No.

as per MR UOM

Page 1 of 14

Page 7: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

PRICE SCHEDULE FOR INDIAN BIDDERS

RFQ No.: SM/A872-030-XB-MR-0600/1004

ITEM: HV SYSTEM PACKAGE

NAME OF BIDDER : M/S

OFFER REFERENCE NO.:

01.08.01 [BD-201 A.01]

Busduct for outdoor

installation,including all horizontal and

vertical bends, copper flexible etc. as

required

07 M

01.08.02 [BD-201 A.02]

Busduct for indoor installation,including

all horizontal and vertical bends, copper

flexible, etc. as required

03 M

01.08.03 [BD-201 A.03]

Transformer end termination with all

accessories such as copper flexible,

matching flanges, gaskets, nuts, bolts

etc

01 SET

01.08.04 [BD-201 A.04]

Switchboard end termination with all

accessories such as copper

flexible,matching flanges, gaskets, nuts

bolts etc

01 SET

01.09 EARTHING TRK-10133kV Earthing trucks, accessories for 33

KV Isolator panels as per ITB01 LOT

01.10 EARTHING TRK-2013kV Earthing trucks, accessories for 33

KV switch board in S/S as per ITB01 LOT

01.11 EARTHING TRK-2026.6 kV Earthing trucks, accessories for

6.6 KV switch board in S/S as per ITB01 LOT

01.12 LIFTING TRK-10133 kV lifting trucks, accessories for 33

KV VCB isolator panel as per ITB01 LOT

01.13 LIFTING TRK-20133 kV lifting trucks, accessories for 33

KV switch board in S/S as per ITB01 LOT

01.14 LIFTING TRK-2026.6 kV lifting trucks, accessories for

6.6 KV switch board in S/S as per ITB01 LOT

01.15 HV CABLE-1

33KV 3C x 300 sq mm,unearthed XLPE

insulated,Aluminium conductor, as per job

specification,DS-0610

900 M

01.16 HV CABLE-2

33KV 3C x 240 sq mm,unearthed XLPE

insulated,Aluminium conductor, as per job

specification,DS-0610

75 M

01.17 METERING PANEL

33KV Relay and metering panel for item

no.01.07 as per attached SLD and job

specifications SP-602

01 NOS

Page 2 of 14

Page 8: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

PRICE SCHEDULE FOR INDIAN BIDDERS

RFQ No.: SM/A872-030-XB-MR-0600/1004

ITEM: HV SYSTEM PACKAGE

NAME OF BIDDER : M/S

OFFER REFERENCE NO.:

02.00 -------------------

Unloading at site, handling, transportation to store

and from store to work site, storage at site,

assembly at site, installation, testing,

precommissioning,

painting, insulation, commissioning, performance

guarantee run, handing over to client and other field

works including civil-structural work and supply of

commissioning spares for the following, as per the

enclosed EIL standard specifications, instructions to

vendors, job specification, data sheets etc.(

excluding of service tax, krishi kalyan cess and

swachh bharat cess)

02.01 For Item 01.01 01 NOS

02.02 For Item 01.02 01 NOS

02.03 For Item 01.03 01 NOS

02.04 For Item 01.04 01 NOS

02.05 For Item 01.05 01 NOS

02.06 For Item 01.06 01 NOS

02.07 For Item 01.07 01 NOS

02.08 For Item 01.08 01 NOS

02.09 For Item 01.09 01 NOS

02.10 For Item 01.10 01 NOS

Lumpsum Amount

Page 3 of 14

Page 9: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

PRICE SCHEDULE FOR INDIAN BIDDERS

RFQ No.: SM/A872-030-XB-MR-0600/1004

ITEM: HV SYSTEM PACKAGE

NAME OF BIDDER : M/S

OFFER REFERENCE NO.:

02.11 For Item 01.11 01 NOS

02.12 For Item 01.12 01 NOS

02.13 For Item 01.13 01 NOS

02.14 For Item 01.14 01 NOS

02.15 For Item 01.15 900 M

02.16 For Item 01.16 75 M

02.17 For Item 01.17 01 NOS

04.00

Training to Owner's engineers ( excluding of

service tax, krishi kalyan cess and swachh

bharat cess)

04.01 For Item 01.01 01 LOT

04.02 For Item 01.02 01 PER DIEM

05.00 ______

06.00 ______

Unit Rates of items for addition/

deletion purpose, as per the enclosed

instructions to vendor.

- LOT

NOTE:

EVALUATION SHALL BE DONE ON A BOTTOMLINE BASIS i.e. SUPPLY PRICES + SITE WORK + TARAINING CHARGES

SHALL BE QUOTED IN A SEPARATE ANNEXURE AS PER THE FORMAT "SS-I" ENCLOSED

HEREWITH

IF THER IS ANY DIFFRENCE IN ITEM DESCRIPTION & ITEM TAGS IN ABOVE PRICE SCHEDULE AND MATERIAL REQUISITION, ITEM DESCRIPTION AND ITEM TAGS GIVEN IN MATERIIAL REQUSITION SHALL PREVAIL.

Supply of Two Years Operation and

Maintenance Spares, as per enclosed

instructions to vendor

SHALL BE QUOTED IN A SEPARATE ANNEXURE AS PER THE FORMAT "UT-I" ENCLOSED

HEREWITH

SHALL BE QUOTED IN A SEPARATE ANNEXURE AS PER THE FORMAT "SP-I" ENCLOSED

HEREWITH

Page 4 of 14

Page 10: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Rate in Figure Rate in Words Rate in Figure Rate in Words Rate in Figure Rate in Words

1 2

04.02 For Item 01.02

Notes:

1

2

3a) Service Tax _____________

b) Swachh Bharat Cess___________

c) Krishi Kalyan Cess____________

Bidder to indicate the present rate of the following taxes on training charges which is quoted on pre diem basis.

FORMAT- SS-I

PRICE SCHEDULE FOR TRAINING FOR MR ITEM NO. 01.02 (FOR INDIAN BIDDER)RFQ No.: SM/A872-030-XB-MR-0600/1004

ITEM: HV SYSTEM PACKAGE

NAME OF BIDDER: M/S

OFFER REFERENCE NO.

Item SL. No.

as per MR

Description of Items as per

MR

Per diem charges (per person per day) for

8 hours work on normal working days

(Monday to Saturday) excluding Service

Tax , Swachh Bharat Cess & Krishi Kalyan

cess

Overtime rate/ hour beyond normal 8

hours work on normal working days

excluding Service Tax, Swachh Bharat

Cess & Krishi Kalyan cess

Overtime rate/hour for work on weekly off

days/ holidays (as applicable at Project

site) excluding Service Tax, Swachh Bharat

Cess & Krishi Kalyan cess

All amount in Indian Rupees (INR)

In case bidder recommends more than one category of supervisory personnel, the information desired above in the table shall be furnished separately for each category of

supervisory personnel. However, in case a Bidder quotes different per-diem rates for different category of supervisory personnel then highest of the quoted per-diem rates shall be

considered for evaluation.

3 4 5

Training to Owner's engineers of items specified at item 04.02 of MR, as per MR.

The per diem rates for vendor's specialist visit at site shall be based on "Terms & Conditions for Supervision of Erection, Testing & Commissioning" enclosed with the RFQ. For the

cost of 04 man-days for each item shall be considered for the purpose of commercial evaluation. Wherever the word supervision / supervision appearing in the terms and conditions

for supervision of erection, testing & commissioning, the same shall be read as training / trainer.

Page 11: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

NAME OF BIDDER :

OFFER REFERENCE NO.:

Sr. No. as

per MR

Item Code / Tag No.

as per MR Description Qty UOM Unit Price (in Rs.)

06.01

06.01.01 Fully equipped 33KV,630A Incomer feeder 01 Unit

06.01.02 Fully equipped 6.6KV,1250A Incomer feeder 01 Unit

06.01.03Fully equipped 33KV,630A Bus-coupler

feeder01 Unit

06.01.04Fully equipped 6.6KV,1250A Bus-coupler

feeder01 Unit

06.01.05 Fully equipped Bus Riser Cum PT feeder 01 Unit

06.01.06 Fully equipped Bus PT feeder 01 Unit

06.01.07Fully equipped Induction Motor Feeder

(150A CT )01 Unit

06.01.08Fully equipped Induction Motor Feeder

(30A CT )01 Unit

06.01.09 Fully Equipped Capacitor Feeder 01 Unit

06.01.10Each type of dummy panel (For Beam

Crossing)01 Unit

06.01.11Each type of add-on panel for termination

of cables01 Unit

06.01.12Each rating of circuit breaker

(33kV,630A)01 Unit

Unit Rates of items for addition/ deletion purpose, as per the enclosed instructions to vendor.

PRICE SCHEDULE FOR INDIAN BIDDERS FORMAT-UT-I

Unit Rates of items

RFQ NO.: RFQ No.: SM/A872-030-XB-MR-0600/1004

ITEM: ITEM: HV SYSTEM PACKAGE

Page 6 of 14

Page 12: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

06.01.13Each rating of circuit breaker

(6.6kV,1250A)01 Unit

06.01.14Each rating of circuit breaker

(6.6kV,630A)01 Unit

06.01.15 1250/1-1A, 15VA CL 1.0, 15VA CL 5P10 CT 01 Unit

06.01.16 630/1-1A, 15VA CL 1.0, 15VA CL 5P10 CT 01 Unit

06.01.17630/1A, CL PS CT for Feeder Differential

Protection01 Unit

06.01.181250/1A, CL PS CT for Feeder Differential

Protection01 Unit

06.01.19 150/1-1A, 15VA CL 1.0, 15VA CL 5P10 CT 01 Unit

06.01.20150/1A, CL PS CT for Motor Differential

Protection01 Unit

06.01.21 30/1-1A, 15VA CL 1.0, 15VA CL 5P10 CT 01 Unit

06.01.2233kV/1.732/110/1.732, 50VA CL 1.0, 50VA

CL 3P PT01 Unit

06.01.236.6kV/1.732/110/1.732 50VA CL 1.0, 50VA

CL 3P PT01 Unit

06.01.24Numerical Protection Relay for 6.6KV

Incomer01 Unit

06.01.25Numerical Protection Relay for 6.6KV Bus-

Coupler01 Unit

06.01.26Numerical Protection Relay for 6.6KV Bus

PT01 Unit

06.01.27Numerical Protection Relay for Motor

Feeder (Induction)01 Unit

06.01.28Numerical Protection Relay for

Transformer Feeder (6.6/0.415)01 Unit

06.01.29Numerical Protection Relay for Capacitor

Feeder01 Unit

06.01.30Numerical Protection Relay for Motor Differential

Protection01 Unit

06.01.31Circuit Breaker Contact Multiplication

Relay01 Unit

06.01.32 Master Trip Relay 01 Unit

06.01.33Transformer Auxiliary Fault Relays

01 Unit

06.01.34Control Supply Supervision Relay Type

VAA1101 Unit

Page 7 of 14

Page 13: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

06.01.35 Pluggable Contact Multiplication Relay 01 Unit

06.01.36 CT Supervision Relay 01 Unit

06.01.37Process / LCS / Spare trip Auxiliary

Relay01 Unit

06.01.38 Analog Ammeter with ASS 01 Unit

06.01.39 Analog Voltmeter with VSS 01 Unit

06.01.40 Circuit Breaker Control Switch 01 Unit

06.01.41 Local / Remote Selector Switch 01 Unit

06.01.42 Upstream Breaker Trip Switch 01 Unit

06.01.43 Cluster Type LED Indicating Lamps 01 Unit

06.01.44 Bi-Stable Relay / Contactor 01 Unit

06.01.45 MCB 01 Unit

06.01.46 Metal Oxide Type Surge Suppressor 01 Unit

06.01.47 Numerical Protection Relay for Motor 01 Unit

06.01.48Feeder (Induction) with RTD/BTD analog

inputs01 Unit

06.01.49Fully equipped 6.6KV,630A incomer feeder

for DG01 Unit

06.01.50Numercal Protection relay for relay and

control panel (33KV VCB)01 Unit

06.01.51Numerical protection relay for 33KV

incomer01 Unit

06.01.52Numrical protection relay for transformer

feeder (33/6.9 KV)01 Unit

06.01.53 Numerical rotection relay for DG incomer 01 Unit

06.02

06.02.01 Short Circuit test on transformer 01 Unit

06.02.02 Impulse test on transformer 01 Unit

06.02.03Short circuit test on each type of panel

rated 33kV, 40 kA for 3 second01 Unit

06.02.04Short circuit test on each type of panel

rated 6.6kV, 40 kA for 1 second01 Unit

06.02.05Short circuit duty test on 33KV, 630A

circuit breaker01 Unit

06.02.06Short circuit duty test on 6.6KV, 1250A

circuit breaker01 Unit

06.02.07Short circuit duty test on 6.6KV, 630A

circuit breaker01 Unit

06.02.08 Heat run test on transformer 01 Unit

06.02.09Short circuit test on 6.6KV 1250 A

busduct01 Unit

06.02.10 Heat run test on 33KV switchboard 01 Unit

Unit Rates for Specific tests as per the enclosed instructions to vendor.

Page 8 of 14

Page 14: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

06.02.11 Heat run test on 6.6KV switchboard 01 Unit

06.02.12 Heat run test on 6.6KV 1250 A busduct 01 Unit

06.02.13All type test as per ITP(6-81-1020) on

one capacitor bank01 Unit

06.02.14All type test as per ITP(6-81-1020) on

one no. RVT01 Unit

06.02.15All type test as per ITP(6-81-1020) on

one series reactor of each rating01 Unit

06.02.16 Short circuit test for VCB isolator panel 01 Unit

NOTE: IF THER IS ANY DIFFRENCE IN ITEM DESCRIPTION & ITEM TAGS IN ABOVE PRICE SCHEDULE AND MATERIAL REQUISITION,

ITEM DESCRIPTION AND ITEM TAGS GIVEN IN MATERIIAL REQUSITION SHALL PREVAIL.

Page 9 of 14

Page 15: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

S. No. Description of Taxes & duties Max. Amount on which Taxes

& Duties Shall Be Applicable

Present Rate of

Taxes & Duties in

Percentage

Amount of Taxes &

Duties

Cenvatable / Vatable Portion

of the amount indicated in

column (5)

(1) (2) (3) (4) (5) (6)

1 Excise Duty

2 WB VAT on value of materials

3 CST Againat Form 'C

4 Service Tax on Freight

5 Swatch Bharat Cess on Freight

6 Krishi Kalyan Cess on Freight

7 Service Tax on value of Site work

8 Swatch Bharat Cess on value Site Work

9 Krishi Kalyan Cess on value Site Work

10 Service Tax on value of L/S Training

11 Swatch Bharat Cess on Value L/S Training

12 Krishi Kalyan Cess on Value L/S Training

A) 2 YEARS SPARESB) UNIT RATES FOR ADDITION / DELETION

C) TRAINING CHARGES FOR ITEM NO. 01.02 QUOTED ON PER DIEM BASIS.

BIDDER IS NOT REQUIRED TO INDICATE THE TAXES AND DUTIES APPLICABLE ON FOLLOWING IN THIS FORMAT:

Details of Taxes & Duties (FOR INDIAN BIDDERS)

RFQ No.: SM/A872-030-XB-MR-0600/1004

ITEM: HV SYSTEM PACKAGE

BIDDER'S NAME:

Page 10 of 14

Page 16: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

FORMAT- SP-I

NAME OF BIDDER: M/S

S. NO. Description of spare parts Qty Unit Price on FOT Despatch

Point Basis

(INR)

Total Price on FOT Despatch

Point Basis

(INR)

Freight Charges upto Project

site excluding Service Tax (In %

of quoted FOT Despatch Point

Price for Spares)

5.01 Complete breaker trolley 01 Unit

5.02 Spring charging mtrs 01 Unit

5.03 Closing/tripping coils 01 Unit

5.04

Controlcontactors(20%of the

installed

equipment for each make &

type with

min.10 nos. of each type)

01 Unit

5.05

CT (10% of the installed

equipment for

each make with min. two sets

of each

type/ rating)

01 Unit

5.06

PT (10% of the installed

equipment for

each make with min. two sets

of each

type/ rating)

01 Unit

5.07 Spare vacuum bottles 01 Unit

5.08 Control circuit fuses 01 Unit

5.09 Indicating lamps (LED type) 01 Unit

5.10 Control switches/ MCB 01 Unit

5.11 Primary Bushing 01 Unit

5.12 Secondary bushing 01 Unit

5.13 Neutral Bushing 01 Unit

5.14 Complete sets of gaskets 01 Unit

5.15 Pressure Relief Device 01 Unit

5.16 Double float Bucholz relay 01 Unit

5.17Primary and secondary side

bushing seals

01 Unit

PRICE SCHEDULE FOR 2 YEARS OPERATION & MAINTENANCE SPARES (FOR INDIAN BIDDERS)

RFQ No.: SM/A872-030-XB-MR-0600/1004

ITEM: HV SYSTEM PACKAGE

Page 11 of 14

Page 17: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

5.18Sealing/gauge glass of

conservator

01 Unit

5.19Neutral CT for 51G 01 Unit

5.20Silica gel for breather 01 Unit

5.21Neutral CT for 64R 01 Unit

5.22Spare for OLTC as

recommended by vendor

01 Unit

5.23 Insulator for resistor bank 01 Unit

5.24Terminal bushing with

accessories

01 Unit

5.25Interlink(Copper connections) 01 Unit

5.26 Resistor elements 01 Unit

5.27 Control Switch 01 Unit

5.28 Fuse/fuse base 01 Unit

5.29

Spares for capacitor

bank,RVT,Reactor and

APFC as recommended by

vendor

01 Unit

NOTE: IF THER IS ANY DIFFRENCE IN ITEM DESCRIPTION & ITEM TAGS IN ABOVE PRICE SCHEDULE AND MATERIAL REQUISITION, ITEM DESCRIPTION AND ITEM

TAGS GIVEN IN MATERIIAL REQUSITION SHALL PREVAIL.

Page 12 of 14

Page 18: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Description of

Imported items

Qty.

(Unit____)

*(1)

CUSTOM TARIFF

NO.

BASIC

CUSTOMS DUTY

(%)

(MERIT RATE)

CVD (%) EDU. CESS

ON

CUSTOM

DUTY (%)

SAD (%) TOTAL

CUSTOM

DUTY (%)

2) Bidder to furnish the above details separatly for each Group/ Item of MR.

ENCLOSURE TO PRICE SCHEDULE FOR SUPPLY (INDIAN BIDDERS) FORMAT - "CIF/CD"

RFQ No.: SM/A872-050-LL-MR-4510/1005

ITEM: LOADING ARMS (RAIL/ROAD)

NAME OF BIDDER: M/S __________________________

NOTE: *(1) Unit to be specified by the Bidder.

DETAILS OF BUILT-IN-CIF VALUE OF IMPORT CONTENT, ITEM DETAILS OF IMPORT CONTENT AND MERIT RATES OF IMPORTS DUTY CONSIDERED AND INCLUDED IN QUOTED FOT DESPATCH

POINT PRICES UNDER PRICE SCHEDULE

CIF value of Import Content included in

quoted supply prices for column (2)

Qty.

(In Rs)

MERIT RATE OF CUSTOM DUTY INCLUDED IN QUOTED SUPPLY PRICES

TOTAL CIF VALUE

For Item

Sl . No.

as per

MR

DESCRIPTION

Page 13 of 14

Page 19: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

1

2

3

4

5

6

(SIGNATURE & SEAL OF BIDDER)

FORMAT FOR SUBMISSION OF BREAK UP OF TAXES/DUTIES

As per the Tender/MR provisions wherever Client is entitled for Cenvat/ VAT Credit, it the responsibility of the bidder/supplier to provide the detail of such

Cenvat / VAT credit shall be submitted by the bidder/supplier in the enclosed format.

All statutory variations (increase as well as decrease) in taxes and duties imposed by Government, in taxes and duties, shall be to Client’s Account

As per provisions of the bidding/RFQ document, the non-cenvatable taxes/duties shall be loaded during price evaluation, in case it is not included in the

quoted price, and cenvatable taxes/duties will not be loaded. In case, Cenvatable taxes/duties are included in the quoted price, the same shall be deducted

from the quoted price during price evaluation.

On account of oncoming GST, it is envisaged that there will be merger of various taxes/duties like Central and State taxes etc. As such, it is the

bidder/supplier’s responsibility to critically review and ascertain that the taxes / duties which are applicable as on the final date of submission of price bid as

per the Tender/MR Scope requirement and Terms and Conditions of the bidding/RFQ document, so that on a later date during the execution of the Contract/

Purchase Order (as applicable) for the period for which GST is applicable after its enforcement by the Government of India, such taxes and duties etc. can be

adjusted, as applicable, to the benefit of the Contractor/Supplier/Client to the best extent possible.

In case any taxes/duties are not specifically mentioned in the enclosed format but are applicable for the current scope of work as on the final date of price bid

submission, the Bidder shall indicate such taxes/duties in a separate format along with the detail break up in similar manner as part of this format.

In case, the Contractor/ Supplier does not categorically gives the break-up of all taxes/duties etc. in the price part separately (for both cases where such

taxes/duties are included in quoted price and/or where not included in quoted price, as on the last date of submission of price bid, depending on the

tender/MR specific requirement), it will be deemed considered that no other taxes/duties are applicable other than the title of taxes/duties for which they

have quoted and on implementation of the GST, the adjustment in taxes/duties, if any, for the entire or partial Contract/Delivery period (as applicable

depending on the date of enforcement of GST) shall not be passed on to the Contractor/ Supplier, as applicable.

Page 14 of 14

Page 20: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

TERMS & CONDITIONS FOR SUPERVISION OF ERECTION, TESTING AND COMMISSIONING

Page 1 of 1

1. Bidder shall quote per diem charges which shall include lodging, boarding, medical, local transport, all insurances including Bidder’s personnel and third party insurance, all other incidental charges and all taxes & duties except Service tax (for bidders registered in India) which shall be quoted extra and shall be payable against submission of Invoice as per Service tax rules.

2. The Foreign Bidder has the option to quote prices either gross of Indian income tax or net of Indian income tax and bidder shall furnish all requisite information stipulated elsewhere in the SPC. Applicable rate of withholding tax shall be indicated in the offer wherever a Bidder opts to quote price gross of Indian income tax. In case the Foreign Bidder does not include Indian Income Tax in his prices and Indian Income Tax / withholding tax as applicable is borne & paid by BPCL, the income tax liability shall be added to the Bidder’s price for evaluation.

3. Withholding Tax(s) as per Government policy shall be deducted at source by Purchaser while making payments against each invoice.

4. For Foreign Bidders : To & fro air fare by economy class through most economical route preferably by Air India and/or AC 2 Tier by Train Fare(*) within India nearest to site (HALIDA, KOLKATTA), will be reimbursed at actual. Local transportation in bidder’s country shall be to bidder’s account.

5. For Indian Bidders: To & fro air fare by economy class through most economical route preferably by Air India and/or AC 2 Tier by Train Fare(*) nearest to site (HALIDA, KOLKATTA), will be reimbursed at actual. (*)In case a bidder travel’s by any other mode of transport, the payment shall be made against documentary evidence subject to maximum of AC 2 Tier train fare.

6. Working hours prevailing at site, normally 8 hours/day - Monday through Saturday and holidays as applicable to Purchaser’s site personnel shall apply.

7. Vendor’s supervisory personnel shall observe/abide by site working conditions prevailing at the existing site, safety codes, Indian laws and local laws.

8. A notice period of 15 days will be given for mobilization of supervisory personnel for supervision. 9. Validity period of per diem rate shall be upto the end of guarantee period. 10. Payment: As per Clause No. A-4 (Indian Bidders) and B-4 (Foreign Bidders) and Notes (as applicable) of

Annexure-I to Special Purchase Conditions. 11. Requirement of Employment Visa for Foreign Nationals

All foreign nationals coming to India for execution of Projects / Orders will have to apply for Employment Visa only and that grant of Employment Visa would be subject to strict adherence of following norms:

i) Employment Visa is granted only for the skilled and qualified professional or to a person who is being engaged or appointed by a company, organization, Industry or undertaking etc. in India on contract or employment basis at a senior level, skilled position such as technical expert, senior executive or in managerial position etc.

ii) Request for employment Visa for jobs for which large number of qualified Indian are available, is not considered.

iii) Under no circumstances an Employment Visa is granted for routine, ordinary secretarial / clerical jobs. Bidders are advised in their own interest to check latest Visa rules from Indian Embassy/ High Commission in their country in case foreign nationals are required to be deputed to Indian during execution of the Order.

Signature with Name & Date and Seal/Stamp of the Bidder

Page 21: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

BIDDER’S QUERIES

SL.

NO. BIDDING DOCUMENT SUBJECT BIDDER'S QUERY OWNER'S REPLY

PAGE NO. CLAUSE NO.

NOTE : 1. Bidder’s Queries may be sent by e-mail to as mentioned in the NIT 2. Technical & Commercial queries, if any, must be submitted separately in editable format as per this format.

Page 22: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 1 of 16

LPG IMPORT FACILITIES AT HALDIA OF

BHARAT PETROLEUM CORPORATION LTD. (BPCL)

INSTRUCTIONS TO BIDDERS (ITB)

Page 23: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 2 of 16

INDEX

1. SCOPE OF BID .......................................................................................................... 3 2. ELIGIBLE BIDDERS ................................................................................................... 3 3. ONE BID PER BIDDER/ MULTIPLE BIDS .................................................................. 3 4. COST OF BIDDING .................................................................................................... 4 5. SITE VISIT .................................................................................................................. 4 6. CONTENTS OF BIDDING DOCUMENT ..................................................................... 4 7. CLARIFICATION ON BIDDING DOCUMENTS ........................................................... 4 8. AMENDMENT OF BIDDING DOCUMENTS ............................................................... 5 9. LANGUAGE OF BID ................................................................................................... 5 10. DOCUMENTS COMPRISING THE BID ...................................................................... 5 11. BID PRICES ............................................................................................................... 7 12. BID CURRENCY AND PAYMENT .............................................................................. 9 13. BID VALIDITY ............................................................................................................. 9 14. OFFER WITHOUT ANY DEVIATION ........................................................................ 10 15. AGENTS/CONSULTANTS/REPRESENTATIVES/RETAINERS/ASSOCIATES ........ 10 16. SUBMISSION OF BIDS ............................................................................................ 10 17. DEADLINE FOR SUBMISSION OF BID ................................................................... 10 18. UNSOLICITED BIDS / BID SUBMISSION AT OTHER PLACE ................................. 10 19. MODIFICATION AND WITHDRAWAL OF BIDS ....................................................... 10 20. UN-PRICED BID OPENING ...................................................................................... 10 21. PROCESS TO BE CONFIDENTIAL .......................................................................... 11 22. CONTACTING THE OWNER/ OWNER REPRESENTATIVE ................................... 11 23. EXAMINATION OF BIDS AND DETERMINATION OF RESPONSIVENESS ............ 11 24. PRICE CHANGES / IMPLICATIONS AFTER OPENING OF TECHNICAL BIDS ...... 11 25. PRICE BID OPENING .............................................................................................. 11 26. ARITHMETIC CORRECTIONS ................................................................................. 12 27. CONVERSION TO SINGLE CURRENCY ................................................................. 12 28. BID REJECTION CRITERIA ..................................................................................... 12 29. PRICE EVALUATION & COMPARISON AND LOADING CRITERIA ........................ 12 30. OTHER CRITICAL POINTS FOR EVALUATION OF OFFER ARE AS UNDER ........ 12 31. PRICE CHANGES / IMPLICATIONS AFTER OPENING OF PRICE BIDS ................ 14 32. AWARD OF WORK .................................................................................................. 14 33. QUANTITY VARIATION............................................................................................ 14 34. OWNER'S RIGHT TO ACCEPT ANY BID AND TO REJECT ANY BID..................... 14 35. NOTIFICATION OF AWARD .................................................................................... 15 36. WAIVER OR TRANSFER OF THE AGREEMENT .................................................... 15 37. CARTEL FORMATION ............................................................................................. 15 38. INFORMATION TO BE FURNISHED BY FOREIGN SUPPLIERS/

CONTRACTORS / CONSULTANTS ....................................................................... 15 39. ORDER OF PRECEDENCE ..................................................................................... 16

Page 24: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 3 of 16

A. GENERAL

1. SCOPE OF BID

1.1. EIL hereinafter "the Consultant" on behalf of the Purchaser/Owner/BPCL as defined in the

General Purchase Conditions, hereinafter "the Owner" wishes to receive bids as described in

the Bidding Documents hereinafter shall also mean RFQ documents.

1.2. SCOPE OF WORK: The scope of work shall be as defined in the MR included in the RFQ.

1.3. The successful bidder will be expected to complete the Scope of work within the period stated

in Bidding Document.

1.4. Throughout this Bidding Documents, the term "bid" and "tender" and their derivatives ("bidder/

tenderer", "Bid/tendered/tender", "bidding/tendering", etc.) are synonymous, and day

means calendar day. Singular also means plural.

2. ELIGIBLE BIDDERS 2.1 Documents Establishing Bidder's Qualification.

2.1.1 Pursuant to qualification criteria specified in IFB/NIT/RFQ/Bidding document, the bidder shall furnish all necessary supporting documentary evidence to establish the bidders claim of meeting qualification criteria.

2.1.2 The bidder shall furnish, as part of his bid, documents establishing the bidder's eligibility to bid and his qualifications to perform the contract if his bid is accepted.

2.1.3 The documentary evidence of the bidder's qualifications to perform the contract if their bid are accepted, shall establish to the OWNER'S/CONSULTANT'S satisfaction that, the bidder has the financial, technical and productions capacity necessary to perform the contract.

2.1.4 A bidder shall not be affiliated with a firm or entity:

(i.) that has provided consulting services related to the work to the OWNER during the preparatory stages of the works or of the project of which the works form a part, or

(ii.) that has been hired by the OWNER as engineer/consultant for the contract.

2.2 The bidder shall not be under a declaration of ineligibility by OWNER for corrupt or fraudulent

practices as defined at clause no. 24 of SPC.

2.3 The bidders who are on Holiday/Negative/suspension/banning list of OWNER or EIL or MOP

& NG or other oil PSE on due date of submission of bid/ during the process of evaluation of

the bids, the offers of such bidders shall not be considered for bid opening/evaluation/Award.

If the bidding document were downloaded from website, offers submitted by such bidders

shall also be not considered for bid opening/evaluation/Award.

3. ONE BID PER BIDDER/ MULTIPLE BIDS

3.1 A bidder (i.e. the bidding entity) shall, on no account submit more than one bid either directly

(as a single bidder or as a member of consortium) or indirectly (as a sub-contractor) failing

which following actions shall be initiated:

(i) All bids submitted by such bidder (say ‘A’) directly & indirectly, shall stand rejected and EMD,

if any, in case of direct bid submitted by bidder ‘A’ shall be forfeited.

(ii) If another bidder (say ‘B’) has proposed bidder ‘A’ as a sub-contractor then bidder ‘B’’s bid

shall also be rejected. However, in case the bidder ‘B’ has also proposed an alternative sub-

contractor who is other than the bidder ‘A’, then bidder ‘B”s bid shall be evaluated with the

Page 25: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 4 of 16

proposed alternative sub-contractor only. Hence, every bidder shall ensure in his own interest

that his proposed sub-contractor is not submitting alternative/ multiple

4. COST OF BIDDING 4.1 The bidder shall bear all costs associated with the preparation and submission of the bid, and

OWNER / CONSULTANT, will in no case be responsible or liable for this cost, regardless of

the conduct or outcome of the bidding process.

5. SITE VISIT

5.1. The bidder is advised to visit and examine the site or / locations of warehouse and its surroundings and obtain for itself, at its own responsibility, all the information that may be necessary for preparing the bid and entering into the Contract. The cost of visiting the site shall be at the bidder's own expense.

5.2. The bidder or any of its personnel or agents will be granted permission by the Owner to enter

upon its premises and land for the purpose of such visits, but only upon the express condition

that the bidder, its personnel, and agents will indemnify the Owner and its personnel and agents

from and against all liabilities in respect thereof, and will be responsible for death or personal

injury, loss of or damage to property, and any other loss, damage, costs, and expenses incurred

as a result of the inspection.

5.3. Bidder may contact the following person at site for site visit purpose:

Shri Sunil K Dhakate, Sr. Manager Construction (E&P), Bharat Petroleum Corporation Limited, Haldia Coastal Installation, Patikhali, Durgachak, Haldia, East Medinipur, West Bengal-721602 Mobile No. 09799936500

B. BIDDING DOCUMENTS, CLARIFICATION AND AMENDMENT

6. CONTENTS OF BIDDING DOCUMENT 6.1 Complete Bidding Documents has been hosted on Central Public Procurement Portal (URL:

http://eprocure.gov.in/cppp/app). Notification with CPPP E-tender number for downloading the complete tender from CPPP is also be available on EIL Website http://tenders.eil.co.in/newtenders//other websites mentioned in the RFQ covering letter/Notice Inviting Bid/ Letter Inviting Bid.

6.2 The bidder is expected to examine Bidding Documents, bidding guidelines received from EIL

or available on EIL website, all instructions, formats, terms, specifications and drawings etc., enclosed in the Bidding Documents. The invitation for bid (bidding) together with all its attachment thereto, shall be considered to be read, understood and accepted by the bidder. Failure to furnish all information required by the Bidding Documents or submission of a bid not substantially responsive to the bidding documents in every respect will be at bidder's risk and may result in the rejection of the Bid.

7. CLARIFICATION ON BIDDING DOCUMENTS 7.1 A prospective bidder requiring any information or clarification of the Bidding Documents,

may notify the Consultant in writing by e-mail/fax/post at Consultant's mailing address indicated in the bidding document (Engineers India Limited, Tower-1, Ground Floor, EIL Complex, Sector-16, (Near 32nd Milestone on NH-8), Gurgaon- 122001 Haryana. Kind Attention: (Name mentioned in RFQ document) Dy. General Manager (C&P)). All question/ queries should be

Page 26: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 5 of 16

referred to EIL at least 3 (three) days prior to date of pre-bid meeting. Reply to Pre-Bid Queries shall be hosted on https://eprocure.gov.in/eprocure/app / http://tenders.eil.co.in. The response to pre-bid queries shall not form part of the bidding document unless issued as an amendment. Any modification of the Bidding Document, which may become necessary as a result of the pre-bid discussion, shall be intimated to all bidders through the issue of an Addendum/ Amendment.

8. AMENDMENT OF BIDDING DOCUMENTS 8.1 At any time prior to the deadline for submission of bids, the Owner/Consultant may, for any

reason, whether on its own requirement or in response to a clarification requested by prospective bidders, modify the Bidding Documents by issuing addenda.

8.2 Any addendum thus issued shall be part of the Bidding Documents. The addendum will be hosted on https://eprocure.gov.in/eprocure/app or EIL's website http://tenders.eil.co.in. Bidders are requested to visit the website regularly to keep themselves updated . Bidders have to take into consideration of all the addendum(s) / corrigendum (s) issued/ web hosted, before submitting the bid.

8.3 The Owner/Consultant may, at its discretion, extend the date of submission of Bids in order to allow the bidders a reasonable time to furnish their most competitive bid taking into account the amendments issued.

C. PREPARATION OF BIDS

9. LANGUAGE OF BID 9.1. The Bid prepared by the bidder, all correspondence/drawings and documents relating to the

bid exchanged by the bidder with the Owner/Consultant shall be in English Language alone

provided that any printed literature furnished by the bidder may be written in another language

so long as accompanied by an English translation, in which case, for the purpose of

interpretation of the bid, the English translation shall govern.

9.2. In the event of submission of any document/ certificate by the Bidder in a language other than

English, the English translation of the same duly authenticated by Chamber of Commerce of

Bidder's country shall be submitted by the Bidder.

10. DOCUMENTS COMPRISING THE BID 10.1 No Physical Bids / Offers shall be permitted. The offers/bids submitted online through

Central Public Procurement Portal (CPPP) of Government of India

(http://eprocure.gov.in/eprocure/app) shall only be considered for evaluation and ordering.

Bidders are required to upload the Bid/offer along with all supporting documents including

Priced bid on the E-Tendering website (http://eprocure.gov.in/eprocure/app) only.

However, bidder are required to submit the following documents in original in the manner

prescribed in the Bidding Document in sealed envelope titled “Original Documents for

respective RFQ/Bidding Document No “and shall be send to Engineers India Limited,

Tower-2, Ground Floor, EIL Complex, Sector-16, (Near 32nd Milestone on NH-8),

Gurgaon- 122001 Haryana. Kind Attention: (Name mentioned in RFQ document) Dy..

General Manager (C&P) on or before the Bid submission Due Date. However, bidders

are required to upload the scanned copies of all relevant documents on E-tendering website

along with the e-bid.

1. EMD/Bid Security as applicable as per clause no.10.3 below 2. Documentation against Bidder Qualification Criteria (Technical & Commercial)-if applicable. 3. Integrity Pact (as applicable) 4. Any other document to be submitted in original as per Bidding Document/RFQ.

10.2 The bid shall be submitted by uploading relevant document in respective covers provided in

Page 27: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 6 of 16

the e-tendering website.

10.2.1 BID SECURITY/EARNEST MONEY DEPOSIT: EMD/Bid Security as applicable

10.2.2 TECHNO-COMMERCIAL/UNPRICED BID: Unpriced Bids shall contain followings;

a. Covering letter of Bid on bidder’s letter head.

b. Master Index / List of enclosures of RFQ and copies of all technical and commercial amendments/addendums/corrigendum issued (if any), duly signed and stamped on each page as a token of having received and read all parts of the bidding document and having accepted and considered the same in preparing their bid.

c. Power of attorney in favour of signatory (ies) of the bid.

d. Integrity Pact duly signed & stamped

e. Price Schedule with prices blanked out mentioning “Quoted / Not Quoted” against each item.

f. Financial details as per Proposal Form F1

g. Qualification Documents duly authenticated against Bidder Qualification Criteria (Experience & Financial).

h. Compliance to Bid requirement as per Proposal Form F2.

i. Agreed Terms & Conditions (For Indian/Foreign Bidder as applicable) along with its Annexure as per Proposal Form F3.

j. Bidder’s declaration that they are not under any liquidation, court receiver ship or similar proceedings as per Format Proposal Form F4.

k. Bidder declaration towards Holiday/Negative/suspension/banning list of OWNER or EIL or MOP & NG or other oil PSE as per Format Proposal Form F5.

l. Terms & Conditions for Supervision (For Indian / Foreign Bidders) duly signed and stamped on each page

m. Duly authenticated MSE certificate (as applicable)

n. All technical documents required as per Material Requisition.

o. Any other information required in the RFQ/ Bidding Documents or considered relevant by the bidder.

10.2.3 PRICE BID: Priced Bid shall consist of Price Schedule Formats duly filled.

No corrections, conditions, additions, deletions or modifications in Price Part are permitted. All corrections in quoted rates must be stamped and signed.

No stipulation, deviation, terms & conditions, presumption, basis etc. shall be stipulated in Price Part of the bid. Any condition if stipulated shall be treated as null and void and shall render the bid liable for rejection.

10.3 EARNEST MONEY DEPOSIT/BID SECURITY:

Bidder shall furnish, as part of its Bid, EMD for an amount as indicated in the NIT/NIB/ IFB. If the

Bidder is unable to submit EMD in original within the due date & time, then bidder shall submit

the original EMD within 7 days from the date of unpriced bid opening, provided copy of the

same have been uploaded on E-Tendering Website.

In case the bidder fails to submit the EMD in original within 7 days, then their bid shall

be rejected, irrespective of their status/ ranking in tender and notwithstanding the fact

that a copy of EMD was earlier uploaded by the bidder on E-Tendering Website.

Page 28: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 7 of 16

Owner shall not pay any interest on EMD furnished.

The EMD/Bid Security shall be in favour of the Bharat Petroleum Corporation Limited payable at Noida in the form of crossed demand draft or Bank Guarantees or Standby Letter of Credit (SBLC) in the prescribed pro-forma from Scheduled Commercial banks in India/ Indian Branch of a Foreign Bank recognized as scheduled bank by RBI. The bank guarantee submitted in lieu of EMD shall be valid for 8 (Eight) months more than bid validity. EMD/Bid securities of unsuccessful bidders will be returned upon award of Contract. However, EMD of the successful Bidder will be returned upon the Bidder's executing the Contract, and furnishing the PBG.

The EMD may be forfeited:

If a Bidder withdraws its bid during the period of Bid Validity; or any extension thereto provided by the bidder; or

submits multiple bids / alternative bids; or

If a bidder modifies his bid on his own; or

in case of a successful Bidder, if the Bidder fails, within the specified period:

(a) to submit the order acceptance; and/or

(b) to furnish the PBG.

(c) To accept arithmetical corrections pursuant to clause no. 26 of ITB

11. BID PRICES

11.1. Prices shall be furnished strictly in the appropriate Price Schedule format(s) enclosed with the bidding document. Quoted prices shall be net of discount, if any. Conditional discounts, if offered by a bidder, shall not be considered for evaluation.

11.2. Price quoted by the bidder, shall remain firm & fixed until completion of the contract and will not be subject to any variation, except statutory variation in taxes, duties & levies pursuant to relevant provisions of Special Purchase Conditions.

11.3. The bidder shall quote the price for item in the Price Schedule after careful analysis of cost involved for the performance of complete work considering all parts of the RFQ/Bidding Documents. In case, any activity though specifically not covered but is required to complete the work as per scope of work, scope of supply, specifications, standards, drawings, GPC, SPC or any other part of RFQ Document, the prices quoted shall deemed to be inclusive of cost incurred for such activity.

11.4. Domestic bidder to consider Merit rate of custom duty for their import content. Bidder shall ascertain the applicable merit rate of customs duty and shall be solely responsible towards applicability and correctness of such rates. The evaluation and ordering shall be carried out based on the merit rates of customs duty considered by the bidder. The bidder(s) must indicate quantity, CIF value & rate of custom duty considered in the Price Schedule.

11.5. Owner shall issue concessional form for Central Sales Tax and VAT for Supply order, however in case of LSTK work, same shall not be issued by Owner.

11.6. Indian Bidders shall indicate the following in their offer:

11.6.1 FOT despatch Point price of item including packing & forwarding, (such price to include fabrication /manufacturing of item, all costs as well as duties and taxes paid or payable on components and raw materials incorporated or to be incorporated in the goods, inspection testing etc.) but excluding applicable taxes and duties on finished goods. Bidder’s prices shall be firm and fixed on account of Foreign Exchange variation due to incorporation of import content, if any.

Page 29: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 8 of 16

11.6.2 FOT despatch Point price shall be exclusive of Excise Duty (including Cess) and CST (with

concessional form) or VAT (with concessional form) which will be applicable on the finished goods.

11.6.3 Item wise Transportation Charges upto respective project site exclusive of Service Tax, Swachh Bharat Cess and Krishi Kalyan Cess. Transit Insurance and Road permit shall be arranged by Owner for the materials directly consigned to the Owner.

11.6.4 Site work Prices, if applicable as per MR for the scope of work mentioned in MR / RFQ Documents, exclusive of Service Tax, Swachh Bharat Cess and Krishi Kalyan Cess but inclusive of VAT on Work Contracts. All necessary taxes & duties and registration, if required for carrying out the site activities shall be done by the bidder and cost towards the same shall be included in quoted site work prices.

11.6.5 Training , Post Warranty/Annual Maintenance and Per-diem Supervision Charges shall be exclusive of Service tax, Swachh Bharat Cess and Krishi Kalyan Cess, if applicable as per MR.

11.6.6 Bidder shall indicate the following separately:

11.6.6.1 CIF value (in Indian Rupees) of import for raw material and components incorporated or to be incorporated in the goods and included in quoted price. The bidder shall provide description of such material, quantity, rate, value etc.

11.6.6.2 Merit rate of Import Duties (rate) considered on above CIF value of import for raw material and components and included in the quoted prices.

11.6.6.3 If a bidder does not furnish built-in CIF value and confirmed that quoted prices are

firm and fixed, in that case bidder will not be entitled to claim any variation in the Import Duties even if bidder has quoted their prices considering Import Duties.

11.6.6.4 Foreign Exchange Rate Variation/Custom Duty Variation (On Built-in Import Content):

a. The prices shall be firm and fixed on account of FE variation.

b. Prices shall remain firm and fixed without any escalation except for statutory

variation in customs duty rate up to 2/3rd of delivery period for which the following

methodology shall be followed:

i. Indigenous bidders shall be required to quote their prices including customs

duty (Merit rate) towards their built in import content. Maximum CIF value of

import content in Indian Rupees shall also be furnished by Bidders along with

the merit rate of customs duty considered and list of items to be imported.

ii. Any increase in price due to increase in customs duty rate beyond two-third

of the contractual delivery period will be to supplier’s account. However, any

decrease in price due to decrease in customs duty rate at the time of actual

clearance of imported materials shall be passed on to BPCL.

iii. Variation in price due to customs duty rate will be dealt with separately after

receipt of materials at site against documentary evidence.

11.7. Foreign Bidders shall indicate the following in their offer: 11.7.1 Bidders shall submit their prices on FOB -International Port of Exit basis and also quote for

Ocean Freight charges upto the port of entry- Haldia (India) as detailed out in the price schedule.

11.7.2 Order shall be on CFR Haldia /Kolkatta port of entry in India basis, wherein the ocean transportation from FOB Port of Exit to Haldia/ Kolkatta Port in India shall be arranged by the

Page 30: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 9 of 16

bidders.

11.7.3 The seller shall not be allowed to change port of shipment after quoting unless the seller absorbs any additional cost on account of change.

11.7.4 FOB Prices quoted shall be inclusive of all applicable taxes, packing & forwarding etc. applicable upto FOB - International Port of Exit.

11.7.5 Site work Prices, if applicable as per MR for the scope of work mentioned in MR / RFQ Documents exclusive of Service Tax, Swachh Bharat Cess and Krishi Kalyan Cess but inclusive of VAT on Work Contracts. All necessary taxes & duties registration, if required for carrying out the site activities shall be done by the bidder and cost towards the same shall be included in quoted site work prices.

11.7.6 Training, Post Warranty/Annual Maintenance and Per-diem Supervision Charges, if applicable

as per MR, shall be exclusive of Service Tax, Swachh Bharat Cess and Krishi Kalyan Cess.

11.7.7 Indian Income Tax applicable rate & concession if any (under Double Taxation Avoidance Agreement (DTAA) etc.). Bidder to provide PAN No. along with offer.

11.7.8 Concessional rate of Custom Duty:

a) The bidder must ascertain and confirm along with supporting documents in the bid, if any Customs Duty exemption / waiver is applicable to the products being supplied by him under any multi-lateral / bi-lateral trade agreement between India and bidder's country.

b) The bidder shall be liable to provide all documentation to ensure availment of the exemption / waiver. In case the bidder defaults on this due to any reason, whatsoever, he shall be liable to bear the incremental Customs Duty applicable, if any.

c) Any Customs Duty applicability on account of any change in the bi-lateral / multi-lateral

agreement shall be to bidder's account.

d) Documentation to be furnished for availing the exemption / waiver of Customs Duty shall be specifically listed in the Letter of Credit also as the pre-requisite for release of payment against shipping documents and this documentation shall necessarily form a part of shipping documents.

12. BID CURRENCY AND PAYMENT 12.1 Bidding currency shall be Indian Rupees for Indian bidders and US Dollars / EUROs /

Indian Rupees for foreign bidders in accordance with RBI guidelines.

12.2 A bidder expecting to incur a portion of his expenditure in the performance of Order in more than one currency (limited to maximum two currencies) (In case foreign bidder supply some minor components of supply from their Indian subsidiary/Branch Office) and wishing to be paid accordingly shall indicate the same in the bid. In such a case, the bid shall be expressed in different currencies with the respective amounts in each currency together making up the total price.

12.3 Currency once quoted will not be allowed to be changed. Owner/EIL shall not be compensating for any exchange rate fluctuation.

12.4 Payment shall be released to the supplier in the currency of quote.

13. BID VALIDITY 13.1 The bid shall remain valid for acceptance for period mentioned in RFQ/Notice Inviting Bid

(NIB) from the final bid due date. Owner/EIL shall reject a bid valid for a shorter period being non-responsive.

Page 31: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 10 of 16

13.2 In exceptional circumstances, prior to expiry of the original bid validity period, the Owner/EIL may request that the bidder extend the period of validity for a specified additional period. The requests and the responses thereto shall be made in writing (by fax/post/e-mail).

14. OFFER WITHOUT ANY DEVIATION Owner/EIL will appreciate submission of offer based on the terms and conditions in the enclosed SPC, GPC, ITB, Scope of Work, and Technical Specification etc. to avoid wastage of time and money in seeking clarifications on technical/ commercial aspect of the offer. Bids having any deviation to the RFQ Terms & Conditions shall make Bidder’s offer liable for rejection, except deviations for which loading is defined in Clause No. 29 below.

15. AGENTS/CONSULTANTS/REPRESENTATIVES/RETAINERS/ASSOCIATES

Owner would prefer to deal directly with the manufacturers/ principals abroad without involving any Indian agent. Agents/consultants/representatives/retainers/associates bids found at any stage of evaluation i.e. from un-priced bid opening till priced bid opening shall be liable for rejection.

16. SUBMISSION OF BIDS 16.1 No Physical bids / offers shall be permitted. The offers submitted through Central Public

Procurement Portal (CPPP) of Government of India shall only be considered for evaluation & ordering. Bidders are required to upload the bid along with all supporting documents including priced bid on the e-tendering website (http://eprocure.gov.in/eprocure/app) only.

17. DEADLINE FOR SUBMISSION OF BID 17.1 The E-Bids must be submitted on or before the last date and time mentioned in the RFQ.

17.2 The Owner / EIL may, in exceptional circumstances and at its discretion, on giving reasonable

notice to all prospective bidders, extend the deadline for the submission of e-bids in which case all rights and obligations of the Owner /EIL and bidders, previously subject to the original deadline will thereafter be subject to deadline as extended.

18. UNSOLICITED BIDS / BID SUBMISSION AT OTHER PLACE

18.1 Unsolicited bids or bids being submitted to address other than one specifically stipulated in the bid documents will not be considered for opening / evaluation / award.

19. MODIFICATION AND WITHDRAWAL OF BIDS 19.1 The Bidder may modify or withdraw its Bid after the Bid's submission but prior to the due date

prescribed for submission of Bids by selecting the “Re-Submission” option available in the e-tender portal.

19.2 No bid shall be modified subsequent to the deadline for submission of bids.

19.3 No bid shall be allowed to be withdrawn in the interval between the deadline for submission of bids and the expiration of the period of bid validity specified by the bidder. Withdrawal of a bid during this interval shall result in the forfeiture of bidder's EMD/Bid security.

19.4 There are two specific features in CPPP viz, “Withdraw” and “Re-Submission”. Bidders should not use the feature “withdraw” unless they have decided to withdraw their bids. It is to be noted that once “withdraw” feature is used they will not be allowed to re-submit their bid against this RFQ. In case a Bidder desires to change his bid for any reason before bid due date, Bidder shall use “Re-Submission” feature.

20. UN-PRICED BID OPENING 20.1 The un-priced Bids shall be opened online through e-tender portal, at the specified date and

time given in the RFQ document or extended otherwise. The Bidders who have submitted their Bid will be able to view online the name & status of all the Bidders at their respective windows, after un-priced Bid opening by Owner/Consultant.

Page 32: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 11 of 16

20.2 Only those bidders, whose bids meet the qualification criteria and are technically and commercially acceptable, will be informed the date, time and venue for price bid opening.

D. E-BID OPENING AND EVALUATION

21. PROCESS TO BE CONFIDENTIAL

Information relating to the examination, clarifications, evaluation and comparison of bids, and recommendations for the award of Order shall not be disclosed to bidders or any other person officially concerned with such process.

22. CONTACTING THE OWNER/ OWNER REPRESENTATIVE 22.1 From the time of the bid opening to the time of the award, if any bidder wishes to contact the

Owner for any matter relating to the bid, it should done in writing.

22.2 Any effort by a bidder to influence the Owner/EIL in any manner in respect of bid evaluation or award will result in the rejection of that bid.

23. EXAMINATION OF BIDS AND DETERMINATION OF RESPONSIVENESS 23.1 The Owner/EIL will examine the bids to determine whether they are complete, whether any

computational errors have been made, whether the documents have been properly signed, and whether the bids are generally in order.

23.2 Prior to the detailed evaluation, the Owner/EIL will determine whether each bid is of acceptable quality, is generally complete and is responsive to the RFQ/Bidding Documents. For the purposes of this determination, a responsive bid is one that conforms to all the terms, conditions and specifications of the RFQ/Bidding Documents without deviations, objections, conditionality or reservations.

23.3 Bidder shall not be allowed to submit any Price Implication or Revised Price after submission of Bid, unless there is change in the stipulations of the RFQ/ Bidding Document and such changes are incorporated through an Amendment. In case Exceptions and Deviations submitted by Bidder along with Bid are not considered as acceptable and no Amendment is issued, then in such a case the Bidders would be required to withdraw such Exceptions/Deviations in favour of stipulations of the RFQ/ Bidding document and Bidders would not be eligible for submission of Price Implication/Revised Price, failing which such Bid(s) shall be considered as non responsive and rejected.

23.4 The Owner/EIL determination of a bid's responsiveness is to be based on the contents of the bid itself without recourse to extrinsic evidence. If a bid is not responsive, it will be rejected by the Owner/EIL, and may not subsequently be made responsive by the bidder by correction of the nonconformity.

24. PRICE CHANGES / IMPLICATIONS AFTER OPENING OF TECHNICAL BIDS

24.1 In the event of any suo-moto increase in price sought by a Bidder subsequent to the bid due

date and which is not as a result of any change in scope of supply or terms and conditions, the bid of such a bidder shall be rejected and EMD of that Bidder shall be forfeited by Owner.

24.2 In the event of any suo-moto decrease in price sought by a vendor subsequent to the bid due

date and which is not as a result of any change in scope of supply or terms and conditions, the reduction in price shall not be considered for evaluation however the same shall be considered for ordering in case the bidder happens to be lowest.

25. PRICE BID OPENING 25.1 The Owner/EIL shall inform the time, date and venue for price bid opening to all such bidders

who qualify pursuant to bid evaluation.

25.2 The Owner/EIL will open price bids of all bidders notified to attend price bid opening in presence of authorised bidders' representatives present at the time of priced bid opening. The

Page 33: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 12 of 16

bidder's representatives who are present shall sign bid-opening register evidencing their attendance.

25.3 The bidder's name, prices, and such other details as the Owner/EIL, at its discretion, may consider appropriate will be announced and recorded at the time of bid opening.

26. ARITHMETIC CORRECTIONS If there is correction/wrong entry or a difference between the values entered in figures and in words, applicable as per price schedule, the following procedure shall be adopted for evaluation: i) When there is a difference between the rate in figures and in words for an item, the

rate which corresponds to the amount worked out by the Bidder for the item based on the notional quantity specified, shall be taken as correct.

ii) When the rate quoted by the Bidder in figures and words tallies but the amount is

incorrect, the rate quoted by the Bidder shall be taken as correct. iii) When it is not possible to ascertain the correct rate as detailed above, the rate quoted

for the item in words shall be adopted as the quoted rate. iv) If the total amount written against an item does not correspond to the rate written in

figures and if the rate in words is not written by the bidder, then the higher of the rates, i.e. higher of the rate worked out by dividing the amount by the notional quantity and the rate quoted shall be considered for evaluation. In the event that such a bid is determined as the lowest bid, the lower of the rates shall be considered for ordering.

27. CONVERSION TO SINGLE CURRENCY Foreign Bidder’s bids shall be compared on equivalent Indian Rupees basis considering RBI reference rate of foreign exchange published on the day of opening of the Price Bids. In case the RBI reference rate of foreign exchange published on the day of opening is not available, immediate preceding exchange rate published by RBI shall be considered.

28. BID REJECTION CRITERIA The bidders shall adhere to the provisions of the Bidding Document without taking any deviations. In case a bidder retains any deviations to the provisions even after techno-commercial clarifications, the Bid shall be considered to be non-responsive and shall be rejected.

29. PRICE EVALUATION & COMPARISON AND LOADING CRITERIA

29.1 Evaluation criteria for comparison of bids shall be as per Annexure-II of Special Purchase Conditions (SPC).

30. OTHER CRITICAL POINTS FOR EVALUATION OF OFFER ARE AS UNDER

30.1 The prices quoted in the price bid is to be considered for evaluation and no cognizance will be given to the supplementary/supporting document attached to the price bid, break-up of prices, etc.

30.2 In case bidder intend not to quote for certain item/tags/groups as applicable, then the bidder shall mention "Not Quoted (NQ)" in respective cells of price schedule. Wherever cell is found blank in the price schedule, then it shall be treated as "Not Quoted (NQ)" and evaluation of bids shall be carried out accordingly.

30.3 OWNER reserves the right to consolidate the quantities of PO where it is commercially prudent to place single order as per provision of Clause No. 25.0 of SPC. In case L-1 bidder is MSE bidder, shifting shall be done as per provision of Cl. No. 25.0 of SPC only when items are shifting to MSE bidder.

30.4 The Purchase Preference, if applicable, to Central PSUs shall be considered during

Page 34: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 13 of 16

evaluation of bids as per the existing Govt. Guidelines. However, no Purchase preference to Central PSUs is applicable as on date.

30.5 OWNER shall follow Public Procurement Policy from Micro and Small Enterprises

(MSEs) order 2012, in MRs including MRs where Site Work is also included in the scope.

The same shall be executed as follows:

a. Purchase Preference:

i. For claiming purchase preference, the MSE certificate should be valid as on date of

un-priced bid opening.

ii. Participating Micro and Small Enterprises having evaluated price within price brand

of L1 (evaluated price) + 15% shall also be allowed to supply a portion of

requirement by bringing down their prices to L1 (evaluated) price in a situation

where L1 price is from someone other than a micro and small enterprises and such

micro and small enterprises shall be allowed to supply up to 20% of the total

tendered value. In case of more than one such Micro and Small Enterprises, the

supply shall be shared proportionately (to tendered quantity). Further, out of above

20%, 4% (20% of 20%) shall be from MSEs owned by SC/ST entrepreneurs. This

quota is to be transferred to other MSEs in case of non-availability of MSEs owned

by SC/ST entrepreneurs. It is clarified that in case, 20% quantity works out to a

fraction of quantity, MSEs shall be considered for next higher quantity.

Accordingly, the quoted prices against various items of MR shall remain valid in

case of splitting of quantities of the items in view of the same.

However, in case where quantity against a line item cannot be split (i.e. minimum

20% to MSEs) or items with single quantity or in group item, the complete line

item/group shall be awarded on MSE bidder within the price range of L1 bidder’s

evaluated price+15% subject to their matching L1 bidder’s price. First, the MSE

Bidder next to the price of L1 Bidder shall be considered for purchase preference. In

case that MSE Bidder, does not match the price, next MSE Bidder (within the price

range of L1 Bidder + 15%) shall be considered for matching the L1 Bidder prices

and so on. Accordingly, the MSE Bidder who matches the price of L1 Bidder, shall

be considered for award of contract. No separate preference will be given to MSE

owned by Scheduled Caste & Scheduled Tribe entrepreneurs over MSE owned by

general person as quantity cannot be split in such cases.

b. If the MSE is owned by SC/ST Entrepreneurs, the bidder shall furnish appropriate

documentary evidence in this regard.

Definition of MSEs owned by SC/ST Entrepreneurs shall be:

In case of proprietary MSE, proprietor should be SC/ST.

In case of partnership MSE, the SC/ST partner(s) should be holding at least

51% shares in the unit.

In case of Private Limited Companies, at least 51% share shall be held by

SC/ST share holder(s).

In order for MSE owned by SC/ST Entrepreneurs to qualify for benefits available

under Public Procurement Policy for MSEs order 2012, the MSE shall additionally

submit a relevant SC/ ST certificate in the name of SC/ ST proprietor or partner(s)

holding minimum 51% shares in case of partnership or person(s) holding minimum

51% shares in limited companies, issued by any of the following:

District Magistrate/ Additional District Magistrate/ Collector/ Deputy

Commissioner/ Deputy Collector/ Ist Class Stipendiary Magistrate/ City

Page 35: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 14 of 16

Magistrate/ Sub-Divisional Magistrate/ Taluka Magistrate/ Executive

Magistrate/ Extra Assistant Commissioner (not below the rank of Ist Class

Stipendiary Magistrate).

Chief Presidency Magistrate/ Additional Chief Presidency Magistrate/

Presidency Magistrate.

Revenue Officers not below the rank of Tehsildar

Sub-Divisional Officer of the area where the candidate and/ or his family

normally resides.

Administrator/ Secretary to Administrator/ Development Officer (Lakshadweep

Islands)

c. If the MSE bidder does not provide the appropriate document or any evidence to

substantiate the above, then it will be presumed that he does not qualify for any

preference admissible in the Public Procurement Policy, 2012.

d. For facilitating promotion and development of micro and small enterprises,

BPCL/EIL is committed to promote the procurement of supplies/ services from MSEs

in Orders/ contracts. Accordingly, bidders are also encouraged to promote the same

by considering MSE sub-suppliers/Contractors to the extent possible under the

Orders/ Contracts awarded on them. After award of item/work, Supplier/Contractor

shall furnish a statement along-with copies of orders/ FOAs placed by them on their

sub-suppliers/ sub-Supplier/Contractors who are MSEs, to Project Manager.

31. PRICE CHANGES / IMPLICATIONS AFTER OPENING OF PRICE BIDS 31.1 After opening of price bid, if the party increases the price, though within the validity period and

even though the offer remains lowest, the bid should be rejected. Such bidders shall be

debarred for future enquiries for such action of bidders as a penal measure and EMD of such

Bidder shall be forfeited by Owner.

31.2 Suo-moto Price reduction after price bid opening are to be ignored for evaluation. However, if

the same party happens to be the lowest based on original price bids, the benefit of such

reduction may be availed of.

E. AWARD OF CONTRACT

32. AWARD OF WORK

32.1 The Owner will award the order to the successful bidder (s) whose bid has been

determined to be substantially responsive, and/or have been determined as a lowest bid

on least cost basis to Owner and is determined to be qualified to satisfactorily perform

the Order.

33. QUANTITY VARIATION 33.1 The Owner/EIL reserves the right to vary the quantity of goods, if specified in MR, without any

change in quoted unit price or other terms and conditions.

33.2 Owner/EIL reserves the right to delete the requirement of any one or more items of MR

without assigning any reason.

34. OWNER'S RIGHT TO ACCEPT ANY BID AND TO REJECT ANY BID The Owner/EIL reserves the right to accept or reject any bid, and to annul the bidding process and reject all bids at any time prior to award of the order without thereby incurring any liability to the affected bidder or bidders or any obligations to inform the

Page 36: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 15 of 16

affected bidder or bidders of the ground for Owner/EIL's action.

35. NOTIFICATION OF AWARD 35.1 Prior to the expiration of period of bid validity Owner /EIL will notify the successful bidder

in writing by fax/e-mail to be confirmed in writing, that his bid has been accepted. The

notification of award / Fax of Acceptance will constitute the formation of the Order.

35.2 The Delivery Schedule shall commence from the date of notification of award / Fax of

Acceptance (FOA).

35.3 Award of Contract/Order will be by issuing Fax of Acceptance (FOA) of your bid. FOA will

contain price, delivery and other salient terms of bid and RFQ Document.

Bidder will be required to confirm receipt of the same by returning "Copy of the FOA" duly signed and stamped by the bidder as a token of acknowledgement to Owner and EIL. On receipt of acknowledgement without any deviation / condition, detail Purchase Order / Contract will be issued in quadruplicate. Three copies of the same without any condition / deviation will be returned duly signed and stamped by the bidder as a token of acknowledgement to Owner and EIL.

36. WAIVER OR TRANSFER OF THE AGREEMENT 36.1 The successful bidder shall not waive the Agreement or transfer it to third parties, whether

in part or in whole, nor waive any interest that is included in the Agreement without the prior written permission of the Owner.

37. CARTEL FORMATION 37.1 In case any bidder is found to be involved in cartel formation, his bid will not be considered

for evaluation /placement of order. Such bidder will also be debarred from bidding in future.

38. INFORMATION TO BE FURNISHED BY FOREIGN SUPPLIERS/ CONTRACTORS / CONSULTANTS

It is mandatory for the foreign supplier/contractor/consultant to furnish the following information in case his receipts are subject to tax deduction at source in India:

i) PAN No. as per the Indian Income Tax requirements failing which the

Supplier/Contractor/Consultant shall be responsible for any additional tax deduction at source as per the provisions of the Indian Income Tax Act/Rules and the same shall be deducted from the payment made to supplier/contractor/consultant.

ii) Tax Residency Certificate (TRC) containing prescribed particulars as per the enclosed

Appendix-A from the Government of foreign country in order to claim the benefits of DTAA as per the Indian Income Tax requirements failing which the relief under DTAA will not be available and consequently the higher rate of withholding tax @25% will be applicable and deducted from the payment made to supplier/contractor/consultant (i.e., non-resident taxpayer). The TRC shall be duly verified by the Government of the country of which the assess claims to be a resident for the purposes of tax.

iii) In additional to TRC, bidder in order to claim the benefits of DTAA shall also submit

additional information in form no. 10F (enclosed as Appendix-B). Form 10F has to be signed & verified by the assesses himself.

If some information is already contained in TRC, the bidder shall not be required to provide that information in Form no. 10F but even then Form no. 10F is required to be provided by the bidder. However, the bidder may write Not Applicable in the relevant column in case that information is already contained in TRC.

The above shall be furnished before release of any payment or within one month of the release of Order, whichever is earlier failing submission of the above information, any additional tax liability on purchaser, will be deducted from the payment due to the bidder.

Page 37: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 16 of 16

39. ORDER OF PRECEDENCE

The Instructions to Bidders (ITB) shall supplement to the Special Purchase Conditions (SPC) and General Purchase Conditions (GPC). Where any portion of Special Purchase Conditions (SPC) and/or General Purchase Conditions (GPC) is in conflict with or at variance with any provisions of Instructions to Bidders, the provisions of Instructions to Bidders shall over-ride such provision(s) of Special Purchase Conditions (SPC) and /or General Purchase Conditions (GPC), only to the extent of such repugnancy or variation.

Page 38: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Annexure – 1 to ITB

E-TENDERING METHODOLOGY

Instructions for Online Bid Submission:

The bidders are required to submit soft copies of their bids electronically on the CPP Portal (URL: http://eprocure.gov.in) only, using valid Digital Signature Certificates. The instructions given below are meant to assist the bidders in registering on the CPP Portal, prepare their bids in accordance with the requirements and submitting their bids online on the CPP Portal.

More detailed information useful for submitting online bids on the CPP Portal may be obtained at: https://eprocure.gov.in/eprocure/app.

REGISTRATION

1) Bidders are required to enroll on the e-Procurement module of the Central Public Procurement Portal (URL: https://eprocure.gov.in/eprocure/app) by clicking on the link “Click here to Enroll” on the CPP Portal is free of charge.

2) As part of the enrolment process, the bidders will be required to choose a unique username and assign a password for their accounts.

3) Bidders are advised to register their valid email address and mobile numbers as part of the registration process and submit in EIL tender portal for updation of records (http://tenders.eil.co.in). These details would be used for any communication from the CPP Portal.

4) Upon enrolment, the bidders will be required to register their valid Digital Signature Certificate (DSC) (Class II or Class III Certificates with signing key usage) issued by any Certifying Authority recognized by CCA India (e.g. Sify / TCS / nCode / eMudhra etc.), with their profile.

5) Foreign Bidders have to refer “DSC details for foreign Bidders” for Digital signature Certificates requirements which comes under Download Tab at https://eprocure.gov.in/eprocure/app and the remaining part is same as above and below.

6) Only one valid DSC should be registered by a bidder. Please note that the bidders are responsible to ensure that they do not lend their DSC’s to others which may lead to misuse.

7) Bidder then logs in to the site through the secured log-in by entering their user ID / password and the password of the DSC / e-Token.

SEARCHING FOR TENDER DOCUMENTS

1) There are various search options built in the CPP Portal, to facilitate bidders to search active tenders by several parameters. These parameters could include Tender ID, organization name, location, date, value, etc. There is also an option of advanced search for tenders, wherein the bidders may combine a number of search parameters such as organization name, form of contract, location, date, other keywords etc. to search for a tender published on the CPP Portal.

2) Once the bidders have selected the tenders they are interested in, the same can be moved to the respective ‘My Tenders’ folder. This would enable the CPP Portal to intimate the bidders through SMS / e-mail in case there is any corrigendum issued to the tender document.

Page 39: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

3) The bidder should make a note of the unique Tender ID assigned to each tender, in case they want to

obtain any clarification / help from the Helpdesk.

PREPARATION OF BIDS

1) Bidder should take into account any corrigendum published on the tender document before submitting their bids.

2) Please go through the tender advertisement and the tender document carefully to understand the documents required to be submitted as part of the bid. Please note the number of covers in which the bid documents have to be submitted, the number of documents - including the names and content of each of the document that need to be submitted. Any deviations from these may lead to rejection of the bid.

3) Bidder, in advance, should get ready the bid documents to be submitted as indicated in the tender document and generally, they can be in PDF / XLS / RAR / DWF formats. Bid documents may be scanned with 100 dpi with black and white option. However, Price Schedule / SOR shall be strictly in RAR format without altering any contents of the formats uploaded by EIL in their Bidding Document.

4) To avoid the time and effort required in uploading the same set of standard documents which are required to be submitted as a part of every bid, a provision of uploading such standard documents (e.g. PAN card copy, annual reports, auditor certificates etc.) has been provided to the bidders. Bidders can use “My Space” area available to them to upload such documents. These documents may be directly submitted from the “My Space” area while submitting a bid, and need not be uploaded again and again. This will lead to a reduction in the time required for bid submission process.

SUBMISSION OF BIDS

1) Bidder should log into the site well in advance for bid submission so that he/she upload the bid in time i.e. on or before the bid submission time. Bidder will be responsible for any delay due to other issues.

2) The bidder has to digitally sign and upload the required bid documents one by one as indicated in the tender document.

3) Bidder has to select the payment option as “offline” to pay the tender fee / EMD as applicable and enter details of the instrument.

4) Bidder should prepare the EMD as per the instructions specified in the tender document. The original should be posted/couriered/given in person to the Tender Processing Section, with in 7 calendar days of the date of Unpriced bid opening. The details of the DD/any other accepted instrument, physically sent, should tally with the details available in the scanned copy and the data entered during bid submission time. Otherwise the uploaded bid will be rejected.

5) A Price Bid format has been provided with the tender document to be filled by all the bidders. Bidders are requested to note that they should necessarily submit their financial bids in the format provided and no other format is acceptable. Bidders are required to download the Price Bid file, open it and complete the cells with their respective financial quotes and other details (such as name of the bidder). No other cells should be changed. Once the details have been completed, the bidder should save it and submit it online, without changing the filename. If the Price Bid file is found to be modified by the bidder, the bid will be rejected.

Page 40: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

6) The server time (which is displayed on the bidders’ dashboard) will be considered as the standard time

for referencing the deadlines for submission of the bids by the bidders, opening of bids etc. The bidders should follow this time during bid submission.

7) All the documents being submitted by the bidders would be encrypted using PKI encryption techniques to ensure the secrecy of the data. The data entered cannot be viewed by unauthorized persons until the time of bid opening. The confidentiality of the bids is maintained using the secured Socket Layer 128 bit encryption technology. Data storage encryption of sensitive fields is done.

8) The uploaded tender documents become readable only after the tender opening by the authorized bid openers.

9) Upon the successful and timely submission of bids, the portal will give a successful bid submission message & a bid summary will be displayed with the bid no. and the date & time of submission of the bid with all other relevant details.

10) The bid summary has to be printed and kept as an acknowledgement of the submission of the bid. This acknowledgement may be used as an entry pass for any bid opening meetings.

RETENDER

1) Please note that if Tender has been retendered, than it is mandatory for the bidder to submit their offer again on CPP Portal.

ASSISTANCE TO BIDDERS

1) Any queries relating to the tender document and the terms and conditions contained therein should be addressed to the Tender Inviting Authority for a tender or the relevant contact person indicated in the tender.

2) Any queries relating to the process of online bid submission or queries relating to CPP Portal in general may be directed to the 24x7 CPP Portal Helpdesk. The contact number for the helpdesk is 1800 3070 2232.

Page 41: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

EIL-A872 Page 1 of 12

LPG IMPORT FACILITIES AT HALDIA OF

BHARAT PETROLEUM CORPORATION LTD.

(BPCL)

SPECIAL PURCHASE CONDITIONS (SPC)

Page 42: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

EIL-A872 Page 2 of 12

INDEX 1.0 DEFINITIONS .................................................................................................... 3 2.0 SUPPLIER’S SCOPE ........................................................................................ 3

3.0 BID VAILIDTY .................................................................................................... 3 4.0 DELIVERY SCHEDULE / COMPLETION PERIOD ........................................... 4 5.0 DESPATCH INSTRUCTIONS ............................................................................ 4 6.0 PACKING, MARKING AND SHIPMENT .......................................................... 4 7.0 INSURANCE ...................................................................................................... 4

8.0 INSPECTION ..................................................................................................... 5 9.0 INDEPENDENT SUPPLIER ............................................................................... 5 10.0 TAXES & DUITES ............................................................................................. 5 11.0 RECOVERY OF CUSTOM DUTY, EXCISE DUTY AND SALES TAX .............. 7 12.0 CONTRACT PERFORMANCE BANK GUARANTEE (CPBG): ........................ 7

13.0 PAYMENT TERMS ............................................................................................ 7 14.0 DEDUCTION AT SOURCE ................................................................................ 7

15.0 LIMITATION OF LIABILITY ............................................................................... 7 16.0 STATUTORY APPROVAL ................................................................................ 7 17.0 FINANCIAL DETERRENT FOR VIOLATION OF HSE (applicable only for

case where Site work is involved) .................................................................. 7

18.0 LIEN ................................................................................................................... 8 19.0 Ocean Freight charges (For Foreign bidders) ............................................... 8

20.0 SINGLE ORDER ................................................................................................ 8 21.0 Make in India Policy: In case Material requisition calls for “Make in India

Policy”, the following commercial requirements shall be modified to the following extent. All other provisions of these clauses remain unaltered: .... 8

22.0 SETTLEMENT OF DISPUTE BETWEEN GOVT. DEPT./ PUBLIC SECTOR UNDERTAKINGS .............................................................................................. 9

23.0 INTEGRITY PACT / INDEPENDENT EXTERNAL MONITORS ........................ 9

24.0 FRAUDULENT PRACTICES ............................................................................. 9 25.0 SHIFTING ........................................................................................................ 10 26.0 EVALUATION CRITERIA FOR COMPARISON OF BIDS .............................. 10

27.0 Bid Rejection Criteria:.................................................................................... 10 EVALUATION CRITERIA FOR COMPARISON OF BIDS............................................. 11

Page 43: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

EIL-A872 Page 3 of 12

SPECIAL PURCHASE CONDITIONS (SPC)

1.0 DEFINITIONS

1.1. In addition to meaning ascribed to certain capitalised terms in “General Purchase Conditions

(GPC)”, following initial capitalised terms shall have the meaning as ascribed to such term hereunder. In case any term defined hereunder is also defined in “GPC”, the meaning ascribed to such term hereunder shall prevail:

1.1.1. Definitions

RFQ Documents shall mean documents issued to the bidder

Effective Date shall mean the date on which Supplier’s obligations will commence and that will be date of Fax of Acceptance (FOA).

1.2. Interpretations

1.2.1. Where any portion of the GPC is repugnant to or at variance with any provisions of the SPC then, unless a different intention appears, the provisions of the SPC shall be deemed to govern the provisions of the GPC, and SPC provisions shall prevail to the extent of such repugnancy or variations exist.

1.2.2. In RFQ Documents unless otherwise stated specifically, the singular shall include the plural and vice versa wherever the context so requires.

1.2.3. Notwithstanding the sub-division of the RFQ Documents into separate sections and volumes every part of each shall be deemed to be supplementary to and complementary of every other part and shall be read with and into the Agreement so far as it may be practicable to do so.

1.2.4. All headings, subtitles and marginal notes to the clauses of the GPC, SPC or to the Specifications or to any other part of RFQ Document are solely for the purpose of giving a concise indication and not a summary of the contents thereof, and they shall never be deemed to be part thereof or be used in the interpretation or construction thereof.

1.2.5. The terms fully capitalized and/or initial capitalized shall be interchangeable and shall have the meaning as assigned to fully capitalized term or initial capitalised term.

1.2.6. Except the obligation of payment to Seller, Consultant may discharge all other Purchaser’s obligations. In RFQ documents at all such places where obligations are confined to Purchaser alone such provision to read as ‘Purchaser/Consultant’s’ obligation to the extent the context so means/ requires.

1.2.7. Throughout RFQ Document terms “Letter of Acceptance”, “Letter of Intent”, “Letter of Award”, “Fax of Acceptance” are synonymous.

2.0 SUPPLIER’S SCOPE

Supplier’s scope shall include (a) manufacturing of Items as per Material Requisition including Technical Specifications; (b) preparation of Quality Assurance / Quality control programme; (c) obtaining Consultant’s approval; (d) Inspection by Purchaser’s/Consultant/Agency Designated by Purchaser and obtaining Inspection Release Note; (e) obtaining despatch clearance; (f) Packing; and (g) Loading on truck/trailer and transportation upto site for Indian Bidder/ loading on ship at FOB/FCA port of exit including stowing and Ocean freight charges upto designated Port in India for foreign bidder.

3.0 BID VAILIDTY

3.1 The bid shall remain valid for acceptance for period mentioned in RFQ from the final bid due date. Owner/EIL shall reject a bid valid for a shorter period being non-responsive.

3.2 In exceptional circumstances, prior to expiry of the original bid validity period, the Owner/EIL may request that the bidder extend the period of validity for a specified additional period. The requests and the responses thereto shall be made in writing (by fax/post/e-mail).

3.3 The validity of recommended spares (If applicable as per MR) for 2 years normal operation and maintenance will be 12 months beyond the validity of bid.

Page 44: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

EIL-A872 Page 4 of 12

4.0 DELIVERY SCHEDULE / COMPLETION PERIOD

4.1 All goods under the scope of the Supplier shall be delivered as per delivery schedule / completion period specified in Request for Quotation (RFQ) and no variation shall be permitted.

4.2 Failing to meet the delivery schedule / completion period will be subject to Price Reduction and/or other remedies available to the Purchaser in RFQ Documents.

4.3 Price Reduction Schedule (PRS) shall be applicable as per Clause 20 of GPC subject to condition that the contractual delivery/completion date shall be reckoned from the date of Fax of Acceptance in all cases.

4.4 Where erection/testing/commissioning supervision, commissioning assistance is required as per RFQ Documents / Material requisition, penalty for non-mobilization/delay in mobilization as per order shall be applicable. The penalty shall generally be 1.5 times the per diem rate for each day of delay of reporting to site and shall be in addition to price reduction for delayed delivery.

4.5 For Indian Bidder, date of LR/GR shall be considered as date of delivery or date of receipt of material at site shall be the date of delivery as specified in RFQ Cover Letter /Fax of acceptance/Purchase Order. For Foreign Bidder, date of clean Bill of Lading /Airway Bill shall be considered as date of Delivery.

5.0 DESPATCH INSTRUCTIONS

5.1 Supplier shall obtain despatch clearance from the purchaser prior to despatch.

5.2 Following despatch documents are required to be submitted by the Supplier immediately after shipment is made.

Commercial Invoice

Dispatch instructions/ clearance by Purchaser/Consultant.

Inspection Release Note by Purchaser / Consultant.

LR/ GR / Clean Bill of Lading/Airway Bill.

Packing List

Test Certificates (NDT reports, MTC, etc. as per MR)

Certificate of Measurement and Weight

List of documents as specified in Vendor Data Requirement in Material Requisition & counter signed & stamped by Purchaser / Consultant.

In addition to above documents in case of Foreign Bidder following documents are also required to be submitted ETA Haldia Seaport /Airport (In case of CFR/CPT Contract)

Documents pertaining to ocean/air freight (In case of CFR/CPT Contract)

Country of origin certificate

6.0 PACKING, MARKING AND SHIPMENT

6.1 The Supplier wherever applicable shall after proper painting, pack and crate all goods for sea/road/rail transportation in such a manner so as to protect it from damage and deterioration. The Supplier shall be held responsible for all damages due to improper packing. The Supplier shall ensure sizing or packing of all oversized consignments in such a way that availability of carrier and/or road/rail route is properly taken into consideration.

6.2 Supplier shall comply with the Packing, Marking and Shipping Instructions as in respective documents given as part of RFQ Document.

7.0 INSURANCE

7.1 For cases where only supply is involved and where divisible scope of supply and site work with separate delivery /completion period for respective scope of work is specified, Transit insurance, marine insurance and comprehensive (transit cum marine, storage, erection, till handing over of equipment) insurance, as applicable shall be excluded from the supplier’s scope and, the same shall be arranged by the owner.

Page 45: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

EIL-A872 Page 5 of 12

7.2 For purchases involving indivisible/turnkey works where single time schedule of completion is specified, the comprehensive (transit cum marine, storage, erection, till handing over of equipment) insurance shall be in the scope of supplier/contractor.

7.3 However, the insurance required under prevailing Indian laws for Contractor’s personnel, equipment as well as Third Party Insurance shall be arranged by Contractor.

8.0 INSPECTION

8.1 Inspection of Imported Items against orders on Foreign Suppliers shall be carried out by EIL. No additional charges shall be payable to seller on account of the same. In the case of a foreign supplier sourcing items from India, the inspection shall be carried out by EIL, no additional charges shall be payable to seller on account of the same.

8.2 Inspection of items supplied by Indian bidders shall be in the scope of EIL. In case Indian party sourcing materials from abroad, the bidder shall arrange inspection through EIL, if required.

8.3 Travel, Living and Personnel expenses of EIL’s Representative shall be borne by the Owner.

9.0 INDEPENDENT SUPPLIER

It is expressly understood and agreed that Supplier is an independent party and that neither the Supplier/ its personnel are servants, agents or employees of Purchaser/ Consultant nor the Supplier has any kind of interest in other Suppliers.

10.0 TAXES & DUITES

10.1 EXCISE DUTY (Applicable only for Indian Bidder / Indigenous Supplies):

Quoted Price should be exclusive of Excise Duty applicable on Finished Goods. Applicable rate of Excise Duty should be indicated by the bidder in Price Schedule / Annexure-1 to Agreed Terms and Conditions.

10.2 CENTRAL SALES TAX (CST) / VAT (Applicable only for Indian Bidder / Indigenous Supplies):

Quoted Price should be exclusive of CST (with concessional form) or VAT (with concessional form) applicable on the finished goods. Applicable rate should be indicated by the bidder in Price Schedule / Annexure-1 to Agreed Terms and Conditions.

Owner shall issue concessional form for Central Sales Tax and VAT, in case of supply, however in case of LSTK or Turnkey work form C shall not be issued by Owner.

10.3 IMPORT DUTIES (Applicable only for Indian Bidder):

Quoted Price shall be inclusive of Import Duties on the import content if any in the supply. Bidder to indicate CIF value of the import content and applicable merit rate of Import Duties on the import content in the Price Schedule / Annexure-1 to Agreed Terms and Condition. Statutory variation on Import Duties within the 2/3rd of contractual delivery period shall be to Owner’s account against submission of the documentary evidence and shall be given as per CIF value and applicable merit rate of import duties indicated by the bidder in their offer. Any increase in the rate of Import Duties on CIF value beyond the 2/3rd of contractual completion period shall be to bidder’s account. Any decrease in the rate of Import Duties on CIF shall be passed on to the Owner.

Owner shall not issue Project Authority Certificate (PAC) / Import License to the Suppliers.

10.4 SERVICE TAX:

10.4.1 TRANSPORTATION CHARGES (Applicable only for Indian Bidders):

Quoted Transportation charges shall be exclusive of applicable Service Tax, Swachh Bharat Cess and Krishi Kalyan Cess. Applicable rate of Service Tax, Swachh Bharat Cess and Krishi Kalyan Cess should be indicated by the bidder in Price Schedule / Annexure-1 to Agreed Terms and Conditions.

10.4.2 SUPERVISION / TRAINING CHARGES:

Page 46: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

EIL-A872 Page 6 of 12

Quoted Supervision / Training Charges shall be exclusive of applicable Service Tax, Swachh Bharat Cess and Krishi Kalyan Cess. Indian Bidder to indicate applicable rate of Service Tax, Swachh Bharat Cess and Krishi Kalyan Cess on Supervision / Training Charges in Price Schedule.

For Foreign Bidder Service Tax on Supervision / Training Charges shall be paid by the Owner directly.

10.4.3 SITE WORK:

Quoted Site Work Prices shall be exclusive of applicable Service Tax, Swachh Bharat Cess and Krishi Kalyan Cess. Bidder to indicate applicable rate of Service Tax, Swachh Bharat Cess and Krishi Kalyan Cess on Site Work Charges in Price Schedule.

For cases where only supply is involved and where divisible scope of supply and site work with separate delivery /completion period for respective scope of work is specified, Bidder to quote their rates exclusive of Service tax at full rate.

10.4.4 VAT ON WORK CONTRACTS:

Quoted Site Work Prices shall be inclusive of applicable VAT on Work Contracts.

VAT on Work Contracts as applicable shall be deducted at source and TDS certificate shall be issued to the Bidder.

The bidder has to be a registered dealer under the State VAT Act before getting payment for his works contract. The contractor has to produce an authenticated copy of the certificate of registration under State VAT Act or furnish an undertaking for getting so registered.

10.5 OCTROI / ENTRY TAX:

10.5.1 For cases where only supply is involved and where divisible scope of supply and site work with separate delivery /completion period for respective scope of work is specified:

Entry Tax & Octroi, shall be reimburse / payable directly by BPCL.

10.5.2 For purchases involving indivisible/turnkey works where single time schedule of completion is specified: Entry Tax / Octroi on material brought by the Seller to site for execution of work at site shall be borne by the Seller and quoted prices should be inclusive of such Entry Tax / Octroi. Bidder to furnish the details such as rate, amount etc in their Price Bid.

10.6 ADDITIONAL TAXES & DUTIES (Applicable for Indian Bidder)

Within the contractual delivery period, if any new taxes and/or duties come into force the same will be reimbursed to bidder against documentary evidence. However any new or additional taxes/ duties imposed after contractual delivery shall be to Vendor’s account.

10.7 Cenvat /input tax credit on customs duty (CVD/ Additional CVD) / service tax / VAT / Excise Duty and education cess is not available to BPCL.

10.8 In case of Foreign Bidder quoted FOB Prices shall be inclusive of all charges inclusive of all applicable taxes & duties, applicable upto FOB International Port of Exit.

10.9 All necessary taxes & duties registration, if required for carrying out the site activities shall be done by the supplier and cost towards the same shall be included in quoted prices.

10.10 Any Statutory variation in taxes and duties, within the contractual delivery date, shall be on owner’s account, against submission of documentary evidence. However, in case of delay in delivery beyond the contractual date, for reasons attributable to seller, any increase in these rates shall be borne by seller, whereas any decrease shall be passed on to the owner.

10.11 Further, in case of delay in delivery, due to reasons attributable to seller, any new or additional taxes, duties or levies imposed after the contractual delivery date shall be on seller’s account.

10.12 For the purpose of applicability of statutory variations on taxes and duties (including imposition of any new taxes/duties/levies, etc.) under above terms, each staggered delivery of lots (due in a specific month as per delivery schedule for bulk items) shall be considered as delivery date for the respective lot(s).

Page 47: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

EIL-A872 Page 7 of 12

11.0 RECOVERY OF CUSTOM DUTY, EXCISE DUTY AND SALES TAX

In case of Indian Bidders, if the Statutory Variation entitles the employer to recover the amount (irrespective of contractual delivery) such amount will be recovered from any bill of the Supplier immediately on enforcement of such variation under intimation to the Supplier.

12.0 CONTRACT PERFORMANCE BANK GUARANTEE (CPBG):

12.1 Contract Performance Bank Guarantee (CPBG) for 10% of total order value shall be furnished by successful vendors in format attached with GPC for order value above INR 10 Lakh (or equivalent foreign currency) for Limited enquiries, however, CPBG shall be required for all orders irrespective of value for Press enquiries.

12.2 Contract Performance Bank Guarantee (CPBG) shall be furnished by successful vendor within 15 days from the date of Fax of Acceptance.

13.0 PAYMENT TERMS

In partial modification of the payment terms as mentioned in the General Purchase Conditions, the payment terms shall be applicable as per attached Annexure-I to this SPC.

14.0 DEDUCTION AT SOURCE

14.1 Purchaser will release the payment to the Supplier after effecting deductions as per applicable laws in force. Owner shall deduct VAT on Works Contract as applicable & shall furnish TDS certificate to supplier.

14.2 Purchaser will release payments to the Supplier after offsetting all dues to the Purchaser payable by the Supplier under the Contract.

15.0 LIMITATION OF LIABILITY

Notwithstanding anything contrary contained herein, the aggregate total liability of Supplier under the Contract or otherwise shall be limited to 100% of contract value. However, neither party shall be liable to the other party for any indirect and consequential damages, loss of profits or loss of production.

16.0 STATUTORY APPROVAL

Approval from any authority (i.e. Inspector of Boiler, Electrical Inspector etc.) required as per

statutory rules and regulations of Central / State Government shall be the responsibility of

supplier and the quoted prices shall be inclusive of the same.

The application on behalf of the OWNER for submission to relevant authorities along with

copies of required certificate complete in all respects shall be prepared and submitted by the

supplier well ahead of time so that the actual construction / commissioning of the work is not

delayed for want of the approval / inspection by concerned authorities. The supplier shall

arrange the inspection of the works by the authorities and necessary coordination and liaison

work in this respect shall be the responsibility of the supplier. Reimbursement by the

OWNER of the statutory fees payable by supplier (as per advance approval of OWNER) may

be provided for, subject to submission of receipt.

The supplier shall carry out any change / addition required to meet the requirements of the

statutory authorities, within the quoted rates. The inspection and acceptance of the work by

statutory authorities shall be the responsibility of the supplier.

List of all documents, drawings, forms, affidavits etc required for the approvals shall be submitted by the supplier.

17.0 FINANCIAL DETERRENT FOR VIOLATION OF HSE (applicable only for case where Site work is involved)

The financial deterrent/ penalty for violation of HSE mentioned elsewhere in the RFQ documents shall be applicable for all case involving Site work.

Page 48: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

EIL-A872 Page 8 of 12

18.0 LIEN

Supplier shall ensure that the Scope of Supply supplied under the Agreement shall be free from any claims of title/liens from any third party. In the event of such claims by any party, Supplier shall at his own cost defend, indemnify and hold harmless Purchaser or its authorised representative from such disputes of title/liens, costs, consequences etc.

19.0 Ocean Freight charges (For Foreign bidders)

19.1 Order shall be on CFR port of entry in India basis, wherein the ocean transportation from FOB Port of Exit to the designated Indian Port shall be arranged by the bidders. All shipments of break bulk material and containerized cargo shall be made by suitab le vessels certified for sea worthiness and complying with National/International safety regulations and age of the vessel being less than 25 years. Bidder to coordinate with Owner’s nominated Customs House Agent for smooth discharge/delivery of the cargo at the Port of arrival.

19.2 Quoted prices shall be on FOB Port of Exit basis and separate price for Ocean Freight transportation charges shall be quoted. Quoted Ocean freight charges for Break Bulk cargo delivery shall be on FLT (Full Line Terms), i.e., all charges at destination port shall be borne by the bidder till the cargo is unloaded on to the wharf/vehicle as the case may be. No Trans-shipment is permitted for Break Bulk Cargo.

19.3 Bidder shall inform 07 days prior to the expected date of arrival of vessel in port of entry in India. Detention & Demurrages, if any, due to early arrival of vessel, shall be to bidder’s account.

19.4 Wherever, the foreign bidder does not accept the ocean transportation in his scope, offer of such bidder shall be rejected.

20.0 SINGLE ORDER

20.1 A single order, covering the entire scope of work (including supplies and site work/services, as applicable), shall be placed. Split ordering will not be permitted. Complete responsibility shall be taken by main bidder on single point responsibility basis.

20.2 In case, a foreign supplier requests for a separate order on his Indian sub-supplier, the same shall not be accepted. However, payment to Indian sub-supplier shall be released directly in Indian Rupees against invoices duly certified by the Foreign supplier. For this purpose, the Indian sub-supplier’s name, material and corresponding price along with freight, Taxes & Duties, in Indian Rupees shall be clearly spelt out in the purchase order on foreign supplier. “C” form shall be issued to Indian sub-suppliers.

20.3 Further, obligation of Contract Performance Bank Guarantee & Price Reduction Schedule for complete package shall always be in scope of foreign (principal) Bidder.

20.4 For any liability of Seller (Foreign principal), total order value shall include value of components (Supplies/Services) sourced from India.

21.0 Make in India Policy: In case Material requisition calls for “Make in India Policy”, the following commercial requirements shall be modified to the following extent. All other provisions of these clauses remain unaltered:

21.1 CPBG for additional 5% (over and above 10% required as per GPC) shall be submitted.

21.2 Total CBPG of 15% shall remain valid for additional 12 months.

21.3 Certificate of Incorporation of bidder shall be submitted in Unpriced bid.

21.4 The bidder from his statutory auditor or statutory auditor/CEO/CFO/Company Secretary of the qualifying company, shall submit the letter clearly stating the relationship (100% owned subsidiary and time period) between them or any other document (like MOA/AOA, wherein the relationship can be established) to substantiate the same.

Page 49: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

EIL-A872 Page 9 of 12

22.0 SETTLEMENT OF DISPUTE BETWEEN GOVT. DEPT./ PUBLIC SECTOR UNDERTAKINGS

22.1 In the event of any dispute or difference relating to the interpretation and application of the provisions of the contracts, such dispute or difference shall be referred by either party for Arbitration to the sole Arbitrator in the Department of Public Enterprises to be nominated by the Secretary to the Government of India in-charge of the Department of Public Enterprises. The Arbitration and Conciliation Act, 1996 shall not be applicable to arbitration under this clause. The award of the Arbitrator shall be binding upon the parties to the dispute, provided, however, any party aggrieved by such award ay make a further reference for setting aside or revision of the award to the Law Secretary, Department of Legal Affairs, Ministry of Law & Justice, Government of India. Upon such reference the dispute shall be decided by the Law Secretary or the Special Secretary/Additional Secretary, when so authorized by the Law Secretary, whose decision shall bind the Parties finally and conclusively. The Parties to the dispute will share equally the cost of arbitration as intimated by the Arbitrator.

23.0 INTEGRITY PACT / INDEPENDENT EXTERNAL MONITORS

23.1 Integrity Pact shall be applicable if specified in RFQ documents.

23.2 Proforma of Integrity Pact (IP) attached shall be returned by the Bidder/s along with the bid documents, duly signed by the same signatory who is authorized to sign the bid documents. All the pages of the Integrity Pact shall be duly signed. Bidder's failure to submit the IP duly signed shall result in the bid not being considered for further evaluation.

23.3 Bidders may raise disputes/complaints, if any, with the nominated Independent External Monitor, mentioned below:

Mr. Shantanu Consul No.9 MCHS (IAS officers colony), 16th Main (IAS officers colony), BTM 2nd stage, Bangalore-560076 Mobile No.: 09740069318 [email protected]

24.0 FRAUDULENT PRACTICES

24.1 The OWNER requires that Bidders/Vendors/Contractors observe the highest standard of ethics during the award/execution of Contract. “Fraudulent Practice” means a misrepresentation of facts in order to influence the award of a Contract to the detriment of the OWNER, and includes collusive practice among bidders ( prior to or after bid submission ) designed to establish bid prices at artificial non-competitive levels and to deprive the OWNER of the benefits of free and open competition.

24.2 The OWNER will reject a bid for award if it determines that the bidder recommended for award has engaged in fraudulent practices in competing for the Contract in question.

Bidder is required to furnish the complete and correct information/ documents required for evaluation of their bids, if the information/ documents forming basis of evaluation is found to be false/ forged, the same shall be considered adequate ground for rejection of bids and forfeiture of Earnest Money Deposit.

24.3 In case, the information/ document furnished by the Bidder/vendor/Contractor forming basis of evaluation of his bid is found to be false/ forged after the award of the contract, OWNER shall have full right to terminate the contract and get the remaining job executed at the risk & cost of such Bidder/Vendor/ Contractor without any prejudice to other rights available to OWNER under the contract such as forfeiture of PBG/CPBG, withholding of payment etc.

24.4 In case, this issue of submission of false document comes to the notice after execution of work, OWNER shall have full right to forfeit any amount due to the Bidder/Vendor/Contractor along with forfeiture of PBG/Security Deposit furnished by the Bidder/Vendor/Contractor.

24.5 Further, such Bidder/Vendor/ Contractor shall be put on Blacklist/ Holiday/Negative List of OWNER debarring them from future business with OWNER and EIL for a time period, as per the prevailing policy of OWNER and EIL.

Page 50: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

EIL-A872 Page 10 of 12

25.0 SHIFTING

25.1 OWNER also reserves the right to consolidate the quantities of PO where it is commercially prudent to place single order. In the case of shifting of order as above, the following shall govern:

a) In order to avoid splitting of order on number of bidders, particularly when order value is

small, shifting shall be resorted to so that time and effort on ordering, expediting,

inspection etc. is saved in dealing with extra suppliers. For the purpose of shifting, cost of

order management per order is considered as Rs.1,00,000/-. However, shifting shall not

be resorted to where MSE is the recommended bidder even if the items are being shifted

to another MSE Bidder, if the recommended order value is above Rs. 25,000/-

b) Based on lowest evaluated item wise prices the shifting shall be carried out provided the

following conditions are met:

Shifting shall be done only if shifting cost of each order is up to Rs. 1,00,000/.

Shifting shall not be resorted to if the value of the order is more than 25% of the total

order value of the recommendation. However, this ceiling will not be applicable

where total order value of recommendation is up to Rs. 4.0 Lakhs.

In case the order value on L1 bidder is more than Rs 2,00,000/- then shifting shall

not be resorted.

With above shifting the selected bidder for award will be deemed to be L1 bidder.

26.0 EVALUATION CRITERIA FOR COMPARISON OF BIDS

Evaluation criteria for comparison of bids shall be as per Annexure-II enclosed.

27.0 Bid Rejection Criteria: The bidders shall adhere to the provisions of the Bidding Document without taking any deviations. In case a bidder retains any deviations to the provisions even after techno-commercial clarifications, the Bid shall be considered to be non-responsive and shall be rejected.

Page 51: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 1 of 10

Annexure-I to SPC

Job No: A872

PAYMENT TERMS

A. FOR INDIGENOUS SUPPLIERS:

1. Supply:

1.1. Where the MR is for supply of materials and there is no Vendor Data Requirement (VDR) specified in the MR:

- 15% against identification of raw materials at Supplier’s works and against submission

of ABG of equivalent amount.

- 60% against despatch documents (along with copy of LR/GR and IRN) directly to EIL

together with full taxes, duties and transportation charges.

- 15% against receipt of material at site.

- 10% on receipt of all material at site and on submission of E1/E2 Form (wherever

applicable).

1.2. Where the MR is for supply of materials and calls for Vendor Data requirement:

- 5% against approval of drawings, wherever required (identified in PO/ PR) at least in

Code-2.

- 15% against identification of raw materials at Supplier’s works and against submission

of ABG of equivalent amount.

- 55% (60% where drawing/doc approval not required) against despatch documents

(along with copy of LR/GR and IRN) directly to EIL together with full taxes, duties and

transportation charges.

- 10% against receipt of material at site.

- 5% on receipt of all Final/As built Drawings/Documents/Data/Manual in requisite

number of copies/sets/CDs as per VDR specified in Purchase Requisition.

- 10% on receipt of all material at site and on submission of E1/E2 Form (wherever

applicable).

1.3. Where the MR is for supply of materials and calls for vendor Data requirement (With site work) :

- 5% against approval of drawings, wherever required (identified in PO/ PR) at least in

Code-2.

- 15% against identification of raw materials at Supplier’s works and against submission

of ABG of equivalent amount.

- 55% (60% where drawing/doc approval not required) against despatch documents

(along with copy of LR/GR and IRN) directly to EIL together with full taxes, duties and

transportation charges

- 10% against receipt of material at site.

- 5% on receipt of Final/As built Drawings/Documents/Data/Manual in requisite number

of copies/sets/CDs as per VDR specified in Purchase Requisition.

Page 52: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 2 of 10

Annexure-I to SPC

Job No: A872

- 10% on completion of Site Work and submission of E1/E2 Form (wherever applicable).

1.4. Where the MR is for Packages, fabricated equipment like Columns/Pressure vessels/Reactors/Heat Exchangers /Pumps/Compressors/EOT Crane/Air Fin Cooler etc (with significant Bought out item) and calls for Vendor Data requirement (Without site work):

- 5% against approval of drawings, wherever required (identified in PO/ PR) at least in

Code-2.

- 10% against placement of sub-order for specified major raw material (to be identified

during kick off meeting, if not specified in enquiry) and against submission of ABG of

equivalent amount.

- 15% against identification of raw materials at Supplier’s works (to be identified during

kick off meeting, if not specified in enquiry) and against submission of ABG of

equivalent amount.

- 50% against despatch documents (along with copy of LR/GR and IRN) directly to EIL

together with full taxes, duties and transportation charges.

- 5% against receipt of material at site.

- 5% on receipt of Final/As built Drawings/Documents/Data/Manual in requisite number

of copies/sets/CDs as per VDR specified in Purchase Requisition.

- 10% on receipt of all material at site and on submission of E1/E2 Form (wherever

applicable).

Major Raw Material for payment against placement of orders:

Columns/Vessels/Reactors : Plates & Forgings

Heat Exchangers : Plates, Tube, Tube sheets

Pumps : Castings for casings, impellers and drivers

Compressors : Castings for casings and rotors and drivers

Air Fin Coolers : Tubes, Header Plates, Fin Material

Major Raw Material for payment against receipt & identification of raw materials:

Columns/Vessels/Reactors : Plates & Forgings

Heat Exchangers : Plates, Tubes, Tube sheets

Pumps : Castings for casings and impellers

Compressors : Castings for casings and rotors

Air Fin Coolers : Tubes, Header Plates, Fin Material

1.5. Where the MR is for Packages, fabricated equipment like Columns/Pressure vessels/Reactors/Heat Exchangers /Pumps/Compressors/EOT Crane/Air Fin Cooler etc (with significant Bought out item) and calls for Vendor Data requirement (With site work) :

- 5% against approval of drawings, wherever required (identified in PO/ PR) at least in

Code-2.

Page 53: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 3 of 10

Annexure-I to SPC

Job No: A872

- 10% against placement of sub-order for specified major raw material (to be identified

during kick off meeting, if not specified in enquiry) and against submission of ABG of

equivalent amount.

- 15% against identification of raw materials at Supplier’s works (to be identified during

kick off meeting, if not specified in enquiry) and against submission of ABG of

equivalent amount.

- 50% against despatch documents (along with copy of LR/GR and IRN) directly to EIL

together with full taxes, duties and transportation charges.

- 5% against receipt of material at site.

- 5% on receipt of Final/As built Drawings/Documents/Data/Manual in requisite number

of copies/sets/CDs as per VDR specified in Purchase Requisition.

- 10% on completion of site work and submission of E1/E2 Form (wherever applicable).

Major Raw Material for payment against placement of orders:

Columns/Vessels/Reactors : Plates & Forgings

Heat Exchangers : Plates, Tube, Tube sheets

Pumps : Castings for casings, impellers and drivers

Compressors : Castings for casings and rotors and drivers

Air Fin Coolers : Tubes, Header Plates, Fin Material

Major Raw Material for payment against receipt & identification of raw materials:

Columns/Vessels/Reactors : Plates & Forgings

Heat Exchangers : Plates, Tubes, Tube sheets

Pumps : Castings for casings and impellers

Compressors : Castings for casings and rotors

Air Fin Coolers : Tubes, Header Plates, Fin Material

1.6. Mobile Water cum foam tenders (Truck loaded)

For Chassis: (Supplier shall furnish the sub order copy on the chasis manufacturer and

furnish confirmation regarding direct payment to chasis manufacturer against chasis value

out of total quoted value of complete package).

- 10% of sub-order value to Chasis manufacturer directly against placement of sub-order

for Chasis against submission of equivalent Bank Guarantee having validity upto

dispatch of Chasis from Chasis manufacturer’s works.

- 90% of sub-order value shall be made to the chasis manufacturer against commercial

invoice to Supplier (against dispatch readiness), duly endorsed by Supplier and against

submission of following:

- Ownership of chasis shall be in the name of EIL/Client by sub-vendor along with

Insurance policy with the Client as beneficiary to cover all risks during transit and

Page 54: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 4 of 10

Annexure-I to SPC

Job No: A872

storage at main vendor works.

In addition Supplier to confirm that they shall assist Owner in final and firm

registration of duly built up vehicle at project site.

No other charges shall be payable on any account w.r.t chassis including

transportation of chassis, insurance from Chasis Supplier works to Supplier

works etc.

Supplier to carry out the works in their work shop/ Works which shall be insured

including work in progress materials in the shop. Supplier shall furnish all such

necessary documents to this effect enabling Owner to release payment to

Chasis Supplier.

For Fabrication works at Vendor shop (Total quoted price of package excluding price of chassis as per Work order on chasis vendor):

- 5% against approval of drawings, wherever required (identified in PO/ PR) at least in

Code-2.

- 75% against despatch documents including but not limited to Invoice for the complete

package including Chasis (along with copy of LR/GR and IRN) directly to EIL together

with full taxes, duties and transportation charges.

- 5% against receipt of material at site.

- 5% on receipt of Final/As built Drawings/Documents/Data/Manual in requisite number

of copies/sets/CDs as per VDR specified in Purchase Requisition.

- 10% on receipt of all material at site and on submission of E1/E2 Form (wherever

applicable).

2. For supply of Mandatory Spares (wherever price of mandatory spares obtained separately)

- 90% on receipt of spares at site after dispatch of main equipment.

- 10% on receipt of materials at site and on submission of EI/E2 FORM (wherever

applicable).

3. Site Work:

- 90% against monthly progressive bills (based on agreed billing schedule) duly certified

by Engineer-in-charge.

- 10% on successful completion of site work and handing over of goods/equipment at

site.

4. Any services on per diem basis like: Supervision of Erection, Testing & Commissioning/ assistance during erection , Testing & Commissioning / Training at site / Supplier’s works on per diem basis

- 100% prorate against monthly bills to be submitted by Supplier duly certified by

Engineer-in-Charge.

5. Training (lumpsum)

- 100 % on successful completion of Training duly certified by EIL/OWNER, as per

Page 55: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 5 of 10

Annexure-I to SPC

Job No: A872

Purchase Requisition.

6. Annual Maintenance Contract (AMC):

- 100% payment shall be paid at the end of each quarter against quarterly progressive

bills to be submitted by Supplier duly certified by authorized representative of Owner.

B. FOR FOREIGN SUPPLIERS

1. Supply

1.1. Where the MR is for supply of materials and there is no Vendor Data Requirement (VDR) specified in the MR (Without Site Work):

- 15% thru wire transfer against identification of raw materials at Supplier’s works and

against submission of ABG of equivalent amount.

- 85% along with 100% Ocean freight (in case of CFR contracts) against shipping

documents through irrevocable Letter of Credit

1.2. Where the MR is for supply of materials and calls for Vendor Data Requirement: (Without site work)

- 5% against approval of drawings, wherever required (identified in PO/ PR) at least in

Code-2.

- 15% thru wire transfer against identification of raw materials at Supplier’s works and

against submission of ABG of equivalent amount

- 75% (80% in cases where drawing approval is not required) along with 100% Ocean

freight (in case of CFR contracts) against shipping documents through irrevocable

Letter of Credit.

- 5% on receipt of Final/ As built Drawings/Documents/Data/Manual in requisite number

of copies/sets/CDs as per VDR specified in Purchase Requisition through wire transfer.

1.3. Where the MR is for supply of materials and calls for Vendor Data Requirement: (With site work)

- 5% against approval of drawings, wherever required (identified in PO/ PR) at least in

Code-2.

- 15% thru wire transfer against identification of raw materials at Supplier’s works and

against submission of ABG of equivalent amount

- 65% (70% in cases where drawing approval is not required) along with 100% Ocean

freight (in case of CFR contracts) against shipping documents through irrevocable

Letter of Credit.

- 5% on receipt of Final/ As built Drawings/Documents/Data/Manual in requisite number

of copies/sets/CDs as per VDR specified in Purchase Requisition through wire transfer.

- 10% on successful completion of Site Work through wire transfer.

Note: In case Customs clearance and further transportation of material upto Project site is

in the supplier’s scope, 65% against shipping documents shall be split in 5% + 60% and

5% shall be paid after receipt of material at Project site.

Page 56: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 6 of 10

Annexure-I to SPC

Job No: A872

1.4. Where the MR is for Packages/fabricated equipments like Columns/Pressure vessels/Reactors/Heat Exchangers/Air Fin Cooler/Pumps/Compressors/EOT Cranes etc (with significant Bought out item) and calls for Supplier Data requirement: (Without site work)

- 5% against approval of drawings, wherever required (identified in PO/ PR) at least in

Code-2.

- 10% against placement of sub-order for specified major raw material (to be identified

during kick off meeting, if not specified in enquiry) and against submission of ABG of

equivalent amount.

- 15% against identification of raw materials at Supplier’s works (to be identified during

kick off meeting, if not specified in enquiry) and against submission of ABG of

equivalent amount.

- 65% along with 100% Ocean freight (in case of CFR contracts) against shipping

documents through irrevocable Letter of Credit.

- 5% on receipt of Final/As built Drawings/Documents/Data/Manual in requisite number

of copies/sets/CDs as per VDR specified in Purchase Requisition.

Major Raw Material for payment against placement of orders:

Columns/Vessels/Reactors : Plates & Forgings

Heat Exchangers : Plates, Tube, Tube sheets

Pumps : Castings for casings, impellers and drivers

Compressors : Castings for casings and rotors and drivers

Air Fin Coolers : Tubes, Header Plates, Fin Material

Major Raw Material for payment against receipt & identification of raw materials:

Columns/Vessels/Reactors : Plates & Forgings

Heat Exchangers : Plates, Tubes, Tube sheets

Pumps : Castings for casings and impellers

Compressors : Castings for casings and rotors

Air Fin Coolers : Tubes, Header Plates, Fin Material

1.5. Where the MR is for Packages/fabricated equipments like Columns/Pressure vessels/Reactors/Air Fin Cooler /EOT Cranes etc (with significant Bought out item) and calls for Vendor Data requirement: (With site work)

- 5% against approval of drawings, wherever required (identified in PO/ PR) at least in

Code-2.

- 10% against placement of sub-order for specified major raw material (to be identified

during kick off meeting, if not specified in enquiry) and against submission of ABG of

equivalent amount.

- 15% against identification of raw materials at Supplier’s works (to be identified during

kick off meeting, if not specified in enquiry) and against submission of ABG of

Page 57: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 7 of 10

Annexure-I to SPC

Job No: A872

equivalent amount.

- 55% along with 100% Ocean freight (in case of CFR contracts) against shipping

documents through irrevocable Letter of Credit.

- 5% on receipt of Final/As built Drawings/Documents/Data/Manual in requisite number

of copies/sets/CDs as per VDR specified in Purchase Requisition.

- 10% on completion of site work through wire transfer

Major Raw Material for payment against placement of orders:

Columns/Vessels/Reactors : Plates & Forgings

Heat Exchangers : Plates, Tube, Tube sheets

Pumps : Castings for casings, impellers and drivers

Compressors : Castings for casings and rotors and drivers

Air Fin Coolers : Tubes, Header Plates, Fin Material

Major Raw Material for payment against receipt & identification of raw materials:

Columns/Vessels/Reactors : Plates & Forgings

Heat Exchangers : Plates, Tubes, Tube sheets

Pumps : Castings for casings and impellers

Compressors : Castings for casings and rotors

Air Fin Coolers : Tubes, Header Plates, Fin Material

Note: In case Customs clearance and further transportation of material upto Project site is in the supplier’s scope, 55% against shipping documents shall be split in 5% + 50% and 5% shall be paid after receipt of material at Project site.

2. For supply of Mandatory Spares:

- 100% thru irrevocable Letter of Credit against shipping documents after dispatch of

main equipment.

3. Site Work:

- 90% against monthly progressive bills (based on agreed billing schedule) duly certified

by Engineer-in-charge.

- 10% on successful completion and handing over of goods/equipment at site.

Page 58: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 8 of 10

Annexure-I to SPC

Job No: A872

4. Any services on per diem basis like: Supervision of Erection, Testing & Commissioning/ assistance during erection, Testing & Commissioning / Training at:

- 100% against monthly bills to be submitted by Supplier duly certified by Engineer-in-

Charge.

5. Training (Lumpsum):

- 100% through Wire Transfer on successful completion of Training duly certified by

EIL/OWNER, as per Purchase Requisition (PR).

6. Annual Maintenance Contract (AMC):

- 100% payment shall be paid at the end of each quarter against quarterly progressive

bills to be submitted by Supplier duly certified by authorized representative of Owner.

7. Indian sub-supplies in case of a Foreign bidder:

- 85% through E-Payment with taxes and duties will be paid against receipt of Indian

sourced goods/material at project site.

- 10% against receipt of Indian supplies at site and delivery of main equipment by foreign

bidder, as per Terms of bidding document and completion of site work, wherever

applicable.

- 5% on submission of Final/As built Drawings/Documents/Data/Manual in requisite

number of copies/sets/CDs as per VDR specified in Purchase Requisition, by main

bidder.

Payment of Indian sub supplies/Services shall be released directly to Indian counterpart against Invoices raised by Indian counterpart duly certified by foreign principal.

In case of Foreign bids with Indian sub supplies, the payment terms of Foreign

bidder against shipping documents stands reduced by 5% which shall be released as follows:

o 5% payment shall be released thru wire transfer, on delivery of main equipment

by foreign principal (as per terms of enquiry document) as well as receipt of

Indian supplies at site.

C. For all Site Fabricated Columns, Vessels etc. (Fabrication yard within project site)

- 5% against approval of drawings, wherever required (identified in PO/ PR) at least in

Code-2.

- 10% against placement of sub-order for specified major raw material (Plates &

Forgings) against submission of ABG of equivalent amount. ABG shall be returned after

receipt and identification of material at Fabrication yard located within Project site.

- 25% against receipt and identification of raw materials (Plates & Forgings) at

Fabrication yard located within Project site.

- 40% on completion of fabrication in all respect, Third party inspection and making

Page 59: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 9 of 10

Annexure-I to SPC

Job No: A872

completed column ready for hydro-testing.

- 5% after hydro-testing of completed column, painting and inspection clearance for

shifting of equipment to erection site.

- 10% along with taxes & duties against submission of tax invoice and on transportation

of completed column from fabrication yard/ assembly yard to erection site, erection in

position (wherever applicable) and acceptance thereof.

- 5% on receipt of Final/As built Drawings/Documents/Data/Manual in requisite number

of copies/sets/CDs as per VDR specified in Purchase Requisition.

NOTES :

(i) 1ST Milestone payment shall be released only after receipt of CPBG (wherever

applicable) and manufacturing schedule (in template available on eDMS portal).

(ii) Prorata payments shall be applicable on dispatch of equipment. In case of equipment,

prorate shall not be on part of equipment.

(iii) In case of indigenous SUPPLIERs, wherever taxes/duties are separately indicated, the

order value shall be exclusive of taxes/duties. 100% payment of taxes/duties shall be

paid along with the payment released against dispatch documents on receipt of

Cenvatable/Duplicate Copy of Excise Invoice / vattable documents (wherever

applicable).

(iv) Payment to indigenous SUPPLIERs shall be released through Electronic Clearing

System (ECS) and to foreign SUPPLIERs, payments other than against shipping

documents, i.e., for Site Work and Supervision/Training etc. shall be through wire

transfer.

(v) Status of bills after submission can be viewed on our website

http://www.engineersindia.com .

(vi) Irrevocable Letter of credit shall be acceptable from foreign Suppliers in place of

Advance Bank Guarantee as well as Contract cum Performance Bank Guarantee.

(vii) Irrevocable Letter of Credit for payment to Foreign SUPPLIERs shall be established in

favour of the supplier in a bank in his country, for an appropriate amount (in line with

Payment Terms). L/C shall be opened within 45 days of receipt of acknowledgement

of FOA/PO and receipt of CPBG (wherever applicable). In case confirmed L/C is

insisted by supplier, L/C confirmation charges shall be to supplier’s account.

(viii) All payments (other than through L/C) shall be released within 30 days of receipt of

invoice and all requisite documents, complete in all respects.

(ix) All bank charges of respective bankers shall be to respective account.

(x) Supplier shall submit Billing Schedule within three weeks after placement of FOA/PO

(whichever is issued earlier) for EIL/OWNER’s approval (wherever applicable).

Suppliers requiring multiple despatches will restrict the number of despatches to

maximum three, unless agreed otherwise by Project Manager.

(xi) In case of Annual Maintenance Contract (AMC), CPBG @ 5% of maximum annual

AMC amount shall be submitted within 2 weeks from the date of order and shall be

valid for the entire AMC period plus 2 months claim period.

Page 60: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Page 10 of 10

Annexure-I to SPC

Job No: A872

(xii) In case of Columns/Vessels/Reactors where Template to be supplied by Supplier,

15% payment against raw material identification shall be split in 1%+14% and it shall

be specified that 1% payment out of 15% shall be paid after receipt of templates at

site. Supplier has to ensure supply of templates within two month from the approval of

drawings at least in code.

(xiii) In case C form is not issued up to 4.5 months and/or site is not available up to 6 (Six)

months (wherever site work is applicable), after receipt of all supplies at site, the

payment against the same shall be released on submission of additional Bank

Guarantee of equivalent amount valid for 1 (One) year or such extended period as

may be required.

(xiv) Certification for placement of sub-order and/or identification of major raw material, in

the above payment terms, shall be carried out by EIL/TPI agency, as applicable.

Page 61: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

EIL-A872 Page 11 of 12

ANNEXURE-II

EVALUATION CRITERIA FOR COMPARISON OF BIDS

1.1. Where only Indian Bids are under comparison

• Bids shall be evaluated on the basis of net effective price, i.e., landed cost at Site inclusive of transportation charges and all applicable Taxes/ Duties etc.

1.2. Where only Foreign Bids are under comparison

• Bids shall be evaluated on CFR basis. In case of pipes wherever the supplier has not indicated stowage charges, the FOB price shall be loaded @ 10% of the bidder’s quoted ocean freight.

• Safeguard duty as applicable as on contractual delivery date as per policy of Government of India shall be considered for evaluation. For the purpose of evaluation, the contractual delivery date shall be established considering delivery period plus (1) one month from the date of priced bid opening

• Comparison shall be done on equivalent Indian Rupees considering RBI reference rate of foreign exchange published on the day of opening of the Price Bids. In case RBI holiday on date of Priced Bid Opening, exchange rates published on immediate preceding day shall be considered.

1.3. Where Indian as well as Foreign Bids are under comparison

Domestic Bidders:

• Bids shall be evaluated on the basis of net effective price, i.e., landed cost at Site inclusive of transportation charges and all applicable Taxes/ Duties etc

Foreign Bidders:

• Bids shall be evaluated on the basis of landed cost at Site, considering the following.

a) F.O.B./FCA price quoted by the bidder

b) Ocean/Air freight as quoted by the bidder

c) Marine insurance @ 1% of FOB Value

d) Prevailing merit rate of Customs duty calculated with Landing Charges @1 %

of CIF Value

e) Port handling charges @ 2% of CIF value

f) Inland freight charges from Port of entry in India to project site(s) @ 1% of

landed cost at Port of Entry,i.e., sl.no.(a)to(e)

g) In case of pipes, where the supplier has not indicated stowage charges, the

price shall be loaded @10% of the bidder’s quoted ocean freight.

h) LC charges@1%ofFOB

i) Safeguard duty as applicable

j) Entry Tax & Octroi (presently applicable @ 1%)

• Comparison shall be done on equivalent Indian Rupees considering RBI reference rate of foreign exchange published on the day of opening of the Price Bids. In case RBI holiday on date of Priced Bid Opening, exchange rates published on immediate preceding day shall be considered.

1.4. Cost of Mandatory (Insurance) spares if identified in the Material Requisition, commissioning spares and special tools and tackles will be included for price evaluation of bids, but costs of Spares for two years normal operation and maintenance shall be

Page 62: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

EIL-A872 Page 12 of 12

excluded.

1.5. For Indian bidders, Entry Tax/ Octroi (presently applicable @ 1%) shall be considered for evaluation of prices.

1.6. Bidder (Indian/Foreign) shall quote firm freight charges as per price schedule format/ Agreed Terms & Condition. If a vendor does not quote freight charges bidder shall be asked to absorb the same without any reservation failing which his bid shall be rejected

1.7. Wherever the bidder is required to quote any specific charges as per the scope of Material Requisition including charges towards site work, supervision charges, PWAMC charges, charges towards custom clearance and any other charges, the same shall be added to arrive at the landed cost at site as per the provisions of RFQ document .

1.8. Per Diem rates for supervision, Hazop, Training services etc.:

a) If a vendor does not mention any thing about per diem charges and have not quoted per Diem charges for any of the services, bidder shall be asked to absorb the same (for total number of days for which the services considered for evaluation) without any reservation failing which his bid shall be rejected.

b) In such a case, since the per diem services may increase beyond the number of days specified in the enquiry document, lowest quoted per diem charges (for respective services) by other bidders (Prices quoted by other Indian bidder for order on Indian bidder and prices quoted by other Foreign bidder in case of order on Foreign bidder) shall be taken for negotiation with the bidder, which shall be applicable beyond number of days specified in the enquiry document.

1.9. Any differential in taxes and duties will be cost loaded on case to case basis. However, if a vendor does not quote for taxes and duties in their offer or the vendor states that taxes/duties are not applicable at present and will be charged as applicable at the time of delivery, then his bid shall be loaded by the maximum rate of taxes/duties applicable as on the date of Priced bid opening.

1.10. Cost of loading towards Technical Parameters (Utilities etc.) wherever applicable shall be carried out.

1.11. Cenvat /input tax credit on customs duty (CVD/ Additional CVD) / service tax / VAT / Excise Duty and education cess is not available to BPCL, accordingly, the credit on account of the same shall not be considered for evaluation.

Page 63: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Annexure-A to SPC

TRC obtained by the Non-resident from Government of foreign country shall contain the following particulars:

(i) Name of the assessee;

(ii) Status (individual, company, firm etc.) of the assessee;

(iii) Nationality (in case of individual);

(iv) Country or specified territory of incorporation or registration (in case of others);

(v) Assessee’s tax identification number in the country or specified territory of residence or in case no such number, then, a unique number on the basis of which the person is identified by the Government of the country or the specified territory;

(vi) Residential status for the purposes of tax;

(vii) Period for which the certificate is applicable; and

(viii) Address of the applicant for the period for which the certificate is applicable;

Page 64: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Annexure- B to SPC

"FORM NO. 10F

[See sub-rule (1) of rule 21AB]

Information to be provided under sub-section (5) of section 90 or sub-section (5)

of section 90A of the Income-tax Act, 1961

I ................... *son/daughter of Shri ................... in the capacity of ..................

(designation) do provide the following information, relevant to the previous year

................... *in my case / in the case of................... for the purposes of sub-section (5)

of * section 90/section 90A:-

Sl. No. Nature of information : Details#

(i) Status (individual; company, firm etc.)

of the assessee

:

(ii) Permanent Account Number (PAN) of

the assessee if allotted

:

(iii) Nationality (in the case of an

individual) or Country or specified

territory of incorporation or registration

(in the case of others)

:

(iv) Assessee's tax identification number in

the country or specified territory of

residence and if there is no such

number, then, a unique number on the

basis of which the person is identified

by the Government of the country or

the specified territory of which the

assessee claims to be a resident

:

(v) Period for which the residential status

as mentioned in the certificate referred

to in sub-section (4) of section 90 or

sub-section (4) of section 90A is

applicable

:

(vi) Address of the assessee in the country

or territory outside India during the

period for which the certificate,

mentioned in (v) above, is applicable

:

Page 65: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

2. I have obtained a certificate to in sub-section (4) of section 90 of sub-section (4) of

section 90A from the Government of................... (name of country or specified territory

outside India).

Signature:...................

Name:...................

Address:...................

Permanent Account Number:...................

Verification

I................... do hereby declare that to the best of my knowledge and belief what is

stated above is correct complete and is truly stated.

Verified today the................... day of....................

...................

Signature of the person providing the information

Place:...................

Notes :

1. *Delete whichever is not applicable.

2. #Write N.A. if the relevant information forms part of the certificate referred to in sub-

section (4) of section 90 or sub-section (4) of section 90A."

Page 66: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED
Page 67: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED
Page 68: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED
Page 69: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED
Page 70: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED
Page 71: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED
Page 72: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

EIL-ATC (I)-A872 Rev. 0 Page 1 of 8

BHARAT PETROLEUM CORPORATION LIMITED (Job No. A872)

AGREED TERMS & CONDITIONS (ATC) (FOR INDIAN BIDDERS)

Vendor Name: M/s ______________________________________________________________

RFQ No. : __________________________________________________________________

Vendor’s Offer Ref No. : ___________________________________________________________

Tel. No. ___________________Mob. No. ______________________ Fax No. ________________

Contact Person: ___________________________ E-mail _________________________________

1. ALL CORRESPONDENCE MUST BE IN ENGLISH LANGUAGE ONLY. 2. DULY SIGNED & STAMPED COPIES OF THIS “QUESTIONNAIRE”, WITH ALL THE

CLAUSES DULY CONFIRMED/ PRECISELY REPLIED TO BY THE VENDOR, SHALL BE ENCLOSED.

3. ALL COMMERCIAL TERMS ARE GIVEN/CONFIRMED IN THE QUESTIONNAIRE ITSELF

AND NOT ELSEWHERE IN THE QUOTATION. IN CASE OF CONTRADICTION, THE SAME GIVEN HEREIN SHALL PREVAIL.

4. FAILURE ON THE PART OF VENDOR IN SUBMITTING THIS DULY FILLED-UP "QUESTIONNAIRE WITH UNPRICED BID AND/OR UPLOADING / SUBMITTING INCOMPLETE REPLIES MAY LEAD TO REJECTION OF VENDOR'S QUOTATION”.

5. YOUR OFFER SHALL BE IN TOTAL COMPLIANCE WITH RFQ DOCUMENTS

CONTAINING COMMERCIAL AND TECHNICAL SPECIFICATIONS INCLUDING GENERAL / TECHNICAL NOTES AND SCOPE OF SUPPLY INCLUDING DOCUMENTATION AS PER MATERIAL REQUISITION (MR) AND SUBSEQUENT TECHNICAL/COMMERCIAL AMENDMENT AND TECHNICAL/COMMERCIAL CORRIGENDUM, IF ANY.

SL. NO.

DESCRIPTION VENDOR’S CONFIRMATION

1. i) Quoted supply prices are on FOT Dispatch Point basis inclusive of Packing & Forwarding.

Confirmed

ii) Specify Dispatch Point

----------------------- iii) a) b)

c)

Confirm that Transportation upto site shall be arranged by the Supplier on behalf of the Owner. Confirm firm transportation charges exclusive of Service Tax, upto project site, have been quoted separately in Price Schedule. Percentage of Service Tax as applicable extra on Freight

a. Confirmed

b. Confirmed, Quoted in Price Schedule

c. Refer Annexure-A to ATC

iv) Transit Insurance shall be arranged by the client & charges of the same shall also be borne by client.

For LSTK Packages, the comprehensive insurance (transit cum storage, erection, till handing over of equipment) shall be in the scope of Contractor.

Confirmed

v) Owner shall pay Entry Tax, wherever applicable.

Noted

Page 73: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

EIL-ATC (I)-A872 Rev. 0 Page 2 of 8

SL. NO.

DESCRIPTION VENDOR’S CONFIRMATION

2. a. b. c. d.

Excise Duty applicable extra in percentage. Excise Tariff sub heading no. Any variations in ED at the time of supplies for any reasons including variation due to turn-over shall be borne by the Seller. Only statutory variations shall be borne by Purchaser.

If Excise Duty is not applicable at present due to any reason, the same shall be borne by vendor if it becomes applicable later.

a. Refer Annexure-A to ATC

b. _____________

c. Confirmed

d. Confirmed

2.1 a. b.

Confirm Excise Duty will not be applicable on transportation charges.

If Excise Duty is not applicable on transportation charges presently, and if it becomes applicable at the time of delivery due to any reasons other than statutory, the same will be borne by the Vendor. Confirm acceptance.

a. Confirmed

b. Confirmed

3. a.

b. c. d. e.

Central Sales Tax applicable extra in percentage against Form ‘C’

VAT applicable extra:

If CST / VAT is not applicable at present due to any reason, the same shall be borne by vendor if it becomes applicable later.

Confirm CST/ VAT will not be applicable on transportation charges.

If CST / VAT is not applicable on transportation charges presently, and if it becomes applicable at the time of delivery due to any reasons other than statutory, the same will be borne by the Vendor. Confirm acceptance.

a. Refer Annexure-A to ATC

b. Refer Annexure-A to ATC

c. Confirmed

d. Confirmed

e. Confirmed

4. Any new or additional taxes/ duties and any increase in the existing taxes/duties imposed after contractual completion period shall be to Vendor’s account whereas any corresponding decrease in the existing taxes/ duties shall be passed on to the Owner.

Confirmed

5

Spares Parts:

Confirm item wise unit price (FOT Despatch Point) of following spare parts as required in Material Requisition (MR) have been included indicating itemised quantity.

i) Mandatory Spares are included/quoted as per MR. ii) Commissioning spares as specified in MR are included in

the quoted Price.

iii) Special Tools & Tackles as specified in the MR are included in the quoted prices.

iv) Confirm spares wherever required as per MR have been included in the quoted price and list of spares is also furnished. v) Confirm validity of recommended spares (if applicable as per MR) for 2 years operation and maintenance will be 12 months over and above the validity of offer.

Confirmed

Confirmed (if Applicable as per MR)

Confirmed (if Applicable as per MR)

Confirmed (if Applicable as per MR)

Confirmed (if Applicable as per MR)

Confirmed (if Applicable as per MR)

Page 74: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

EIL-ATC (I)-A872 Rev. 0 Page 3 of 8

SL. NO.

DESCRIPTION VENDOR’S CONFIRMATION

6.

a.

b.

c.

Site Work: For Site Work, if in the scope of the Bidder as per MR, please confirm the following:

Confirm that quoted site work prices are exclusive of Service Tax on value of services inclusive of all other applicable taxes & duties including Work Contract Tax.

Confirm that value of services and full rate of Service Tax as applicable extra have been quoted in Price Schedule.

Work Contract Tax (WB WCT) as per WB VAT Act, as applicable, shall be deducted at source and WCT certificate shall be issued to the Bidder.

a. Confirmed

b. Confirmed, Quoted in Price Schedule

c. Noted

7.

a.

b.

c.

d.

e.

Supervision / Participation in Hazop Study / #D Modelling/Training Charges: Charges for Supervision / Participation in Hazop Study / Training/ 3D Modeling, if in the scope of the Bidder as per MR have been indicated by bidder separately in the Price Schedule. Percentage of Service Tax & Edu. Cess as applicable extra on Supervision / Participation in Hazop Study/ Training/ 3D Modelling. Rate for supervision has been quoted in accordance with the Terms & Conditions for Supervision enclosed with the RFQ Documents. Where erection/ testing/ commissioning supervision, commissioning assistance is required as per RFQ Documents / Material requisition, penalty for non mobilization/delay in mobilization as per order shall be applicable. The penalty shall generally be 1.5 times the per diem rate for each day of delay of reporting to site and shall be in addition to price reduction for delayed delivery. Bidders shall also provide additional BG of an amount equal to the per diem charges for the number of days considered for evaluation, over and above 10% CPBG to cover compensation for delay in mobilizing the erection/ commissioning personnel. This BG will be released to the bidder upon the erection/ commissioning personnel reporting at site. This BG shall be furnished along with payment milestone for submission of final documentation as per MR and shall be initially valid up to six months which shall be extended based on the request by Owner.

Confirmed, Quoted in Price

Schedule

----------------%

Confirmed

Noted & Confirmed

Noted & Confirmed

8. Confirm documentation charges as per MR are included in quoted prices.

Confirmed

Page 75: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

EIL-ATC (I)-A872 Rev. 0 Page 4 of 8

SL. NO.

DESCRIPTION VENDOR’S CONFIRMATION

9. Price Reduction for delay in completion/ delivery: a) Confirm acceptance of price reduction schedule for delay in

deliveries / completion as specified in GPC/ SPC/ RFQ Cover sheet. Liquidated damages or penalty are not acceptable.

b) In case of delay, vendor will reduce the invoice amount by

applicable reduction.

a. Confirmed

b. Confirmed

10. Delivery / Completion Period: Please confirm completion period as specified in the RFQ document

Confirmed

11.

Payment Term: Confirm acceptance of “Payment Terms” as per respective clause given in RFQ Cover Letter & SPC.

Confirmed

12. a. b.

Part Order: Confirmed acceptance to Part Order (As per MR / RFQ Requirement). The quantities against a particular item will not be split. Any charges quoted extra as lumpsum shall be applicable prorata on value basis in the event of part order.

a. Confirmed.

b. Confirmed

13. Repeat Order: Confirm Acceptance to Repeat Order as per RFQ Covering Letter / SPC / GPC.

Confirmed

14.

Contract Performance Bank Guarantee: a) In the event of award of order, submission of Contract

Performance Bank Guarantee (CPBG) for 10% of total contract value valid till full guarantee period plus three months claim period.

b) The Contract Performance Bank Guarantee shall be

strictly as per proforma enclosed with GPC document.

a. Confirmed

b. Confirmed

15. Guarantee / Warranty Confirm acceptance to Guarantee / Warranty clause as mentioned in the RFQ Covering Letter / GPC/ SPC.

Confirmed

16. Firmness of prices: Confirm quoted prices shall remain firm and fixed till complete execution of order. Price Variation shall not be considered on any account.

Confirmed

Page 76: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

EIL-ATC (I)-A872 Rev. 0 Page 5 of 8

SL. NO.

DESCRIPTION VENDOR’S CONFIRMATION

17. a. b. c. d.

Testing and Inspection charges: i) Inspection of items / equipment order by BPCL shall be

carried out by EIL. Bought out components/raw materials shall also be in the scope of EIL. Travel, Boarding & Lodging charges of EIL personnel shall be borne and paid by Owner.

Quoted prices are: i) Inclusive of all testing and inspection charges (if applicable)

as per MR. ii) Inclusive of all IBR/IGC/NACE charges (if applicable) as

required in the Material Requisition. iii) Inclusive of all statutory certification charges PESO/CCOE

etc. (if applicable) as required in the Material Requisition Is your shop approved by IBR/CCE authority, if yes, indicate validity. Inspection for Bought-out Items as well as for the main equipment shall be done by EIL. Prices Towards same shall be borne by Owner and not to be included in the Equipment Prices.

a. Confirmed

b. Confirmed

i) Confirmed

ii) Confirmed

c. i. IBR__________(Validity Date) ii. CCE_________(Validity Date)

d. Confirmed

18. a. b. c. d. e. f. g. h. i.

Import Content: If your offer is based on certain imported raw materials required for equipments/ materials offered, please specify the following : Confirm that quoted prices are based on Merit rate of Customs duty, CVD, Customs Educational Cess and SAD as applicable. Indicate rate of Import Duties considered and included in the quoted prices. Indicate brief description/ specification with itemised CIF value and country of origin of imported material. Indicate classification with tariff no. under which Vendor intends to import. Confirm prices shall be firm on account of variation in foreign exchange rate. Owner shall not provide any import license. Quoted prices are after considering the benefit of CENVAT on CVD including Edu. Cess. In case material is sold/consigned directly to Client from port quoted prices are excluding CENVAT benefit. In case material is directly dispatched from port, CVD amount shall be reimbursed subject to submission of bill of entry documents along with CVD invoice. Any upward variation due to change in Customs Duty classifications shall be absorbed by the vendor. However, any reduction in customs duty due to change in classification shall be passed on to Owner.

a. Confirmed

b. Refer Price Schedule

c. Refer Price Schedule

d. Refer Price Schedule

e. Confirmed

f. Noted

g. Confirmed

h. Confirmed i. Confirmed

Page 77: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

EIL-ATC (I)-A872 Rev. 0 Page 6 of 8

SL. NO.

DESCRIPTION VENDOR’S CONFIRMATION

j. k.

Statutory variations, if any, in the rate of Import Duties upto 2/3rd contractual delivery period shall be to Owner’s account. Any increase in price due to increase in the rate of Import Duties, due to any reasons, whatsoever, beyond the 2/3 rd contractual delivery period, shall be to vendor's account. However, any decrease in Import Duties rate at the time of actual clearance of imported materials shall be passed on to Owner.

j. Confirmed

k. Confirmed

l. m.

The CIF Value(s) indicated by the vendor shall be deemed to be the maximum value(s) for the purpose of payment of variation in custom duty and/or other statutory variations, if any, thereon. Variation in price due to Customs duty rate will be dealt separately after receipt of material at site, against documentary evidence.

l. Confirmed

m. Confirmed

19. a) b)

c)

Confirm your offer is in total compliance with RFQ Document containing technical specifications including General / Technical notes, scope of supply including documentation as per Material Requisition (MR) and subsequent amendment and corrigendum, if any. Confirm your offer is in total compliance with RFQ documentation containing commercial terms and conditions as per the following documents, without any deviation: i) Instruction to Bidders (ITB) ii) Special Purchase Condition (SPC) iii) General Purchase Conditions (GPC) iv) Terms & Conditions of Site work / HSE v) Compliance to E-Tendering Instructions vi) Addendum / Corrigendum / Amendments, if any vii) RFQ Covering Letter viii) Terms & Condition of Supervision/ Training Any deviation to Terms & Conditions shall lead to rejection of offer, except deviations for which loading is defined in the RFQ Documents.

Confirmed

Confirmed

Confirmed

Confirmed

Confirmed (if Applicable as per MR)

Confirmed Confirmed Confirmed

Confirmed (if Applicable as per MR) Noted

20. Whether any of the Directors of Bidder is a relative of any Director of Owner/EIL or the Bidder is a firm in which any Director of Owner/EIL or his relative is a Partner or the Bidder is a private company in which any director of Owner/EIL is a member or Director.

Confirmed No relation

21. If the bidder / bidder’s proposed subcontractor are on Holiday/Negative list of OWNER or EIL or MOP & NG or other Oil PSE on due date of submission of bid/ during the process of evaluation of the bids, the offers of such bidder(s) shall not be considered for bid opening/evaluation/Award. If the bidding document were issued inadvertently/ downloaded from website, offers submitted by such bidders shall also be not considered for bid opening/evaluation/Award

Confirmed

Page 78: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

EIL-ATC (I)-A872 Rev. 0 Page 7 of 8

SL. NO.

DESCRIPTION VENDOR’S CONFIRMATION

22. 22.1 22.2

Please confirm you have uploaded the following in the E-Tendering Portal: UNPRICED OFFER- without any Deviations & ATC in Unpriced Folder PRICED FOLDER-Duly filled Price Schedule

Confirmed

Confirmed

23. Please confirm that you have quoted strictly for items based on your registration/approval with EIL as on date of issue of RFQ.

Confirmed

24. Any claim arising out of order shall be sent to Owner in writing with a copy to EIL within 3 months from the date of last despatch. In case the claim is received after 3 months, the same shall not be entertained by Consultant/ Owner.

Confirmed

25. Printed terms and conditions, if any, appearing in quotation, shall not be applicable in the event of order. In case of contradiction between the confirmations given above and terms & conditions mentioned elsewhere in the offer, the confirmation given/confirmed herein above shall prevail.

Confirmed

26. Confirm that Net worth of the bidder’ company is positive as per the immediate preceding year’s audited annual financial results and the Immediate preceding year’s audited annual financial results have been submitted along with unpriced bid.

Confirmed

27. Bidder to confirm the validity of Bid as per RFQ covering letter.

Confirmed

VENDOR’S NAME:

SIGNATURE & SEAL:

Page 79: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

EIL-ATC (I)-A872 Rev. 0 Page 8 of 8

ANNEXURE-A TO AGREED TERMS & CONDITIONS (FOR INDIAN BIDDERS)

BIDDER NAME:

OFFER NO.:

Bidder to furnish the below details & submit the same along with Unprice offer.

1. Despatch Point ----------------------------------

2. Freight charges Extra Upto Project Site (excluding Service Tax) (Bidder to indicate freight charges here only in case not quoted in Price Schedule)

Extra------------------------ %

3. Service tax on Freight charges Extra------------------------ %

4. Swachh Bharat Cess applicable Freight Extra------------------------ %

5. Krishi Kalyan Cess (KKC) on Freight Extra------------------------ %

6. Excise Duty on Freight charges (in case no option is selected, ED on freight shall be considered as Not Applicable)

Applicable

Not Applicable

7. CST/ VAT on Freight charges (in case no option is selected, ED on freight shall be considered as Not Applicable)

Applicable

Not Applicable

8. Excise Tariff Sub Heading No. ----------------------------------

9. Excise Duty Extra------------------------ %

10. Central Sales Tax against Form 'C' Extra------------------------ %

11. MP VAT Extra------------------------ %

12. Service Tax on Site Work/Supervision/participation in HAZOP Study/Training/3D Modelling, if applicable Extra------------------------ %

13. Swachh Bharat Cess on Site Work/Supervision/participation in HAZOP Study/Training/3D Modelling, if applicable Extra------------------------ %

14. Krishi Kalyan Cess (KKC) on Freight on Site Work/Supervision/participation in HAZOP Study/Training/3D Modelling, if applicable Extra------------------------ %

Note: In case bidder doesn’t furnish any of above details, his offer shall be evaluated as per provisions of Bidding Document.

SIGNATURE & SEAL:

Page 80: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Client: BPCL Proposal Form LPG IMPORT TERMINAL FACILITIES PROJECT AT HALDIA Job Number: A872 Sheet 1 of 5

PROPOSAL FORM F-1

FINANCIAL DETAILS

The Bidder shall indicate herein his annual turnover during immediately preceding 3 financial years based on the audited balance sheet/profit & loss account statement.

FINANCIAL YEAR

ANNUAL TURNOVER

(Indicate Currency)

NET WORTH

(Indicate Currency)

WORKING CAPITAL

(Indicate Currency)

NOTE:

1. Authenticated copies of audited financial statement for immediately preceding 3 financial years are enclosed along with the Bid.

SIGNATURE OF BIDDER : _______________________ NAME OF BIDDER : _______________________ COMPANY SEAL : _______________________

FO

Page 81: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Client: BPCL Proposal Form LPG IMPORT TERMINAL FACILITIES PROJECT AT HALDIA Job Number: A872 Sheet 2 of 5

RM-D

PROPOSAL FORM F-2

COMPLIANCE TO BID REQUIREMENT

ITEM: ________________________________________________ BIDDING DOCUMENT NO.: ___________________________________ We M/s ___________________________________hereby agree to fully comply with, abide by and accept without variation, deviation or reservation all technical, commercial and other conditions whatsoever of the Bidding Documents and Addendum/Amendment/ Corrigendum to the Bidding Documents, if any, for subject work issued by Engineers India Limited.

We hereby further confirm that any terms and conditions if mentioned in our bid (Un-priced as well as Priced Part), shall not be recognised and shall be treated as null and void. SIGNATURE OF BIDDER : _______________________ NAME OF BIDDER : _______________________ COMPANY SEAL : _______________________

Page 82: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Client: BPCL Proposal Form LPG IMPORT TERMINAL FACILITIES PROJECT AT HALDIA Job Number: A872 Sheet 3 of 5

PROPOSAL FORM F-3

Agreed Terms and Conditions (as applicable)- Attached

Page 83: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Client: BPCL Proposal Form LPG IMPORT TERMINAL FACILITIES PROJECT AT HALDIA Job Number: A872 Sheet 4 of 5

PROPOSAL FORM F-4

ITEM: ________________________________________________ BIDDING DOCUMENT NO.: ___________________________________ We confirm that we are not under any liquidation, court receivership or similar proceedings. (_____________________________)

Signatures of the authorised Person) NAME : ________________________ DESIGNATION: __________________ STAMP OF THE BIDDER:

Page 84: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Client: BPCL Proposal Form LPG IMPORT TERMINAL FACILITIES PROJECT AT HALDIA Job Number: A872 Sheet 5 of 5

PROPOSAL FORM F-5

ITEM: ________________________________________________ BIDDING DOCUMENT NO.: ___________________________________ We confirm that we are not under Holiday/Negative/suspension/banning list of OWNER or EIL or MOP & NG or other oil PSE. (_____________________________)

Signatures of the authorised Person) NAME : ________________________ DESIGNATION: __________________ STAMP OF THE BIDDER:

Page 85: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

GENERAL CONDITIONS OF CONTRACT (GCC)

BHARAT PETROLEUM CORPORATION LIMITED

APRIL 2016

Page 86: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

INDEX

SECTION / DETAILS PAGE NO. CLAUSE

I DEFINITION OF TERMS 3 II GENERAL INFORMATION ABOUT SITE 4 2.1 LOCATION OF SITE & ACCESSIBILITY 4 2.2 SCOPE OF WORK 4 2.3 WATER SUPPLY, POWER SUPPLY AND OWNER’S LAND FOR CONTRACTOR’S FIELD, GODOWN AND 4

WORKSHOP

2.4 SAFETY STANDARDS FOR TEMPORARY BUILDINGS 4 III GENERAL INSTRUCTION FOR THE TENDERER 5 3 SUBMISSION OF TENDER 5 4 DOCUMENTS 5 5 PURCHASE PREFERENCE 6 6(a) EARNEST MONEY 6 6(b) CONVERSION OF EMD TO SECURITY DEPOSIT 6 7 TENDER VALIDITY 6 7 A FIRMNESS OF QUOTE 6 7 B LANGUAGE OF BID 6 7 C CURRENCIES OF BID & PAYMENT 7 8 ADDENDA / CORRIGENDA 7 9 RIGHT OF OWNER TO ACCEPT OR REJECT TENDER 7 10 A INTEGRITY PACT (IP) 7 10 B HOLIDAY LISTING 7 10 C CONSULTANCY CONTRACTS 7 10 D FOREIGN BIDDERS 8 11 COLLECTION OF DATA TENDERER’S RESPONSIBILITY 8 12 TIME SCHEDULE 8 13 SIGNING OF THE CONTRACT 8 14 A FIELD MANAGEMENT 8 14B RETIRED GOVERNMENT OR COMPANY OFFICER 8 IV INTERPRETATION OF CONTRACT DOCUMENTS 9 15 INTERPRETATION OF CONTRACT DOCUMENT 9 16 SPECIAL CONDITIONS OF CONTRACT 9 17 CONTRACTOR TO OBTAIN HIS OWN INFORMATION 9 18 SECURITY DEPOSIT TOWARDS PERFORMANCE/RETENTION MONEY 10 19 TIME OF PERFORMANCE 10 20 FORCE MAJEURE 11 21 EXTENSION OF TIME 11 22 LIQUIDATED DAMAGES FOR DELAY 11 23 SUM PAYABLE BY WAY OF COMPENSATION TO BE CONSIDERED AS REASONABLE COMPENSATION 11

WITHOUT REFERENCE TO ACTUAL LOSS

24 TERMINATION / OFFLOADING 11 25 FORFEITURE OF SECURITY DEPOSIT 11 26 ACTION WHEN WHOLE OF SECURITY DEPOSIT IS FORFEITED 12 27 CONTRACTOR REMAINS LIABLE TO PAY COMPENSATION IF ACTION NOT TAKEN UNDER CLAUSE 26 12 28 NO COMPENSATION FOR ALTERATION IN OR RESTRICTION OF WO9RK 12 29 CHANGES IN CONSTITUTION OF THE CONTRACTOR 13 30 IF THE CONTRACTOR DIES 13 31 EMPLOYEES OF THE OWNER NOT INDIVIDUALLY LIABLE 13 32 OWNER NOT BOUND BY PERSONAL REPRESENTATIONS 13 33 CONTRACTOR’S OFFICE AT SITE 13 34 CONTRACTOR’S SUBORDINATE STAFF AND THEIR CONDUCTS 13 35 SUB-LETTING OF WORK 14 36 POWER OF ENTRY 14 37 CONTRACTOR’S RESPONSIBILITY WITH OTHER AGENCIES 14 38 OTHER AGENTS AT SITE 15 39 NOTICES 15 40 RIGHTS OF VARIOUS INTERESTS 15 41 RIGHT OF OWNER TO DETERMINE / TERMINATE CONTRACT 15 42 PATENTS AND ROYALTIES 15 43 LIENS 16 44 OPERATION OF CONTRACT 16 V PERFORMANCE OF WORK 17

1

Page 87: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

45 EXECUTION OF WORKS 17 46 COORDINATION AND INSPECTION OF WORK 17 47 WORK IN MONSOON AND DEWATERING 17 48 WORK ON SUNDAYS AND HOLIDAYS 17 49 GENERAL CONDITIONS FOR CONSTRUCTION AND ERECTION WORK 17 50 DRAWINGS TO BE SUPPLIED BY THE OWNER 18 51 DRAWINGS TO BE SUPPLIED BY THE CONTRACTOR 18 52 SETTING OUT WORKS 18 53 RESPONSIBILITY FOR LEVEL AND ALIGNMENT 18 54 MATERIALS TO BE SUPPLIED BY CONTRACTOR 18 55 MATERIALS SUPPLIED BY OWNER 19 56 CONDITIONS FOR ISSUE OF MATERIALS 19 57 MATERIALS PROCURED WITH ASSISTANCE OF OWNER 20 58 MATERIALS OBTAINED FROM DISMANTLING 20 59 ARTICLES OF VALUE FOUND 20 60 DISCREPANCIES BETWEEN INSTRUCTIONS 20 61 ALTERATIONS IN SPECIFICATIONS AND DESIGNS AND EXTRA WORK 20 62 ACTION WHERE NO SPECIFICATIONS ISSUED 21 63 ABNORMAL RATES 21 64 INSPECTION OF WORK 21 65 ASSISTANCE TO THE ENGINEERS 21 66 TESTS FOR QUALITY OF WORKS 21 67 SAMPLES 22 68 ACTION AND COMPENSATION IN CASE OF BAD WORK 22 69 SUSPENSION OF WORKS 22 70 OWNER MAY DO PART OF WORK 22 71 POSSESSION PRIOR TO COMPLETION 22 72 PERIOD OF LIABILITY FROM THE DATE OF COMPLETION OF WORK 22 VI BILLS / MEASUREMENT / PAYMENT 25 73 SCHEDULE OF RATES AND PAYMENTS 25 74 PROCEDURE FOR MEASUREMENT / BILLING OF WORK IN PROGRESS 26 75 LUMPSUMS IN TENDER 26 76 RUNNING ACCOUNT PAYMENTS TO BE REGARDED AS ADVANCES 26 77 EXTRA WORK 26 78 PAYMENT OF CONTRACTOR’S BILL 26 79 MODE OF PAYMENT 27 80 COMPLETION CERTIFICATE 27 81 FINAL DECISION AND FINAL CERTIFICATE 27 82 CERTIFICATE FOR PAYMENTS AND EVIDENCE OF COMPLETION 28 VII TAXES / DUTIES / INSURANCE 29 83 TAXES, DUTIES, OCTROI, ETC. 29 84 INSURANCE 29 85 DAMAGE TO PROPERTY 30 VIII LABOUR LAWS AND OTHER REGULATIONS 31 86 LABOUR LAWS 31 87 IMPLEMENTATION OF APPRENTICES ACT, 1961 31 88 CONTRACTOR TO INDEMNIFY THE OWNER 31 89 A HEALTH AND SANITARY ARRANGEMENTS FOR WORKERS 32 89 B MEDICAL FITNESS CERTIFICATION 32 90 SAFETY REGULATIONS 32 91 A ARBITRATION 32 92 JURISDICTION 33 IX VARIOUS PROFORMA

ANNEXURE 1 PROFORMA OF AGREEMENT 34

ANNEXURE 2 PROFORMA OF BANK GUARANTEE FOR EARNEST MONEY /INITIAL / FULL SECURITY DEPOSIT 36 ANNEXURE 3 PROFORMA OF BANK GUARANTEE FOR MOBILIZATION ADVANCE 38 ANNEXURE 4 PROFORMA OF BANK GUARANTEE TOWARDS ADVANCE 40 ANNEXURE 5 PROFORMA FOR TAX RESIDENCY CERTIFICATE FOR FOREIGN BIDDERS 41 ANNEXURE 6 FORM 10 F 42 ANNEXURE 7 INTEGRITY PACT 43

ACKNOWLEDGEMENT 47

2

Page 88: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

GENERAL CONDITIONS OF CONTRACT

SECTION - I DEFINITION OF TERMS

In the contract documents as herein defined where the context so admits, the following words and expressions will have following meanings : 1) “The Owner/Company/BPCL” means the Bharat Petroleum Corporation Limited, incorporated in India having its

registered office at 4 & 6, Currimbhoy Road, Ballard Estate, Mumbai - 400 038 or their successors or assigns 2) “The Contractor” means the person or the persons, firm or Company whose tender has been accepted by the

Owner and includes the Contractor’s legal representative, his successor and permitted assigns. 3) The “Managing Director” shall mean the Chairman and Managing Director of the Bharat Petroleum Corporation

Limited or his successor in office designated by the Owner. 4) The “Engineer-in-Charge” shall mean the person designated as such by the Owner and shall include those who are

expressly authorised by the Owner to act for and on his behalf for operation of this contract. 5) The “Work” shall mean the works to be executed in accordance with the contract or part thereof as the case may be

and shall include extra, additional, altered or substituted works as required for purpose of the contract. 6) The “Permanent Work” means and includes works which will be incorporated in and form a part of the work to be

handed over to the Owner by the Contractor on completion of the contract. 7) The “Construction Equipment” means all appliances, Tools/Tackles and equipment of whatsoever nature for the

use in or for the execution, completion, operation or maintenance of the work unless intended to form part of the Permanent work.

8) The “Site” means the areas on which the permanent works are to be executed or carried out and any other places provided by the Owner for purpose of the contract.

9) The “Contract Document” means collectively the Tender Document. Designs. Drawings or Specifications, agreed variations, if any, and such other document constituting the tender and acceptance thereof.

10) The “Consultant” means the consulting engineers Nominated/appointed by the Owner for this Project / job. 11) The “Sub-Contractor” means any person or firm or Company (other than the Contractor) to whom any part of the

work has been entrusted by the Contractor, with the written consent of the Engineer-in-Charge, and the legal personal representatives, successors and permitted assigns of such person, firm or company.

12) The “Contract” shall mean the Agreement between the Owner and the Contractor for the execution of the works including therein all contract documents.

13) The “Specification” shall mean the various technical specifications attached and referred to in the tender documents. It shall also include the latest editions, including all addenda/corrigenda, of relevant Indian Standard Specification, specifications of the other country published before entering into Contract.

14) The “Drawings” shall include maps, plans and tracings or prints thereof with any modifications approved in writing by the Engineer-in-Charge and such other drawings as may, from time to time, furnished or approved in writing by the Engineer-in-Charge.

15) The “Tender” means the tender submitted by the Contractor for acceptance by the Owner. 16) The “Alteration Order” means an order given in writing by the Engineer-in-Charge to effect additions to or deletion

from and alterations in the works. 17) The “Completion Certificate” shall mean the certificate to be issued by the Engineer-in-Charge to the contractor

when the works have been completed to his satisfaction. 18) The “Final Certificate” in relation to a work means the certificate issued by the Engineer-in-Charge after the period

of liability is over for releasing the retention money/PBG. 19) The “Period of Liability” in relation to a work means the specified period during which the Contractor stands

responsible for rectifying all defects that may appear in the works.

3

Page 89: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

SECTION - II GENERAL INFORMATION ABOUT SITE

2.1 LOCATION OF SITE & ACCESSIBILITY:

The site location is described in the Special Conditions of Contract which may be within the premises of existing Refinery. The intending tenderer should inspect the site and make himself familiar with site conditions and available facilities.

Entry into the BPCL areas is restricted depending on location/site. Only pass holders as also vehicles with special permits are permitted in such restricted areas. Inside the premises access to various work spots is also further regulated by permits issued for each area.

Non-availability of access roads or permits for entry of vehicles/equipment to any specific area shall in no case be the cause to condone any delay in execution of works or be the cause for any claims or extra compensations.

2.2 SCOPE OF WORK

The scope of work is defined in the Special Conditions of Contract and specifications. The Contractor shall provide all necessary materials, equipments / Tools and Tackles / Supervision / labour etc. for the execution and maintenance of the work till completion unless otherwise mentioned in these tender documents. All materials that go with the work shall be approved by Engineer-in-Charge prior to procurement and use.

2.3 WATER SUPPLY, POWER SUPPLY AND OWNER’S LAND FOR CONTRACTOR’S FIELD, GODOWN AND

WORKSHOP:

Unless otherwise provided under Special Conditions of Contract, the tenderer will have to make his own arrangement for supply of water and power.

The tenderer should visit the site and acquaint himself with site conditions, availability of water, electricity, approach roads, construction materials as per specifications, shelter for his staff, etc. since these are to be provided/arranged by the tenderer (unless otherwise specified) at his cost.

The owner will, at his discretion and convenience based on availability for the duration of the execution of the work, make available, land for construction of contractor’s field office, go-downs, workshop and fabrication yard required for the execution of the contract. The contractor shall at his own cost construct all these temporary buildings and provide suitable water supply and sanitary arrangement approved by the Engineer-in-Charge.

On completion of the works undertaken by the Contractor, he shall remove all temporary works/ shed erected by him and have the site cleaned as directed by Engineer-in-Charge if the contractor shall fail to comply with these

requirements, the Engineer-in-charge may at the expenses of the Contractor remove such surplus and rubbish material, dispose off the same as he deems fit and get the site cleared as aforesaid; and the contractor shall

forthwith pay the amount of all expenses so incurred and shall have no claim in respect of any such surplus materials disposed off as aforesaid. But the Owner reserves the right to ask the Contractor any time during the

pendency of the contract to vacate the land by giving seven days notice on security reasons or on material interest

otherwise. 2.4 SAFETY STANDARDS FOR TEMPORARY BUILDINGS

All temporary buildings, sheds, workshops, field stations etc. shall be constructed in conformation with the safety and security regulations of the owner as regards location and type of structure.

4

Page 90: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

SECTION - III GENERAL INSTRUCTION FOR THE TENDERER

3 SUBMISSION OF TENDER:

3.1 The quotation should be submitted only in the manner and the form prescribed in the Request For Quotation

(RFQ)/Tender enquiry. 3.2 Addenda/Corrigenda to this tender document if issued must be signed and submitted along with the tender

document. The tenderer should consider the Addenda/Corrigenda and should price the work based on revised quantities when amendments for quantities are issued in addenda.

3.3 Tenders should always be placed in double sealed covers, superscribing Tender No. ____________ Tender for

____________________(name of job), Bharat Petroleum Corporation Limited, due for opening on ___________ The full name, postal address and telegraphic address of the tenderer shall be written on the bottom left hand corner of the sealed cover. (This will not be applicable in the case of e-tenders) Tenders received in open condition (priced bid) are liable to be rejected.

3.4 Instructions for two part bidding

i) The bid should be submitted in two parts viz.

a. Techno-commercial bid. b. Price bid.

ii) Techno-commercial bid shall have the following information/details a. Technical deviation if any. b. Commercial deviation if any like extra taxes, duties etc. c. Copy of price bid with prices blanked off. d. Any other relevant information.

iii) Price Bid shall have only prices as per schedule of Rates. iv) Techno-commercial bid and price bid shall be enclosed in two separate envelopes with the subject job, type of

bid, bidders name super-scribed on top. Both these envelopes shall be sealed in a common envelope and submitted as specified above and in covering letter. (This will not be applicable in the case of e-tenders)

4 DOCUMENTS:

4.1 The tenders, as submitted shall include all documents/details asked for by BPCL in the RFQ/Tender enquiry.

4.2 All pages to be initialed:

Wherever signed tender documents are submitted, all signatures in the documents shall be dated, as well as all the pages of the documents shall be initialed at the lower right hand corner and signed wherever required in the tender papers by the tenderer or by a person holding power of attorney authorizing him to sign on behalf of the tenderer before submission of tender. Tenders without signatures as stated above are liable to be rejected.

4.3 Rates to be in Figures and Words:

The tenderer should quote the rates in English both in figures as well as in words. Offers received without the rates in figures and in words are liable for rejection. In case of discrepancy exists between the rate quoted in figures and in words, the rates quoted in words will prevail.

4.4 Corrections and Erasures:

All corrections and alteration in the entries of tender papers will be signed in full by the tenderer with date. No erasures or over-writings are permissible.

In case of priced bids containing overwriting/cuttings/erasures in the quoted rates and in case these are not attested by the signatory of the bid, such priced bids are liable to be rejected without giving any further notice.

4.5 Signature of Tenderer:

The tender shall contain the name, residence and place of business of person or persons making the tender and shall be signed by the tenderer with his usual signature with company stamp. Partnership firms shall furnish the full names of all partners in the tender. It should be signed in the partnership name by all the partners or by duly authorized representative followed by the name and designation of the person signing with company stamp. Tender by Company or Corporation registered under the relevant companies act, shall be signed by the authorized representative and a power of attorney in that behalf shall accompany the tender.

4.6 Transfer of tender documents issued to one intending tenderer to another is not permissible.

5

Page 91: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

5 PURCHASE PREFERENCE:

Owner reserves its right to allow Public Sector Enterprises (Central/State), purchase preference as admissible/applicable from time to time under the existing Govt. policy.priced.

Owner reserves its right to allow Micro and Small Enterprises (MSEs) and MSEs owned by Scheduled Caste (SC) or the Scheduled tribe (ST) entrepreneurs, purchase preference as admissible/applicable from time to time under the existing Govt. policy.

Subject to meeting terms and conditions stated in the tender document including but

not limiting to prequalification criteria, in present tender, as the tendered quantity

cannot be split due to nature of job, MSE shall be allowed for supply and installation of

total tendered quantity provided their quoted price is within a price band of L1 + 15

percent and they match the L1 price. In case of more than one such MSEs are in the

price band of L1 + 15%, then L1 MSE will be offered first and if matches the L1 price,

MSE shall be allowed for supply and installation of total tendered quantity. If L1 MSE

does not matches L1 price, other MSES falling in range of L1+15% band will be offered

in order of L2 MSE,L3 MSE etc. until they match L1 price. No separate preference will be

given to MSE owned by Scheduled Caste & Scheduled Tribe entrepreneurs over MSE

owned by general person as quantity cannot be split in this tender.

6 EARNEST MONEY:

(a) The tenderer must submit/ deposit earnest money, if specified in the RFQ/Tender enquiry, failing which the tender is liable to be rejected. Earnest Money Deposit shall be submitted in the form of crossed Demand Draft

in favour of “Bharat Petroleum Corporation Ltd.” / Electronic Funds Transfer to BPCL Bank Account / Bank Guarantee executed by any Scheduled Bank approved by Reserve Bank of India (as per Proforma provided in Annexure 2). Earnest Money Deposit (EMD) shall be valid for a period of 6 (Six) months from the due date of opening of Techno-commercial Bids and shall be submitted from any Indian Scheduled Commercial Bank /

Indian Branch of Foreign Bank. EMD submitted by foreign vendors shall be in USD / EURO only.

In case of limited tender, Earnest Money deposit (EMD) is not applicable for registered contractors of BPCL. NOTE : Exemption of Bidding Document fee and EMD will be applicable for Micro and Small Enterprises

(MSEs) registered with National Small Industries Corporation (NSIC)/ District Industries Centers (DIC) as per applicable government guidelines .Such bidder shall submit Notary attested copy of the certificate issued by

NSIC or DIC, valid as on the date of bid opening, indicating that their registration includes the items/works

under tender. The registration certificate should remain valid during the period of the contract that may be entered into such successful bidder. Such tenderers should ensure validity of the Registration Certificate for

the purpose.

NOTE: No interest shall be paid by the Owner on the earnest money deposit by the tenderer. The earnest money of the unsuccessful tenderer will be refunded after the completion of BQC evaluation / Technical Evaluation / Priced Bid Evaluation as applicable.

(b) CONVERSION OF EMD TO SECURITY DEPOSIT:

The earnest money deposit (EMD) of the contractor whose tender may be accepted, if paid in forms other than Bank Guarantee, can be converted to security deposit for due performance of the contract if the contractor so desires. The “performance security deposit/retention money” vide clause 18 shall also be applicable limiting to a maximum of 10% of the contract value.

7 TENDER VALIDITY:

Tender submitted by tenderers shall remain valid for acceptance for a period of four months from the date of opening of the tender (Technical Bid in the case of two bid). The tenderer shall not be entitled during the said period of four months, without the consent in writing of the Owner, to revoke, or cancel his tender or vary the tender given or any term thereof.

In case of tenderer revoking or canceling his tender, varying any terms in regard thereof without prior consent of Owner in writing, appropriate penal action will be taken by BPCL as deemed fit including putting the tenderer/contractor on ‘Holiday listing’/’Delisting’ barring the tenderer/contractor from participating in future tenders for an appropriate period from the date of revocation/cancellation/varying the terms besides forfeiture of Earnest

Page 92: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Money deposited by tenderer.

7.A FIRMNESS OF QUOTE :

Once the quotation is accepted, the rates quoted shall be firm till the entire work is completed. 7.B LANGUAGE OF BID:

The Bid, all correspondence and documents relating to the bid, between Bidder and BPCL, shall be written in English language only. Any supporting document furnished by Bidder may be written in other language provided that this literature is accompanied by an authenticated English translation in which case, for purpose of interpretation of the Bid, the English translation shall govern.

6

Page 93: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

7.C CURRENCIES OF BID & PAYMENT: For materials and services to be procured from India, Bidder shall quote the prices in INR only.

Indian bidders shall quote the rates/prices in Indian Rupees (INR) only for Indian component and in USD / EURO for Foreign Component. Foreign Bidders can quote their prices in INR / USD / EURO. Payment shall be subject to RBI guidelines.

8 ADDENDA / CORRIGENDA:

Addenda/ Corrigenda to the tender documents may be issued prior to the date of opening of the tenders to clarify documents or to effect modification in the design or tender terms. All addenda/corrigenda issued shall become part of tender Document.

9 RIGHT OF OWNER TO ACCEPT OR REJECT TENDER:

9.1 The right to accept the tender will rest with the Owner. The Owner, however, does not bind itself to accept the

lowest tender, and reserves to itself the authority to reject any or all the tenders received without assigning any reason whatsoever.

9.2 The whole work may be split up between two or more contractors or accepted in part and not entirely if considered expedient.

9.3 Tenders in which any of the particulars and prescribed informations are missing or are incomplete in any respect and/or the prescribed conditions are not fulfilled are liable to b rejected.

9.4 Canvassing in connection with tenders is strictly prohibited and tenders submitted by the tenderer who resort to canvassing will be liable to rejection.

9.5 Tender containing uncalled remarks or any additional conditions are liable to be rejected.

10 A INTEGRITY PACT (IP):

Vendors are requested to sign & return IP document, attached as Annexure 7, if applicable as per the terms of the tender. This document is essential & binding.

Proforma of Integrity Pact shall be returned by the Bidder along with the bid documents (Technical Bid), duly filled up and signed by the same signatory who is authorized to sign the bid documents. All the pages of the Integrity Pact shall be duly signed. Bidder’s failure to return the Integrity Pact duly signed along with the bid documents may result in the bid not being considered for further evaluation.

If the Bidder has been disqualified from the tender process prior to the award of the contract in accordance with the provisions of the Integrity Pact, BPCL shall be entitled to demand and recover from Bidder Liquidated Damages amount by forfeiting the EMD/ Bid Security as per provisions of the Integrity Pact.

If the contract has been terminated according to the provisions of the Integrity Pact, or if BPCL is entitled to terminate the contract according to the provisions of the Integrity Pact, BPCL shall be entitled to demand and recover from Contractor Liquidated Damages amount by forfeiting the Security Deposit/ Performance bank Guarantee as per provisions of the Integrity Pact.

Bidders may raise disputes/ complaints, if any, with the nominated Independent External Monitor.

10 B HOLIDAY LISTING:

The vendors / contractors are expected to adopt the ethics of highest standards and a very high degree of integrity, safety and quality consciousness, commitment and sincerity towards the work undertaken and dealing with BPCL in such matters. Also, while participating in the tender and performing the contracts, Contractors are required to meet certain performance criteria and adherence to the terms and conditions of the tender / contract. BPCL shall have the right to remove from the list of approved suppliers / contractors or to ban business dealings, if any agency has been found to have committed misconduct or fraud or poor performance or anything unethical not expected from a reputed agency. The guidelines and procedures for Holiday Listing as adopted by BPCL and available separately in BPCL website shall be applicable in the context of all tenders floated and consequently, all Orders / Contracts / Purchase Orders placed, by BPCL.

Policy for Holiday Listing of vendor in BPCL as per enclosed. 10 C CONSULTANCY CONTRACTS:

This General Conditions of Contract (GCC) will be binding for Consultancy jobs only to the extent of its applicability to the context of consultancy jobs.

7

Page 94: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

10 D FOREIGN BIDDERS:

It is mandatory for the foreign bidder to furnish the documents for the compliance to requirement of PAN No. , Tax

Residency Certificate and Form No.10F (applicable for foreign bidder in case of services in India is required as per scope

of bidding document) as per Income Tax Act in case his receipts are subject to tax deduction at source in India: (a) PAN No.

PAN as per the Indian Income Tax requirements shall be submitted, failing which the

Supplier/Contractor/Consultant shall be responsible for any additional tax deduction at source as per the provisions

of the Indian Income Tax Act/Rules and the same shall be deducted from the payment made to

supplier/contractor/consultant.

(b) Tax Residency Certificate (TRC)

TRC containing prescribed particulars as per the Annexure 5 from the Government of foreign country in order to

claim the benefits of DTAA as per the Indian Income Tax requirements shall be submitted, failing which the relief

under DTAA will not be available and consequently the actual rate of withholding tax will be applicable and

deducted from the payment made to supplier/contractor/consultant (i.e., non-resident taxpayer). The TRC shall be

duly verified by the Government of the country of which the assessee claims to be a resident for the purposes of

tax.

(c) Form 10F

In additional to TRC, in order to claim the benefits of DTAA, bidder shall also submit additional information in form no. 10F as per Annexure 6. Form 10F has to be signed & verified by the assessee himself.

The above shall be furnished before release of any payment or within one month of the release of Order, whichever is earlier. In case of failure to submit the above information, any additional tax liability on Owner, will be deducted from the payment due to the contractor.

11 COLLECTION OF DATA TENDERER’S RESPONSIBILITY :

The tenderer shall visit the site and acquaint himself fully of the site and no claims whatsoever will be entertained on the plea of ignorance or difficulties involved in execution of work or carriage of materials.

12 TIME SCHEDULE :

The time period allowed for carrying out the job shall be as shown in tender document. Request for revision for time schedule after tenders are opened will not be received for consideration.

13 SIGNING OF THE CONTRACT:

The successful tenderer shall be required to execute an agreement in the proforma attached with tender enquiry within a period of one month of the receipt by him of the notification of acceptance of tender. The payment will not be processed till the time the agreement is executed.

14 A FIELD MANAGEMENT:

The field management will be the responsibility of the Engineer-in-Charge, who will be nominated by the Owner. The Engineer-in-Charge may also authorize his representatives to perform his duties and functions. Coordination of Work - The Engineer-in-Charge shall coordinate the work of various agencies engaged at site to ensure minimum disruption of work carried out by different agencies. It shall be the responsibility of the contractor to plan and execute strictly in accordance with the site instructions to avoid hindrance to the works being executed by other agencies.

14 B RETIRED GOVERNMENT OR COMPANY OFFICER:

No Engineer of Gazetted rank or other Gazetted Officer, employed in Engineering or Administrative duties in an

Engineering Department of the States/Central Government or of the Owner is allowed to work as a Contractor for a period of two years after his retirement from Government service or from the employment of the Owner without the previous permission of the Owner. The contract, if awarded, is liable to be cancelled if either the contractor or any of his employees is found at any time to be such a person, who had not obtained the permission of the State/ Central

Government, or of the Owner as aforesaid before submission of tender, or engagement in the Contractor’s service as the case may be.

8

Page 95: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

SECTION - IV

INTERPRETATION OF CONTRACT DOCUMENTS 15 INTERPRETATION OF CONTRACT DOCUMENT: 15.1 Except if and to the extent otherwise provided by the Contract, the provisions of the General Conditions of Contract

and special conditions shall prevail over those of any other documents forming part of the contract. Several documents forming the contract are to be taken as mutually explanatory. Should there be any discrepancy, inconsistency, error or omission in the contract or any of the matter may be referred to Engineer-in-Charge, who

shall give his decisions and issue to the Contractor instructions directing in what manner the work is to be carried out. The decision of the Engineer-in-Charge shall be final and conclusive and the contractor shall carry out work in accordance with this decision.

15.2 Works shown upon the drawing but not mentioned in the specifications or described in the specification without being shown on the drawings shall nevertheless be held to be included in the same manner as if they had been specifically shown upon the drawings and described in the specifications.

15.3 Headings and marginal notes to the clauses of these General Conditions of Contract or to specifications or to any other tender document are solely for the purpose of giving a concise indication and not a summary of the content thereof, and they shall never be deemed to be part thereof or be used in the interpretation or construction thereof of the Contract.

15.4 Singular and Plural: In these contract documents unless otherwise stated specifically, the singular shall include the plural and vice-versa wherever the context so requires. Words indicating persons shall include relevant incorporated companies/ registered as associations/ body of individual/ firm or partnership.

16 SPECIAL CONDITIONS OF CONTRACT: 16.1 Special Conditions of contract shall be read in conjunction with the General Conditions of Contracts, specification of

work, Drawings and any other documents forming part of this contract wherever the context so requires. 16.2 Notwithstanding the sub-division of the documents into these separate sections and volumes every part of each

shall be deemed to be supplementary to and complementary of every other part and shall be read with and into the contract so far as it may be practicable to do so.

16.3 Where any portion of the General Conditions of Contract is repugnant to or at variance with any provisions of the Special Conditions of Contract then, unless a different intention appears the provisions of the Special Conditions of Contract shall be deemed to over-ride the provision of the General Conditions of Contract and shall to the extent of such repugnance or variations, prevail.

16.4 Wherever it is mentioned in the specifications that the Contractor shall perform certain work or provide certain facilities, it is understood that the contractor shall do so at his own cost.

16.5 The materials, designs and workmanship shall satisfy the relevant Indian Standards, the Job specifications contained herein and codes referred to. Where the job specifications stipulate requirements in addition to those contained in the standard codes and specifications, these additional requirements shall also be satisfied.

17 CONTRACTOR TO OBTAIN HIS OWN INFORMATION:

The contractor in fixing rate shall for all purposes whatsoever be deemed to have him self independently obtained

all necessary information for the purpose of preparing his tender. The contractor shall be deemed to have examined

the Contract Documents, to have generally obtained his own information in all matters whatsoever that might affect

the carrying out the works at the scheduled rates and to have satisfied himself to the sufficiency to his tender. Any

error description of quantity or omission there from shall not vitiate the contract or release the Contractor from

executing the work comprised in the contract according to drawing and specifications at the scheduled rates. He is

deemed to have known the scope, nature and magnitude of the works and the requirements of materials and labour

involved etc. and as to what all works he has to complete in accordance with the contract documents whatever be

the defects, omissions or errors that may be found in the Contract Documents. The Contractor shall be deemed to

have visited surrounding to have satisfied himself to the nature of all existing structures, if any, and also as to the

nature and the conditions of the Railways, roads, bridges and culverts means of transport and communications,

whether by land, water or air, and as to possible interruptions thereto and the access to and regress from the site, to

have made enquiries, examined and satisfied himself as to the sites for obtaining sand, stones, bricks and other

materials, the sites for disposal of surplus materials the available accommodation as to whatever required, depots

and such other building as may be necessary for executing and completing the works, to have made local

independent enquiries as to the sub-soil water and variations thereof, storms, prevailing winds, climate conditions

and all other similar matters affecting these works. He is deemed to have acquainted himself as to his liability for

payment of Government taxes, customs duty and other charges.

Any neglect or failure on the part of the Contractor in obtaining necessary and reliable information upon the foregoing or any other matters affecting the contract shall not relieve him from any risk or liabilities or the entire responsibility from completion of the works at the scheduled rates and time in strict accordance with the contract documents.

9

Page 96: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

No verbal agreement or inference from conversation with any officer or employee of the owner either before or after the execution of the contract agreement shall in any way affect or modify any of the terms or obligations herein contained.

18 SECURITY DEPOSIT TOWARDS PERFORMANCE/RETENTION MONEY:

18.1 To ensure performance of the contract and due discharge of the contractual obligations, the successful contractor

will have to provide security deposit of 10% of the contract value within 30 days of receipt by him of the notifications of acceptance of tender unless otherwise specified in the Special Conditions of Contract.

This Security deposit may be furnished in the form of an Account payee Demand Draft payable to BPCL or Bank Guarantee in the prescribed format. The contractor shall have the option to adjust any Earnest Money Deposit-(EMD), if paid in forms other than Bank Guarantee, towards security deposit if he so desires.

In the case of security deposit submitted in the form of Bank guarantee, the Bank Guarantee shall be valid and remain in force till the completion of contractual completion period, defect liability period (if applicable) plus a claim period of 3 months. The Bank Guarantee shall be in the form prescribed (Annexure 2).

The security deposit will be retained till the successful completion of the work and thereafter till the expiry of the defect liability period (refer clause-72), if applicable. This retention money/Bank guarantee held shall be released after the expiry of the defect liability period provided that any defects appearing during that period are corrected by the contractor and subject to Clause 18.2 below.

If the Contract Value is in more than one currency, the Security deposit shall also be in multiple currencies amounting to 10% for each currency of awarded contract.

In the case of value/rate/quantity contracts, the security deposit shall be based on individual release orders issued.

18.2 If the contractor/ sub-contractor or their employees shall break, deface or destroy any property belonging to the Owner or other agency during the execution of the contract, the same shall be made good by the Contractor at his own expenses and in default thereof, the Engineer-in-Charge may cause the same to be made good by other agencies and recover expenses from the contractor (for which the certificate of the Engineer-in-Charge shall be final). These expenses can be recovered from the security deposit/retention money if recovery from other sources is not possible.

18.3 All compensation or other sums of money payable by the contractor to the Owner under terms of this contract may be deducted from his security deposit/retention money or from any sums which may be or may become due to the contractor by the Owner on any account whatsoever and in the event of his security deposit/retention money being reduced by reasons of any such deductions. The contractor shall within ten days thereafter make good any sum or sums, which may have been deducted from his security Deposit/retention money. No interest shall be payable by the Owner from sum deposited as security deposit/retention money.

18.4 The security deposit shall be held by the Owner, as security for the due performance of the Contractor’s obligations under the contract, provided that nothing herein stated shall make it incumbent upon the Owner to utilize the security deposit/retention money in preference to any other remedy which the Owner may have, nor shall be construed as confining the claims of the Owner against the contractor to the quantum of the Security Deposit/retention money.

18.5 The Bank guarantee if submitted shall be from any Indian scheduled bank or an international bank of repute having a branch in India or a corresponding banking relationship with an Indian scheduled bank. The security deposit/retention money shall be in Indian Rupee in the case of domestic bidders and in the quoted currency in the case of foreign bidders (INR/USD/EURO as the case may be.).

19 TIME OF PERFORMANCE:

19.1 The work covered by this contract shall be commenced as detailed in the purchase order or as per the instructions

of the Engineer in charge and be completed in stages on or before the dates as mentioned in the time schedule of completion of work. The contractor should bear in mind that time is the essence of this agreement unless such time

10

Page 97: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

be extended pursuant to the provision of clause No. 21. Request for revision of Completion time after tenders are opened will not receive consideration.

19.2 Time Schedule of Completion: The general time schedule of completion is given in the tender document. Contractor

should prepare a detailed monthly and weekly execution programme, jointly with the Engineer-in-Charge within two weeks of receipt of Letter of Intent or acceptance of tender. The work shall be executed strictly as per the time schedule given in this document. The period of completion given includes the time required for testing, rectifications, if any, retesting and completion in all respects to the entire satisfaction of the Engineer-in-Charge.

20 FORCE MAJEURE:

Any delays in or failure of the performance of either party hereto shall not constitute default here under or give rise to any claims for damages, if any, to the extent such delays or failure of performance is caused by occurrences such as Acts of God or the public enemy expropriation or confiscation of facilities by Govt./authorities, compliances with any order or request of any Government authorities, acts of war, rebellion or sabotage or fires, floods, explosions, riots or strikes. The contractor shall keep records of the circumstances referred to above and bring these to the notice of Engineer-in-Charge in writing immediately on such occurrences.

21 EXTENSION OF TIME:

If the contractor shall desire an extension of the time for completion of the work on the grounds of his having been unavoidably hindered in its execution or on any other grounds, he shall apply in writing to the Engineer-in-Charge within two weeks of the date of hindrance on account of which he desires such extension as aforesaid, and the Engineer-in-Charge shall if in his opinion (which shall be final), reasonable grounds have been shown thereof, authorize such extension of time as may in his opinion be necessary or proper. In the event of extension of Time of the contract, if granted, the contractor shall be required to suitably extend the period of Bank Guarantee if submitted, towards security Deposit/retention money suitably.

22. LIQUIDATED DAMAGES FOR DELAY:

22.1 Time is the essence of the contract. In case the contractor fails to complete the whole work within the stipulated

period, he shall be liable to pay liquidated damages of 0.5% of the value of contract per week and or part thereof of the delay subject to a maximum of 5% of the value of the contract. The parties agree that this is a genuine pre-estimate of the loss/damage which will be suffered by the owner on account of delay on the part of the contractor

and the said amount will be payable on demand without there being any proof of the actual loss or damages having been caused by such delay/breach. The owner shall be at liberty to adjust or deduct the said amount of liquidated damages from any amount due to the contractor including Security Deposit.

22.2 The owner shall be at liberty to deduct or retain from any amount payable to the contractor periodically, the proportionate or full amount of liquidated damages as the case may be for the delay periodically caused by the contractor.

22.3 Service tax is applicable on LD amount, and that service tax shall be collected in addition to LD amount as per applicable rate at the time of deduction of LD

23 SUM PAYABLE BY WAY OF COMPENSATION TO BE CONSIDERED AS REASONABLE COMPENSATION

WITHOUT REFERENCE TO ACTUAL LOSS:

All sums payable by way of compensation under any of the conditions shall be considered as reasonable compensation without reference to the actual loss or damage, which shall have been sustained by the Owner.

24 TERMINATION/OFFLOADING:

24.1 The contractor fully understands that timely completion of the work as per the schedule is of paramount necessity

as otherwise it would lead to adversely affecting the schedules of other works/project with resultant financial and other losses to the Company/owner. In view of this, the contractor unconditionally agrees and binds himself to be liable for all the consequences for non-completion of the work within the stipulated time.

24.2 In case a situation is brought about by the contractor warranting termination/off-loading of the whole or any part of the work for any reason whatsoever, the Company/owner shall have the liberty and right to entrust/engage/award the work so terminated/off loaded at the risk and cost of the contractor to any other agency/contractor by adopting any mode of inviting tenders, i.e. open/limited/single party/negotiation basis etc. in order to ensure completion of the work as per the schedule or at the quickest possible time.

25. FORFEITURE OF SECURITY DEPOSIT:

Whenever any claim against the Contractor for the payment of a sum of money arises out of or under the contract, the Owner shall be entitled to recover such sum by appropriating in part or whole, security deposit of the contractor, forming whole or part of such security being insufficient or if no security has been taken from the Contractor then the balance or the total sum recoverable, as the case may be, shall be deducted from any sum then due or which at any time thereafter may become due to the Contractor. The contractor shall pay to the owner on demand any balance remaining due.

11

Page 98: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

26 ACTION WHEN WHOLE OF SECURITY DEPOSIT IS FORFEITED:

In any case in which, under any clause or clauses of this contract, the contractor shall have forfeited the whole of his security deposit (whether paid in one sum or deducted by installment) or have committed a breach of any of the terms contained in this contract the owner shall have power to adopt any of the following courses as he may deem best suited to his interest.

a) To rescind the contract (of which rescission notice in writing to the contractor under the hand of the owner shall be conclusive evidence) in which case the security deposit of the contractor shall stand forfeited and be absolutely at the disposal of the Owner.

b) To employ labour paid by the owner and to supply materials to carry out the work any part of the work, debiting contractor with the labour cost of tools and plants and equipment charges, the cost of the materials for which a certificate of the Engineer-in-Charge shall be final and conclusive against the

Contractor and 10% of costs as above to cover all departmental charges and crediting him with the value of the work done in all respects in the manner and at the same rates as if it had been carried out by the Contractor under the term of his contract. The certificate of Engineer-in-Charge as to the value of the work done shall be final and conclusive against the contractor.

c) To measure up the work of the contractor and to take such part thereof as shall be unexecuted out of his hand to give it to another contractor to complete in which case any expenses which may be incurred in excess of the sum which would have been paid to the original contractor, if the whole work had been executed by him (of the amount of which excess, the certificate in writing of the Engineer-in-Charge shall

be final and conclusive) shall be borne and paid by the original contractor and may be deducted from any money due to him by the Owner under the contract or otherwise or from his security deposit or from the proceeds of sale thereof, of a sufficient part thereof.

In the event of any of the above course being adopted by the Owner, the contractor shall have no claim to

compensation for any loss sustained by him by reason of his having purchased or procured any materials or entered into any agreements or made any advances on account of or with a view to the execution of the work of the performance of the contract. In case the Contractor shall not be entitled to recover or be paid any sum for any work actually performed under this contract unless the Engineer-in-Charge will

certify in writing the performance of such work and the value payable in respect thereof and he shall only be entitled to be paid the value so certified.

27 CONTRACTOR REMAINS LIABLE TO PAY COMPENSATION IF ACTION NOT TAKEN UNDER CLAUSE 26:

In any case in which any of the powers conferred upon the owner by clause 26 thereof shall have become

exercisable and the same had not been exercised, the non exercise thereof shall not constitute a waiver of any of

the conditions hereof and such powers shall notwithstanding be exercised in the event of any further case of default

by the contractor for which any clause hereof he is declared liable to pay compensation amounting to the whole of

his security deposit and the liability of the contractor for past and future compensation shall remain unaffected. In

the event of the Owner putting in force the power under sub-clause (a), (b) or (c) of clause 26 vested in him under

the proceeding clause he may, if he so desires takes possession of all or any tools and plants materials and stores

in or upon the works or the site thereof belonging to the contractor or procured by him and intended to be used for

the execution of the work or any part thereof paying or allowing for the same in account at the contract rates or in

case of these not being applicable at current market rates to be certified by the Engineer-in-Charge whose

certificate thereof shall be final otherwise the Engineer-in-Charge may give notice in writing to the contractor or his

clerk of the works, supervisor or other authorized agent, requiring him to remove such tools, plant, materials or

stores from the premises (within a time to be specified in such notice) and in the event of the contractor failing to

comply with any such requisition, the Engineer-in-Charge may remove them at the contractors expense or sell them

by auction or private sale on account of the contractor and at his risk in, all respects without any further notice as to

the date, time or place of sale and the certificate of the Engineer-in-Charge as to the expense of any such removal

and the amount of proceeds and any expenses of any such sale shall be final and conclusive against the

contractor.

28 NO COMPENSATION FOR ALTERATION IN OR RESTRICTION OF WORK:

If at any time from the commencement of the work the owner shall for any reasons whatsoever, not require the

whole or part thereof as specified in the tender to be carried out, the Engineer-in-Charge shall give notice in writing of the fact to the contractor, who shall have no claim to any payment or compensation whatsoever on account of any profit or advantage which he might have derived from the execution of the work in full, but which he did not

derive in consequence of the full amount of the work not having been carried out, neither shall he have any claim for compensation by reason of any alterations having been made in the original specifications, drawings, designs and instructions which shall involve any curtailment of the work as originally contemplated.

12

Page 99: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

29 CHANGES IN CONSTITUTION OF THE CONTRACTOR:

The Contractor, whether an individual, Proprietary Concern, Hindu Undivided Family, Partnership Firm, Private Limited Company or Public Limited Company, shall not make any change(s) in its constitution, by transfer of substantial shareholding or of management (in case of a company) or by addition or deletion of Partners, change in the terms of Partnership, or make any other material change(s) without prior approval of Owner. Any such unauthorized change shall attract the provisions of clause 35 hereof.

30 IF THE CONTRACTOR DIES:

Without prejudice to any of the rights or remedies under his contract, if the contractor (if an individual) dies, the Owner shall have the option of terminating the contract without compensation to the contractor.

31 EMPLOYEES OF THE OWNER NOT INDIVIDUALLY LIABLE:

No director or official or employee of the Owner shall in any way be personally bound or liable for the acts or obligations of the Owner under the contract or answerable for any default or omission in the observance or performance of any of the acts, matters or things which are herein contained.

32 OWNER NOT BOUND BY PERSONAL REPRESENTATIONS:

The contractor shall not be entitled to any increase on the item rates of the contract or any other right or claim whatsoever by reason of representation, explanation or statement or alleged representation, promise or guarantees given or alleged to have been given to him by any person.

33 CONTRACTOR’S OFFICE AT SITE:

The contractor shall provide and maintain an office at the site, if space provided by the owner, for the accommodation of his agent and staff and such office shall be open at all reasonable hours to receive instruction, notices, or other communications.

34 CONTRACTOR’S SUBORDINATE STAFF AND THEIR CONDUCTS:

34.1 The contractor, on or after award of the work shall name and depute a qualified personnel having

sufficient experience in carrying out work of similar nature to whom the equipments materials, if any, shall

be issued and instructions for works given. The contractor shall also provide to the satisfaction of the

Engineer-in-Charge sufficient and qualified staff to supervise the execution of the-works, competent sub-

agents, supervisor and leading hands including those specially qualified by previous experience to

supervise the type of works comprised in the contract in such manner as will ensure work of the best

quality, expeditious working. Whenever in the opinion of the Engineer-in-Charge, additional properly

qualified supervision staff is considered necessary, they shall be employed by the contractor without

additional charges on account thereof. The Contractor shall ensure to the satisfaction of the Engineer-in-

Charge that sub-contractors, if any shall provide competent and efficient supervision over the work

entrusted to them. 34.2 If and whenever any of the Contractor’s or sub-contractor’s agents, sub-agents, assistants supervisor or

other employees shall in the opinion of Engineer-in-Charge be guilty of any misconduct or be incompetent or insufficiently qualified or negligent in the performance of their duties or that in the opinion of the owner

or Engineer-in-Charge, it is undesirable for administrative or any other reason for such person or persons

to be employed in the works, the contractor, if so directed by the Engineer-in-Charge, shall at once

remove such person or persons from employment thereon. Any person or persons so removed from the

works shall not again be employed in connection with the works without the written permission of the

Engineer-in-Charge. Any person so removed from the works shall be immediately replaced at the

expense of the contractor by a qualified and competent substitute. Should the contractor be requested to

repatriate any person removed from the works he shall do so and shall bear all costs in connection

herewith. 34.3 The contractor shall be responsible for the proper behaviour of all the staff, supervisor, workmen and

others and shall exercise a proper degree of control over them and in particular, and without prejudice to

the said generality, the contractor shall be bound to prohibit and prevent any employees from trespassing

or acting in any way detrimental or prejudicial to the interest of the community or of the properties or

occupiers of land and properties in the neighborhood and in the event of such employee so trespassing,

the contractor shall be responsible therefore and relieve the Owner of all consequent claims or actions for

damages or injury or any other grounds whatsoever. The decision of the Engineer-in-Charge upon any

matter arising under this clause shall be final. Contractor shall ensure that none of their employees are

ever engaged in any anti-national activities. 34.4 All contractor’s personnel entering upon the Owner’s premises shall be properly identified by badges

issued by owner which must be worn all times on Owner’s premises.

13

Page 100: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

35 SUB-LETTING OF WORK:

Sub letting of contracts shall not be generally permitted. However owner may permit sub letting of work on specific cases subject to the following:-

i) No part of the contract nor any share of interest there shall in any manner or degree be transferred assigned sublet by the contractor directly or indirectly to any firm or corporation whosoever except as provided for in the succeeding sub-clause, without the consent in writing of the Owner.

ii) Sub Contractors for Temporary Works Etc.:- The Owner may give written consent to sub-contract for execution of any part of the works at the site, being entered into by the contractor provided each individual sub-contract is submitted to the Engineer-in-Charge before being entered into and is approved by him.

iii) List of Sub-Contractors to be supplied: - At the commencement of every month the contractor shall furnish to the Engineer-in-Charge list of all sub-contractors or firms engaged by the contractor and working at the site during the previous month with particulars of the general nature of the sub-contract or works.

iv) Contractor’s Liability Not Limited By Sub-Contractors:- Notwithstanding any sub-letting with such approval as aforesaid and notwithstanding that the Engineer-in-Charge shall have received copies of any sub-contracts, the contractor shall be and shall remain solely responsible for the quality and proper and expeditious execution of the works and the performance of all the conditions of the contract in all respects as if such sub-letting or sub-contracting had not taken place and as if such work had been done directly by the Contractor.

v) Owner may Terminate Sub-Contracts:- If any sub-contractor engaged upon the works at the site executes any work which in the opinion of the Engineer-in-Charge is not in accordance with the Contract documents, the owner may by written notice to the contractor request him to terminate such sub-contract and the contractor upon the receipt of such notice shall terminate such sub contract and the latter shall forthwith leave the works, failing which the owner shall have right to remove such sub-contractors from the Site.

vi) No Remedy For Action Taken Under This Clause:- No action taken by the owner under the clause shall relieve the contractor of any of his liabilities under the contract or give rise to any right to compensation, extension of time or otherwise failing which, the owner shall have right to remove such sub-contractors from the Site.

36 POWER OF ENTRY:

If the contractor shall not commence the work in the manner previously described in the contract document or if he shall, at any time in the opinion of the Engineer-in-Charge.

i. Fail to carry out the works in conformity with the contract documents, or ii. Fail to carry out the works in accordance with the time schedule, or iii. Substantially suspend work or the works for a period of Fourteen days without authority from the

Engineer-in-Charge, or iv. Fail to carryout and execute the works to the satisfactions of the Engineer-in-Charge, or v. Fail to supply sufficient or suitable constructional equipments, temporary works, labour materials or

things, or vi. Commit or suffer or permit any other breach of any of the provisions of the contract on his part to be

performed or observed or persist in any of the above mentioned breaches of the contract for the fourteen days, after notice in writing shall have been given to the Contractor by the Engineer-in-Charge requiring such breach to be remedied, or

vii. Abandon the works, or viii. During the continuance of the contract, become bankrupt, make any arrangement or composition with his

creditors, or permit any execution to be levied or go into liquidation whether compulsory or voluntary not being merely a voluntary liquidation for the purpose of amalgamation or reconstruction.

Then in any such case, the Owner shall have the power to enter upon the works and take possession thereof and of

the materials, temporary works, constructional equipment, and stock thereon, and to revoke the contractor’s license

to use the same, and to complete the works, by his agents, other contractor or workmen, or to re-let the same upon

any terms and to such other person firm or corporation as the Owner in his absolute discretion may think proper to

employ and for the purpose aforesaid to use or authorize the use of any materials, temporary works constructional

equipment, and stock as aforesaid without making payment or allowances to the contractor for the said materials

other than such as may be certified in writing by the Engineer-in-Charge to be reasonable, and without making any

payment or allowance to the contractor for the use of the temporary said works, constructional equipments and

stock or being liable for any loss of damage thereto, and if the Owner shall by reason of his taking possession of the

works or of the works being completed by other contractors (due account being taken of any such extra work or

works which may be omitted) then the amount of such excess as certified by the Engineer-in-Charge shall be

deducted from any money which may be due for work done by the contractor under the contract and not paid for.

Any deficiency shall forthwith be made good and paid to the Owner by the contractor and the Owner shall have

power to sell in such manner and for such price as he may think fit all or any of the constructional equipment,

materials etc. belonging to and to recoup and retain the said deficiency or any part thereof out of the proceeds of

the sale. 37 CONTRACTOR’S RESPONSIBILITY WITH OTHER AGENCIES:

Without repugnance to any other condition, it shall be the responsibility of the contractor executing the work, to work in close co-operation and co-ordinate the works with other contractors or their authorized representatives and

14

Page 101: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

the contractor will put up a joint scheme, showing the arrangements, with other contractors / agencies for carrying his portion of work to the Engineer-in-Charge, and get the approval. The contractor before finally submitting the schemes to the Engineer-in-Charge shall have the written agreement of the other agencies. The Engineer-in-Charge before communicating his approval of the scheme, with any required modifications shall get the final agreement of all the agencies, which shall be binding. No claim shall be entertained on account of the above.

The contractor shall conform in all respects with the provisions of any statutory regulations, ordinances or by laws of any local or duly constituted authorities or public bodies which may be applicable from time to time to the works or any temporary works. The contractor shall keep the Owner Indemnified against all penalties and liabilities of every kind arising out of non-adherence to such statutes ordinances, laws, rules, regulations, etc.

38 OTHER AGENTS AT SITE:

The contractor shall have to execute the work in such place and condition where other agencies might also be engaged for other works such as site grading, filling and leveling, electrical and mechanical engineering works etc. No claim shall be entertained to works being executed in the above circumstances.

39 NOTICES:

Any notice hereunder may be served on the contractor or his duly authorized representative at the job site or may be served by registered mail or speed post direct to the address furnished by the Contractor. Proof of issue of any such notice could be conclusive of the contractor having been duly informed of all contents therein.

40 RIGHTS OF VARIOUS INTERESTS:

i) The Owner reserves the right to distribute the work between more than one contractor. The contractor shall co-operate and afford other contractors reasonable opportunity for access to the works for the carriage and storage of materials and execution of their works. ii) Whenever the work being done by any department of the Owner or by other contractors employed by the Owner is contingent upon work covered by the contract, the respective rights of the various interests involved shall be determined by the Engineer-in-Charge to secure the completion of the various portions of the work in general harmony.

41 RIGHT OF OWNER TO DETERMINE / TERMINATE CONTRACT

i) Owner shall, at any time be entitled to determine and terminate the contract, if in the opinion of the Owner the cessation of the work becomes necessary owing to paucity of funds or for any other cause whatsoever, in which

case, the cost of approved materials at the site at current market rates as verified and approved by Engineer-in-Charge and of the value of the work done to date by the contractor shall be paid for in full at the rates specified in the contract. A notice in writing from the Owner to the contractor of such determination and termination and the reason thereof, shall be the conclusive proof of the fact that the contract has been so determined and terminated by

the Owner.

ii) Should the contract be determined under sub-clause (i) of this clause and the contractor claims payments to compensate expenditure incurred by him in the expectation of completing the whole of the work, the Owner shall consider and admit such claim as are deemed fair and reasonable and are supported by vouchers to the satisfaction of the Engineer-in-Charge. The Owner’s decision on the necessity and propriety of any such expenditure shall be final and conclusive and binding on the contractor.

42 PATENTS AND ROYALTIES:

42.1 The contractor, if licensed under any patent covering equipment, machinery, materials or compositions of matter to

be used or supplied or methods and process to be practiced or employed in the performance of this contract,

agrees to pay all royalties and licence fees which may be due with respect thereto. If any equipment, machinery,

materials or composition matters, to be used or supplied or methods and process to be practised or employed in the

performance of this contract, is covered by a patent under which contractor is not licensed then the contractor

before supplying or using the equipment, machinery, materials, compositions method or processes shall obtain

such licences, and pay such royalties and licence fees as may be necessary for performance of the contract. In the

event, the contractor fails to pay any such royalties or obtain any such licence, any suit for infringement of such

patents which is brought against the contractor or the Owner as a result of such failure will be defended by the

contractor at his own expenses and the contractor will pay any damages and costs awarded in such suit. The

contractor shall promptly notify the owner if the contractor has acquired knowledge of any patent under which a suit

for infringement could be reasonably brought because of the use by the Owner of any equipment, machinery,

materials, and process methods to be supplied hereunder. The contractor agrees to and does hereby grant to

Owner, together with the right to extend the same to any of the subsidiaries of the Owner as irrevocable, royalty-

free licence to use in any country, any invention made by the contractor or his employee in or as a result of the

performance of the work under the contract.

15

Page 102: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

The Owner shall indemnify and save harmless the contractor from any loss on account of claims on contractor for the contributory infringement of patent rights arising out and based upon the claim that the use by the Owner of the process included in the design prepared by the Owner and used in the operation of the plant infringes on any patent right with respect to any sub-contract entered into by contractor pursuant to the provisions of sub-contractor an undertaking to provide the Owner with the same patent protection that contractor is required to provide under the provisions of this clause.

42.2 All drawings, blue prints, tracings, reproducible, models, plans, specification and copies thereof, furnished by the

Owner as well as drawings, tracings, reproducible, plans specifications, design, calculations etc. prepared by the contractor for the purpose of execution of works covered in or connected with this contract shall be the property of Owner and shall not be used for any other work but are to be delivered to the Owner at the completion of the contract.

42.3 Where so desired by Engineer-in-Charge, the contractor agrees to respect the secrecy of any document, drawings etc. issued to him for the execution of this contract, and restrict access to such documents, drawing etc. to the minimum and further, the contractor agrees to execute an individual SECRECY agreement from each or any person employed by contractor having access to such documents, drawings and to any other agency or individual, without the written approval by Engineer-in-Charge.

43 LIENS: 43.1 If, at any time, there should be evidence or any lien or claim for which the Owner might have become liable and

which is chargeable to the contractor, the Owner shall have the right to retain out of any payment then due or thereafter to become due an amount sufficient to completely indemnify the owner against such lien or claim and if such lien or claim be valid the Owner may pay and discharge the same and deduct the amount so paid from any money which may be or may become due and payable to the Contractor. If any lien or claim remain unsettled after

all payments are made, the contractor shall refund or pay to the Owner all moneys that the latter may be compelled to pay in discharging such lien or claim including all costs and reasonable expenses.

43 2 Contractor will not disclose details of the work to any person or persons except those engaged in its performance, and

only to the extent required for the particular portion of the work being done. Contractor will not give any items concerning details of the work to the press or a news disseminating agency without prior written approval from Engineer-in-Charge. Contractor shall not take any pictures on site without written approval of Engineer-in-Charge

44 OPERATION OF CONTRACT: 44.1 Law Governing:

Regardless of the place of contracting, place of performance or otherwise, this Agreement, and all amendments, modifications, alterations, or supplements, thereto shall be governed by the laws of India and respective state laws for the nature, validity and interpretation thereof.

44.2 Non-Waiver of Default:

Any failure by the Owner or Contractor at any time, or from time to time, to enforce or require the strict keeping and performance of any of the terms or conditions of this agreement, or to exercise a right hereunder, shall not constitute a waiver of such terms, conditions or rights, and shall not affect or impair same, or the right of the Owner or the Contractor, as the case may be at any time to avail itself of same.

16

Page 103: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

SECTION - V PERFORMANCE OF WORK

45 EXECUTION OF WORKS: 45.1 All the works shall be executed in strict conformity with the provisions of the contract documents and with such

explanatory detailed drawings, specifications, and instructions as may be furnished from time to time to the contractor by the Engineer-in-Charge whether mentioned in the contract or not. The contractor shall be responsible

for ensuring that works throughout are executed in the most substantial, proper and workman like manner with the quality of material and workmanship in strict accordance with the specifications following all safety requirements of BPCL and as stipulated in work permits as per the directions and to the entire satisfaction of the Engineer-in-Charge.

45.2 Wherever it is mentioned in the specifications that the Contractor shall perform certain work or provide certain facilities/materials, it is understood that the contractor shall do, so at his cost unless otherwise specified.

45.3 The materials, design and workmanship shall satisfy the relevant Indian Standards, the Job specification contained herein and codes referred to. Where the job specification stipulate requirements in addition to those contained in the standards codes and specifications, these additional requirements shall also be satisfied.

46 COORDINATION AND INSPECTION OF WORK:

The coordination and inspection of the day-to-day work under the contract shall be the responsibility of the Engineer-in-Charge. The written instructions regarding any particular job will be normally be passed by the Engineer-in-Charge or his authorized representative. A work order book / logbook will be maintained by the Contractor for each job in which the aforesaid written instructions will be entered. These will be signed by the contractor or his authorized representative by way of acknowledgment within 12 hours. The non maintaining of the order book or non signing by the contractor shall not preclude the contractor from complying with the instructions.

47 WORK IN MONSOON AND DEWATERING:

47.1 The completion of the work may entail working in the monsoon also. The contractor must maintain a minimum

labour force as may be required for the job and plan and execute the construction and erection according to the prescribed schedule. No extra rate will be considered for such work in monsoon.

47.2 During monsoon and other period, it shall be the responsibility of the contractor to keep the construction work site free from water at his own cost.

48 WORK ON SUNDAYS AND HOLIDAYS:

For carrying out work on Sundays and Holidays if needed, the contractor will approach the Engineer-in-Charge or his representative at least two days in advance and obtain permission in writing. No special compensation on this account will be payable.

49 GENERAL CONDITIONS FOR CONSTRUCTION AND ERECTION WORK:

49.1 Place of Work:

The work has to be executed at specified premises as per the tender. Contractor should apprise himself of all the conditions prevailing in such location and the restrictions placed on movement of personnel and equipment, types of equipment and tools permitted, working methods allowed etc. in the light of security and safety regulations operative in the area. The safety regulations to be complied with, by the contractor will also be provided along with the tender. No idle

time wages or compensation for temporary stoppage of work or restrictions would be paid, and the rate quoted for the various items of work should cover the cost of all such contingencies and eventualities. Substantial structures

and utilities exist both above ground and underground, adjacent to the work site. (The construction activity gets restrained by the existence of such structures and utilities). Special care is necessary in transportation, storage,

working on equipments and other construction activities to protect the existing features and prevent damage to any

facility. Necessary protective structures barricades etc. have to be erected at various places as directed by Engineer-in-Charge. No extra payment of such protective works will be made unless specially provided in the

tender. 49.2 The working time or the time of work is 48 hours per week normally. Overtime work is permitted in cases of need

and the Owner will not compensate the same. Shift working at 2 or 3 shifts per day may become necessary and the contractor should take this aspect into consideration for formulating his rates for quotation. No extra claims will be entertained by the Owner on this account.

49.3 The contractor must arrange for the placement of workers in such a way that the delayed completing of the work or any part thereof for any reasons whatsoever will not affect their proper employment. The Owner will not entertain any claim for idle time payment whatsoever.

49.4 The contractor shall submit to the Owner reports at regular intervals regarding the state and progress of work. The details and proforma of the report will mutually be agreed after the award of contract.

17

Page 104: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

50 DRAWINGS TO BE SUPPLIED BY THE OWNER: 50.1 Where drawings are attached with tender, these shall be for the general guidance of the contractor to enable him to

visualize the type of work contemplated and scope of work involved. The contractor will be deemed to have studied the drawings and formed an idea about the work involved.

50.2 Detailed working drawings on the basis of which actual execution of the work is to proceed will be furnished from time to time during the progress of the work. The contractor shall be deemed to have gone through the drawings supplied to him thoroughly and carefully and in conjunction with all other connected drawings and bring to the notice of the Engineer-in-Charge, discrepancies, if any, therein before actually carrying out the work.

50.3 Copies of all detailed working drawings relating to the works shall be kept at the contractor’s office of the site and shall be made available to the Engineer-in-Charge at any time during the contract. The drawings and other documents issued by the Owner shall be returned to the Owner on completion of the works. Reference is also invited to clause 42.2 and 42.3 above regarding drawings and other documents.

51 DRAWINGS TO BE SUPPLIED BY THE CONTRACTOR: 51.1 Where drawings/data are to be furnished by the contractor, they shall be as enumerated in the special conditions of

contract, and shall be furnished within the specified time. 51.2 Where approval of drawings before manufacture / construction / fabrication has been specified, it shall be

contractor’s responsibility to have these drawings prepared as per the directions of Engineer-in-Charge and got approved before proceeding with manufacture construction / fabrication, as the case may be. Any changes that may have become necessary in these drawings during the execution of the work shall have to be carried out by the contractor to the satisfaction of Engineer-in-Charge at no extra cost. All final drawings shall bear the certification stamps duly signed by both the contractor and the Engineer-in-Charge.

51.3 A period of 3 weeks from the date of receipt shall be required normally for approval of drawings by the Engineer-in-Charge.

52 SETTING OUT WORKS: 52.1 The Engineer-in-Charge shall furnish the contractor with only the four corners of the work site and a level bench

mark and the contractor shall set out the works and shall provide efficient staff for the purpose and shall be solely responsible for the accuracy of such setting out.

52.2 The contractor shall provide, fix and be responsible for the maintenance of all stacks, templates, level marks, profiles and other similar things and shall take all necessary precaution to prevent their removal or disturbance and shall be responsible for the consequence of such removal or disturbance should the same take place and for their efficient and timely reinstatement. The contractor shall also be responsible for the maintenance of all existing survey

marks, boundary marks, distance marks and centre line marks, either existing or supplied and fixed by the contractor. The, work shall be set out to the satisfaction of the Engineer-in-Charge. The approval thereof or joining in setting out the work shall not relieve the contractor of any of his responsibilities.

52.3 Before beginning the works, the contractor shall at his own cost, provide all necessary reference and level posts,

pegs, bamboos, flags, ranging rods, strings and other materials for proper layout of the work in accordance with the scheme, for bearing marks acceptable to the Engineer-in-Charge. The centre, longitudinal or face lines and cross

lines shall be marked by means of small masonry pillars. Each pillar shall have distinct marks at the centre to

enable theodolite to be set over it. No work shall be started until all these points are checked and approved by the Engineer-in-Charge in writing but such approval shall not relieve the contractor of any of his responsibilities. The

contractor shall also provide all labour, material and other facilities, as necessary, for the proper checking of layout and inspection of the points during construction.

52.4 Pillars bearing geodetic marks located at the site of work under construction should be protected and fenced by the contractor.

52.5 On completion of works, the contractor must submit the geodetic documents according to which the work was carried out.

53 RESPONSIBILITY FOR LEVEL AND ALIGNMENT:

The contractor shall be entirely and exclusively responsible for the horizontal and vertical alignment, the levels and correctness of every part of the work and shall rectify effectually any errors or imperfections therein. Such rectifications shall be carried out by the contractor, at his own cost, when instructions are issued to that effect by the Engineer-in-Charge.

54 MATERIALS TO BE SUPPLIED BY CONTRACTOR:

54.1 The contractor shall procure and provide the whole of the materials required for construction including tools, tackles,

construction plant and equipment for the completion and maintenance of the works except the materials which will be issued by Owner and shall make his own arrangement for procuring such materials and for the transport thereof.. The materials procured by the contractor shall be BPCL approved/specified quality.

54.2 All materials procured should meet the specifications given in the tender document. The Engineer-in-Charge may, at his discretion, ask for samples and test certificates for any batch of any material procured. Before procuring, the contractor should get the approval of Engineer-in-Charge for any material to be used for the works.

18

Page 105: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

54.3 Manufacturer’s certificate shall be submitted for all materials supplied by the contractor. If, however, in the opinion of the Engineer-in-Charge any tests are required to be conducted on the materials supplied by the contractor, these will be arranged by the contractor promptly at his own cost.

55 MATERIALS SUPPLIED BY OWNER: 55.1 If the specifications of the work provides for the use of any materials of special description to be supplied from the

Owner’s stores, price for such material to be charged therefore as hereinafter mentioned being so far as practicable for the convenience of the contractor but not so as in any way to control the meaning or effect of the contract. The

contractor shall be bound to purchase and shall be supplied such materials as are from time to time required to be

used by him for the purpose of the contract only. The sums due from the contractor for the value of the actual

materials supplied by the Owner will be recovered from the running account bill on the basis of the actual

consumption of materials in the work covered and for which the running account bill has been prepared. After the

completion of the works, however, the contractor has to account for the full quantity of materials supplied to him as

per relevant clauses in this document. 55.2 The value of the materials as may be supplied to the contractor by the Owner will be debited to the contractor’s

account at the rates shown in the schedule of chargeable materials and if they are not entered in the schedule, they

will be debited at cost price, which for the purpose of the contract shall include the cost of carriage and all other

expenses whatsoever such as normal storage supervision charges which shall have been incurred in obtaining the

same at the Owner’s stores. All materials so supplied to the contractor shall remain the absolute property of the

Owner and shall not be removed on any account from the site of the work, and shall be at all times open for

inspection to the Engineer-in-Charge. Any such materials remaining unused at the time of completion or termination

of the contract shall be returned to the Owner’s stores or at a place as directed by the Engineer-in-Charge in

perfectly good condition, at contractor’s cost.

56 CONDITIONS FOR ISSUE OF MATERIALS:

i) Materials specified to be issued by the Owner will be supplied to the contractor by the Owner from his stores/location. It shall be the responsibility of the contractor to take delivery of the materials and arrange for its loading, transport and unloading at the site of work at his own cost. The materials shall be issued between the working hours and as per the rules of the Owner framed from time to time.

ii) The contractor shall bear all incidental charges for the storage and safe custody of materials at site after these have been issued to him.

iii) Materials specified to be issued by the Owner shall be issued in standard sizes as obtained from the manufacturer.

iv) The contractor shall construct suitable godown at the site of work for storing the materials safe against damage by rain, dampness, fire, theft etc. He shall also employ necessary watch and ward establishment for the purpose.

v) It shall be duty of the contractor to inspect the material supplied to him at the time of taking delivery and satisfy himself that they are in good condition. After the materials have been delivered by the Owner, it shall be the responsibility of the contractor to keep them in good condition and if the materials are damaged or lost, at any time, they shall be repaired and/ or replaced by him at his own cost, according to the directions of the Engineer-in-Charge.

vi) The Owner shall not be liable for delay in supply or non-supply of any materials which the Owner has undertaken to supply where such failure or delay is due to natural calamities, act of enemies, transport and procurement difficulties and any circumstances beyond the control of the Owner. In no case, the contractor shall be entitled to claim any compensation or loss suffered by him on this account.

vii) It shall be the responsibility of the contractor to arrange in time all materials required for the works other than

those to be supplied by the Owner. If, however, in the opinion of the Engineer-in-Charge the execution of the

work is likely to be delayed due to the contractor’s inability to make arrangements for supply of materials which

normally he has to arrange for, the Engineer-in-Charge shall have the right, at his own discretion, to Issue such

materials If available with the Owner or procure the materials from the market or elsewhere and the contractor

will be bound to take such materials at the rates decided by the Engineer-in-Charge. This, however, does not in any way absolve the contractor from responsibility of making arrangements for the supply of such materials in

part or in full, should such a situation occur, nor shall this, constitute a reason for the delay in the execution of

the work. viii) None of the materials supplied to the contractor will be utilized by the contractor for manufacturing item, which

can be obtained from standard manufacturer in finished form. ix) The contractor shall, if desired by the Engineer-in-Charge, be required to execute an indemnity bond for safe

custody and accounting of all materials issued by the Owner. x) The contractor shall furnish to the Engineer-in-Charge sufficiently in advance a statement showing his

requirements of the quantities of the materials to be supplied by the Owner and the time when the same will be required by him for the works, so as to enable the Engineer-in-Charge to make necessary arrangement for procurement and supply of the material.

xi) A daily account of the materials issued by the Owner shall be maintained by the contractor indicating the daily receipt, consumption and balance in hand. This account shall be maintained in a manner prescribed by the Engineer-in-Charge along with all connected papers viz. requisition, issues etc. and shall be always available for inspection in the contractor’s office at site.

19

Page 106: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

xii) The contractor should see that only the required quantities of materials are got issued. The contractor shall not be entitled to cartage and incidental charges for returning the surplus materials, if any, to the stores/location where from they were issued or to the place as directed by the Engineer-in-Charge.

xiii) Materials/ Equipment supplied by Owner shall not be utilized for any other purpose(s) than issued for.

57 MATERIALS PROCURED WITH ASSISTANCE OF OWNER:

Notwithstanding anything contained to the contrary in any or all the clause of this document where any materials for

the execution of the contract are procured with the assistance of Owner either by issue from Owner’s stock or

purchase made under orders or permits or licences issued by Government, the contractor shall hold the said

materials as trustee for the Owner and use such materials economically and solely for the purpose of the contract

and not dispose them off without the permission of the owner and return, if required by the Engineer-in-Charge, all

surplus or unserviceable materials that may be left with him after the completion of the contract or at its termination

for any reason, whatsoever on his being paid or credited such prices as the Engineer in-Charge shall determine

having due regard to the condition of the materials. The price allowed to the contractor however, shall not exceed

the amount charged to him excluding the storage charges if any. The decision of the Engineer-in-Charge shall be

final and conclusive in such matters. In the event of breach of the aforesaid condition, the contractor shall in terms

of the licenses or permits, and/or for criminal breach of trust, be liable to compensate the Owner a double rate or

high rate, in the event of those materials at that time having higher rate or not being available in the market, then

any other rate to be determined by the Engineer-in-Charge and his decision shall be final and conclusive.

58 MATERIALS OBTAINED FROM DISMANTLING:

If the contractor in the course of execution of the work is called upon to dismantle any part for reasons other than those stipulated in clauses 64 & 68 hereunder, the materials obtained in the work of dismantling etc. will be considered as the Owner’s property and will be disposed off to the best advantage of the Owner.

59 ARTICLES OF VALUE FOUND:

All gold, silver and other materials, of any description and all precious stones, coins, treasure relies, antiquities and other similar things which shall be found in, under or upon the site, shall be property of the Owner and the contractor shall duly preserve the same to the satisfaction of the Engineer-in-Charge and shall from time to time deliver the same to such person or person indicated by the Owner.

60 DISCREPANCIES BETWEEN INSTRUCTIONS:

Should any discrepancy occur between the various instructions furnished to the contractor, his agents or staff or any doubt, arise as to the meaning of any such instructions or should there be any misunderstanding between the contractor’s staff and the Engineer-in-Charge’s staff, the contractor shall refer the matter immediately in writing to the Engineer-in-Charge whose decision thereon shall be final and conclusive and no claim for losses alleged to have been caused by such discrepancies between instructions, or doubts, or misunderstanding shall in any event be admissible.

61 ALTERATIONS IN SPECIFICATIONS AND DESIGNS AND EXTRA WORK:

A) The Engineer-in-Charge shall have power to make any alterations in, omissions from, additions to of

substitutions for, the schedule of rates, the original specifications, drawings, designs and instructions that may

appear to him to be necessary or advisable during the progress of the work and the contractor shall be bound to

carry out such altered / extra / new items of work in accordance with any instructions which may be given to him

in writing signed by the Engineer-in-Charge and such alterations, omissions, additions or substitutions shall not

invalidate the contract and any altered additional or substituted work which the contractor may be directed to do

in the manner above specified as part of the work shall be carried out by the contractor on the same conditions in

all respect on which he agree to do the main work. The time for completion of work may be extended for the part

of the particular job at the discretions of the Engineer-in-Charge, for only such alteration, additions or substitutions of the work, as he may consider as just and reasonable. The rates for such additional, altered or

substituted work under this clause shall be worked out in accordance with the following provisions:

a) If the rates for the additional, altered or substituted work are specified in the contract for the work, the contractor is bound to carry out the additional, altered or substituted work at the same rates as are specified in the contract.

b) If the rates for the additional, altered or substituted work are not specifically provided in the contract for the work, the rates will be derived from the rates for similar class of works as specified in the contract for the work. The opinion of the Engineer-in-Charge as to whether the rates can be reasonably so derived from items in the contracts will be final and binding on the contractor.

c) If the rates for the altered, additional or substituted work cannot be determined in the manner specified in sub-clause (a) and (b) above, then the contractor shall inform the Engineer-in-Charge of the rate which is his intension to charge for such class of work supported by analysis of the rate or rates claimed, and the Engineer-in-Charge shall determine the rates on the basis of the prevailing market rates of materials, labour

20

Page 107: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

cost at schedule of labour plus 10% to cover contractor’s supervision, overheads and profit and pay the contractor accordingly. The opinion of the Engineer-in-Charge as to the current market rates of materials and the quantum of labour involved per unit of measurement will be final and binding on the contractor.

d) Provisions, contained in sub-clause (a) to (c) above shall not, however, apply: Where the value of alterations / additions / deletions or substitutions exceeds beyond plus or minus 25% of the estimated contract value (i.e. quoted item rates of contractor shall hold good for variations etc. within plus or minus 25% of estimated contract value)

B) In the event and as a result of such alternatives / additions / substitutions / deletion, the scope of contract work

exceed the value stipulated in the contract by more than the limits given in clause (d) above, the Contractor shall claim revision of the rates supported by the proper analysis in respect of such items for quantities in excess of

the above limits, notwithstanding the fact that the rates for such items exist in the tender for the main work or can be derived in accordance with the provision of sub-clause (b) of Clause 61 A, and the Engineer-in-Charge may

revise their rates having regard to the prevailing market rates, and the contractor shall be paid in accordance with the rates so fixed. But, under no circumstances the contractor shall suspend / stop / slowdown the work on

the plea of non-settlement of rates of items falling under this clause.

62. ACTION WHERE NO SPECIFICATIONS ISSUED:

In case of any class of work for which there is no such specification given by the Owner in the tender documents, such work shall be carried out in accordance with Indian Standard Specifications and if the Indian Standard Specifications do not cover the same the work should be carried out as per standard Engineering Practice subject to the approval of the Engineer-in-Charge.

63. ABNORMAL RATES:

The contractor is expected to quote rate for each item after analysis of cost involved for the completion of item/work, considering all specifications and conditions of contract. This will avoid loss of profit or gain, in case of curtailment or change of specification for any item. In case it is noticed that the rates for any item, quoted by the tenderer are unusually high or unusually low (i.e. in case of variation plus or minus 25% between tendered rates and estimates), it will be sufficient cause for the rejection of the tender unless the Owner is convinced about the reasonableness of the rates on scrutiny of the analysis for such rate to be furnished by the tenderer on demand.

64 INSPECTION OF WORK: 64.1 The Engineer-in-Charge will have full power and authority to inspect the works at any time wherever in progress

either on the Site or at the contractor’s premises / workshop where situated premises /workshops of any person,

firm or corporation where work in connect with the contract may be in hand or where materials are being or are to

be supplied, and the contractor shall afford or procure for the Engineer-in-Charge every facility and assistance to

carry out such Inspection. The contractor shall at all time during the usual working hours and at all other time for

which reasonable notice of the intention of the Engineer in-Charge or his representative to visit the works have

been given to the contractor, either himself be present to receive order and instructions or post a responsible agent

duly accredited in writing for the purpose. Orders given to the contractor’s agent shall be considered to have the

same force as if they had been given to the contractor himself. The contractor shall give not less than seven days,

notice in writing to the Engineer-in-Charge before covering up or placing any work beyond reach of inspection and

measurement any work in order that the same may be inspected and measured. In the event of breach of above

the same shall be uncovered at contractor’s expense carrying out such measurement or inspection.

64.2 No materials shall be dispatched by the contractor before obtaining the approval of Engineer-in-Charge in writing. The contractor is to provide at all times during the progress of the work and the maintenance period, proper means of access with ladders, gangways, etc. and the necessary attendance to move and adopt as directed for inspection or measurement of the works by the Engineer- in-Charge.

65 ASSISTANCE TO THE ENGINEERS:

The contractor shall make available to the Engineer-in-Charge, free of cost necessary instruments and assistance in checking of setting out of works and taking measurement of work.

66. TESTS FOR QUALITY OF WORKS:

66.1 All workmanship shall be of the respective kinds described in the contract documents and in accordance with the

instructions of the Engineer-in-Charge and shall be subjected from time to time to such test at contractor’s cost as the Engineer-in-Charge may direct at place of manufacture or fabrication or on the site or at all or any such places. The contractor shall provide assistance, instruments, labour and materials as are normally required for examining, measuring and testing any workmanship as may be selected and required by the Engineer-in-Charge.

66.2 All the tests necessary in connection with the execution of the work as decided by Engineer-in-Charge shall be carried out at the field testing laboratory of the Owner by paying the charges as decided by the Owner from time to time. In case of non-availability of test facility with the Owner, the required test shall be carried out at the cost of contractor at government or any other testing laboratory as directed by Engineer-in-Charge.

21

Page 108: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

66.3 If any tests are required to be carried out in connection with the work or materials of which workmanship is not supplied by the contractor, such tests shall be carried out by the contractor as per the instructions of Engineer-in-Charge and cost of such tests shall be reimbursed by the Owner.

67. SAMPLES:

The contractor shall furnish to the Engineer-in-Charge for approval when requested or if required by the specifications, adequate samples of all materials and finishes to be used in the work. Such samples shall be submitted before the work is commenced and in ample time to permit tests and examinations thereof. All materials furnished and finishing applied in actual work shall be fully identical to the approval samples.

68. ACTION AND COMPENSATION IN CASE OF BAD WORK:

If it shall appear to the Engineer-in-Charge that any work has been executed with unsound, imperfect or unskilled

workmanship or with materials of any inferior description, or that any materials or articles provided by the contractor

for the execution of the work are unsound or of a quality inferior to that contracted for, or otherwise not in

accordance with the contract, the contractor shall on demand in writing from the Engineer-in-Charge or his

authorised representative, specifying the work, materials or articles complained of, notwithstanding that the same

have been inadvertently passed, certified and paid for forthwith shall rectify or remove and reconstruct the works

specified and provide other proper and suitable materials or articles at his own charge and cost, and in the event of

failure to do so within a period to be specified by the Engineer-in-Charge in his demand aforesaid, the contractor

shall be liable to pay compensation at the rate of one percentage of the estimated cost of the whole work, for every

week limited to a maximum of 10 per cent of the estimated cost of the whole work, while his failure to do so shall

continue and in the case of any such failure the Engineer-in-Charge may on expiry of notice period rectify or remove

and re-execute the work or remove and replace with others, the materials or articles complained of as the case may

be at the risk and expenses of the contractors in all respects. The decision of the Engineer-in-Charge as to any

question arising under this clause shall be final and conclusive. 69. SUSPENSION OF WORKS:

The contractor shall, if ordered in writing by the Engineer-in-Charge or his representative, temporarily suspend the works or any part thereof for such period and such time as so ordered and shall not, after receiving such written

order, proceed with the work therein ordered to be suspended, until he shall have received a written order to proceed therewith. The contractor shall not be entitled to claim/ compensation for any loss or damage sustained by

him by reason of temporary suspension of the works aforesaid. An extension of time for completion, corresponding

with the delay caused by any such suspension of the works as aforesaid will be granted to the contractor, should he apply for the same, provided that suspension was not consequent to any default or failure on the part of the

contractor.

70. OWNER MAY DO PART OF WORK:

Upon failure of the contractor to comply with any instructions given in accordance with the provisions of the contract, the owner has the alternative right, instead of assuming charge for entire work to place additional labour force, tools, equipments and materials on such parts of the work, as the owner may designate or also engage another contractor to carry out the work. In such cases, the owner shall deduct from the amount which otherwise

might become due to the contractor, the cost of such work and materials with ten percent added to cover all departmental charges and should the total amount thereof exceed the amount due to the contractor, the contractor shall pay the difference to the owner.

71. POSSESSION PRIOR TO COMPLETION:

The Engineer-in-Charge shall have the right to take possession of or use any completed or partially completed work or part of the work. Such possessions or use shall not be deemed to be an acceptance of any work completed in accordance with the contract agreement. If such prior possession or use by the Engineer-in-Charge delays the progress of work, suitable adjustment in the time of completion will made and contract agreement shall be deemed to be modified accordingly.

72. PERIOD OF LIABILITY FROM THE DATE OF COMPLETION OF WORK:

72.1 The contractor shall guarantee the installation/site work for a period of - 12 (twelve) Months from the date of

completion of work, unless otherwise specified. Any damage that may lie undiscovered at the time of issue of completion certificate, connected in any way with the equipment or materials supplied by him or in the workmanship shall be rectified or replaced by the contractor at his own expense as deemed necessary by the Engineer-in-

Charge or in default, the Engineer-in-Charge may cause the same made good by other workmen and deduct expenses (for which the certificate of Engineer-in-Charge shall be final) from any sums that may be then or at any time thereafter, become due to the contractor or from his security deposit.

22

Page 109: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

72.2 If the contractor feels that any variation in work or in quality of materials or proportions would be beneficial or necessary to fulfill the guarantee called for, he shall bring this to the notice of the Engineer-in-Charge in writing. The work will not be considered as complete and taken over by the Owner until all the temporary works etc., constructed by the contractor is removed and work site cleaned to the satisfaction of Engineer-in-Charge.

72.3 Care of Works:

From the commencement to completion of works, the contractor shall take full responsibility for the care of all works including all temporary works, and in case any damage, loss or injury happens to the works or to any part thereof or to any temporary work, from any cause whatsoever, he shall at own cost repair and make good the same, so that at completion, the work shall be in good order and in conformity in every respect with the requirements of the contract and the Engineer-in-Charge’s instructions.

72.4 Effects prior to taking over:

If at any time, before the work is taken over, the Engineer-in-Charge shall

a) Decide that any work done or materials used by the contractor or any sub-contractor is defective or not in accordance with the contract or that the works or any portion thereof are defective or do not fulfill the requirements of contract (all such matters being herein after called ‘Defects’ in this clause) and

b) As soon as reasonably practicable, notice given to the contractor in writing of the said decisions specifying particulars of the defects alleged to exist or to have occurred, then the contractor shall at his own expenses and with all speed make good the defects so specified.

In the case contractor shall fail to do so, the Owner may take, at the cost of the contractor, such steps as may in all

circumstances, be reasonable to make good such defects. The expenditure, so incurred by the Owner shall be

recovered from the amount due to the contractor. The decision of the Engineer-in-Charge with regard to the

amount be recovered from the contractor will be final and binding on the contractor. As soon as the works have

been completed in accordance with the contract (except in minor respects that do not affect their use for the

purpose for which they are intended and except for maintenance thereof provided in clause 72.1) and have passed

the tests on completion, the Engineer-in-Charge shall issue a certificate (hereinafter called completion certificate) in

which he shall certify the date on which the work have been so completed and have passed the said tests and the

Owner shall be deemed to have taken over the works on the date so certified. If the works have been divided into

various groups in the contract, the Owner shall be entitled to take over any group or groups before the other or

others and thereupon the Engineer-in-Charge shall issue a completion certificate which will however, be for such

group or groups as taken over only. 72.5 Defects after taking over:

In order that the contractor could obtain a completion certificate, he shall make good with all possible speed, any

defect arising from the defective materials supplied by the Contractor or workmanship or any act of omission of the

contract that may have been noticed or developed after the works or group of the works has been taken over. The

period allowed for carrying out such work will be normally one month. If any defect be not remedied within a

reasonable time, the Owner may proceed to do the work at the contractor’s risk and expense and recover such

expenses and other charges from amount payable to the contractor including security deposit and the contractor,

on demand of owner, shall pay the balance amount, if any, to the owner. If by reason of any default on the part of

the contractor a completion certificate has not been issued in respect of every portion of the work within one month

after the date fixed by the contract for the completion of the works, the Owner shall be at his liberty to use the works

or any portion thereof in respect of which a completion certificate has been issued provided that the works or the

portion thereof so used as aforesaid shall be afforded reasonable opportunity for completing these works for the

issue of completion certificate.

72.6 The Security Deposit/retention money deducted / furnished as per clause 18 of GCC shall be retained for the period of liability as given in clause 72.1 above. This Retention amount or Bank Guarantee furnished against Security Deposit/retention money shall be released only on expiry of the period of liability and also based on the certification of the Engineer-in-charge that no defect/damage has been reported / observed during the stipulated period of liability for the contract.

72.7 Performance of contractor shall be evaluated on each job by Engineer-in-Charge and recorded. The format given below is only indicative of major parameters on which performance will be evaluated. However, the detailed contractor performance monitoring format prevailing at the time of evaluation of contractor performance will be used. Review of performance will be carried out at appropriate intervals by BPCL.

23

Page 110: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

PERFORMANCE OF CONTRACTOR

Date... .................

JOB : ....................................................................................................................... ............................................ CONTRACTOR : ..................................................................................................................................................

CONTRACT NO. & DATE .....................................................................................................................................

DATE OF START : .................................................... DATE OF COMPLETION: ...................................................

PARAMETERS REMARKS

Resource Mobilisation

Quality consciousness

Safety awareness

Concern for Housekeeping

ENGINEER-IN-CHARGE NAME DESIGNATION

24

Page 111: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

SECTION VI BILLS / MEASUREMENT / PAYMENT

73. SCHEDULE OF RATES AND PAYMENTS:

i) Contractor’s Remuneration The price to be paid by the Owner to contractor for the whole of the work to be done and the performance of all the

obligations undertaken by the contractor under the contract documents shall be ascertained by the application of

the respective item rates (the inclusive nature of which is more particularly defined by way of application but not of limitation, with the succeeding sub-clause of this clause) and payment to be made accordingly for the work actually

executed and approved by the Engineer-in-Charge. The sum so ascertained shall (excepting only as and to the extent expressly provided herein) constitute the sole and inclusive remuneration of the contractor under the

contract and no further payment whatsoever shall be or become due or payable to the contractor under the

contract.

ii) Schedule of rates to be inclusive: The prices/rates quoted by the contractor shall remain firm till the issue of final completion certificate and shall not be subject to escalation. Schedule of rates shall be deemed to include and cover all costs, expense and liabilities of

every description and all risk of every kind to be taken in executing, completing and handing over the work to the Owner by the Contractor. The Contractor shall be deemed to have known the nature, scope, magnitude and the

extent of the works and materials required, though the contract document may not fully and precisely furnish them.

He shall make such provision in the item rates as he may consider necessary to cover the cost of such items of work and materials as may be reasonable and necessary to complete the works. The opinion of the Engineer-in-

Charge as to the items of work which are necessary and reasonable for completion of work shall be final and binding on the contractor, although the same may not be shown on or described specially in contract documents. Generality of this present provision shall not be deemed to cut down or limit in any way because in certain cases it may and in other cases it may not be expressly stated that the contractor shall do or perform a work or supply articles or perform services at his own cost or without addition of payment or without extra charges or words to the same effect or that it may be stated or not stated that the same are included in and covered by the schedule of rates.

iii) Schedule of Rates to Cover Constructional Equipments, Materials, Labour etc. Without in any way limiting the provisions of the preceding sub-clause, the schedule of rates shall be deemed to include and cover the cost of all constructional equipment, temporary work (except as provided for herein), pumps, materials, labour, the insurance, fuel, stores and appliances to be supplied by the contractor and other matters in connection with each item in the schedule of rates and the execution of the works or any portion thereof, finished, complete in every respect and maintained as shown or described in the contract documents or may be ordered in writing during the continuance of this contract.

iv) Schedule of Rates to cover Royalties, Rents and Claims: The Schedule of Rates shall be deemed to include and cover the cost of all royalties and fees for the articles and processes, protected by letters, or otherwise incorporated in or used in connection with the works, also all royalties, rents and other payments in connection with obtaining materials of whatsoever kind for the works and shall include an indemnity to the Owner which the contractor hereby gives against all actions, proceedings, claims damages,

costs and expenses arising from the incorporation in or use on the works of a such articles, processes or materials, Octroi or other municipal or local Board charges levied on materials, equipment or machineries to be brought to site for use on work shall be borne by the contractor. v) Schedule of Rates to Cover Taxes and Duties:

No claim or exemption or reduction of customs duties, excise duties, sales tax, quarry or any port dues, transport charges, stamp duties or Central or States Government or Local Body or Municipal Taxes or duties, taxes or charges (from or of any other body), whatsoever, will be granted or obtained, all of which expenses shall be deemed to be included in and covered by the Schedule of Rates. Contractor shall also obtain and pay for all permits, or other privileges necessary to complete work.

vi) Schedule of Rates to cover Risk of Delay: The schedule of Rates shall be deemed to include and cover the risk of all possibilities of delay and interference with the contractors conduct of work which occur from any cause including orders of owner in the exercises of his powers and on account of extension of time granted due to various reasons and for all other possible or probable cause of delay.

vii) Schedule of Rates cannot be altered:

For work under unit rate basis, no alteration will be allowed in the schedule of Rates by reason of work or any part of them being modified, altered, extended, diminished or omitted. The schedule of Rates are fully Inclusive rates which have been fixed by the contractor and agreed to the Owner and cannot be altered.

25

Page 112: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

For lumpsum contract, the payment will be made according to the work actually carried out for which purpose an item wise or workwise, Schedule of rates shall be furnished, suitable for evaluating the value of work done and preparing running account bills.

74. PROCEDURE FOR MEASUREMENT / BILLING OF WORK IN PROGRESS:

i) Measurements: All measurements shall be in metric system. All the works in progress will be jointly measured by the representative of the Engineer-in-Charge and the Contractor’s authorised agent progressively. Such measurement will be got recorded in the measurement book by the Engineer-in-Charge or his authorised representative and signed in token of acceptance by the contractor or his authorised representative. For the purpose of taking joint measurement the contractor’s representative shall be bound to be present whenever required by the Engineer-in-Charge. If, however, he absents for any reason whatsoever the measurement will be taken by the Engineer-in-Charge or his representative and this will be deemed to be correct and binding on the contractor.

ii) Billing: The contractor will submit a bill in approved proforma in duplicate (triplicate in the case of jobs executed through PMC) to the Engineer-in-Charge of the work giving abstract and detailed measurements for the various items executed during a month, before the expiry of the 1st week of the succeeding month. The Engineer-in-Charge shall take or cause to be taken the requisite measurements for the purpose of having the same verified and the claim, as far as admissible, adjusted, if possible, before the expiry of 10 days from presentation of the bill.

iii) Dispute in Mode of Measurements: In case of any dispute as to the mode of measurement not covered by the contract to be adopted for any item of work, mode of measurement as per latest Indian Standard Specifications shall be followed.

75. LUMPSUMS IN TENDER:

For the items in tender where it includes lumpsum in respect of parts of work, the contractor shall be entitled to payment in respect of the items at the same rates as are payable under this contract for such items, or if part of the work in question is not In the opinion of the Engineer-in-Charge capable of measurement of determination, the owner may at his discretion pay the lumpsum amount entered in the tender or a percentage thereof and the certificate in writing of the Engineer-in-Charge shall be final and conclusive against the contractor with regards to any sum or sums payable to him under the provisions of the clause.

76. RUNNING ACCOUNT PAYMENTS TO BE REGARDED AS ADVANCES:

All running account payments shall be regarded as payment by way of advance against the final payment only and not as payments for work actually done and completed and shall not preclude the requiring of bad, unsound and imperfect, or unskilled work to be removed and taken away and reconstructed or re-erected or be considered as an admission of the due performance of the contract, or any part thereof in this respect, or of the accruing of any claim

by the contractor, nor shall it conclude, determine or affect in any way the powers of the Owner under these conditions or any of them as to the final settlement and the adjustments of the accounts or otherwise, or in any other way vary or affect the contract.

The final bill shall be submitted by the contractor within one month of the date of physical completion of the work, and settled immediately but not later than 60 days. Otherwise the Engineer-in charge’s certificate of the measurement and of total amount payable for the work accordingly shall be final and binding on all parties. The final bill shall be presented by the contractor along with ‘No claim certificate’ in a format acceptable to the owner or such other documents as directed by the owner.

77. EXTRA WORK:

Should the contractor consider that he is entitled to any extra payment for extra job carried out whatsoever in respect of the works, he shall forthwith give notice in writing to the Engineer-in-Charge that he claims extra payment

for the extra work. Such notice shall be given to the Engineer-in-Charge within one week from the ordering of any

extra work or happening of any event, upon which the contractor bases such claims, and such notice shall contain full particulars of the nature of such claim with full details and amount claimed. Failure on part of the contractor to

put forward any claim with the necessary particulars as above within the time above specified shall be an absolute waiver thereof. No omission by the owner to reject any such claim and no delay in dealing therewith shall be waiver

by the owner of any rights in respect thereof. 78. PAYMENT OF CONTRACTOR’S BILL:

Generally no payment shall be made for works estimated to cost less than Rs. 50,000/- till the whole of the work shall have been completed. But in case of works estimated to cost more than Rs. 50,000/-, the contractor on submitting the bill thereof shall be entitled to receive a monthly payment proportionate to the part thereof

26

Page 113: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

approved and passed by the Engineer-in-Charge, whose certificate of such approval and passing of the sum so payable shall be final and conclusive against the contractor. This payment will be made after making necessary deductions as stipulated elsewhere in the contract document for materials, security deposit or any moneys due to the Owner etc.

79. MODE OF PAYMENT:

Payment will be made to the contractor normally through NEFT or RTGS mode.

80. COMPLETION CERTIFICATE:

80.1 Application for Completion Certificate:

When the contractor fulfills his obligation under clause 72.4, he shall be eligible to apply for completion certificate. The contractor may apply for separate completion certificate in respect of each such portion of the work by submitting the completion documents along with such application for completion certificate. The Engineer-in-Charge shall normally issue to the contractor the completion certificate within one month after receiving an application from the contractor after verifying from the completion documents and satisfying himself that the work has been completed in accordance with and as set out in the construction and erection drawings and the contract documents.

The contractor, after obtaining the completion certificate is eligible to present the final bill for the work executed by him under the terms of contract.

80.2 Completion Certificate:

The contractor shall be furnished with a certificate by the Engineer-in-Charge of such completion, but no certificate

shall be given nor shall the work be deemed to have been executed until all scaffolding surplus materials and rubbish is cleared off the site completely or until the work shall have been measured by the Engineer-in-Charge whose measurement shall be binding and conclusive. The work will not be considered as complete and taken over

by the Owner, until all the temporary works, labour and staff colonies etc. constructed are removed and the work site cleaned of all debris etc., as described in clause in 80.3 below and to the satisfaction of the Engineer-in-Charge.

If the contractor shall fail to comply with the requirements of this clause on or before the date fixed for the completion of the work, the Engineer-in-Charge may at the expenses of the contractor remove such scaffolding, surplus materials and rubbish and dispose off the same as he thinks fit and clean off such dirt as aforesaid, and the contractor shall forthwith pay the amount of all expenses so incurred and shall have no claim in respect of any such scaffolding or surplus materials as aforesaid except for any sum actually realised by the sale thereof.

80.3 Clearing the site:

Cart away all debris generated from the work and dispose it off without giving rise to any complaints from local, municipal or government authorities. Metal scraps or any other scrap including wooden packing materials shall be disposed as instructed by the Engineer-in-Charge or as follows: a) All unused scrap steel bar/ structural steel sections/pipe materials etc., (Free issue by owner) shall be the

property of the owner and the same shall be returned by the contractor category-wise at their own cost to Owner’s store. The weighment slip issued by the Warehouse (in original) is required to be attached along with the final bill/ material reconciliation statement. In case, the material is supplied by the contractor, as per their scope of work, the scrap material generated out of the same should be taken out at their own cost before the settlement of the final bill.

b) Insulation material (either issued by owner to the contractor or supplied by contractor) shall be kept in the area allocated by owner. During the insulation activities, the contractor should keep the work area clean on day-to-day basis. On completion of insulation job, all debris/packing should be taken out to the designated location or as directed by the Engineer in charge for disposal at their own cost before the settlement of the final bill.

80.4. The financial implication of above, if any, should be taken care of in the quoted rates; and no separate claim shall

be entertained on this account. The final bill of the contractor shall be linked with the area cleaning in all respects, including removal of shuttering material, disposal of debris/scrap etc. to the entire satisfaction of Engineer-in-Charge.

81. FINAL DECISION AND FINAL CERTIFICATE:

Upon Expiry of the period of liability and subject to the Engineer-in-Charge being satisfied that the works have been duly maintained by the contractor during monsoon or such period as herein before provided in clause 72 and that the contractor has in all respect duly made up any subsidence and performed all his obligations under the contract, the Engineer-in-Charge shall (without prejudice to the rights of the Owner to retain the provisions of relevant clause hereof) give a certificate herein referred to as the final certificate to that effect. The contractor shall not be considered to have fulfilled the whole of his obligations under the contract until Final Certificate have been given by

27

Page 114: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

the Engineer-in-Charge notwithstanding any previous entry upon the work and taking possession, working or using of the same or any part thereof by the owner.

82. CERTIFICATE FOR PAYMENTS AND EVIDENCE OF COMPLETION:

Except the final certificate, no other certificate or payments against a certificate or on general account shall be taken to be an admission by the Owner of the due performance of the contract or any part thereof or occupancy or validity of any claim by the contractor.

28

Page 115: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

SECTION VII TAXES/DUTIES/INSURANCE

83. TAXES, DUTIES, OCTROI ETC.:

The contractor agrees to and does hereby accept full and exclusive liability for the payment of any and all taxes,

duties, octroi etc. now in force or hereafter Imposed, increased or modified, from time to time in respect of work and

materials and all contributions and taxes for unemployment compensation, insurance and old age pensions or

annuities now or hereafter imposed by any Central or State Government authorities which are imposed with respect

to or covered by the wages, salaries, or other compensations paid to the persons employed by the contractor and

the contractor shall be responsible for the compliance with all obligations and restrictions imposed by the Labour

Law or any other law affecting employer - employee relationship and the contractor further agrees to comply and

secure the compliance by all sub-contractors, with all applicable Central, State, Municipal and local laws and

regulations and requirements of any Central, State or Local Government agency or authority. Contractor further

agrees to defend, indemnify and hold harmless from any liability or penalty which may be Imposed by the Central,

State of Local Authority by reason of any violation by contractor or sub-contractor of such laws, regulations or

requirements and also from all claims, suits or proceeding that may be brought against the Owner arising under,

growing out of, or by reason of the work provided for by this contract by third parties, or by Central or State

Government authority or any administrative sub-division thereof. 84. INSURANCE:

Contractor shall at his own expenses carry and maintain insurance with reputable insurance companies to the satisfaction of the Owner as follows:

i) Employees State Insurance Act:

The Contractor agrees to and does hereby accept full and exclusive liability for the compliance with all obligations imposed by the Employees State Insurance Act, 1948, and the contractor further agrees to

defend, indemnify and hold Owner harmless from any liability or penalty which may be imposed by the

Central, State or Local Authority by reason of any asserted violation by contractor or sub-contractor, of the Employee State Act, 1948 and also from all claims suits or proceedings that may be brought against

the Owner arising under, growing out of or by reason of the work provided for by this contract whether brought by employees of the contractor, by third parties or by Central or State Government authority or

any political sub-division thereof. The contractor agrees to filing, with the Employees State Insurance Corporation, the Declaration Forms

and all forms which may be required in respect of the contractor’s or sub-contractor’s employees whose

aggregate remuneration as fixed by the concerned authorities and who are employed in the work

provided for or those covered by ESI Act under any amendment to the Act from time to time. The

contractor shall deduct and secure the agreement of the sub-contractor to deduct the employee’s

contribution as per the first schedule of the Employee State Insurance Act from wages and affix the

Employee’s contribution Cards at Wages payment intervals. The contractor shall remit and secure the

agreement of the sub-contractor to remit to the authorized bank, Employee’s State Insurance Corporation

Account, the Employee’s contribution as required by the Act. The contractor agrees to maintain all Cards

and records as required under the Act in respect of employees and the payments and the contractor shall

secure the agreement of the subcontractor to maintain such records. Any expenses incurred for the

contribution, making contribution or maintaining records shall be to the contractor’s or sub-contractor’s

account. The Owner shall retain such sum as may necessary, from the total contract value until contractor shall furnish satisfactory proof that all contributions as required by the Employees State Insurance Act, 1948, have been paid.

ii) Workman’s Compensation and Employee’s Liability Insurance: Insurance shall be effected for all the Contractor’s employees engaged in the performs of this contract, if any of the work is sublet, the contractor shall require the sub-contractor to provide workman’s compensation and employer’s liability Insurance for the latter’s employees if such employees are not covered under the contractors insurance.

iii) Any other Insurance Required Under Law or Regulations or by Owner: Owner shall cover Project Material and Equipments under and over all Marine-cum-Erection Insurance Policy. Contractor shall carry and maintain any and all other insurance which be required under any law or regulation from time to time. He shall also carry and main any other insurance which may be required by the Owner.

iv) Automobile Liability Insurance: Contractor shall take out an Automobile Liability Insurance to cover all risks to Owner for each of his vehicles plying on works of this contract and these insurance shall be valid for the total contract period. No extra payments will be made for this insurance. Owner shall not be liable for any damage or loss not made good by the insurance company, should such damage or toss result from unauthorised use of the vehicle.

29

Page 116: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

85. DAMAGE TO PROPERTY:

i) Contractor shall be responsible for making good, to the satisfaction of the Owner any loss of and any damage to all structures and properties belonging to the Owner or being executed or procured or being procured by the Owner or of other agencies within the premise all the work of the Owner, if such loss or damage is due to fault and/or the negligence willful acts or omission of contractor, his employees, agents, representative or sub-contractor.

ii) The contractor shall indemnify and keep the Owner harmless of all claims for damage to property other than Owner’s property arising under or by reason of this agreement if such claims results from the fault and/or negligence or willful acts or omission of contractor, his employees, agents, representatives or sub-contractors.

30

Page 117: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

SECTION VIII LABOUR LAWS AND OTHER REGULATIONS

86. LABOUR LAWS:

i) No labour below the age of eighteen years shall be employed on the work. ii) The contractor shall not pay less than what is provided under the Minimum Wages Act for the applicable

trade or category of workman to the worker engaged by him on the work and also ensure that any sub-contractors engaged by him also pay not below the applicable minimum wages under the Act and hold the company, indemnified in respect of any claims that may arise in respect or non-compliance with this requirements.

iii) The contractor shall observe all the formalities required under the provisions of the contract labour

(Regulation and abolition) Act 1970 and the rules made thereunder and as may be amended from time to

time. He shall pay the required deposit under the Act Appropriate to the number of workmen to be

employed by him or through sub-contractor and get him self registered under the Act. He shall produce

the certificate of registration granted by the Govt. authority under the Act to the company before

commencement of work. The company recognises only the contractor and not his sub-contractors under

the provisions of the Act. The contractor will have to submit daily a list of his employees, who will be

entering the Company’s premises for the work awarded. He will also keep his wage register available at

all times as close to the work site as possible and produce the same for inspection whenever required by

designated Company officials. If the company so desires, a deposit may be taken from the Contractor to

be refunded only after the Company is satisfied that all the workmen employed by the contractor have

been fully paid for the period of work in Company’s premises at least at rates equal to or better than

wages provided for under the Minimum Wages Act. iv) The Contractor will comply with the provisions of the employee’s Provident Fund Act and the Family

Pension Fund Act as may be applicable and as amended from time to time. Contractor shall obtain their own provident fund account number. Offer of the contractor who does not have provident fund account will be liable for rejection.

v) The Contractor will comply with the provisions of the Payment of Gratuity Act 1972 as may be applicable and as amended from time to time.

87. IMPLEMENTATION OF APPRENTICES ACT 1961:

The Contractor shall comply with provisions of the Apprentices Act 1961 and the Rules/orders issued thereunder from time to time. If he fails to do so, his failure will be breach of the contract and the Engineer-in-Charge may, at his discretion, cancel the contract. The contractor shall also be liable for any pecuniary liability arising on account of any violation by him of the provision of the act.

88. CONTRACTOR TO INDEMNIFY THE OWNER:

i) The contractor shall indemnity the owner and every member, officer and employee of the Owner, also the Engineer-in-Charge and his staff against all actions, proceedings, claims, demands, costs, and expenses

whatsoever arising out of or in connection with the matters referred to in clause 84 and all actions/

proceedings, claims, demands, costs and expenses which may be made against the Owner for or in

respect of or arising out of any failure by the contractor in the performance of his obligations under the

contract documents. The Owner shall not be liable for or in respect of any demand or compensation

payable by law in respect of or in consequence of any accident or injury to any workmen or other person

in the employment of the contractor or his sub-contractor and contractor shall indemnify and keep

indemnified the Owner against all such damages and compensations and against all claims, damage,

proceedings, costs, charges and expenses whatsoever, thereof or in relation thereto. ii) Payment of Claims and Damages:

Should the Owner have to pay any money in respect of such claims or demands as aforesaid the amount so paid and the costs incurred by the Owner shall be charged to and paid the Contractor and the contractor shall not be at liberty to dispute or question the rig of the Owner to make such payments notwithstanding the same may have been made without his consent or authority or in law or otherwise to the country. In every case to which by virtue of the provisions of Section 12, sub-section (I) of workmen’s

compensation Act 1923 or other applicable provisions of workmen’s Compensation Act any other Act, the

Owner is obliged to pay compensation to a workmen employed by contractor in execution of the works,

the Owner will recover from the contractor the amount of compensation so paid and without prejudice to the rights of Owner under Section 12 sub-section (2) of the said Act. Owner shall be at liberty to recover

such amount or any part thereof by deducting it from the security deposit or from any sum due to the

contractor whether under the contract or otherwise. The Owner shall not be bound to contest any clime

made under Section 12, sub-section (I) of the said Act except on the written request of contractor and

upon his giving to the Owner full security for all costs for which the Owner might become liable on

consequence of contesting such claims.

31

Page 118: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

iii) Employment Liability: a) The contractor shall be solely and exclusively responsible for engaging or employing persons for the

execution of work. All employees engaged by the contractor shall be on his/ their payroll and paid

by him/ them. All disputes or differences between the contractor and his/ their employees shall be

settled by him/ them. Owner has absolutely no liability whatsoever concerning the employees of the

contractor. The contractor shall indemnify owner against all loss or damage or liability arising out of

or in the course of his/ their employees. The contractor shall make regular and full payment of

wages without giving any complaint by any employee of the contractor or his sub-contractor

regarding non-payment of wages/ salaries or other dues. Owner reserves the right to make such

payments directly, to such employee or sub-contractor of the contractor and recover the amount in

full from the bills of Contractor, and the contractor shall not claim any compensation or

reimbursement thereof. The Contractor shall comply with the Minimum Wages Act applicable to the

area with regard to payment of wages of his employees and also of employees of his sub-

contractor.

b) The Contractor shall advise in writing to all of his employees and the employees of his sub-

contractor as follows: It is fully understood that your appointment and/ or deployment is only in connection with the work / job and it does not give you any right of claim for employment by owner.

89.A HEALTH AND SANITARY ARRANGEMENTS FOR WORKERS:

In respect of all labour directly employed in the works for performance of the contractor’s par this agreement, the contractor shall comply with or cause to be complied with all the rules and regulations of the local sanitary and other authorities or as framed by the Owner from time to time for the protection of health and sanitary arrangements for all workers.

89.B MEDICAL FITNESS CERTIFICATION :

Contractor shall follow guidelines for medical fitness certification of workers employed for working at height more than 30 metres using temporary structures.

90. SAFETY REGULATIONS:

i) In respect of all labour, directly or indirectly employed In the work for the performance of contractor’s part of this agreement, the contractor shall at his own expenses arrange for all safety provisions as per safety codes of C.P.W.D. Indian Standard Institution, the Electricity Act, The Mines Act and any such other acts as applicable.

ii) The Contractor shall ensure that he, his sub-contractor and his, or their personnel or representatives shall comply with all Fire / Safety regulations issued from time to time by the Company or otherwise howsoever and should any injury resulting in death or not or loss / or damage due to Fire to any property or a portion thereof, occurred as a result of failure to comply with such regulations, the contractor shall be held responsible for the consequences thereof and shall keep the company harmless and indemnified.

91. A ARBITRATION:

a) Any dispute or difference of any nature whatsoever, any claim, cross-claim, counter-claim or set off of the Company against the Contractor or regarding any right, liability, act, omission or account of any of the parties hereto arising out of or in relation to this agreement shall be referred to and finally resolved by Sole Arbitrator, who shall be appointed by Director (Refinery) of BPCL as per the procedure given in sub-clause (b) given herein below.

b) Procedure for appointing the sole arbitrator: A party wishing to commence an arbitration (the “Claimant”) shall file with

the Director (Refinery) of BPCL a Notice of Arbitration which shall comprise: i. a demand that the dispute be referred to arbitration; ii. a reference to the arbitration clause or the arbitration agreement that is invoked and a copy of it; iii. a reference to the contract out of or in relation to which the dispute arises and where possible, a copy of it; iv. a brief statement describing the nature and circumstances of the dispute, specifying the relief claimed and,

where possible, an initial quantification of the claim amount. v. any other details which the claimant wishes to refer and rely upon.

Upon receipt of the above notice of arbitration, the Director (Refinery) of BPCL shall appoint the Sole Arbitrator as per

the provisions of the Arbitration and Conciliation Act, 1996.

c) The venue of arbitration shall be Mumbai (in case of Mumbai Refinery) or Kochi (in case of Kochi Refinery). The award of the arbitrator so appointed shall be final, conclusive and binding on all parties to the agreement subject to the provisions of the Arbitration & Conciliation Act, 1996 or any statutory modification or re-enactment thereof and the rules made thereunder for the time being in force shall apply to the arbitration proceedings under this clause.

32

Page 119: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

d) The arbitrator shall have power to order and direct either of the parties to abide by, observe and perform all such directions as the arbitrator may think fit having regard to the matters in difference i.e. dispute, before him. The arbitrator shall have all summary powers and may take such evidence oral and/or documentary, as the arbitrator in his absolute discretion thinks fit and shall be entitled to exercise all powers under the Indian Arbitration & Conciliation Act 1996 including admission of any affidavit as evidence concerning the matter in difference i.e. dispute before him.

e) The parties against whom the arbitration proceedings have been initiated, that is to say, the Respondents in the proceeding, shall be entitled to prefer a cross-claim, counter claim or set off before the Arbitrator in respect of any matter in issue arising out of or in relation to the Agreement without seeking a formal reference of arbitration for such counter-claim, cross claim, or set off and the Arbitrator shall be entitled to consider and deal with the same as if the matters arising therefrom has been referred to him originally and deemed to form part of the reference made by the Director(Refinery).

f) The arbitrator shall be at liberty to appoint, if necessary any accountant or engineering or other technical person to

assist him, and to act by the opinion so taken.

g) The arbitrator shall have power to make one or more awards whether interim or otherwise in respect of the dispute and

difference and in particular will be entitled to make separate awards in respect of claims of cross claims of the parties.

h) The arbitrator shall be entitled to direct any one of the parties to pay the costs to the other party in such manner and to such extent as the arbitrator may in his discretion determine and shall also be entitled to require one or both the parties to deposit funds in such proportion to meet the arbitrators expenses whenever called upon to do so.

i) The parties hereby agree that the courts in the city of Mumbai (in case of Mumbai Refinery) or Kochi (in case of Kochi Refinery) alone shall have jurisdiction to entertain any application or other proceedings in respect of anything arising under this agreement and any award or awards made by the Sole Arbitrator hereunder shall be filed (if so required) in the concerned courts in the city of Mumbai (in case of Mumbai Refinery) or Kochi (in case of Kochi Refinery) only.

j) SETTLEMENT OF DISPUTE BETWEEN GOVT. DEPT. /PUBLIC SECTOR UNDERTAKINGS

IN A PURCHASE OR SERVICE CONTRACT :

In the event of any dispute or differences between the VENDOR/ CONTRACTOR/

SUPPLIER and the OWNER, if the VENDOR/ CONTRACTOR/ SUPPLIER is a Government

Department, a Government Company or a Undertaking in the public sector, then in

suppression of the provisions of clause 23 of the GPC (corresponding clause no of GCC

or NIT etc.), stands modified to the following extent:-

all disputes and differences of whatsoever nature arising out of or in relation to this

Contract/ Agreement or in relation to any subsequent contract/ agreement between

the parties shall be attempted to be resolved amicably by mutual discussions between

the parties. If they are not settled at the implementation level of officers, then these

unresolved disputes/ differences will be referred for resolution by discussions with the

concerned Director of BPCL and the concerned Director of vendor/ contractor/

supplier. In case same does not resolve the difference within 30 days, arbitration clause

as hereunder would apply.

In the event of any dispute or difference relating to the interpretation and application

of the provisions of the contract, such dispute or difference shall be referred by either

party for Arbitration to the sole Arbitrator in the Department of Public Enterprises to

be nominated by the Secretary to the Government of India in-charge of the

Department of Public Enterprises. The Arbitration and Conciliation Act, 1996 shall not

be applicable to arbitration under this clause. The award of the Arbitrator shall be

binding upon the parties to the dispute provided, however, any party aggrieved by such

award may make a further reference for setting aside or revision of the award to the

Page 120: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Law Secretary, Department of Legal Affairs, Ministry of Law & Justice, Government of

India. Upon such reference the dispute shall be decided by the Law Secretary or the

Special Secretary/ Additional Secretary, when so authorized by the Law Secretary,

whose decision shall bind the Parties finally and conclusively. The parties to the

dispute will share equally the cost of arbitration as intimated by the arbitrator.

92. JURISDICTION :

The contractor shall be governed by the Laws in force in INDIA. The contractor hereby submits to the jurisdiction of the Courts situated at Mumbai (Ernakulam-in the case of Kochi Refinery), for the purpose of actions and proceedings arising out of the contract and the courts at Mumbai (Ernakulam-in the case of Kochi Refinery), only will have jurisdiction to hear and decide such actions and proceedings.

33

Page 121: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

SECTION - IX VARIOUS PROFORMA

ANNEXURE 1

PROFORMA OF AGREEMENT CONTRACT AGREEMENT FOR THE WORK OF ...................................................................................... .................................................................................... DATED ............................................................. ................................................................................................................................................................ between M/s ................................................................................................................................................................. in the town of ....................................................................................... hereinafter called the “CONTRACTOR” (which term shall unless excluded by or repugnant to the subject or context include its successors and permitted assignees) of the one part and the Bharat Petroleum Corporation Limited hereinafter called the “OWNER” (which term shall, unless excluded by or repugnant to the subject to context include its successors and assignees) of the other part.

WHEREAS

A. B. The contractor has inspected the site and surroundings of the works specified in the tender documents and has satisfied

himself by careful examination before submitting his tender as to the nature of the surface strata, soil, sub-soil and

ground, the form and nature of site and local conditions, the quantities, nature and magnitude of the work, the availability

of labour and material necessary for the execution of work, the means of access to site, the supply of power and water

thereto and the accommodation he may require and has made local and independent enquiries and obtained complete

information as to the matters and things referred to, or implied in the tender documents or having any connection

therewith and has considered the nature and extent of all probable and possible situations, delays, hindrances, or

interferences to or with the execution and completion of the work to be carried out under the Contract and has examined

and considered all other matters, conditions and things and probable and possible contingencies and generally all

matters incidental thereto and ancillary and thereof effecting the execution and completion of the work and which might

have influenced him in making his tender. C. The Notice Inviting Tender, General Conditions of Contract, Special Conditions of Contract, Specification, Drawings,

Plans, Time Schedule of Jobs, and other documents, copies of all which are hereto annexed and marked “A”, the letter of submission of tender and Acceptance of Tender and statement of agreed variations with its enclosures, copies of which are also hereto annexed and marked “B” form part of his contract though separately set out herein and or included in the expression “CONTRACT” wherever herein used. And whereas: The Owner accepted the Tender of the Contractor for the Provision and the execution of the said work at the rates stated in the Schedule of Quantities of works and finally approved by Owner (hereinafter called the “Schedule of Rates”) upon the terms and subject to the conditions of contract. Now this Agreement Witnesseth And, it is hereby agreed and declared as follows: In consideration of the payment to be made to the contractor for the work to be executed by him, the contractor hereby convensants with the owner that the contractor shall and will duly provide, execute and complete the said works and shall do and perform all other acts and things in the contract mentioned or described or which are to the implied therefrom or may be reasonably necessary for the completion of the said works and at the said times and in the manner and subject to the terms and conditions or stipulations mentioned in the contract. In consideration of the due provision, execution and completion of the said works, the Owner does hereby agree with the contractor that the Owner will pay to the contractor the respective amounts for the works actually done by him and approved by the Owner at the Schedule of Rates and such other sum payable to the contractor under provision of Contract, such payments to be made at such time in such manner as provided for in the contract.

AND In consideration of the due provision, execution and completion of the said works the contractor does hereby agree to pay such sums as may be due to the Owner for the services rendered by the owner to the contractor, such as power supply, water supply and other as set for in the said contract and such other as may become payable to the Owner towards the controlled items of consumables materials or towards loss, damage to the Owner equipments, materials, construction equipments and machinery, such payments to be made at such time and in such manner as is provided in the contract. It is specifically and distinctly understood and agreed between the Owner and the Contractor that the contractor shall

have no right title or interest in the site made available by the Owner for the execution of the work or in the buildings, structures or works executed on the said site by the contractor or in the goods, articles, materials etc. brought on the said site (unless the same specifically belongs to the contractor) and the contractor shall not have or dressed to have any lien whatsoever charge for unpaid bills nor will be entitled to assume or retain possession or control of the site or

structures and the Owner shall have an absolute and unfattered right to take full possessions of the site and remove the contractor, their servants, agents and materials belonging to the contractor and lying on the site. The contractor shall be allowed to enter upon the site for execution of the works only as a licenses simplicater and shall not have any claim, right, titles or interest in the site or the structures erected thereon and the Owner shall be entitled to terminate such licence at any time without assigning reason. The materials including sand, gravel, stone, loose earth, rock etc., dug up or excavated from the said site shall, unless otherwise expressly agreed under this contract, exclusively belong to the Owner and the contractor shall have no right

The Owner being desirous of having provided and executed works mentioned, enumerated or referred to in the tender documents including Short Tender Notice. General Tender Notice, General Conditions of Contract, Special Conditions of Contracts, Specifications, Drawings, Plans, Time Schedule for Completion of jobs, Agreed Variations, other documents, has called for Tender.

Page 122: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

34

Page 123: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

to claim over the same and such excavations and materials should be disposed off on account of the Owner according to the instructions in writing issued form time by the Engineer-in-Charge. In witness whereof the parties have executed these presents in the day the year first above written

Signed and Delivered for and Signed and Delivered for and on behalf of Owner i.e. on behalf of Contractor Bharat Petroleum Corporation Limited (Name, designation and address of authorized signatory)

DATE.... ... ... ... ... ... .... ... ... ... ... ... .... ... ... ... ... ... .... ... ... .. DATE.........................................................................

PLACE... ... .... ... ... ... ... ... .... ... ... ... ... ... .... ... ... ... ... ... ... PLACE......................................................................

In Presence of Two Witnesses

BPCL witnesses – Signature,Name & Address:- Contractor’s witnesses – Signature, Name & Address:-

1. .......................................................................... 1. ..........................................................................

2. ........................................................................... 2. .........................................................................

35

Page 124: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

ANNEXURE 2

PROFORMA OF BANK GUARANTEE for EARNEST MONEY /INITIAL/ FULL SECURITY DEPOSIT (On non-judicial paper of appropriate value)

To, Bharat Petroleum Corporation Ltd. (Address) Dear Sirs, M/s. ______________________(hereinafter referred as “BIDDER”/”CONTRACTOR") (Bidder’s / Contractor’s name and address) have

taken tender for the WORK of _______________________ (Name of Work) for Bharat Petroleum Corporation Limited, with registered

office in Bharat Bhavan, 4 & 6 Currimbhoy Road, Ballard Estate, Mumbai, India (hereinafter referred as “OWNER”).

The tender conditions provide that the BIDDER / CONTRACTOR shall pay a sum of Rs. _____________ (Rupees ___________________________________) as earnest money /initial/ full security deposit in the form therein mentioned . The form of payment of earnest money / initial / full security deposit includes guarantee executed by schedule “A” Bank, undertaking full

responsibility to indemnify OWNER in case of default. The said BIDDER/CONTRACTOR have approached us and at their request and

in consideration of the premises, we _________________(Bank’s name) having our office at ________________ ( hereinafter referred

as “GUARANTOR’) have agreed to give such guarantee as hereinafter mentioned.

1. GUARANTOR hereby undertake and agree that if default shall be made by BIDDER / CONTRACTOR in performing any of

the terms and conditions of the tender, GUARANTOR do hereby irrevocably bind themselves and undertake to pay the

OWNER on first demand in writing by OWNER without protest or demur or proof or condition and without reference to the

BIDDER / CONTRACTOR, the said amount of Rs. __________(Rupees ______________________________)

2. OWNER will have the full liberty without reference to GUARANTOR and without effecting this guarantee to postpone for any

time or from time to time the exercise of any of the powers and rights conferred on OWNER under the tender with the said

BIDDER/CONTRACTOR and to enforce or to forbear from endorsing any powers or rights or by reason of time being given to

the said BIDDER / CONTRACTOR which under law relating to the sureties would but for provision have the effect of releasing

the GUARANTOR.

3. OWNER will have the right to recover the said sum of Rs.___________________(Rupees ______________________) from

GUARANTOR in manner aforesaid and such rights will not be affected or suspended by reason of the fact that any dispute or

disputes have been raised by the said BIDDER / CONTRACTOR and or that any dispute or disputes are pending before any

officer, tribunal or court.

4. The guarantee herein contained shall not be determined or affected by the liquidation or winding up, dissolution or change of

constitution or insolvency of the said _______________(Bidder’s / Contractor’s Name).

5. GUARANTOR’S liability under this guarantee is restricted to Rs. __________(Rupees ______________________). This

guarantee shall remain in force until ___________________ unless a demand (3 months beyond bid validity) under

guarantee is made against GUARANTOR within the aforesaid date, in which event the validity of this bank guarantee shall

automatically be extended for another 3 (three) months, all rights under the said guarantee shall be forfeited and

GUARANTOR shall be relieved and discharged from all liabilities thereunder.

36

Page 125: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

6. GUARANTOR have power to issue this guarantee in your favour under Memorandum and Articles of Association and the

undersigned has full power to do under the Power of Attorney dated ______________________granted to him by the Bank.

Yours faithfully,

_________________Bank

by its Constituted Attorney.

Signature of a person duly authorized to Sign on behalf of the bank.

NOTE: In case of earnest money, BIDDER shall be applicable and in case of initial / full security deposit, CONTRACTOR shall be applicable.

37

Page 126: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

ANNEXURE 3

PROFORMA OF BANK GUARANTEE FOR MOBILIZATION ADVANCE

(On non-judicial paper of appropriate value)

To,

Bharat Petroleum Corporation Ltd. (Address)

Dear Sirs,

In consideration of Bharat Petroleum Corporation Limited, with registered office in Bharat Bhavan, 4 & 6 Currimbhoy Road, Ballard Estate,

Mumbai, India and having Refinery at …….(Mumbai / Kochi as the case may be) (hereinafter referred to as “The Company” which expression

shall unless repugnant to the context or meaning thereof include its successors and assigns) having placed on Messrs………………………

(Name) ……………………………. (Constitution) ……………………………………………………………………... (address) (hereinafter referred to

as “The Contractor” which expression shall unless repugnant to the context or meaning thereof include its successors, administrators,

representatives and assigns) an order for …………………………….. (Name of Job) under and in terms of a Contract as evidenced by a Letter of

Acceptance No. …………………… and / or Purchase Order No. …………………. dated …………….. valued at Rs. …………… (Rupees …………………………….. only), issued by the Company to the Contractor, read with the relevant Tender Documents (hereinafter collectively called "the Contract" which expression shall include any formal contract entered into between the Company and the Contractor in supersession of the said Letter of Acceptance and all amendments and/or modifications therein or in the terms of the said advance as herein stipulated).

AND WHEREAS the Company has agreed to advance the Contractor, inter-alia, recoverable interest bearing mobilization advance up to a maximum of 10% ( ten percentage) of the contract value (hereinafter referred to as “MOBILIZATION ADVANCE) in the manner

provided for in the Bidding Document, a sum of Rs…………………..(Rupees…………….only) being the first / second installment (Delete whichever is not applicable) of Mobilization Advance upon the condition, inter-alia, that the said Advance together with interest thereon at

the rate of 10% (10 percentage) per annum on reducing balance basis on the amount of the said Advance for the time being outstanding shall, without prejudice to any other mode of recovery available to the Company, be recoverable by the Company by deduction from the

gross accepted amount of any Running Account Bills of the Contractor commencing from the first Running Account Bill of the Contractor

in equal monthly installments together with the interest accrued within a time span of ………… Months in the manner provided for in the Bidding Document and meanwhile, the said Advance shall be secured by an undertaking from a Bank as hereinafter appearing.

We____________________________ (Name of the Bank), a body registered/constituted under the ______________________________________________Act, having Registered Office/Head Office at______________________________(hereinafter called the "Bank" which expression shall include its successors and assigns), at the request of the Contractor and with the intent to bind the Bank and its successors and assigns, do hereby unconditionally and irrevocably undertake to pay the Company forthwith on first demand without protest or demur or proof or satisfaction and without reference to the

Contractor, any and all amounts demanded from us by the Company with reference to this Undertaking upto an aggregate limit of Rs.______________ (Rupees __________________________________________ only) being 110% of the aforesaid advance and interest thereon at the rate hereinabove provided.

AND the Bank doth hereby further agree as follows: -

i) This Guarantee/Undertaking shall be a continuing guarantee and shall remain valid and irrevocable for all claims of the Company upon

the Bank made up to the midnight of______________(contractual completion date) provided that the Bank shall upon the written request of the Company made upon the Bank at any time within 6 (six) months from the said date extend the validity of the Bank Guarantee by a further 6 (six) months so as to enable claims to be made under this Guarantee by a further 6 (six) months from the said date with the intent that the validity of this Guarantee shall automatically stand extended by a further 6 (six) months upon such request by the Company.

ii) The Company shall have the fullest liberty without reference to the Bank and without affecting in any way the liability of the Bank under

this guarantee/undertaking, at any time and/or from time to time to amend or vary the contract and/or any of the terms and conditions

thereof or relative to the said Advance and/or to extend time for performance of the said contract in whole or part and/or payment of the

said Advance in whole or part or to postpone for any time and/or from time to time any of the said obligations of the Contractor and/or

the rights, remedies or powers exercisable by the Company against the Contractor and either to enforce or forbear from enforcing any of

the terms and conditions of or governing the said Contract and/or the said Advance, or the securities, available to the Company and the

Bank shall not be released from its liability under these Presents and the liability of the Bank shall remain in full force and effect

notwithstanding any exercise by the Company of the liberty with reference to any or all the matters aforesaid or by reason of time being

given to the Contractor or any other forbearance, act or omission on the part of the Company or any indulgence by the Company to the

Contractor or of any other act, matter or thing whatsoever which under any law could (but for this provision) have the effect of releasing

the Bank from its liability hereunder or any part thereof and the Bank hereby specifically waives any and all contrary rights whatsoever.

38

Page 127: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

iii) The obligations of the Bank to the Company hereunder shall be as principal to principal and shall be wholly independent of the Contract and it shall not be necessary for the Company to proceed against the Contractor before proceeding against the Bank and the guarantee/undertaking herein contained shall be enforceable against the Bank as Principal debtor notwithstanding the existence of any undertaking or security for any indebtedness of the Contractor to the Company (including relative to the said Advance) and notwithstanding that any such undertaking or security shall at the time when claim is made against the bank or proceedings taken against the Bank hereunder, be outstanding or unrealised.

iv) As between the Bank and the Company for the purpose of this undertaking, the amount stated in any claim, demand or notice made by the Company on the Bank with reference to this undertaking shall be final and binding upon the Bank as to be the amount payable by the Bank to the Company hereunder notwithstanding any dispute or disputes has been raised by the Seller and are pending before any arbitration, Tribunal or Court.

v) The liability of the Bank to the Company under this undertaking shall remain in full force and effect notwithstanding the existence of any difference or dispute between the Contractor and the Company, the Contractor and/or the Bank and/or the Bank and the Company or otherwise howsoever touching or affecting these presents or the liability of the Contractor to the Company, and notwithstanding the existence of any instructions or purported instructions by the Contractor or any other person to the Bank not to pay or for any cause withhold or defer payment to the Company under these presents, with the intent that notwithstanding the existence of such difference, dispute or instruction, the Bank shall be and remain liable to make payment to the Company in terms hereof.

vi) This undertaking shall not be determined or affected by any change in the constitution of the Bank or that of the Contractor or the

Company or any irregularity in the exercise of borrowing powers by or on behalf of the Contractor.

vii) The Bank agrees that the guarantee herein contained shall continue to be enforceable till the sum due to the Company on account of

the said advance is adjusted as aforesaid or till the Company discharges this guarantee.

viii) The Bank further undertakes not to revoke this guarantee during its currency without the previous consent of the Company. ix) The Bank also agrees that the Company shall be entitled to enforce this guarantee, notwithstanding any other security or guarantee

that it may have in relation to the vendor’s liability for the said advance.

x) Without prejudice to any other mode of service, a demand or claim or other communication may be transmitted by the Company to the

Bank either by post or by fax. If transmitted by fax, the transmission shall be complete as soon as acknowledged by bank.

xi) Notwithstanding anything contained herein:

(i) The Bank's liability under this guarantee/undertaking shall not exceed ______________________________________________________ (Amount in figures & words);

(ii) This guarantee/undertaking shall remain in force upto______________ and any extension(s) thereof; and (iii) The Bank shall be released and discharged from all liability under this guarantee/undertaking unless a written claim or

demand is issued to the Bank on or before_________________ or the date of expiry of any extension(s) thereof if this guarantee/undertaking has been extended.

xii) This Guarantee shall be treated as an unconditional guarantee and the Contractor shall have no right to object or obstruct in any way

the enforcement of this guarantee.

Yours faithfully,

Signature: _________________________________________

Name & Designation: ________________________________

Name of the Branch: _________________________________

Dated: ____________________________________________

39

Page 128: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

ANNEXURE 4 PROFORMA OF BANK GUARANTEE TOWARDS ADVANCE

(On non-judicial stamp paper of appropriate value) To, Bharat Petroleum Corporation Ltd. (Address)

Dear Sir, WHEREAS Bharat Petroleum Corporation Ltd. with registered office in Bharat Bhavan, 4 & 6 Currimbhoy Road, Ballard Estate, Mumbai, India and having Refinery at …….(Mumbai / Kochi as the case may be) (hereinafter referred to as “the Corporation” which expression shall unless repugnant to the context include their legal representatives, successors and assigns, have entered into a contract (hereinafter referred to as “the Contract”) with M/s ______________________AND WHEREAS one of the conditions of the said contract is that the Corporation should make an advance payment to the contractor _____________(Rupees___________________only) being ………% (……….. percent) of the value of the contract against a bank guarantee from Schedule ‘A’ bank. AND WHEREAS at the request of the contractor, the Corporation has agreed to accept the Bank Guarantee from ___________________ Bank (hereinafter referred to the “Surety”) having their registered office at ________________________________________________________. NOW THIS GUARANTEE WITNESSETH that in consideration of the Corporation having at the request of the contractor agreed to accept bank

guarantee of the surety in respect of advance of Rs. ______ (Rupees ______________________only) payable by the Corporation to the

contractor as per terms of the said contract, the Surety hereby undertake and agree that if the said amount advance payment shall become

reduced and/ or extinguished under terms of the contract between Corporation and Contractor, the Surety do hereby irrevocably bind themselves

and undertake to pay to the Corporation on first demand in writing by the Corporation without protest or demur or proof or condition and without

reference to the contractor, the amount not exceeding altogether a sum of Rs. ____ (Rupees _______________only) being the amount of advance payment or such other unadjusted amount of the said advance. The decision of the Corporation as to the whether the terms and conditions of the Contract or this guarantee have been observed shall be final and binding on the Surety. THE GUARNTEE HEREIN CONTAINED is not revocable during the currency of the contract and will remain in force until:

a) Payment has been made to the Corporation by the Surety of the aggregate amount payable hereunder.

b) The Contract for which this advance payment is being made is completed to the entire satisfaction of the Corporation and

intimation thereof has been given to the surety by the Corporation whichever is earlier.

NOTWITHSTANDING anything stated above, the liability of the surety under this guarantee is restricted to Rs._____ (Rupees ______________only) and this guarantee will remain in force upto ______in the first instance and in case Contractor’s obligations under the contract are not completed within the said period, the Surety to hereby agree to further extend the guarantee till such time as is required to fulfill the contractor’s obligation.

Our grantee shall remain in force until _______________unless a demand in writing for claim under this guarantee is lodged with us before that date i.e. on or before _____________all your rights under the said guarantee shall be frofieted and we shall be released and discharged from liability hereunder.

We have the power to issue this guarantee in your favour under Memorandum and Articles of Association and the undersigned has full power to do so under the Power of Attorney dated _________granted to him by the bank.

___________________Bank By its Constituted Attorney

_______________ Signature of Person duly Authorised to sign on Behalf of the Bank

40

Page 129: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

ANNEXURE 5

TAX RESIDENCY CERTIFICATE TRC obtained by the Non-resident from Government of forign country shall contain the following particulars:

i. Name of the assessee ii. Status (individual, company, firm, etc.) of the assessee iii. Nationality (in case of individual) iv. Country or specified territory of incorporation or registration (in case of others) v. Assessee’s tax identification number in the country or specified territory of residence or in case of no such number, then, a

unique number on the basis of which the person is identified by the Government of the country or the specified territory vi. Residential status for the purpose of Tax vii. Period for which the certificate is applicable viii. Address of the applicant for the period for which the certificate is applicable

41

Page 130: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

ANNEXURE 6

FORM NO. 10 F [See sub-rule (1) of rule 21AB of the Income-tax Act, 1961]

Information to be provided under sub-section (5) of section 90 or sub-section (5) of section 90A of the Income-tax Act, 1961

1. I_________________*son/daughter of Shri _____________ in the capacity of ___________________(designation)do provide the

following information, relevant to the previous year _________,*in my case/in the case of __________for the purposes of sub-section (5) of *section 90/section 90A:-

Sl. No. Nature of information Details #

(i) Status (individual, company, firm etc.) of the assessee : (ii) Permanent Account Number (PAN) of the assessee if allotted : (iii) Nationality (in the case of an individual) :

or

Country or specified territory of incorporation or registration (in the case

of others)

(iv) Assessee’s tax identification number in the country or specified territory : of residence and if there is no such number, then, a unique number on

the basis of which the person is identified by the Government of the

country or the specified territory of which the assessee claims to be a

resident

(v) Period for which the residential status as mentioned in the certificate : referred to in sub-section (4) of section 90 or sub-section (4 )of section

90A is applicable

(vi) Address of the assessee in the country or territory outside India during : the period for which the certificate, mentioned in (v) above, is applicable

2. I have obtained a certificate referred to in sub-section (4) of section 90 or sub-section (4) of section 90A from the Government of

_________________________(name of country or specified territory outside India).

Signature:_________________________ Name:____________________________ Address:__________________________

Permanent Account Number :___________________ Verification

I_________________do hereby declare that to the best of my knowledge and belief what is stated above is correct, complete and is truly stated.

Verified today the ___________day of _________________

________________________________________ Signature of the person providing the information

Place:_________________

Notes: 1. * Delete whichever is not applicable. 2. #Write N.A. if the relevant information forms part of the certificate referred to in sub-section (4) of section 90 or sub-section (4) of section 90A.”.

42

Page 131: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

ANNEXURE 7

Format of Integrity Pact

(To be executed on plain paper and applicable for all tenders of value above Rs. 1 crore)

INTEGRITY PACT

Between Bharat Petroleum Corporation Limited (BPCL) hereinafter referred to as "The Principal", And

………………………………………. hereinafter referred to as "The Bidder/ Contractor/ Supplier"

Preamble The Principal intends to award, under laid down organization procedures, contract/s for ....................... The Principal values full compliance with all relevant laws and regulations, and the principles of economic use of resources, and of fairness and transparency in its relations with its Bidder/s, Contractor/s and Supplier/s. In order to achieve these goals, the Principal cooperates with the renowned international Non-Governmental Organisation "Transparency International" (TI). Following TI's national and international experience, the Principal will appoint an Independent External Monitor (IEM) who will monitor the tender process and the execution of the contract for compliance with the principles mentioned above. Accordingly, the Principal has appointed Mr. ………… as IEM with the following address:-

Mr. ………….. ……………….. ……………………. ……………….. Tel: ………………………..

Section 1 – Commitments of the Principal 1) The Principal commits itself to take all measures necessary to prevent corruption and to observe the following principles:

a) No employee of the Principal, personally or through family members, will in connection with the tender, or the execution of the contract, demand, take a promise for or accept, for himself/herself or third person, any material or immaterial benefit which he/she is not legally entitled to.

b) The Principal will, during the tender process, treat all Bidders with equity and reason. The Principal will, in particular, before and during the tender process, provide to all Bidders the same information and will not provide to any Bidder confidential / additional information through which the Bidder could obtain an advantage in relation to the tender process or the contract execution.

c) The Principal will exclude from the process all known prejudiced persons.

2) If the Principal obtains information on the conduct of any of its employees which is a criminal offence under the relevant Anti-Corruption Laws of India, or if there be a substantive suspicion in this regard, the Principal will inform its Vigilance Office and in addition can initiate disciplinary actions.

Section 2 – Commitments of the Bidder / Contractor / Supplier

1) The Bidder / Contractor / Supplier commits itself to take all measures necessary to prevent corruption. He commits himself to observe

the following principles during his participation in the tender process and during the contract execution.

a) The Bidder / Contractor/Supplier will not, directly or through any other person or firm, offer, promise or give to any of the Principal's employees involved in the tender process or the execution of the contract or to any third person, any material or immaterial benefit which he/she is not legally entitled to, in order to obtain in exchange, any advantage of any kind whatsoever during the tender process or during the execution of the contract.

43

Page 132: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

b) The Bidder / Contractor / Supplier will not enter with other Bidders into any undisclosed agreement or understanding, whether formal or informal. This applies in particular to prices, specifications, certifications, subsidiary contracts, submission or non-submission of bids or any other actions to restrict competitiveness or to introduce cartelisation in the bidding process.

c) The Bidder / Contractor / Supplier will not commit any offence under the relevant Anti-Corruption Laws of India; further the Bidder / Contractor / Supplier will not use improperly, for purposes of competition or personal gain, or pass on to others, any information or document provided by the Principal as part of the business relationship, regarding plans, technical proposals and business details, including information contained or transmitted electronically.

d) The Bidder / Contractor / Supplier will, when presenting his bid, disclose any and all payments he has made, is committed to, or intends to make to agents, brokers or any other intermediaries in connection with the award of the contract.

2) The Bidder / Contractor / Supplier will not instigate third persons to commit offences outlined above or be an accessory to such

offences.

Section 3 – Disqualification from tender process and exclusion from future contracts

If the Bidder, before contract award, has committed a transgression through a violation of Section 2 or in any other form such as to put his reliability or credibility as Bidder into question, the Principal is entitled to disqualify the Bidder from the tender process or to terminate the contract, if already signed, for such reason. 1) If the Bidder/Contractor/Supplier has committed a transgression through a violation of Section 2 such as to put his reliability or

credibility into question, the Principal is also entitled to exclude the Bidder / Contractor / Supplier from future Contract award process. The imposition and duration of the exclusion will be determined by the severity of the transgression. The severity will be determined by the circumstances of the case, in particular the number of transgressions, the position of the transgressors within the company hierarchy of the Bidder and the amount of the damage. The exclusion will be imposed for a minimum of 6 months and maximum of 3 years.

2) A transgression is considered to have occurred if the Principal after due consideration of the available evidences, concludes that no

reasonable doubt is possible. 3) The Bidder accepts and undertakes to respect and uphold the Principal's absolute right to resort to and impose such exclusion and

further accepts and undertakes not to challenge or question such exclusion on any ground, including the lack of any hearing before the decision to resort to such exclusion is taken. This undertaking is given freely and after obtaining independent legal advice.

4) If the Bidder / Contractor / Supplier can prove that he has restored / recouped the damage caused by him and has installed a

suitable corruption prevention system, the Principal may revoke the exclusion prematurely.

Section 4 – Compensation for Damages

1) If the Principal has disqualified the Bidder from the tender process prior to the award according to Section 3, the Principal is entitled

to demand and recover from the Bidder liquidated damages equivalent to Earnest Money Deposit/Bid Security.

2) If the Principal has terminated the contract according to Section 3, or if the Principal is entitled to terminate the contract according to

Section 3, the Principal shall be entitled to demand and recover from the Contractor/Supplier liquidated damages equivalent to Security Deposit / Performance Bank Guarantee.

3) The Bidder agrees and undertakes to pay the said amounts without protest or demur subject only to condition that if the Bidder / Contractor / Supplier can prove and establish that the exclusion of the Bidder from the tender process or the termination of the contract after the contract award has caused no damage or less damage than the amount of the liquidated damages, the Bidder / Contractor/Supplier shall compensate the Principal only to the extent of the damage in the amount proved.

Section 5 – Previous Transgression

1) The Bidder declares that no previous transgression occurred in the last 3 years with any other Company in any country conforming to

the TI approach or with any other Public Sector Enterprise in India that could justify his exclusion from the tender process.

2) If the Bidder makes incorrect statement on this subject, he can be disqualified from the tender process or the contract, if already

awarded, can be terminated for such reason.

44

Page 133: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

Section 6 – Equal treatment of all Bidders /Contractors /Suppliers/ Subcontractors

1) The Bidder/Contractor/Supplier undertakes to demand from all subcontractors a commitment in conformity with this Integrity Pact,

and to submit it to the Principal before contract signing.

2) The Principal will enter into agreements with identical conditions as this one with all Bidders, Contractors/Suppliers and Subcontractors.

3) The Principal will disqualify from the tender process all Bidders who do not sign this Pact or violate its provisions.

Section 7 – Punitive Action against violating Bidders /Contractors /

Suppliers/Subcontractors If the Principal obtains knowledge of conduct of a Bidder, Contractor, Supplier or Subcontractor, or of an employee or a representative or an associate of a Bidder, Contractor, Supplier or Subcontractor which constitutes corruption, or if the Principal has substantive suspicion in this regard, the Principal will inform the Vigilance Office.

Section 8 – Independent External Monitors

Contact details of Independent External Monitor

Mr. Shantanu Consul No.9 MCHS (IAS officers colony), 16th Main (IAS officers colony), BTM 2nd stage, Bangalore-560076 Mobile No.: 09740069318 [email protected] In case of any complain only please contact Mr. Shantanu Consul

1) The Principal has appointed competent and credible Independent External Monitors for this Pact. The task of the Monitor is to

review independently and objectively, whether and to what extent the parties comply with the obligations under this agreement.

2) The Monitor is not subject to instructions by the representatives of the parties and performs his functions neutrally and

independently. He reports to the Chairperson of the Board of the Principal.

3) The Bidder/Contractor/Supplier accepts that the Monitor has the right to access without restriction to all Project documentation of the Principal including that provided by the Bidder/Contractor/Supplier. The Bidder/Contractor/Supplier will also grant the Monitor, upon his request and demonstration of a valid interest, unrestricted and unconditional access to this project documentation. The same is applicable to Subcontractors. The Monitor is under contractual obligation to treat the information and documents of the Bidder/Contractor/Supplier/Subcontractor with confidentiality.

4) The Principal will provide to the Monitor sufficient information about all meetings among the parties related to the Project provided such meetings could have an impact on the contractual relations between the Principal and the Bidder/Contractor/Supplier. The parties offer to the Monitor the option to participate in such meetings.

5) As soon as the Monitor notices, or believes to notice, a violation of this agreement, he will so inform the Management of the Principal and request the Management to discontinue or heal the violation, or to take other relevant action. The Monitor can in this regard submit non-binding recommendation. Beyond this, the Monitor has no right to demand from the parties that they act in a specific manner, refrain from action or tolerate action. However, the Independent External Monitor shall give an opportunity to the Bidder/Contractor/Supplier to present its case before making its recommendations to the Principal.

6) The Monitor will submit a written report to the Chairperson of the Board of the Principal within 8 to 10 weeks from the date of

reference or intimation to him by the 'Principal' and, should the occasion arise, submit proposals for correcting problematic situations.

7) If the Monitor has reported to the Chairperson of the Board a substantiated suspicion of an offence under relevant Anti-Corruption Laws of

India, and the Chairperson has not, within reasonable time, taken visible action to proceed against such offence or reported it to the Vigilance

Office, the Monitor may also transmit this information directly to the Central Vigilance Commissioner, Government of India.

8) The word 'Monitor' would include both singular and plural.

Section 9 – Pact Duration

This Pact begins when both parties have legally signed it. It expires for the Contractor/Supplier 12 months after the last payment under the respective contract, and for all other Bidders 6 months after the contract has been awarded.

Page 134: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

If any claim is made / lodged during this time, the same shall be binding and continue to be valid despite the lapse of this pact as specified above, unless it is discharged / determined by Chairperson of the Principal.

Section 10 - Other provisions 1) This agreement is subject to Indian Law. Place of performance and jurisdiction is the Registered Office of the Principal, i.e. Mumbai.

The Arbitration clause provided in the main tender document / contract shall not be applicable for any issue / dispute arising under Integrity Pact.

2) Changes and supplements as well as termination notices need to be made in writing. Side agreements have not been made.

45

Page 135: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

3) If the Bidder/Contractor/Supplier is a partnership or a consortium, this agreement must be signed by all partners or consortium members.

4) Should one or several provisions of this agreement turn out to be invalid, the remainder of this agreement remains valid. In this case,

the parties will strive to come to an agreement to their original intentions.

............................. …………………………………………………….. For the Principal For the Bidder/Contractor/Supplier

Place ……………… Witness 1

(Signature/Name/Address)

Witness 2:

Date ………….….. (Signature/Name/Address)

46

Page 136: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

BHARAT PETROLEUM CORPORATION LTD

ACKNOWLEDGEMENT

We, M/s.__________________________________________________ having office at _______________________________ received the copy of GENERAL CONDITIONS OF CONTRACT and confirm our acceptance to all the terms and conditions as mentioned herein in this General Conditions of Contract and we are hereby returning this copy of Acknowledgement duly signed.

For & on behalf of M/s.___________________________________________________ Signature : Name : ____________________________________________________ Designation : ____________________________________________________

( Seal / Stamp ) Place : Date :

47

Page 137: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

1

Bharat Petroleum Corporation Limited

General Purchase Conditions

The following conditions shall be applicable for all procurement unless specifically

mentioned in the Special Purchase Conditions.

INDEX

1. DEFINITIONS

2. REFERENCE FOR DOCUMENTATION

3. RIGHT OF OWNER TO ACCEPT OR REJECT TENDER

4. LANGUAGE OF BID

5. PRICE

6. TAXES AND DUTIES

7. INSPECTION

8. SHIPPING

9. INDIAN AGENT COMMISSION

10. ORDER AWARD / EVALUATION CRITERIA

11. CONFIRMATION OF ORDER

12. PAYMENT TERMS

13. GUARANTEE/WARRANTY

14. PERFORMANCE BANK GUARANTEE

15. PACKING & MARKING

16. DELIVERY

17. UNLOADING AND STACKING

18. TRANSIT INSURANCE

19. VALIDITY OF OFFER

20. DELIVERY DATES AND PRICE REDUCTION SCHEDULE

21. RISK PURCHASE CLAUSE

22. FORCE MAJEURE CLAUSE

23. ARBITRATION CLAUSE

24. INTEGRITY PACT (IP)

25. RECOVERY OF SUMS DUE

26. CONFIDENTIALITY OF TECHNICAL INFORMATION

27. PATENTS & ROYALTIES

28. LIABILITY CLAUSE

29. COMPLIANCE OF REGULATIONS

30. REJECTION, REMOVAL OF REJECTED GOODS AND REPLACEMENT

31. NON-WAIVER

32. NEW & UNUSED MATERIAL

33. PURCHASE PREFERENCE CLAUSE

34. CANCELLATION

35. ANTI –COMPETITIVE AGREEMENTS/ABUSE OF DOMINANT POSITION

36. ASSIGNMENT

37. GOVERNING LAW

38. AMENDMENT

39. SPECIAL PURCHASE CONDITIONS

40. Expediting

41. Spare Part

42. Part order & Repeat Order

43. Oils & Lubricants

44. Jurisdiction

45. Address

Page 138: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

2

46. Holiday Listing

47. NOTICES

Bharat Petroleum Corporation Limited

General Purchase Conditions

1. DEFINITIONS :

The following expressions used in these terms and conditions and in the purchase order

shall have the meaning indicated against each of these:

1.1. OWNER: Owner means Bharat Petroleum Corporation Limited (a Government of India

enterprise), a Company incorporated in India having its registered office at Bharat

Bhavan, 4 & 6 Currimbhoy Road, Ballard Estate, Mumbai 400038 and shall include its

successors and assigns (hereafter called BPCL as a short form).

1.2. VENDOR: Vendor means the person, firm or the Company / Corporation to whom this

Request for quotation (RFQ)/purchase order is issued and shall include its successors and

assigns.

1.3. INSPECTOR: Person/agency deputed by BPCL for carrying out inspection,

checking/testing of items ordered and for certifying the items conforming to the purchase

order specifications..

1.4. GOODS / MATERIALS: means any of the articles, materials, machinery, equipments,

supplies, drawing, data and other property and all services including but not limited to

design, delivery, installation, inspection, testing and commissioning specified or required

to complete the order.

1.5. SITE / LOCATION: means any Site where BHARAT PETROLEUM CORPORATION

LTD. desires to receive materials any where in India as mentioned in RFQ.

1.6. “RATE CONTRACT” means the agreement for supply of goods/ materials between

Owner and Vendor, for a fixed period of time (i.e till validity of Rate Contract, with no

commitment of contractual quantity) on mutually agreed terms and conditions. The actual

supply of goods/ materials shall take place only on issue of separate purchase orders for

required quantity as and when required by Owner.

1.7. “FIRM PROCUREMENT” means the agreement between the parties for mutually

agreed terms and conditions with commitment of Quantity Ordered.

2. REFERENCE FOR DOCUMENTATION :

2.1. The number and date of Request for Quotation (CRFQ) must appear on all

correspondence before finalization of Rate Contract / Purchase Order.

Page 139: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

3

2.2. After finalization of Contract / Purchase Order: The number and date of Rate Contract /

Purchase Order must appear on all correspondence, drawings, invoices, dispatch advices,

(including shipping documents if applicable) packing list and on any documents or papers

connected with this order.

2.3. In the case of imports, the relevant particulars of the import Licence shall be duly indicated

in the invoice and shipping documents as well as on the packages or consignments.

3. RIGHT OF OWNER TO ACCEPT OR REJECT TENDER :

The right to accept the tender will rest with the Owner.

4. LANGUAGE:

The Bid and all supporting documentation and all correspondence whatsoever exchanged

by Vendor and Owner, shall be in English language only.

5. Price :

Unless otherwise agreed to the terms of the RFQ, price shall be :Firm and no escalation will be

entertained on any ground, except on the ground of statutory levies applicable on the tendered

items.

6. TAXES AND DUTIES :

All vendors shall have VAT / CST/GST/Service tax registration in the concerned State

and vendor shall quote their TIN number in the quotation.

6.1. EXCISE DUTY :

6.1.1. Excise duty extra as applicable at the time of delivery within scheduled delivery period

will be payable by BPCL against documentary evidence. Vendor shall mention in their

offer, the percentage of excise duty applicable at present. Any upward variation in excise

duty rates, beyond the contractual delivery period, shall be to vendor’s account.

6.1.2. In case Excise Duty is not applicable at present : Excise duty due to change in turn over is

not payable. If applicable in future, the same will be borne by vendor.

6.1.3. Owner may shall take CENVAT Credit on the material supplied for both excise duty and

cess component and accordingly Excise duty / Cess should be quoted separately wherever

applicable.

Vendor shall ask the transporter of the goods to hand over the copy of excise invoice

(transporter’s copy) at the time of delivery of goods at owner’s site.

6.2. SALES TAX / VAT/GST :

6.2.1. Sales Tax as applicable at the time of delivery within scheduled delivery period will be

Page 140: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

4

payable by BPCL. Vendor shall give details of local sales tax and/or central sales tax

currently applicable in their offer. The rates applicable for “CST without form C”, “CST

with form C" and “VAT” shall be clearly indicated.

6.2.2. Input VAT Credit may be claimed by BPCL, wherever applicable. Vendor shall submit

the TAX invoice.

6.3 Service tax :

All vendors shall have service tax registration wherever applicable. BPCL may also

claim CENVAT Credit on service tax. The vendor should quote service tax separately, if

applicable. Vendor shall submit the TAX invoice. Vendor is required to furnish serially

numbered and signed invoice / bill / challan containing the following details:

a) Name, address and registration number of the service provider b) Name and address of person receiving taxable service c) Description, classification and value of taxable service provided d) Service Tax Payable

6.4 FREIGHT AND OCTROI :

6.4.1 Freight: Firm freight charges to be quoted as indicated in the Tender documents. Freight

shall be payable after receipt of the Material(s) at the site, unless otherwise specified.

6.4.2. Octroi and entry taxes, if any, shall be invoiced separately and shall be re-imbursed by

BPCL at actuals after receipt of the Material(s) at the Site against the submission of

original documentary evidence for proof of payment of the related octroi and entry taxes,

as the case may be.

6.5. NEW STATUTORY LEVIES :

All new statutory levies leviable on sale of finished goods to owner , if applicable are

payable extra by BPCL against documentary proof, within the contractual delivery

period.

6.6 Variation in Taxes/Duties

Any increase/decrease in all the above mentioned statutory levies on the date of delivery

during the scheduled delivery period on finished materials will be on BPCL's account.

Any upward variation in statutory levies after contractual delivery date shall be to

vendor’s account.

7. INSPECTION :

7.1. Materials shall be inspected by EIL / BPCL approved third party inspection agency if

applicable before dispatch of materials. However, arranging and providing inspection

facilities is entirely vendor’s responsibility and in no way shall affect the delivery

schedule.

Page 141: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

5

7.2. Scope of Inspection shall be as per RFQ. Our registered third party inspection agencies

are /LRIS/CEIL/DNV///EIL/ as amended time to time unless otherwise specified in the

Special Purchase Conditions.

7.3. Unless otherwise specified, the inspection shall be carried out as per the relevant

standards/scope of inspection provided along with the Tender Enquiry/Purchase Order.

7.4. BPCL may, at its own expense, have its representative(s) witness any test or inspection.

In order to enable BPCL’s representative(s) to witness the tests/inspections. BPCL will

advise the Vendor in advance whether it intends to have its representative(s) be present at

any of the inspections.

7.5. Even if the inspection and tests are fully carried out, the Vendor shall not be absolved

from its responsibilities to ensure that the Material(s), raw materials, components and

other inputs are supplied strictly to conform and comply with all the requirements of the

Contract at all stages, whether during manufacture and fabrication, or at the time of

Delivery as on arrival at site and after its erection or start up or consumption, and during

the defect liability period. The inspections and tests are merely intended to prima-facie

satisfy BPCL that the Material(s) and the parts and components comply with the

requirements of the Contract. The Vendor’s responsibility shall also not be anywise

reduced or discharged because BPCL or BPCL’s representative(s) or Inspector(s) shall

have examined, commented on the Vendor’s drawings or specifications or shall have

witnessed the tests or required any chemical or physical or other tests or shall have

stamped or approved or certified any Material(s).

7.6. Although material approved by the Inspector(s), if on testing and inspection after receipt

of the Material(s) at the location, any Material(s) are found not to be in strict conformity

with the contractual requirements or specifications, BPCL shall have the right to reject

the same and hold the Vendor liable for non-performance of the Contract.

8. SHIPPING :

8.1 SEA SHIPMENT :

All shipment of materials shall be made by first class direct vessels, through the

chartering wing, Ministry of Surface Transport as per procedure detailed hereunder. The

Foreign Supplier shall arrange with Vessels Owners or Forwarding Agents for proper

storage of the entire Cargo intended for the project in a specific manner so as to facilitate

and to avoid any over carriage at the port of discharge. All shipment shall be under deck

unless carriage on deck is unavoidable.

The bills of lading should be made out in favour of `Bharat Petroleum Corporation Ltd..

or order'.

All columns in the body of the Bill of Lading namely marks and nos., material

description, weight particulars etc., should be uniform and accurate and such statements

should be uniform in all the shipping documents. The freight particulars should mention

the basis of freight tonnage, heavy lift charges, if any, surcharge, discount etc. clearly and

separately. The net total freight payable shall be shown at the bottom.

Page 142: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

6

SHIPPING DOCUMENTS :

All documents viz. Bill of Lading, invoices, packing list, freight memos, country of

origin certificates, test certificate, drawings and catalogues should be in English

language.

In addition of the bill of lading which should be obtained in three stamped original plus

as many copies as required, invoices, packing list, freight memos,(if the freight

particulars are not shown in the bills of lading), country of origin certificate, test /

composition certificate, shall be made out against each shipment in as many number of

copies as shown below.

The bill of lading, invoice and packing list specifically shall show uniformly the mark

and numbers, contents case wise, country of origin, consignees name, port of destination

and all other particulars as indicated under clause 2. The invoice shall show the unit

rates and net total F.O.B. prices. Items packed separately should also be invoiced and the

value shown accordingly. Packing list must show apart from other particulars actual

contents in each case, net and gross weights and dimensions, and the total number of

packages. All documents should be duly signed by the Vendor's authorised

representatives.

The bill of lading shall indicate the following :

Shipper : Government of India

Consignee : Bharat Petroleum Corporation Ltd.

In case of supplies from USA, Export Licences, if any required from the American

Authorities shall be Obtained by the U.S. Suppliers. If need be assistance for obtaining

such export licences would be available from India Supply Mission at Washington.

8.2 AIRSHIPMENT :

In case of Airshipment, the materials shall be shipped through freight consolidator

(approved by us). The airway bill shall be made out in favour of BHARAT

PETROLEUM CORPORATION LTD.

TRANSMISSION OF SHIPPING DOCUMENTS :

Foreign Supplier shall obtain the shipping documents in seven complete sets including

three original stamped copies of the Bill of Lading as quickly as possible after the

shipment is made, and airmail as shown below so that they are received at least three

weeks before the Vessels arrival. Foreign Supplier shall be fully responsible or any delay

and / or demurrage in clearance of the consignment at the port due to delay in

transmittal of the shipping documents.

If in terms of letter or otherwise, the complete original set of documents are required to

be sent to BPCL through Bank the distribution indicated below will confine to copies of

documents only minus originals.

Page 143: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

7

Documents BPCL (Delhi)

Bill of Lading 4 (including 1 original)

Invoice 4

Packing List 4

Freight Memo 4

Country of Origin Certificate 4

Third party inspection certificate 4

Drawing 4

Catalogue 4

Invoice of Third Party 4

for inspection charges whenever applicable.

9. INDIAN AGENT COMMISSION :

Any offer through Indian agents will be considered only after authorization mentioning

them as Indian agents, is received from Vendor. Indian agents commission if applicable

will be payable only in Indian currency. Indian agents should be registered with

Directorate General of Supplies and Disposals, Government of India and agency

commission will be payable only after registration with DGS&D, New Delhi.

10. ORDER AWARD / EVALUATION CRITERIA :

Unless otherwise specified, Order award criteria will be on lowest quote landed price

basis. Landed price will be summation of Basic Price, Packing & Forwarding Charges,

Excise Duty, Sales Tax, Freight, Inspection, Octroi, Supervision of Installation &

Commissioning and other taxes & levies, loading etc, if any, reduced by cenvat/vat credit

as applicable

11. CONFIRMATION OF ORDER :

The vendor shall acknowledge the receipt of the purchase order within 10 days of mailing

the same. The vendor shall sign, stamp the acknowledgement copy of the purchase order

and return the same to BPCL.

12. PAYMENT TERMS :

12.1. Unless otherwise specified, 100% payment shall be made within 30 days from date of

receipt and acceptance of materials at Site against submission of Peformance Bank

Guarantee (PBG) for 10% of basic order value if PBG is applicable for the tender.

12.2. In the case of imports, payment will be made on submission of original documents

directly to Owner (Telegraphic Transfer-TT) or through Bank (Cash against documents-

CAD) or through irrevocable Letter of Credit.

12.3. Unless otherwise mentioned, the specified documents (All documents listed below (one

Page 144: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

8

original and two copies)) should be submitted to originator of P.O. (the name and contact

details of whom are given in PO) and payments for despatches will be made by the

originator of Purchase Order :

a) Invoice

b) Excise invoice

c) The Lorry Receipt of the consignment

d) Packing list for the consignment

e) Third Party Inspector’s Certificate covering the invoiced Material(s)/ Release

Note, wherever applicable

f) Manufacturers Test/Composition Certificate, wherever applicable

g) Drawing(s)/Catalogue(s) covering the Material(s) , wherever applicable

h) Guarantee/Warranty Certificate(s), wherever applicable.

i) Original Receipt for Octroi/other statutory levies as applicable.

j) Performance Bank Guarantee as applicable.

13. GUARANTEE/WARRANTY :

13.1. Materials shall be guaranteed against manufacturing defects, materials, workmanship and

design for a period of 30 months from the date of commissioning or 36 months from the

date of dispatch whichever is earlier. Warranty for replacement of material / accessories

should be provided free of charges at our premises. The above guarantee/warranty will

be without prejudice to the certificate of inspection or material receipt note issued by us

in respect of the materials.

13.2. All the materials including components and sub contracted items should be guaranteed by

the vendor within the warranty period mentioned above. In the event of any defect in the

material, the vendor will replace / repair the material at BPCL’s concerned location at

vendor’s risk and cost on due notice.

13.3. In case, vendor does not replace / repair the material on due notice, rejected material will

be sent to the vendor on “Freight to pay” basis for free replacement. Material after

rectification of defects shall be dispatched by the vendor on “Freight Paid” basis.

Alternatively, BPCL reserves the right to have the material repaired / replaced at the

locations concerned, at the vendor’s risk, cost and responsibility.

13.4. The Vendor shall provide similar warrantee on the parts, components, fittings,

accessories etc. so repaired and / or replaced.

14. PERFORMANCE BANK GUARANTEE :

14.1. Vendor will have to provide Performance Bank Guarantee for 10% of the basic value of

purchase order unless otherwise specified. This bank guarantee shall be valid (shall

remain in force) for guarantee period (as mentioned in the guarantee clause), with an

invocation period of six months thereafter. In the case of Indigenous vendors, the

Performance Bank Guarantee shall be given on a non-judicial stamp paper of appropriate

value (currently Rs 100). PBG format is as per Annexure I.

In case, PBG is not provided by the Vendor, 10% of the basic value shall be retained in

lieu of PBG, till the expiry of guarantee and claim period.

Page 145: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

9

In the case of imports, the Supplier shall furnish the Performance Bank Guarantee (as per

Annexure I) through the following :

a) Branches of Indian scheduled banks operating in their Country.

b) Foreign bank operating in their Country which is counter guaranteed by branches of

Indian scheduled banks operating in their Country/India.

c) Indian branches of foreign banks.

d) Foreign bank operating in their Country counter guaranteed by their Indian branch

However, in respect of c) and d) above, the Indian branch of foreign banks should be

recognized as scheduled bank by Reserve Bank of India.

14.2. If Vendor wants to submit the PBG at Contract level to avoid multiple number of PBG

(i.e. PBG issued against every purchase/call off order) then the validity of PBG will be

calculated as mentioned below :

14.2.1. Validity of PBG = Rate Contract Issue Date (Start Date of Rate Contract) + Rate

Contract Period (validity of Rate Contract) + Contractual Delivery Period of material +

Contractual Guarantee period + 6 month (for invocation / Claim).

15. PACKING & MARKING :

15.1 PACKING :

15.1.1 Packing shall withstand the hazards normally encountered with the means of transport

for the goods of this purchase order including loading and unloading operation both by

crane and by pushing off.

In the case of imports, all equipments / materials shall be suitably packed in weather

proof, seaworthy packing for ocean transport under tropical conditions and for rail or

road or other appropriate transport in India. The packing shall be strong and efficient

enough to ensure safe preservance upto the final point of destination.

Raw/Solid wood packaging material of imported items has to be appropriately treated &

marked as per International Standard of Phytosanitary Measures (ISPM-15") for material

originating from the contracting countries to the International Plant Protection

Convention or the members of Food & Agriculture Organization. Material from non-

contracting parties would have to be accompanied by a phytosanitary certificate of the

treatment endorsed. The Custom Officer at Indian Port shall not release the material

without appropriate compliance of the above provisions w.e.f. 01.11.2004.

15.1.2 The packing specification incorporated herein are supplementary to the internal and

external packing methods and standards as per current general rules of J.R.A. Good Tariff

Part-I. All packaging shall be done in such a manner as to reduce volume as much as

possible.

15.1.3 Fragile articles should be packed with special packing materials depending on the type of

Materials and the packing shall bear the words "HANDLE WITH CARE GLASS

FRAGILE, DON'T ROLL THIS END UP. THIS END DOWN," to be indicated by

arrow.

Page 146: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

10

15.1.4 Chemicals in powder form, catalyst, refractories and like materials etc. shall be packed in

drums, cans and tins only. However, Catalyst may be supplied in Jumbo bags.

15.1.5 The hazardous materials shall be packed in accordance with the applicable rules,

regulations and tariff of all cognizant Government Authorities and other Governing

bodies. It shall be the responsibility of the seller of hazardous materials to designate the

material as hazardous and to identify each material by its proper commodity name and its

hazardous material class code.

15.1.6 All package requiring handling by crane should have sufficient space at appropriate place

to put sling of suitable dia (strength). Iron/Steel angle should be provided at the place

where sling marking are made to avoid damage to package/ equipment while lifting.

15.1.7 Item shipped in bundles must be securely tied with steel wire or strapping. Steel

reinforcing rods, bars, pipes, structural members etc. shall be bundled in uniform lengths

and the weight shall be within the breaking strength of the securing wire or strapping.

In the case of imports, for bundles the shipping marks shall be embossed on metal or

similar tag and wired securely on each end.

15.1.8 All delicate surface on equipment/materials should be carefully protected and printed

with protective paint/compound and wrapped to prevent rusting and damage.

15.1.9 All mechanical and electrical equipment and other heavy articles shall be securely

fastened to the case bottom and shall be blocked and braced to avoid any

displacement/shifting during transit.

15.1.10 Attachments and spare parts of equipment and all small pieces shall be packed separately

in wooden cases with adequate protection inside the case and wherever possible should

be sent along with the main equipment. Each item shall be suitably tagged with

identification of main equipment, item denomination and reference number of respective

assembly drawing. Each item of steel structure and furnaces shall be identified with two

erection markings with minimum lettering height of 15mm. Such markings will be

followed by the collection numbers in indelible ink/paint. A copy of the packing list shall

accompany the materials in each package.

15.1.11 All protrusions shall be suitably protected by providing a cover comprising of tightly

bolted wooden disc on the flanges. All nozzles, holes and openings and also all delicate

surfaces shall be carefully protected against damage and bad weather. All manufactured

surfaces shall be painted with rust proof paint.

In the case of imports, for bulk uniform material when packed in several cases,

progressive serial numbers shall be indicated on each case.

15.1.12 Wherever required, equipment/materials instruments shall be enveloped in polythene

bags containing silicagel or similar dehydrating compound.

15.1.13 Pipes shall be packed as under:

a. Upto 50mm NB in wooden cases/crates.

Page 147: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

11

b. Above 50mm NB and upto 100mm NB in bundles and should be strapped at minimum

three places.

c. Above 100mm NB in loose.

15.1.14 Pipes and tubes of stainless steel, copper etc. shall be packed in wooden cases

irrespective of their sizes.

15.1.15 Pipes with threaded or flanged ends shall be protected with suitable caps covers, before

packing.

In the case of imports, all pipes and sheets shall be marked with strips bearing

progressive no.

15.1.16 Detailed packing list in waterproof envelope shall be inserted in the package together

with equipment/materials. One copy of the detailed packing list shall be fastened outside

of the package in waterproof envelope and covered by metal cover.

15.1.17 The supplier shall be held liable for all damages or breakages to the goods due to the

defective or insufficient packing as well as for corrosion due to insufficient protection.

15.1.18 Packaged equipment or materials showing damage defects or shortages resulting from

improper packaging materials or packing procedures or having concealed damages or

shortages, at the time of unpacking shall be to the supplier’s account.

All packages which require special handling and transport should have their Centres of

Gravity and the points at which they may be slung or gripped clearly indicated and

marked “ATTENTION SPECIAL LOAD HANDLE WITH CARE” both in

English/Hindi Languages.

In the case of imports, a distinct colour splash in say red black around each package crate

/ bundle shall be given for identification. 15.1.19 Along with the packed material, supplier should attach material list, manuals/instructions

and also the Inspection certificate/release note, wherever applicable.

15.2. MARKING :

The following details to be written on the side face of packing:

a) Purchase Order Number

b) Vendor Name

c) Batch no with Manufacturing date

d) Procedure (in brief) for handling

e) Date of dispatch etc.

Page 148: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

12

15.3 Imported items :

On three sides of the packages, the following marks shall appear, clearly visible, with

indelible paint and on Vendor's care and expenses.

BHARAT PETROLEUM CORPORATION LIMITED

(With detailed address as given in Special Purchase Conditions)

From :

To : Bharat Petroleum Corpn.Ltd.

(With detailed address as given in Special Purchase Conditions)

Order no. Rev. no.

Item :

Equipment Nomenclature :

Net weight : Kgs.

Gross weight : Kgs.

Case No. of Total cases :

Dimensions :

Import Licence No.

NOTE :

Marking shall be bold - minimum letter height 5 cm. For every order and every

shipment, packages must be marked with serial progressive numbering.

Top heavy containers shall be so marked either Top Heavy or Heavy Ends.

When packing material is clean and light coloured, a dark black stencil paint shall be

acceptable. However, where packaging material is soiled or dark, a coat of flat zinc

white paint shall be applied and allowed to dry before applying the specific markings.

In case of large equipments like vessels, heat exchangers, etc. the envelope containing the

documents shall be fastened inside a shell connection, with an identifying arrow sign

"documents" using indelible paint.

16. DELIVERY :

16.1. Unless otherwise mentioned, Vendor is requested to quote their best delivery schedule

from the date of receipt of Purchase order.

16.2. Time being the essence of this contract, the delivery mentioned in the purchase order

shall be strictly adhered to and no variation shall be permitted except with prior

authorization in writing from the Owner. Goods should be delivered, securely packed and

Page 149: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

13

in good order and condition, at the place of delivery and within the time specified in the

purchase order for their delivery.

16.3. The contractual delivery period is inclusive of all the lead time for engineering /

procurement of raw material, the manufacturing, inspection / testing, packing,

transportation or any other activity whatsoever required to be accomplished for effecting

the delivery at the required delivery point.

16.4. Unless otherwise specified, Material(s) shall not be despatched without prior inspection

and/or testing and Release Order/Material(s) Acceptance Certificate issued by the

Inspector(s).

16.5. BPCL shall have the right to advise any change in despatch point or destination in respect

of any Material(s). Any extra expenditure incurred by the Vendor on this account

supported by satisfactory documentary evidence, will be reimbursed to the Vendor by

BPCL.

17. UNLOADING AND STACKING :

Unloading and stacking will be arranged by BPCL. The Vendor shall send BPCL

information of the proposed consignment well in advance by telegram/fax/e-mail/courier

to enable BPCL to take necessary action.

18. TRANSIT INSURANCE :

Unless otherwise mentioned,

18.1. Transit Insurance shall be covered by BPCL under Project Insurance Policy.

18.2 In the case of imports, insurance against all marine and transit risk shall be covered under

the Owner's marine policy. However, the Vendor shall ensure that in effecting

shipments clear bill of lading are obtained and the carrier's responsibility is fully retained

on the Carriers so that the consignee's interests are fully secured and are in no way

jeopardized.

18.2. The Vendor shall send BPCL information of the proposed consignment well in advance

by telegram/fax/e-mail/courier to enable BPCL to take necessary action for the transit

insurance of the consignment. Any failure by the Vendor to do so shall place the

consignment at the Vendor’s risk.

18.3. In the case of imports, as soon as any shipment is made, the Foreign Supplier shall send

advance information by way of Telex message to Bharat Petroleum Corporation Ltd.,

(with detailed address as given in Special Purchase Conditions) giving particulars of the

shipments, vessels name, port of shipment, bill of lading number and date, total FOB and

freight value.

19 VALIDITY OF OFFER:

The rates quoted against this tender shall be valid for a period of 120 Days from the date

of opening of the tender unless otherwise specified in the Special Purchase Conditions.

Page 150: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

14

20. DELIVERY DATES AND PRICE REDUCTION SCHEDULE :

20.1. The time and date of Delivery of Material(s) as stipulated in the Contract shall be adhered

to on the clear understanding that the Price(s) of the Material(s) has/have been fixed with

reference to the said Delivery date(s).

20.2. If any delay is anticipated by the Vendor in the delivery of the Material(s) or any of them

beyond the stipulated date(s) of Delivery, the Vendor shall forthwith inform BPCL in

writing of such anticipated delay and of the steps being taken by the Vendor to remove or

reduce the anticipated delay, and shall promptly keep BPCL informed of all subsequent

developments.

20.3. The delivery period quoted must be realistic & specific. The inability of successful

Vendors to execute orders in accordance with the agreed delivery schedule will entitle

BPCL, at its options, to :

20.3.1. Accept delayed delivery at prices reduced by a sum equivalent to half percent ( 0.5%) of

the basic value of any goods not delivered for every week of delay or part thereof, limited

to a maximum of 5% of the total basic order value. LR date will be considered as

delivery completion date for calculation of price reduction in the case of ex works

contract. Date of receipt of materials at owners premises shall be considered for

calculation of price reduction for F.O.R destination contract.

In the case of imports, the contractual delivery date shall be considered from the

date of FOA plus the delivery schedule as indicated by the vendors. Further the date of B/L or House airway bill shall be considered to find out the delay with

respect to contractual delivery date for all the contract on FOB/CFR basis . In case of

FOB shipments if the vessel is not available then the intimation by vendors regarding

readiness of the goods for the shipment shall be considered for calculating the delay if

any. So vendor shall inform the readiness of material for shipment on FOB (Free on

Board)basis / FCA (Free on Carrier) basis.

20.3.2. Cancel the order in part or full and purchase such cancelled quantities from elsewhere on

account at the risk and cost of the vendor, without prejudice to its right under 20.3.1

above in respect of goods delivered.

21. RISK PURCHASE CLAUSE :

BPCL reserves the right to curtail or cancel the order either in full or part thereof if the

vendor fails to comply with the delivery schedule and other terms & conditions of the

order. BPCL also reserves the right to procure the same or similar materials/equipment

through other sources at vendor's entire risk, cost and consequences. Further, the vendor

agrees that in case of procurement by the owner from other sources the differential

amount paid by the owner shall be on account of the vendor together with any interest

and other costs accrued thereon for such procurement.

Page 151: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

15

22. FORCE MAJEURE CLAUSE :

(A) Definition: The term “Force Majeure” means any event or circumstance or

combination of events or circumstances that affects the performance by the

vendor of its obligations pursuant to the terms of this Agreement (including by

preventing, hindering or delaying such performance), but only if and to the extent

that such events and circumstances are not within the vendor’s reasonable control

and were not reasonably foreseeable and the effects of which the vendor could not

have prevented or overcome by acting as a Reasonable and Prudent person or, by

the exercise of reasonable skill and care. Force Majeure events and circumstances

shall in any event include the following events and circumstances to the extent

they or their consequences satisfy the requirements set forth above in this Clause:

(i) the effect of any element or other act of God, including any storm,

flood, drought, lightning, earthquake, tidal wave, tsunami, cyclone

or other natural disaster;

(ii) fire, accident, loss or breakage of facilities or equipment, structural

collapse or explosion;

(iii) epidemic, plague or quarantine;

(iv) air crash, shipwreck, or train wreck;

(v) acts of war (whether declared or undeclared), sabotage, terrorism

or act of public enemy (including the acts of any independent unit

or individual engaged in activities in furtherance of a programme

of irregular warfare), acts of belligerence of foreign enemies

(whether declared or undeclared), blockades, embargoes, civil

disturbance, revolution, rebellion or insurrection, exercise of

military or usurped power, or any attempt at usurpation of power;

(vi) radioactive contamination or ionizing radiation;

( B) Notice and Reporting:

( i ) The Vendor shall as soon as reasonably practicable after the date

of commencement of the event of Force Majeure, but in any event

no later than two (7) days after such commencement date, notify

the BPCL in writing of such event of Force Majeure and provide

the following information:

(a) reasonably full particulars of the event or circumstance of

Force Majeure and the extent to which any obligation will

be prevented or delayed;

Page 152: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

16

(b) such date of commencement and an estimate of the period

of time required to enable the vendor to resume full

performance of its obligations; and

(c) all relevant information relating to the Force Majeure and

full details of the measures the vendor is taking to

overcome or circumvent such Force Majeure.

(ii) The Vendor shall, throughout the period during which it is prevented

from performing, or delayed in the performance of, its

obligations under this Agreement, upon request, give or procure

access to examine the scene of the Force Majeure including such

information, facilities and sites as the other Party may

reasonably request in connection with such event. Access to any

facilities or sites shall be at the risk and cost of the Party

requesting such information and access.

(C) Mitigation Responsibility:

(i) The Vendor shall use all reasonable endeavours, acting as a

Reasonable and Prudent Person, to circumvent or overcome any

event or circumstance of Force Majeure as expeditiously as

possible, and relief under this Clause shall cease to be available to

the Vendor claiming Force Majeure if it fails to use such

reasonable endeavours during or following any such event of Force

Majeure.

(ii) The Vendor shall have the burden of proving that the

circumstances constitute valid grounds of Force Majeure under this

Clause and that it has exercised reasonable diligence efforts to

remedy the cause of any alleged Force Majeure.

(iii) The Vendor shall notify BPCL when the Force Majeure has

terminated or abated to an extent which permits resumption of

performance to occur and shall resume performance as

expeditiously as possible after such termination or abatement.

(D) Consequences of Force Majeure. Provided that the Vendor has

complied and continues to comply with the obligations of this

Clause and subject to the further provisions:

(i) the obligations of the Parties under this Agreement to the

extent performance thereof is prevented or impeded by the event of

Force Majeure shall be suspended and the Parties shall not be

liable for the non-performance thereof for the duration of the

period of Force Majeure; and

(ii) the time period(s) for the performance of the obligations of the

Parties under this Agreement to the extent performance thereof is

Page 153: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

17

prevented or impeded by the event of Force Majeure shall be

extended for the duration of the relevant period of Force Majeure

except as provided herein.

(E) Force Majeure Events Exceeding 60 Days

(i) If an event or series of events (alone or in combination) of

Force Majeure occur, and continue for a period in excess of 60

consecutive days, then BPCL shall have the right to terminate this

agreement, whereupon the Parties shall meet to mitigate the

impediments caused by the Force Majeure event.

23. ARBITRATION CLAUSE :

23.1 Any dispute or difference of any nature whatsoever, any claim, cross-claim,

counter-claim or set off of BPCL/Vendor against omission or on account of any

of the parties hereto arising out of or in relation to this Contract shall be referred

to the Sole Arbitration of Director (Marketing) / of BPCL as the case may be or

to some officer of BPCL who may be nominated by them.

23.2. In the event the Arbitrator being unable or refusing to act for any reason whatsoever, the

said Directors of BPCL shall designate another person to act as an Arbitrator in

accordance with the terms of the said Contract/Agreement. The Arbitrator newly

appointed shall be entitled to proceed with the reference from the point at which it was

left by his predecessor.

23.3. It is known to the parties herein that the Arbitrator appointed hereunder is an employee of

the Corporation and may be Share holder of the Corporation.

23.4. The award of the Arbitrator so appointed shall be final, conclusive and binding on all the

parties to the contract and the law applicable to arbitration proceedings will be the

Arbitration and Conciliation Act, 1996 or any other enactment in replacement thereof.

23.5. The language of the proceedings will be in English and the place of proceedings will be

Mumbai.

23.6. The parties hereby agree that the Courts in the city of Mumbai alone shall have

jurisdiction to entertain any application or other proceedings in respect of anything

arising under this Agreement and any Award or Awards made by the Sole Arbitrator

hereunder shall be filed, if required, in the concerned Courts in the City of Mumbai alone.

(legal)

23.6 SETTLEMENT OF DISPUTE BETWEEN GOVT. DEPT. /PUBLIC SECTOR UNDERTAKINGS IN A PURCHASE OR SERVICE CONTRACT :

In the event of any dispute or differences between the VENDOR/ CONTRACTOR/ SUPPLIER and the OWNER, if the VENDOR/ CONTRACTOR/ SUPPLIER is a Government Department, a Government Company or a Undertaking in the public sector, then in suppression of the provisions of clause 23 of the GPC

Page 154: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

18

(corresponding clause no of GCC or NIT etc.), stands modified to the following extent:- all disputes and differences of whatsoever nature arising out of or in relation to this Contract/ Agreement or in relation to any subsequent contract/ agreement between the parties shall be attempted to be resolved amicably by mutual discussions between the parties. If they are not settled at the implementation level of officers, then these unresolved disputes/ differences will be referred for resolution by discussions with the concerned Director of BPCL and the concerned Director of vendor/ contractor/ supplier. In case same does not resolve the difference within 30 days, arbitration clause as hereunder would apply. In the event of any dispute or difference relating to the interpretation and application of the provisions of the contract, such dispute or difference shall be referred by either party for Arbitration to the sole Arbitrator in the Department of Public Enterprises to be nominated by the Secretary to the Government of India in-charge of the Department of Public Enterprises. The Arbitration and Conciliation Act, 1996 shall not be applicable to arbitration under this clause. The award of the Arbitrator shall be binding upon the parties to the dispute provided, however, any party aggrieved by such award may make a further reference for setting aside or revision of the award to the Law Secretary, Department of Legal Affairs, Ministry of Law & Justice, Government of India. Upon such reference the dispute shall be decided by the Law Secretary or the Special Secretary/ Additional Secretary, when so authorized by the Law Secretary, whose decision shall bind the Parties finally and conclusively. The parties to the dispute will share equally the cost of arbitration as intimated by the arbitrator.

24. INTEGRITY PACT (IP) :

Vendors are requested to sign & return our pre-signed IP document , if applicable. This

document is essential & binding. Vendor's failure to return the IP document duly signed

along with Bid Document may result in the bid not being considered for further

evaluation.

25. RECOVERY OF SUMS DUE :

Whenever, any claim against vendor for payment of a sum of money arises out of or

under the contract, the owner shall be entitled to recover such sums from any sum then

due or when at any time thereafter may become due from the vendor under this or any

other contract with the owner and should this sum be not sufficient to cover the

recoverable amount of claim(s), the vendor shall pay to BPCL on demand the balance

remaining due.

Page 155: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

19

26. CONFIDENTIALITY OF TECHNICAL INFORMATION :

Drawing, specifications and details shall be the property of the BPCL and shall be

returned by the Vendor on demand. The Vendor shall not make use of drawing and

specifications for any purpose at any time save and except for the purpose of BPCL. The

Vendor shall not disclose the technical information furnished to or organized by the

Vendor under or by virtue of or as a result of the implementation of the Purchase Order to

any person, firm or body or corporate authority and shall make all endeavors to ensure

that the technical information is kept CONFIDENTIAL. The technical information

imparted and supplied to the vendor by BPCL shall at all time remain the absolute

property of BPCL. Imparting of any confidential information by the Vendor will be

breach of contract.

27. PATENTS & ROYALTIES :

The vendor shall fully indemnify BPCL and users of materials specified herein/supplied

at all times, against any action, claim or demand, costs and expenses, arising from or

incurred by reasons of any infringement or alleged infringement of any patent, registered

design, trademark or name, copy right or any other protected rights in respect of any

materials supplied or any arrangement, system or method of using, fixing or working

used by the vendor. In the event of any claim or demand being made or action sought

against BPCL in respect of any of the aforesaid matter, the vendor shall be notified

thereof immediately and the vendor shall at his/its own expense with (if necessary) the

assistance of BPCL (whose all expense shall be reimbursed by the vendor) conduct all

negotiations for the settlement of the same and/or litigation which may arise thereof.

28. LIABILITY CLAUSE :

In case where it is necessary for employees or representatives of the Vendor to go upon

the premises of owner, vendor agrees to assume the responsibility for the proper conduct

of such employees/representatives while on said premises and to comply with all

applicable Workmen's Compensation Law and other applicable Government Regulations

and Ordinances and all plant rules and regulations particularly in regard to safety

precautions and fire hazards. If this order requires vendor to furnish labour at site, such

vendor's workmen or employees shall under no circumstances be deemed to be in owner's

employment and vendor shall hold himself responsible for any claim or claims which

they or their heirs, dependent or personal representatives, may have or make, for damages

or compensation for anything done or committed to be done, in the course of carrying

out the work covered by the purchase order, whether arising at owner's premises or

elsewhere and agrees to indemnify the owner against any such claims, if made against the

owner and all costs of proceedings, suit or actions which owner may incur or sustain in

respect of the same.

29. COMPLIANCE OF REGULATIONS :

Vendor warrants that all goods/Materials covered by this order have been produced, sold,

dispatched, delivered and furnished in strict compliance with all applicable laws,

regulations, labour agreement, working condition and technical codes and statutory

requirements as applicable from time to time. The vendor shall ensure compliance with

Page 156: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

20

the above and shall indemnify owner against any actions, damages, costs and expenses of

any failure to comply as aforesaid.

30. REJECTION, REMOVAL OF REJECTED GOODS AND REPLACEMENT:

In case the testing and inspection at any stage by inspectors reveal that the equipment,

materials and workmanship do not comply with specification and requirements, the same

shall be removed by the vendor at his/its own expense and risk, within the time allowed

by the owner. The owner shall be at liberty to dispose off such rejected goods in such

manner as he may think appropriate. In the event the vendor fails to remove the rejected

goods within the period as aforesaid, all expenses incurred by the owner for such disposal

shall be to the account of the vendor. The freight paid by the owner, if any, on the inward

journey of the rejected materials shall be reimbursed by the vendor to the owner before

the rejected materials are removed by the vendor. The vendor will have to proceed with

the replacement of the equipment or part of equipment without claiming any extra

payment if so required by the owner. The time taken for replacement in such event will

not be added to the contractual delivery period.

31. NON-WAIVER :

Failure of the Owner to insist upon any of the terms or conditions incorporated in the

Purchase Order or failure or delay to exercise any rights or remedies herein, or by law or

failure to properly notify Vendor in the event of breach, or the acceptance of or payment

of any goods hereunder or approval of design shall not release the Vendor and shall not

be deemed a waiver of any right of the Owner to insist upon the strict performance

thereof or of any of its or their rights or remedies as to any such goods regardless of when

such goods are shipped, received or accepted nor shall any purported oral modification or

revision of the order by BPCL act as waiver of the terms hereof. Any waiver to be

effective must be in writing. Any lone incident of waiver of any condition of this

agreement by BPCL shall not be considered as a continuous waiver or waiver for other

condition by BPCL.

32. NEW & UNUSED MATERIAL :

All the material supplied by the vendor shall be branded new, unused and of recent

manufacture.

33. PURCHASE PREFERENCE CLAUSE :

Owner reserves its right to allow Public Sector Enterprises (Central/State), purchase

preference as admissible/applicable from time to time under the existing Govt. policy.

Purchase preference to a PSE shall be decided based on the price quoted by PSE as

compared to L1 Vendor at the time of evaluation of the price bid.

Owner reserves its right to allow Micro and Small Enterprises (MSEs) and MSEs

owned by Scheduled Caste (SC) or the Scheduled tribe (ST) entrepreneurs,

purchase preference as admissible/applicable from time to time under the existing Govt.

policy. Purchase preference to a MSE and a MSE owned by SC/ST entrepreneurs

shall be decided based on the price quoted by the said MSEs as compared to L1 Vendor

at the time of evaluation of the price bid.

Page 157: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

21

Subject to meeting terms and conditions stated in the tender document including but

not limiting to prequalification criteria, in present tender, as the tendered quantity

cannot be split due to nature of job, MSE shall be allowed for supply and installation

of total tendered quantity provided their quoted price is within a price band of L1 +

15 percent and they match the L1 price. In case of more than one such MSEs are in

the price band of L1 + 15%, then L1 MSE will be offered first and if matches the L1

price, MSE shall be allowed for supply and installation of total tendered quantity. If

L1 MSE does not matches L1 price, other MSES falling in range of L1+15% band

will be offered in order of L2 MSE,L3 MSE etc. until they match L1 price. No

separate preference will be given to MSE owned by Scheduled Caste & Scheduled

Tribe entrepreneurs over MSE owned by general person as quantity cannot be split in

this tender

34. CANCELLATION :

34.1. BPCL reserves the right to cancel the contract/purchase order or any part thereof through

a written notice to the vendor if.

34.1.1. The vendor fails to comply with the terms of this purchase order/contract.

34.1.2. The vendor becomes bankrupt or goes into liquidation.

34.1.3. The vendor fails to deliver the goods on time and/or replace the rejected goods promptly.

34.1.4. The vendor makes a general assignment for the benefit of creditors.

34.1.5. A receiver is appointed for any of the property owned by the vendor.

34.2. Upon receipt of the said cancellation notice, the vendor shall discontinue all work on the

purchase order matters connected with it. BPCL in that event will be entitled to procure

the requirement in the open market and recover excess payment over the vendor's agreed

price if any, from the vendor and also reserving to itself the right to forfeit the security

deposit if any, made by the vendor against the contract. The vendor is aware that the said

goods are required by BPCL for the ultimate purpose of materials production and that

non-delivery may cause lossof production and consequently loss of profit to the BPCL. In

this-event of BPCL exercising the option to claim damages for non delivery other than

by way of difference between the market price and the contract price, the vendor shall

pay to BPCL, fair compensation to be agreed upon between BPCL and the vendor. The

provision of this clause shall not prejudice the right of BPCL from invoking the

provisions of price reduction clause mentioned in 20.3.1 as aforesaid.

35. ANTI –COMPETITIVE AGREEMENTS/ABUSE OF DOMINANT POSITION :

The Competition Act, 2002 as amended by the Competition (Amendment) Act, 2007 (the

Act), prohibits anti- competitive practices and aims at fostering competition and at

Page 158: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

22

protecting Indian markets against anti- competitive practices by enterprises. The Act

prohibits anti- competitive agreements, abuse of dominant position by enterprises, and

regulates combinations (consisting of acquisition, acquiring of control and M&A)

wherever such agreements, abuse or combination causes, or is likely to cause, appreciable

adverse effect on competition in markets in India. BPCL reserves the right to approach

the Competition Commission established under the Act of Parliament and file

information relating to anti-competitive agreements and abuse of dominant position. If

such a situation arises, then Vendors are bound by the decision of the Competitive

Commission and also subject to penalty and other provisions of the Competition Act.

36. ASSIGNMENT

The Vendor can / does not have any right to assign his rights and obligations under these

general purchase conditions without the prior written approval of BPCL.

37. GOVERNING LAW

These General Purchase Conditions shall be governed by the Laws of India.

38. AMENDMENT

Any amendment to these General Purchase Conditions can be made only in writing and

with the mutual consent of the parties to these conditions.

39. SPECIAL PURCHASE CONDITIONS

In case of a conflict between the clauses, terms and conditions of General Purchase

Conditions and Special Purchase condition, the clauses, terms and conditions of Special

Purchase Condition will have an overriding effect over General Purchase Conditions and

the same shall be applicable.

40. EXPEDITING

Engineers India Limited have been assigned to expedite both manufacture and shipment of equipment and testing materials covered by the Purchase Order. BPCL/CONSULTANT shall have the free access to Vendor’s shop and/or sub-supplier’s shop at any time and they shall be provided all necessary assistance and information to help them perform their job. In order to facilitate overall execution of the order within the contractual delivery date, Vendor shall furnish to CONSULTANT within 4 weeks of receipt of Purchase Order the required number of copies of documents such as but not limited to schedules/PERT charts, unpriced copies of sub-orders/sub-contracts, phased programme of itemwise manufacturing, testing and delivery and any other information/documentation as may be called for by BPCL/CONSULTANT. Vendor shall furnish Progress Report at the end of each month to CONSULTANT/BPCL

41. OILS & LUBRICANTS The first filling of oils and lubricants, if any required for every equipment shall be included in the price and appropriate products manufactured by

Page 159: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

23

Bharat Petroleum Corporation shall be used. In case, the particular oils and lubricants are not manufactured by BPCL, same of other Government Oil Company can be used. The Vendor shall also recommend the quality/quantity of oils and lubricants required for one year continuous operation.

42 SPARE PARTS

The Vendor must furnish itemised and priced list of mandatory spare parts required for two years operation of the main equipment and prime movers also. The Vendor shall provide the necessary cross sectional drawing to identify the spare parts numbers and their location as well as an interchange ability chart.

43. PART ORDER/REPEAT ORDER

Vendor hereby agrees to accept part order against tender enquiry at Owner’s option without any limitation whatsoever and also accept repeat order during a period of Twelve months after placement of purchase order at the same unit prices, terms and conditions. All lumpsum charges, if any, shall be pro-rata on value basis on acceptance of part order

44. JURISDICTION The contract shall be governed by and constructed according to the laws in force in INDIA. The contractor hereby submits to the jurisdiction of the Courts situated at New Delhi for the purpose of actions and proceedings arising out of the contract and the courts at New Delhi only will have the jurisdiction to hear and decide such actions and proceedings

45. Address Ch Manager (Pipeline Projects) Bharat Petroleum Corporation Ltd Plot A 5 & 6, sector 1 Noida UP – 201301 Fax – 0120-2474368 Note : Performance bang guarantee shall be mailed to the address given in clasuse no 41

46. Holiday listing:

Holiday Listings policy as per enclosed

Page 160: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

24

47. NOTICES

Any notices to be given hereunder by a Party to the other shall be in English and

delivered by hand or sent by courier or facsimile to the other Party at the address

or facsimile number stated below or such other address or number as may be

notified by the relevant Party from time to time:

BPCL

_______________________ _______________________

_______________________

Vendor

_______________________

_______________________

_______________________

Please sign & return all the pages of GPC as a token of your acceptance of all the terms &

conditions as mentioned above.

Page 161: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

25

Annexure I

PERFORMANCE BANK GUARANTEE

(On Non-judicial paper for appropriate value)

To,

Bharat Petroleum Corporation Limited

---------------------------------

--------------------------------

Dear Sir,

In consideration of the Bharat Petroleum Corporation Limited, (hereinafter called ‘the Company’

which expression shall include its successors and assigns) having awarded to M/s. (Name)

………. (Constitution)………….. (address) ……….(hereinafter referred to as “The vendor”

which expression shall wherever the subject or context so permits include its successors and

assigns) a supply contract in terms interalia, of the Company’s Purchase order No…….. dated

………. and the General and Special Purchase Conditions of the Company and upon the

condition of vendor’s furnishing security for the performance of the vendor’s obligations and/or

discharge of the vendor’s liability under and / or in connection with the said supply contract upto

a sum of Rs.(in figures)…………..Rs(in words)…………………………only amounting to 10%

(ten percent)of the total contract value.

We, (Name)…………..(constitution) ……………(hereinafter called “the Bank” which

expression shall include its successors and assigns) hereby jointly and severally undertake and

guarantee to pay to the Company in -----(Currency) forthwith on demand in writing and without

protest or demur of any and all moneys any wise payable by the Vendor to the Company under in

respect of or in connection with the said supply contract inclusive of all the Company’s losses and

expenses and other moneys anywise payable in respect to the above as specified in any notice of

demand made by the Company to the Bank with reference to this Guarantee upto an aggregate

limit of Rs(in figures)…………Rs(in words)……………………….only.

AND the Bank hereby agrees with the Company that

i. This Guarantee/undertaking shall be a continuing guarantee and shall remain valid

and irrevocable for all claims of the Company and liabilities of the vendor arising

upto and until midnight of …………………………………..

This date shall be 6 months from the last date of guarantee period.

Page 162: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED

26

ii This Guarantee / Undertaking shall be in addition to any other guarantee or security of

whatsoever that the Company may now or at any time otherwise have in relation to the vendor’s

obligation/liabilities under and /or connection with the said supply contract, and the Company

shall have full authority to take recourse to or reinforce this security in preference to the other

security(ies) at its sole discretion, and no failure on the part of the Company in enforcing or

requiring enforcement of any other security shall have the effect of releasing the Bank from its

liability hereunder.

ii. The Company shall be at liability without reference to the Bank and without effecting

the full liability of the Bank hereunder to take any other security in respect of the

vendor’s obligations and /or liabilities under or in connection with the said supply

contract and to vary the terms vis a vis the vendor of the said supply contract or to

grant time and / or indulgence to the vendor or to reduce or to increase or otherwise

vary the prices of the total contract value or to release or to forbear from enforcement

all or any of the obligations of the vendor under the said supply contract and / or the

remedies of the Company under any other security(ies) now or hereafter held by the

Company and no such dealing(s), variation(s), reduction(s), increase(s) or the

indulgence(s) or arrangement(s) with the vendor or release or forbearance whatsoever

shall have the effect of releasing the Bank from its full liability to the Company

hereunder or of prejudicing rights of the Company against the Bank.

iv. This Guarantee /Undertaking shall not be determined by the liquidation or winding up

ordissolution or change of constitution or insolvency of the vendor but shall in all respects and for

all purposes be binding and operative until payment of all moneys payable to the Company in

terms hereof.

v. The Bank hereby waives all rights at any time inconsistent with the terms of the Guarantee /

Undertaking and the obligations of the Bank in terms hereof shall not be anywise affected or

suspended by reason of any dispute or disputes having been raised by the vendor (whether or not

pending before any Arbitrator, officer, Tribunal or Court) or any denial of liability by the vendor

or any other order of communication whatsoever by the vendor stopping or preventing or

purporting to stop or prevent any payment by the Bank to the Company in terms hereof.

vi. The amount stated in any notice of demand addressed by the Company to the Guarantor as

liable to be paid to the Company by the vendor or as suffered or incurred by the Company on

account of any losses or damages of costs, charges and or expenses shall as between the Bank and

the Company be conclusive of the amount so liable to be paid to the Company or suffered or

incurred by the Company, as the case may be and payable by the Guarantor to Company in terms

hereof.

Yours faithfully,

(Signature)

NAME & DESIGNATION

NAME OF THE BANK

NOTES:

Page 163: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED
Page 164: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED
Page 165: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED
Page 166: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED
Page 167: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED
Page 168: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED
Page 169: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED
Page 170: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED
Page 171: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED
Page 172: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED
Page 173: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED
Page 174: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED
Page 175: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED
Page 176: REQUEST FOR QUOTATION (RFQ) - Bharat PetroleumREQUEST FOR QUOTATION (RFQ) RFQ No.: SM/A872-030-XB-MR-0600/1004 Date: 12.01.2017 To, M/s Client : BHARAT PETROLEUM CORPORATION LIMITED