1 Report to Rapport au: Transportation Committee Comité des transports 2 May 2018 / 2 mai 2018 Submitted on April 17, 2018 Soumis le 17 avril 2018 Submitted by Soumis par: John Manconi, General Manager / Directeur général, Transportation Services Department / Direction générale des transports Contact Person Personne ressource: Vivi Chi, Director / Directeur, Transportation Planning / Planification des transports, Transportation Services Department / Direction générale des transports (613) 580-2424, 21877, [email protected] Ward: BEACON HILL - CYRVILLE (11) AND RIDEAU-ROCKCLIFFE (13) File Number: ACS2018-TSD-PLN-0005 SUBJECT: Montreal-Blair Road Transit Priority Corridor (St. Laurent Boulevard to Blair Station) Environmental Assessment Study Statement of Work OBJET: Étude d'évaluation environnementale du couloir prioritaire de transport en commun sur le chemin de Montréal et le chemin Blair (du boul. St-Laurent à la station Blair) Énoncé de travail REPORT RECOMMENDATION That the Transportation Committee approve the Statement of Work for the Montreal-Blair Road Transit Priority Corridor (St. Laurent Boulevard to Blair Station) Environmental Assessment Study, as outlined in this report and detailed in Document 1.

Upload: others

Post on 17-Jun-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Report to Rapport au: Transportation Committee Comité des

1

Report to

Rapport au:

Transportation Committee

Comité des transports

2 May 2018 / 2 mai 2018

Submitted on April 17, 2018

Soumis le 17 avril 2018

Submitted by

Soumis par:

John Manconi, General Manager / Directeur général, Transportation Services

Department / Direction générale des transports

Contact Person

Personne ressource:

Vivi Chi, Director / Directeur, Transportation Planning / Planification des

transports, Transportation Services Department /

Direction générale des transports

(613) 580-2424, 21877, [email protected]

Ward: BEACON HILL - CYRVILLE (11)

AND RIDEAU-ROCKCLIFFE (13)

File Number: ACS2018-TSD-PLN-0005

SUBJECT: Montreal-Blair Road Transit Priority Corridor (St. Laurent Boulevard

to Blair Station) Environmental Assessment Study – Statement of

Work

OBJET: Étude d'évaluation environnementale du couloir prioritaire de

transport en commun sur le chemin de Montréal et le chemin Blair

(du boul. St-Laurent à la station Blair) – Énoncé de travail

REPORT RECOMMENDATION

That the Transportation Committee approve the Statement of Work for the

Montreal-Blair Road Transit Priority Corridor (St. Laurent Boulevard to Blair

Station) Environmental Assessment Study, as outlined in this report and detailed

in Document 1.

Page 2: Report to Rapport au: Transportation Committee Comité des

2

RECOMMANDATION DU RAPPORT

Que le Comité des transports approuve l’énoncé de travail de l’étude d’évaluation

environnementale du couloir prioritaire de transport en commun sur le chemin de

Montréal et le chemin Blair (du boul. St-Laurent à la station Blair), comme

présenté dans le présent rapport et expliqué dans le Document 1.

BACKGROUND

The City's Official Plan (OP) emphasizes urban intensification and increased mixed-use

development centred around transit corridors as one of the means to manage future

travel demand and minimize the use of single occupancy vehicles during peak travel

periods.

The Transportation Master Plan (TMP) identifies a number of modifications to road and

transit infrastructure to accommodate future travel demand on the City’s transportation

infrastructure and to meet modal share objectives. Transit priority corridors complement

the rapid transit network by providing improved city-wide transit access to major

employment, commercial, and institutional land uses. Montreal Road and Blair Road are

identified in the TMP as part of the 2031 Affordable Rapid Transit and Transit Priority

Network shown in Figure 1.

Figure 1: TMP Rapid Transit and Transit Priority Corridors

A section of Montreal Road’s transit priority measures was already assessed through

the 2017 Montreal Road Transportation Planning and Functional Design Study (North

Page 3: Report to Rapport au: Transportation Committee Comité des

3

River Road to St. Laurent Boulevard). This new study will examine the section of

Montreal Road from St. Laurent Boulevard to Blair Road, and along Blair Road south to

Blair Station.

The Environmental Assessment (EA) Study will be completed in accordance with the

Transit Project Environmental Assessment Process (Ont. Reg. 231/08).

The EA Study will:

Investigate options to improve transit service efficiency and travel environment for

active and other modes of transportation along the corridor;

Establish right-of-way requirements;

Allow the City to protect land for the project; and,

Allow the project to proceed to design and construction.

Since the corridor is adjacent to federal lands (National Capital Commission (NCC),

National Research Council Canada (NRCC), Canadian Security Intelligence Service

(CSIS), Communications Security Establishment Canada (CSEC) and Canada

Mortgage and Housing Corporation (CMHC)), the project may also need to comply with

requirements from the Canadian Environmental Assessment Act (CEAA) if federal land

is affected. If that is the case, the EA processes will be co-ordinated to avoid duplication

of effort.

This Statement of Work (SoW) report outlines the scope, methodology, and deliverables

of the EA Study. Details of the SoW are outlined in Document 1.

DISCUSSION

The Montreal-Blair Road Transit Priority Corridor (Figure 2) is approximately 4.4 km in

length between St. Laurent Boulevard and Blair Station. The section along Montreal

Road is designated as an Arterial Mainstreet in the City’s Official Plan. Arterial

Mainstreets are prime locations that present opportunities to intensify and enhance

development in a manner that creates attractive pedestrian environments, contributes to

vibrant new neighbourhoods, and creates transit-friendly places. Blair Road (Montreal

Road to Blair Station) is a north-south urban arterial.

Page 4: Report to Rapport au: Transportation Committee Comité des

4

Figure 2: Study Corridor

After the opening of the O-Train Confederation Line, Blair Station will play a critical role

as a high volume transfer station. The EA Study will investigate options to provide an

efficient and reliable transit service connection between the Montreal-Blair Road

corridor and Blair Station. This will complement the on-going planned changes at Blair

Station as part of O-Train Confederation Line project.

Key tasks for the EA Study include the following:

Confirmation of future transportation demand in the study area including transit

service and ridership;

Development of options to address future demand for transit and other modes;

Application of the Complete Streets framework and multi-modal level of service

analysis within the context of existing and future land use;

Assessment of walking and cycling infrastructure requirements and connections;

Assessment and evaluation of environmental implications;

o Geotechnical conditions;

o Wetlands, natural environmental areas and features;

o Stormwater management and hydrology;

Page 5: Report to Rapport au: Transportation Committee Comité des

5

o Noise, Vibration and Air Quality impacts; and,

o Adjacent land uses and communities (existing and future).

Undertaking of climate change adaptation and mitigation assessment and

greenhouse gas emission analysis;

Development of mitigation measures;

Development of a Recommended Plan for the corridor (including functional design);

Identification of capital costs for implementation;

Consultation with federal agencies and departments, community groups, and

stakeholders; and,

Documentation.

The EA Study is expected to be completed in approximately 24 months.

RURAL IMPLICATIONS

This report does not have a direct impact on the rural area of the city, as the study area

is located within the urban boundary.

CONSULTATION

Consultation will include meetings with key stakeholders through the Agency

Consultation Group, Public Consultation Group, and Business Consultation Group.

Stakeholders include Indigenous People, federal government agencies and Crown

corporations such as NCC, NRCC, CSIS, CSEC and CMHC, City’s Advisory

Committees as appropriate, affected landowners, representatives of business groups

and Community Associations. Consultation with the general public will occur primarily

through Open Houses. A dedicated project web page will also be set up to share study

information.

COMMENTS BY THE WARD COUNCILLOR(S)

Comments from Councillor Tierney (Ward 11)

The Councillor is in concurrence with the report and does not have any specific

comments to add to it at this time.

Page 6: Report to Rapport au: Transportation Committee Comité des

6

Comments from Councillor Nussbaum (Ward 13)

Councillor Nussbaum is aware of this report.

ADVISORY COMMITTEE(S) COMMENTS

The City’s Advisory Committees will be engaged as part of consultation process.

Typically, representatives of the Advisory Committees will be invited to participate in the

study’s Public Consultation Group.

LEGAL IMPLICATIONS

There are no legal impediments to approving the recommendation in this report.

RISK MANAGEMENT IMPLICATIONS

There is no risk involved in approving the recommendations of this report.

ASSET MANAGEMENT IMPLICATIONS

The recommendations in this report are consistent with the City’s Comprehensive Asset

Management (CAM) Program (City of Ottawa Comprehensive Asset Management

Program) objectives. Undertaking the recommend studies and environmental

assessments will provide the necessary information for the City to fulfill its obligation to

deliver quality services to the community in a way that balances service levels, risk, and

affordability.

FINANCIAL IMPLICATIONS

Funding for this EA study recommended by this report is available in capital project

account 908554 2017 Rapid Transit EA Studies.

ACCESSIBILITY IMPACTS

There are no accessibility implications in this report. As part of the development of

functional design, the City’s Accessibility Design Standards will be applied.

ENVIRONMENTAL IMPLICATIONS

The EA Study will examine and evaluate the project’s effects on the social, cultural,

physical, and natural environments within the study area. Appropriate mitigation

measures will be developed and post mitigation environmental impacts will be

determined.

Page 7: Report to Rapport au: Transportation Committee Comité des

7

TERM OF COUNCIL PRIORITIES

The recommendation contained herein aims to support the following Strategic

Objectives adopted by Council:

Transportation and Mobility

TM2 - Provide and promote infrastructure to support safe mobility choices;

TM3 - Integrate the rapid transit and transit priority network into the community;

TM4 - Improve safety for all road users; and,

TM5 - Ensure reliable, safe, accessible and affordable transit services.

SUPPORTING DOCUMENTATION

Document 1 – Montreal-Blair Road Transit Priority Corridor (St. Laurent Boulevard to

Blair Station) Environmental Assessment Study – Statement of Work

DISPOSITION

Following the Transportation Committee’s approval of the Statement of Work, the

Transportation Services Department will initiate the process to retain a consulting firm to

assist the City with this Environmental Assessment Study. A call for proposal will be

undertaken with the assistance of Supply Services. Once the consultant has been

selected, the EA Study will proceed as described in Document 1.

Page 8: Report to Rapport au: Transportation Committee Comité des

8

Document 1

Montreal-Blair Road Transit Priority Corridor Environmental Assessment Study –

Statement of Work

1.0 Introduction

The City of Ottawa is the proponent of an Environmental Assessment (EA) Study in

accordance with the Transit Project Environmental Assessment Process (Ont. Reg.

231/08) for the Montreal-Blair Road Transit Priority Corridor (St. Laurent Boulevard to

Blair Station). The study corridor is shown in Figure 1.

Figure 1: Study Corridor

2.0 Planning Context

The Transportation Master Plan (TMP) identifies a number of modifications to road and

transit infrastructure to accommodate future travel demand on the City’s transportation

infrastructure. Transit priority corridors complement the rapid transit network by

providing improved city-wide transit access to major employment, commercial and

institutional land uses.

The TMP identifies the following sections of Montreal Road and Blair Road as part of

the 2031 Affordable Rapid Transit and Transit Priority Network:

Montreal Road: North River Road to St. Laurent Boulevard;

Page 9: Report to Rapport au: Transportation Committee Comité des

9

Montreal Road: St. Laurent Boulevard to Blair Road; and,

Blair Road: Montreal Road to Blair Station.

These roadways are also identified in the TMP as a cycling spine.

In 2017, the City completed the Montreal Road Transportation Planning and Functional

Design Study (North River Road and St. Laurent Boulevard), which recommended a

road corridor design that includes both transit priority and cycling infrastructure.

An Environmental Assessment (EA) Study is required for the Montreal-Blair Road

Transit Priority Corridor (St. Laurent Boulevard to Blair Station) to fulfil Municipal Class

EA requirements before the project proceeds for implementation. This project is

approximately 4.4 km in length. The TMP describes this project as requiring road

widening to provide exclusive bus lanes along the corridor. Engagement with property

owners early and frequently will be required during the course of the study.

Land Use along the corridor is designated in the Official Plan (OP) as General Urban

Area, Urban Employment Area, Major Open Space, and Mixed Use Centre. It includes

commercial, retail, low to high-density residential, government offices, a retirement

residence, and shopping centres.

The section of Montreal Road within the study area (St. Laurent Boulevard to Blair

Road) is identified in the OP as an Arterial Mainstreet. It has an urban section with two

through lanes in each direction, an intermittent two-way-left-turn lane in the median, and

auxiliary left and right turn lanes at major intersections. Except for the 670 m long

section near Blair Road, on-road bicycle lanes exist in both directions. Concrete

sidewalks exist on both sides of the street.

As per the OP, Arterial Mainstreets are prime locations that present opportunities to

intensify and enhance development in a manner that creates attractive pedestrian

environments, contributes to vibrant new neighbourhoods, and creates transit-friendly

places.

Blair Road within the study area (Montreal Road to OR 174 West-bound Off-ramp) is

an arterial road, which has two distinct sections:

Montreal Road to Ogilvie Road: With the exception of a 140 m section north of

Ogilvie Road where the roadway has two southbound lanes, this section generally

has one lane in each direction with auxiliary turn lanes at major intersections. The

easterly portion of the roadway has an urban section, with an on-road bicycle lane

Page 10: Report to Rapport au: Transportation Committee Comité des

10

and asphalt sidewalk. The westerly portion has a rural cross-section with a paved

shoulder for bicycles. This section is bordered on the east by single unit residential

houses. The west section is designated in the OP as an Urban Employment Area,

which houses federal government offices of National Research Council Canada

(NRCC), Canadian Security Intelligence Service (CSIS), and Communications

Security Establishment Canada (CSEC).

Ogilvie Road to OR 174 West-bound Off-ramp has an urban cross-section with a

sidewalk on either side of roadway. It generally has three southbound lanes for

general traffic. The number of lanes in the northbound direction varies between one

and two. The land use along this section of Blair Road includes commercial, retail,

and shopping centers. Transit buses connect to Blair Station through the westerly

approach of Blair- OR 174 West-bound Off-ramp intersection.

In 2015, a Community Development Plan (CDP) Study was completed for the former

Canadian Forces Base (CFB) Rockcliffe, which is located north of Montreal Road

between the Aviation Parkway and the NRCC Campus. This 131 hectare site is

proposed to be redeveloped to create a mixed-use community for approximately 9,800

residents and provide space for employment uses for approximately 2,600 permanent

jobs. The long-term development period to full buildout is estimated to be 15-20 years.

A reliable transit service along the Montreal-Blair Road Transit Priority Corridor will

encourage transit usage and help achieve the TMP’s modal share targets.

Existing bus service along the corridor operates in mixed traffic (Figure 2). OC Transpo

local route # 12 travels along Montreal Road and provides service between Downtown

and Blair Station. Route #s 7, 17, 19, 27 and 129 also serve some sections of Montreal

Road within the project limits. Blair Road corridor is partially served by local route # 23,

which operates during certain times of the day. The EA Study will consider planned

changes to transit bus service in the study area after the opening of the O-Train

Confederation Line.

Page 11: Report to Rapport au: Transportation Committee Comité des

11

Figure 2: OC Transpo routes in the study area

3.0 Project Scope and Major Tasks

3.1 Study Area

Figure 1 illustrates the general study area that extends from Wateridge Village (north of

Montreal Road) to OR 174 in the south. Land use along the corridor includes General

Urban Area, Urban Employment Area, Major Open Space, and Mixed Used Centre.

The land use along Montreal Road includes commercial, retail, low to high-density

residential, a retirement residence, and green space. Notre-Dame Cemetery is located

at the north-west corner of St. Laurent Boulevard-Montreal Road intersection.

Blair Road between Montreal Road and Ogilvie Road is bordered on the east side by

single unit residential homes. However, on the west side the area is designated in the

OP as Urban Employment Area, which houses government offices of NRCC, CSIS, and

CSEC. The section south of Ogilvie Road to OR 174 is identified in the OP as Mixed

Use Centre. It includes commercial, retail, and shopping centres.

The study area also includes the Aviation Parkway, which intersects Montreal Road

east of St. Laurent Boulevard. As the Aviation Parkway is a federally owned roadway,

the project will require consultation with the National Capital Commission (NCC) for any

modifications that may be required at the intersection of Montreal Road and the Aviation

Parkway.

Page 12: Report to Rapport au: Transportation Committee Comité des

12

Some tasks may require examination of a broader area beyond these limits to address

environmental impacts, operational issues, and to coordinate with relevant on-going

studies and projects.

The existing right-of-way along Montreal Road varies between 22 m and 38 m. Along

Blair Road (between Montreal Road and Ogilvie Road), it is generally 23 m with the

exception of a wider right-of-way near the intersection with Montreal Road. Further, a

right-of-way of 46 m or higher is available between Ogilvie Road and OR 174 West-

bound Off-ramp.

The OP identifies protection of 37.5 m right-of-way along Montreal Road (St. Laurent to

OR 174) and 30 m along Blair Road (Montreal Road to Ogilvie Road). Engagement with

property owners early and frequently will be required during the course of the study.

3.2 Timing

The study is expected to be completed in approximately 24 months from award of the

contract.

3.3 Coordination with other studies

The EA Study will take into consideration other relevant studies as well as analysis and

preliminary findings of any ongoing transportation, development, and infrastructure

projects that could influence the direction and/or conclusions of the study. These

include:

Montreal Road Transportation Planning and Functional Design Study-North River

Road to St. Laurent Boulevard (2017);

Former CFB Rockcliffe CDP (2015);

Transit Oriented Development (TOD) Plans (2014);

Ottawa Cycling and Pedestrian Plans (2013);

Urban Design Guidelines for Development along Arterial Mainstreets (2006);

Official Plan Amendments #150 and #180 regarding housing and employment

growth projections; and,

The Plan for Canada’s Capital 2017-2067.

Page 13: Report to Rapport au: Transportation Committee Comité des

13

3.4 Major Tasks

Major tasks for this EA Study include the following:

Review relevant information, studies and reports undertaken for this study area;

Confirm future transportation demand in the study area including transit service and

ridership;

Develop options to address future demand for transit and other modes;

Apply the Complete Streets framework and multi-modal level of service analysis

within the context of existing and future land use;

Assess walking and cycling infrastructure requirements and connections;

Develop alternative solutions and design alternatives for the project;

Assess and evaluate environmental implications;

o Natural environment features;

o Geotechnical conditions;

o Wetlands, natural environmental areas and features;

o Stormwater management and hydrology;

o Noise, Vibration and Air Quality impacts; and,

o Adjacent land uses and communities (existing and future).

Undertake climate change adaptation and mitigation assessment and greenhouse

gas emission analysis;

Develop mitigation measures;

Develop a Recommended Plan for the corridor (including functional design, and

property requirements);

Identify capital costs for implementation as per the Council approved Project

Delivery Review process;

Consult with federal agencies and departments, community groups and

stakeholders;

Page 14: Report to Rapport au: Transportation Committee Comité des

14

Document the EA Process; and,

Follow up support during the 30-day public review of the Environmental Project

Report with the Ministry of Environment and Climate Change as required.

4.0 Planning and Environmental Assessment

The EA Study comprises the following tasks:

4.1 Need and Justification

The TMP identifies the Montreal-Blair Road corridor as part of the 2031 Affordable

Rapid Transit and Transit Priority Network. Using the most current information and

technical data available, the EA Study will identify existing and future travel demand for

all modes of transportation and document opportunities and challenges within the study

area. The study will analyze the need and justification for a Transit Priority Corridor to

provide reliable and efficient transit service to major employment, commercial and

residential destinations along the corridor and to the Transitway station at Blair Station.

The need for safe infrastructure for pedestrian and cyclists along the corridor will also

be included in this study.

4.2 Environmental Inventory/Existing Conditions

An inventory of the existing social, cultural, economic, physical, and natural

environments within the study area will be compiled. This inventory will consider all

available background material and will be supplemented by on-site surveys and/or

detailed studies. The inventory must be detailed enough to enable the analysis of

effects arising from alternatives considered in this study.

In general, the inventory will identify and describe those aspects of the environment that

could potentially affect, or be affected by, the undertaking. Some of the specific aspects

of the environment associated with this project include inventory of:

Adjacent private and public property and the neighbouring community;

Current road, transit, pedestrian, cycling and multi-use pathway corridors/routes;

Current stormwater drainage patterns;

Greenspace, natural environment areas and water courses;

Detailed subsurface (geotechnical) conditions;

Page 15: Report to Rapport au: Transportation Committee Comité des

15

Heritage and archaeological conditions;

Utilities including water, sanitary, hydro, gas, cable, phone, and fibre optic; and,

Noise, air quality and vibration.

The complete inventory will be described and documented within the Environmental

Project Report.

4.3 Develop Alternative Solutions

The study will identify and examine a reasonable range of alternative solutions to

address the transportation issues, options include:

o Do nothing (as a baseline for analysis of options);

o Expand and enhance public transit facilities;

o Expand and enhance pedestrian and cycling infrastructure;

o Implement transportation demand management (TDM) measures to reduce

travel demand; and,

o Improve roadway capacities.

While developing alternative solutions, consideration will also be given to:

o Potential to promote and advance transit-oriented development;

o Community access and land use integration;

o Congestion reduction;

o Visual, cultural landscape, and heritage attributes; and

o Environmental characteristics.

This stage will involve the development of evaluation criteria which will include a range

of indicators to analyze and evaluate alternative options and select the preferred

solution for the study. The preferred solution may involve a combination of alternative

options.

The travel-forecasting component included in this stage of the study must:

Page 16: Report to Rapport au: Transportation Committee Comité des

16

Identify the needs for all modes of transportation (walking, cycling, transit, cars, and

trucks);

Incorporate the principles (e.g. mode share targets) of the current OP and TMP in

balancing demand to capacity while promoting the desire to increase transit use, and

appropriate land uses;

Incorporate the principles of Multi-Modal Level of Service to provide facilities for all

modes within the context of the adjacent land use; and,

Provide supporting analysis and recommendations for the proposed infrastructure.

4.4 Develop Design Alternatives

The study will identify and evaluate various design alternatives for the preferred

solution. Alignment and cross-section design alternatives will be identified based on

consideration of constraints within the study area, input from the public and approval

agencies, landowners, as well as accepted guidelines, standards, and practices.

The various design alternatives will consider:

Transportation performance in terms of access and connectivity to the road, transit,

pedestrian, and cycling networks, including detours during construction;

The Complete Streets framework;

Structure general arrangements;

Impact on public and private lands;

Geotechnical considerations;

Drainage and stormwater management;

Impact on Archaeology and Heritage;

Utility location and relocations;

Noise, vibration and air quality;

Operational considerations;

Overall cost affordability;

Page 17: Report to Rapport au: Transportation Committee Comité des

17

Climate change adaptation and mitigation assessment and greenhouse gas

emission;

Constructability and staging; and,

Landscaping and urban design features where appropriate.

Additional field investigations, surveys, test pits, and boreholes will be taken as

necessary to document the scope and potential impact of the design alternatives.

4.5 Evaluation Criteria and Evaluation Process

The evaluation criteria and methodology will be developed to assess potential effects of

the design alternatives of the preferred solution. Mitigation measures and associated

implications, such as cost of mitigation, will be identified and considered in the

evaluation process. The study will clearly identify the initial impacts of each design

alternative as well as the net post-mitigation effects and enhancement opportunities

using quantifiable indicators and measures wherever possible. To ensure that all

impacts are appropriately evaluated, the following issues will be addressed:

Transportation Service and Existing Infrastructure:

o Impact on the existing and future road, transit, pedestrian and cycling networks;

and,

o Impact on utilities and existing infrastructure.

Natural Environment:

o Impact on lands of natural significance, greenspace and water courses;

o Impact on groundwater and stormwater drainage; and,

o Impact on contaminated lands.

Social Environment:

o Impact on adjacent land uses;

o Impact on air quality, noise and vibration levels;

o Heritage and archaeological matters; and,

o Urban design including landscape and streetscape plans;

Page 18: Report to Rapport au: Transportation Committee Comité des

18

Economic Environment:

o Capital and operating costs.

4.6 4Recommended Plan

Following the evaluation of alternative solutions and design alternatives, and after

determining all necessary mitigation measures to minimize the adverse impacts of the

project, a technically preferred plan will be developed.

The technically preferred plan will be developed to a sufficient level of detail as required

to produce a functional design plan that is adequate for submissions for project

approval, and to establish a complete project scope, budget, and implementation

schedule.

This Recommended Plan will include:

A detailed written description of the undertaking including the design parameters;

Functional design drawings (1:500 scale, plan and profile) for the preferred

alignment with geo-referenced horizontal alignment, vertical profile, grading,

drainage, and property envelope;

Cross-section drawings for typical sections as well as critical areas;

Landscape and urban design plans;

Stormwater management requirements;

Property needs/acquisition plan;

Implementation/staging plan and preliminary detour plan during construction;

Infrastructure implementation/staging plan such as municipal servicing, utility

co-ordination and rehabilitation of roads;

Potential mitigation measures with a commitment to compliance monitoring during

project implementation; and,

Project cost estimate.

The Recommended Plan, including mitigation measures, will identify and set out the

requirements and timing for all subsequent approvals required to proceed with the

construction of the project.

Page 19: Report to Rapport au: Transportation Committee Comité des

19

4.7 Costing

Developing an accurate project budget is an essential component of this study, as it will

contribute to the City’s short and long range capital budget forecasting. The budget

scoping will be developed using a Work Breakdown Structure (WBS) format in current

dollars, and include contingency allowances, as well as cost for detouring during

construction if so required. The budget development will also follow the City’s Council-

approved Project Delivery Review process.

4.8 Project Deliverables

The deliverables for the study include:

Forecast travel demand modelling and analysis;

Environmental Inventory/Existing Conditions Report;

Functional design drawings (1:500 scale) of the recommended plan, including plans

and profiles for recommended alignments, structure general arrangement drawings,

utility relocation details, stormwater management plans, landscape design plans,

supporting infrastructure and property requirement plans;

Functional design plans identifying City right-of-way and property required for the

recommended plan;

Noise, Vibration, and Air Quality Reports;

Geotechnical Report;

Consultation Summary Report;

Project Implementation/Staging Plan, which will identify all future approval

requirements including those for property acquisitions and easements and other

property related matters;

Project capital cost estimates, in Work Breakdown Structure (WBS) format,

following the Council-approved Project Delivery Review process for cost estimating;

Content (written and graphical) for all public notices related to the study;

Open House and Consultation Group presentation display and information materials,

handouts and signage;

Page 20: Report to Rapport au: Transportation Committee Comité des

20

Project web page information in accessible format;

Draft and Final Environmental Project Report (EPR) to document the study process,

activities and findings in support of the Recommended Plan; and,

An Executive Summary which will be translated and in accessible format.

4.9 Environmental Project Report

The EPR will document the entire study process including consultation, the

development of alternatives, the recommended design, and any appropriate mitigation

plans, amending procedures, costing, implementation and staging plans, commitments

to future action, including external approvals required, and Council’s decision pertaining

to the study recommendations.

The final EPR will be prepared and placed on public record for a minimum 30-day

review period. The consultant is expected to provide assistance in responding to

comments during the review period and until completion of the EA Study. An FTP site

for the public to access and download the EPR will be made available during the 30-day

review period.

5.0 Consultation

Consultation will involve stakeholders, the City’s Advisory Committees as appropriate,

community groups, property owners, businesses, approval agencies, Indigenous

People, special interest groups, and area residents. Early in the study process,

stakeholders will be identified through consultation with the Ward Councillors.

The consultation strategy will consist of meetings with key stakeholders through an

Agency Consultation Group (ACG), Business Consultation Group (BCG), Public

Consultation Group (PCG), and the general public through Open Houses. The

membership, roles and responsibilities of each Consultation Group will be defined prior

to the first meeting. Specific aspects of the consultation program are summarized

below.

5.1 Agency Consultation Group

An Agency Consultation Group (ACG) will be formed to review and comment on a full

range of technical issues. The ACG will also ensure that the City is following the

procedures, legislation and addressing appropriate policies. Members will include

representatives primarily from government agencies and approval bodies, including the

NCC, NRCC, MTO, CSIS, CSEC, and CMHC. The ACG will meet at key stages of the

Page 21: Report to Rapport au: Transportation Committee Comité des

21

study. Direct one-on-one consultation with the NCC, federal agencies, and other groups

may be necessary as specific issues arise during the course of the study.

5.2 Business Consultation Group

A Business Consultation Group (BCG) will be formed to enable business owners and

developers along the corridor to inform and provide input to the study, and advise on

local economic and business issues and concerns.

5.3 Public Consultation Groups

A Public Consultation Group (PCG) will be formed to enable community groups, special

interest groups, the City’s Advisory Committees, and adjacent property owners to

provide direct input to the study regarding local issues and community concerns.

5.4 Indigenous People

The Ministry of Indigenous Relations and Reconciliation, and Indigenous and Northern

Affairs Canada will be contacted to review any Indigenous People issues or ongoing

claims within the study area. Recognizing the federal role in this regard, the study will

ensure appropriate coordination with federal authorities pursuant to the federal

guidelines on “Aboriginal Consultation and Accommodation (March 2011 update).”

Direct consultation with affected Indigenous People will also be carried out as

appropriate.

5.5 Notifications

The public and stakeholders will be notified of the EA Study commencement, all Public

Open Houses, the submission of the EPR for Ministry approval, and notifications of

project completion. Notices will be sent out at appropriate stages in the study, and each

announcement will take the following forms as applicable:

Advertisements in local newspapers (Ottawa Citizen, Le Droit) and in community

newspapers if available (Centretown News, Perspectives Vanier);

The project web site on the City’s web portal; and,

Electronic mail out.

5.6 Public Open Houses

A minimum of two Open Houses will be held for the general public, for the study team to

present and obtain feedback on:

Page 22: Report to Rapport au: Transportation Committee Comité des

22

Existing conditions;

Alternative solution and design options;

Results of the evaluation process; and,

The Recommended Plan.

Bilingual staff will be present during Open House meetings and all material presented

will be in both official languages.

5.7 Project Mailing List

A Master Mailing List for the project will be established and updated throughout the

course of the project. The Mailing List will be updated via Open House attendance,

general enquires, e-mails, and other forms of consultation.

5.8 Project Web Page

A Project Information Web Page will be established for this study on the City’s website.

Materials posted will inform the public of the progress and interim findings of the study

and upcoming meetings or activities, and include a point of access for public

consultation and feedback. The web information will conform to the Accessibility for

Ontarians with Disabilities Act.

To assist in providing information to the public, a Frequently Asked Questions (FAQ) will

be prepared and posted to provide answers to common questions raised during the

study. The FAQ document will be developed early in the study process and updated

before each Public Open House event.

5.9 Transportation Committee and Council Meetings

The final study findings will be presented to Transportation Committee and Council for

approval.