report on mejia thermal power plant(dvc)

Upload: pravin-vishwakarma

Post on 11-Oct-2015

203 views

Category:

Documents


9 download

DESCRIPTION

It is a report on M.T.P.S (DVC) that I have made while undergoing my training in MTPS. I have included all facts and necessary figures to pictorially elaborate the subject. I have presented it in a very simple language. ALL THE BEST!

TRANSCRIPT

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    1/68

    at

    NAME:Pravin biswakarma

    JALPAIGURI GOVT ENGG COLLEGE

    ELECTRICAL ENGG DEPARTMENT

    DATE OF TRAINING:From 13thJune,14 to 03thJuly,14

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    2/68

    VOCATIONAL TRAINING PROJECT REPORT ON MEJIA THERMAL POWER STATION

    (M.T.P.S),DAMODAR VALLEY CORPORATION(D.V.C)

    ABOUT M.T.P.S

    Mejia Thermal Power Stationis located at Durlovpur, Dist: Bankura, 26 km

    fromDurgapur city inWest Bengal.Commissioned on 1996, MTPS is the largest thermalpower plant, in terms of electricity generating capacity in the state of West Bengal as

    well as among other DVC power plants.

    Power Plant:

    Mejia Thermal Power Station has an installed capacity of 2340 MW. The plant has 8 units

    under its operation. The individual units have the generating capacities as follows:

    Unit No. Generating Capacity Commissioned on

    U#1 210 MW 1996

    U#2 210 MW 1998

    U#3 210 MW 1999

    U#4 210 MW 2005

    U#5 250 MW 2008

    U#6 250 MW 2009

    U#7 500 MW 2010

    U#8 500 MW 2010

    Units 1 to 6 are collectively named as MTPS-phase1, while the extension of Units 7 & 8 is

    called MTPS-phase 2. All the units have boilers, turbines and generators manufactured by

    Bharat Heavy Electrical Limited (BHEL).

    http://en.wikipedia.org/wiki/Durgapur,_West_Bengalhttp://en.wikipedia.org/wiki/West_Bengalhttp://en.wikipedia.org/wiki/West_Bengalhttp://en.wikipedia.org/wiki/Durgapur,_West_Bengal
  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    3/68

    SUBJECT OF TRAINING: THERMAL POWER STATION GENERATING TRAINING

    PLACE OF TRAINING:

    DAMODAR VALLEY CORPORATION

    Mejia Thermal Power Station

    P.O:MTPS,Dist:Bankura-722183,West Bengal

    Phone:03241-232201 FAX-03241-262231

    ENGINEERS UNDER WHOM TRAINING IS PERFORMED:

    1.

    Mr. Bidhayak Dutta(Deputy Chief Engg. Elec)

    2.Mr. P.K Dubey

    (Training Advisor)

    DURATION OF TRAINING: 13TH

    JUNE,2014 to 03TH

    JULY,2014

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    4/68

    DAMODAR VALLEY CORPORATION

    Mejia Thermal Power StationP.O:MTPS,Dist:Bankura-722183,West Bengal

    Phone:03241-232201 FAX-03241-262231

    No.MT/PL/Voc.Trg./Vol.XII/1682 Dated:29th

    March2014

    TO WHOM IT MAY CONCERN

    This is to certify that Mr.Pravin Biswakarma, student of electrical engineering

    of Jalpaiguri Government Engineering College, Jalpaiguri-735102(W.B)

    undertook vocational training at Mejia Thermal Power Station, DVC, for the

    period of 21(Twenty One) days w.e.f 13.06.2014 under Electrical Dept., MTPS.

    During his training he has been found sincere, hard working and

    well disciplined.

    .........................................

    (Shri Bidhayak Dutta)

    The Dy Chief Engineer (Elect.)

    MTPS, DVC

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    5/68

    ACKNOWLEDGEMENT

    Any project is the fruitful outcome of the hard work of many.

    Through this document we would like to express our gratitude

    towards those who supported us in making us an outcome from us.

    Firstly, we would like to thank Shri. Bidhayak dutta(Deputy Chief

    Engg. Elec.). He inspite of his tremendous workload helped us

    admirably. Our humble thanks to Shri.P.K Dubey(Training Advisor)

    who guided us in each and every step till our completion of our

    training. We are thankful to them for their continued guidance and

    support with their vast pool of knowledge, which was essential for

    the completion of this project. Along the way , we were also ablysupported and guided by staffs of the various departments. And like

    we mentioned, the help is even more credible, considering that the

    workload of the staff was immense.

    We would also like to thank our friends and family for providingencouragement and moral support at every step. We recognise

    everybodys helping hand.

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    6/68

    CONTENTS

    SL

    NO

    TOPIC

    1 INTRODUCTION AND HISTORY

    2 OVERVIEW OF A POWER PLANT

    3 ELECTRICAL SYSTEM

    a) GENERATOR & AUXILIRIES1. BASIC PRINCIPLE & CONSTRUCTION

    2. EXCITATION SYSTEM

    3. AVR

    4. COOLING SYSTEM

    5. PROTECTION SYSTEM

    6. GENERATOR METERING & INSTUMENTATION

    7. ELECTRICAL PROTECTION AND SAFETY INTERLOCKS

    b)OVERVIEW OF GT, UT, UAT,UST, ST, SAT,SST, NGT

    c) SWITCHYARD

    1.VARIOUS COMPONENTS

    2.PROTECTION

    d) STATION GROUNDING SYSTEM

    e) MOTORS

    f)

    g)

    DC SYSTEM

    DG SET

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    7/68

    INTRODUCTION & HISTORY

    DVC, a legacy to the people of India, emerged as a culmination of attempts made over awhole century to control the wild and erratic Damodar river. The river spans over an area

    of 25,000 km2covering the states of Bihar (now Jharkhand) & West Bengal.

    Damodar Valley Corporation was established on 7th

    July 1948.It is one of the most

    reputate company in the eastern zone of India. DVC is established on Damodar river. It

    also consists of the Durgapur Thermal Power Plant in Durgapur. The hydel project in

    Mython is one of the most flourishing part of DVC. The MTPS(Mejia Thermal Power

    Station) under DVC is one of the largest thermal power plant in West Bengal. It is one ofthe four thermal power stations of DVC in the states of West Bengal. The total power

    plant campus area is surrounded by boundary walls and is basically divided into two

    major parts, first power plant area itself and second is the colony area for the residence

    and other facilities for MTPSs employees.

    SALIENT FEATURES

    Location: Mejia in Bankura District in West Bengal.

    Installed Capacity: (210*4 MW+250*2 MW + 500*2 MW)=2340MW

    Coal source: B.C.C.L and E.C.L, also imported from Indonesia

    Fuel quantity:126 TPH(for unit 1 to 4 only)150 TPH(for unit 5 and 6 only)

    272 TPH (for unit-7 only)

    Height of chimney: 220m[205+15](for unit 1 to 6)

    279m (for phase II)

    Water source: DAMODAR RIVER

    Beneficiary State: WEST BENGAL, JHARKHAND

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    8/68

    OVERVIEW OF POWER PLANT OPERATION

    A power plant is basically an energy conversion mechanism. Thermal power plants

    operate on modified Rankin Cycle with reheating and superheating. In essence , it is

    modified from of the basic steam cycle to increase the cycle efficiency. Coal is burnt in a

    boiler, which converts water into steam. The steam is expanded in a turbine, which

    produces mechanical power driving the alternator coupled to the turbine. The working of

    the power is divided into four main circuits:

    Fuel and ash circuit.

    Air and Fuel gas circuit.

    Feed water and steam circuit.

    Cooling water circuit.

    THE ENERGY CONVERSION

    Chemical energy to heat energy ---- In Boiler

    Heat energy to kinetic energy ---- In Turbine

    Mechanical energy to electrical energy --- In Generator

    THERMAL POWER PLANT

    WATER

    FUEL

    AIR

    ELECTRICITY

    FLUE GASES

    ASH

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    9/68

    ENERGY FLOW DIAGRAM OF DIFFERENT PART :

    CHEMICAL ENERGY HEAT ENERGY

    (COAL) (STEAM)

    BOILER

    HEAT ENERGY MECHANICAL ENERGY

    (STEAM) (TURBINE)

    TURBINE

    MECHANICAL ENERGY ELECTRICAL ENERGY

    (TURBINE) (GENERATOR)

    GENERATOR

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    10/68

    OVER VIEW OF A POWER PLANT

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    11/68

    VARIOUS COMPONENTS OF A POWER PALNT:

    DEAERATOR: The condensed water from the condenser is taken to deaerator where the

    water is made free from oxygen mainly i.e. free from air. The deaerator is a direct heat

    exchanger because the steam from IPT is sprayed to the condensed water from the

    bottom and the water is sprayed from the top part of the deaerator. This results in de-

    oxyfication i.e. removal of oxygen from the water.

    BOILER FEED PUMPS (BFPs): The outlet of the deaerator is connected to boiler feed

    pumps, there are three BFP in a row out of which two are in running condition and one is

    at standby,in unit #1 to 6 all BFP are MDBFP,consumes highest power in the plant 4.6MW

    in full load and unit#7 and 8 one of these is MDBFP( motor driven), and other two are

    TDBFP(steam driven).MDBFP consumes the highest power in this plant i.e. 10MW.

    MDBFP is used only at the starting time for its huge power consumption.

    HIGH PRESSURE HEATER: The HPHs are also mechanical heaters that receives the

    heating medium from exhaust of HPT and IPT. There are two HPH named as HPH#5 and

    HPH#6. HPH#5 receives steam from IPT and HPH#6 receives steam from HPT . The BFP

    outlet is connected to the HPH#5 and HPH#6 is connected to HPH#5. Steam of HPT and

    IPT heats the water up to 253C and the pressure is also increased up to 175kg/sq. cm,which is then passes through economiser this done to increase the efficiency of the

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    12/68

    boiler. Extn. Steam Pressure to HPH#5: 16.65 kg/sq. cm and temp. 415C. Extn. Steam

    pressure to HPH#6: 42.84 kg/sq. cm. and temp. 337.8C.

    ECONOMISER: Economiser is another heat exchanger type heater. Here the water fromHPH comes to get more heated up for better steam production and high enthalpy

    resulting in greater efficiency of the boiler and unit as well. The economiser receives the

    heat for heating the water from the flue gas. The flue gas which has very high

    temperature comes from air pre-heater to the economiser and heats up the water

    mechanically which finally reaches the boiler drum. Economiser inlet tepm. is 254C and

    outlet temp. is 315C.

    BOILER DRUM: Boiler drum is the part of boiler where the de-mineralized water is stored

    and is inserted into the boiler through three BCW(Boiler circulating water pump). It is

    also houses the steam that is formed in the boiler. Water stored in the drum comes down

    to the top of the boiler and forms a water ring which is then inserted into the boiler

    through the 6 water walls. Water walls are basically tubes along the walls of the furnace,

    it is here where the water is converted into steam at 130C and then the produced steam

    is taken back to the boiler drum. The drum has a propeller that rotates at high speed and

    makes the steam and water separated due to centrifugal force. The pressure of boilerdrum is 192 kg/sq. cm and must be always maintained. Water in the drum comes from

    feed control station via economiser.

    FURNACE AND BOILER:-Boiler is the main section where the steam is produced by

    coal combustion. Boiler consists of boiler drum, water walls, wind box, heaters. The

    boiler has 8 elevations named as A-B-C-D-E-F-G-H. Coal is inserted into the boiler from A-

    B-C-D-E-F-G-H. There is 8 mills for feeding the pulverized coal to the furnace. Each mill

    has 4 pipe for firing in the four corners of furnace. Furnace is divided into two parts

    named as first pass and second pass. The combustion takes place in the first pass and the

    heating of steam through SH takes place in the second pass.

    SUPER HEATER: The important point is to be always kept in mind that all the heaters

    that are used in thermal power plant are mechanical type heaters i.e. heat exchangedphenomena heats one medium by exchanging heat from another hotter medium. Super

    heaters are actually suspended pipes in the second pass section of the boiler, the flue gas

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    13/68

    having very high temperature heats the steam that comes from the drum before they hit

    the turbines to a temperature up to 540C. The pressure of steam is kept constant when

    passing through super heater. The main concept behind making the steam super heated

    is to make the steam absolutely moisture free before they hit the turbine becausemoisture content of steam will damage the blades of turbine by corrosion.

    TURBINE SECTION: The turbine section consists of three parts named as HPT(High

    pressure turbine), IPT(Intermediate pressure turbine),LPT(Low pressure turbine). The

    superheated steam from the Superheater enters the HPT and hits the blades at 176.2

    kg/sq. cm and 540C and rotates the shaft. The exhaust steam of HPT is taken to IPT

    through a reheating section called Reheater(RH) for enabling the steam to regain its

    previous steps. The exhaust steam of IPT enters LPT directly. The exhaust of LPT is taken

    to condenser.

    CONDENSER: The exhaust steam of LPT is fed to the condenser where the steam is

    converted into water by the principle of condensation. The condenser has three

    extraction pumps known as Condensate Extraction Pumps (CEP-A, CEP-B, CEP-C).

    These pumps create a negative pressure i.e. vacuum in the condenser for better suctionof the condensate. The outlet of the CEP is connected to low pressure heater(LPH);

    where the temperature of condensed water is raised to little higher temperature for

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    14/68

    better efficiency of overall unit.

    FLUE GAS PATH :

    AIR PREHEATER: The flue gas produced as a result of combustion of fossil fuel in the

    furnace is taken to the air pre heater. The air pre heater is used to heat up the

    atmospheric air to make hot air used for combustion and transport of coal dust from mill

    to furnace; which called secondary air. This heater has a unique process of heating, it has

    a shaft attached to rotating wheel type structure(like turbine but arrangement blades are

    different). Atmospheric air are sucked by FD fans passes through one side of the rotating

    shaft and the hot flue gas passes through another side. This way heat of the flue gas gets

    transferred to the atmospheric air and gets heated. There are two air pre heaters for

    each unit named as AH-A and AH-B.

    ELECTROSTATIC PRECIPITATOR (ESP) :-

    Under government rules and regulation for industrial pollution control, ESP is must to

    each and every industry which deals high ash as residing. An electrostatic precipitator is a

    large , industrial emission-control unit. It is used in industries like thermal power plant,cement, paper, chemicals, metallurgical industries etc, which emit particles. In the

    thermal power plant it is designed to trap and remove ash particle from the exhaust gas

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    15/68

    of boiler. Clean gas, up to 99.9% cleaner than when it enter is then passes out of the

    precipitators.

    collecting electrode

    weakest field

    Emitting electrode

    WORKING PRINCIPLE OF ESP

    An ESP is a chamber in which flue gas from the furnace is forced into FD fans.

    Electrostatic precipitation is a physical process by which particles suspended in gas

    stream are charged electrically, and under the influenced of electric field are separated

    from the gas stream. The precipitation system consists of negatively charged high voltage

    discharged electrode wire suspended amidst positively charged collecting electrode

    surfaces. At a very high DC voltage of the order of 20KV-35 KV, a corona discharged

    occurs close to the negative electrode, setting up an electric field between the emitter

    and the charged surface. When the particle laden gas passes through the ESP fields, the

    gas close to the negative electrode is thus ionised upon passing through the corona . As

    the negative ions and electrons migrate towards the charged surface, they in turn charge

    the passing particle. The electrostatic field then draws the particles to the collector

    surface where they are deposited. Periodically, the collected particles are removed from

    the collecting surface by rapping or vibrating the collector to dislodge the particles. The

    dislodged particles drop below the electrical treatment zone and are collected through

    hoppers for ultimate disposal.

    The major components that accomplished above activities in ESP are as follows:

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    16/68

    High voltage discharge electrodes

    Grounded collecting electrodes

    Rapping systems

    Power supplies and control components Hoppers

    In practice the ESP shall consists of several such fields in series in the direction of

    gas flow. There may be two or more parallel passes of such series combination to meet

    the desire level of dust removal from the flue gas . Here four passes and 72 fields are in

    place.

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    17/68

    DRAFT FANS:

    There are basically three types of fans in a thermal power plant.

    i. INDUCED DRAFT (ID FAN)

    ii.

    FORCED DRAFT FAN (FA FAN)iii. PRIMARY AIR FAN (PA FAN)

    INDUCED DRAFT FAN/ ID FAN:

    This fan is used to create negative pressure in the furnace

    i.e. furnace pressure is lower than atmospheric pressure, as a result of which fire balls

    inside the furnace can not come out of the furnace.ID fans also drives the flue gas

    through out its path and finally ejects it out of chimney. It sucks air from the furnace andejects it to the atmosphere. Mechanically ID fan is coupled with one 3-ph synchronous

    type motor. It is the only synchronous motor in the power plant because it gives more

    accurate control to its speed by V/f method for maintaining negative pressure as

    controlling of negative pressure is the most vital factor in any thermal power plant. There

    are two ID fan for each unit.

    FORCED DRAFT FAN:-

    Unlike ID fan, the FD fan is meant for creating positive pressure in

    the furnace and also supplies air from PA fan and secondary air for combustion. The FD

    fan takes air from atmosphere and expel it to the plant (i.e. in the furnace, wind box

    etc).Mechanically FD fan consist of one 3-ph induction motor, main bearing (antifriction

    bearing) and lube oil system.

    PRIMARY AIR FAN/PA FAN: -

    Primary air fan is used for mixing of cold air of FD fan outletwith hot air of air pre-heater outlet. The main function of this is to transport pulverised

    coal from the mill to furnace. Mixing of hot air and cold air is necessary because it is

    needed to maintain the temperature of the pulverised coal from 80C to 90C for better

    transport of coal and better combustion in the furnace. Mechanically the construction of

    PA fan is same as FD fan.

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    18/68

    The Electrical System:-

    The electrical system basically starts at the turbo alternator and through the

    GT(generator transformer) to the switchyard and finally to the transmission lines. Inbetween the network consists of many isolators, circuit breakers, CT, PT and other

    mechanisms. At MTPS the turbo alternator generates a voltage of

    15.75KV(Unit#1/2/3/4),16.6KV(Unit#5/6), 21 KV( Phase II). The GTs steps this up to 220

    KV(400KV for Phase II). The transmission is to Kalyaneswari ,Burnpur,Borjora,Durgapur

    and for phase IIthe transmission is to Mython, DSTPS, Jamshedpur.

    Therefore the electrical system is :

    For Unit#1 to 6 :

    Generator GT 220 KV switchyard Transmission Lines

    For Unit#7 and 8:

    Generator GT 400 KV switchyard Transmission Lines

    Apart from these, the electrical system is intricately intertwined with the entire plant,

    considering that the entire protection and control is somehow done electrically.

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    19/68

    GENERATOR

    BASIC PRINCIPLE AND CONSTRUCTION:

    Principle:

    Generator converts mechanical power into electrical form and feeds it into the power

    system network . The working principle behind the operation of generator is

    Faradays Laws of electromagnetic induction.The induced alternating voltage in a

    generator can be expressed as-

    E=4.44fT Volt

    Where,

    E= Voltage induced in volt.

    f=frequency of rotation in Hz.

    T=No. of turns

    =flux per pole in Wb.

    The frequency of the alternating voltage is given by the following equation

    f=PNs/2

    where,

    f=freq in Hz.

    P=no. of poles

    Ns=revolution/sec.

    Components of Generator:

    The main components of a Generator are:

    1.Stator 2.Rotor

    3.Bearing and lubrication 4.Terminal Bushing and Bus duct

    5.Excitation system 6. Slip ring and Brush gear assembly

    7.Cooling system 8. Sealing system

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    20/68

    Stator:

    The stator embodies the core, stator winding and hydrogen coolers and provides a gas

    tight enclosure for hydrogen gas. It comprises of an inner and an outer frame. The outer

    frame is a rigid fabricated structure of welded steel plates capable of bearing the

    pressure due to minor explosion of H within the casing.Within the cylindrical barrel, a

    fixed cage is formed by grider built circular and axial ribs. These ribs divide the yoke into

    annular components through which cooling gas flows into radial ducts in the stator core

    and

    TURBO GENERATOR

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    21/68

    Exchanges heat in the Hydrogen gas coolers housed horizontally parallel to the rotor

    shaft in the frame. The inner cage is usually fixed to the yoke by an arrangement of

    springs to dampen vibration. Rigid end shields close the stator ends and supports and

    shaft seals.

    ROTOR:

    The rotor forms the rotating magnetic poles of the generator. This is cylindrical type and

    constructed form a cast Chromium , Nickel, Molybdenum and Vanadium steel through

    several stages of machining. Slots are machined on the outer surface to incorporate

    windings . Holes are also drilled for ventilation purposes. High grade copper with 0.03%

    to 1% silver is used for the windings with layers of mica or epoxy impregnated glass cloth

    as the insulation. A mechanically strong insulation (e.g. micanite) is used for lining the

    slots. With increase in generator capacity rotor windings used to carry a fairly high direct

    current for sufficient magnetic strength. This higher loading causes considerable amount

    of heat loss and large rotors incorporate combination of hollow conductors with slots or

    holes arranged to provide for circulation of the cooling gas through the actual conductors

    by gap pick up method .Due to very high rotational speed centrifugal force tries to lift the

    winding out of the slots.

    So they are contained in proper place by duralumin wedges. The end turns outside theslots are covered by non-magnetic steel retaining end rings and are secured to the rotor

    body. The end winding are insulated from retaining rings with the help of glass epoxy

    molded segments. The retaining ring is a single piece forging which protects the rotor end

    winding from high centrifugal force.

    EXCITATION SYSTEM OF TURBO GENERATOR:-

    The purpose of excitation system is to continuously provide the appropriate amount of

    D.C field current to the generator field winding. The excitation system is required to

    function reliably under the following conditions of the generator and the system to which

    it is connected .

    i)During start up of the generator.

    ii)During steady state operating condition.

    iii)At the time of transient disturbances (due to sudden applications or removal of load).

    iv)During prolonged system disturbances.

    The simplest case is that of during start up when the generator isrunning at rated speed with generator circuit breaker open(armature open circuited). The

    terminal voltage will increase with the increase in field current. Amount of field current

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    22/68

    required will be a function of only the terminal voltage. Because of magnetic saturation

    more field current will be required to produce an increment of armature voltage at high

    voltage than at low voltage. This will be governed by open circuit characteristics(O.C.C) of

    the machine. After the closing of generator circuit breaker the machine is connected tothe system and operates in parallel with other machines connected to the system. The

    amount of field current required will be a function of the terminal voltage as before and

    also the load current and the power factor. This will be governed by the V-curves of the

    machine. Unlike the previous case if the generator is connected to a large system change

    in excitation current controls the reactive power(VAR) and the power factor only with a

    very minor influence of the terminal voltage. More severe duty the excitation system

    requires to perform upon is during system disturbances. At the time of transient

    disturbances the generator voltage may dip or rise momentarily. The excitation system

    must response fast to correct this quickly and stably. During prolonged

    disturbances(which may last from several seconds to several minutes) the excitation

    system may require to operate at it maximum or ceiling output. Thus properly designed

    excitation system should permit

    a)Close control of the generator voltage to match closely to the system voltage before

    synchronization.

    b)Close control of VAR after synchronization of the machine, without loss of stability oroverheating of the field system.

    c)Operation of the system at its maximum or ceiling at the time of disturbances in the

    system.

    DEVELOPEMENT OF EXCITATION SYSTEM:

    With increase in generator capacity and

    complexity of interconnection in power system, improved techniques in generator

    excitation have been developed with the aim to achieve higher capacity, ideal rate of

    response, simplicity, reliability, accuracy, sensitivity etc. In the earlier designs several

    concepts govern the majority of the excitation system, such as

    a) Exciters were commutator type and self excited.

    b) Exciters were shaft driven and motor driven rotating machines.

    c) Voltage regulators included magnetic or rotating amplifiers or combination of both.

    d) Manual control was by means of a rheostat.

    Next generation of excitation system introduced newer concepts. Some of

    which were

    a) Use of semiconductors for rectification.

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    23/68

    b) AC(automatic) voltage regulator with transistor pre-amplifiers and thyristors .

    c) New concepts of manual control.

    d) Elimination of commutators.

    e) New physical arrangements,f) New maintenances procedures .

    Present day excitation system have been promoted by

    a) Capacity to meet very high values of excitation suitable for unit capacities as high as

    500MW or even more.

    b) Use of HF AC exciters as source of powers.

    c) Use of digital technologies for control, protection and switching.

    d) Higher stability unit and excellent performance during transient and fault conditions.

    e) Elimination of carbon brushes in brushless excitation system.

    TYPES OF EXCITATION SYSTEM:-

    The types of excitation system are

    i) DC excitation

    ii) Static excitation

    iii) Brushless excitationIn MTPS Carbon Brush Excitation is used in Unit#1 to 4 and in Unit#5to 8 brushless

    excitation system is used.

    BRUSHLESS EXCITATION:-

    Supply of high current by means of carbon brush involves

    considerable operational and maintenance problems. These problems are eliminated in

    brushless excitation system which consists of AC main exciter ,a PMG, a rotating non-

    controlled rectifiers, all mounted on the T.G shaft and static AVR. Field of the PMG whichis permanent salient pole magnet rotates along with the generator shaft and generates

    permanent voltage (usually 400 v at 400 Hz freq.) at the stator windings. These outputs

    from the PMG is connected to the thyristors located in the AVR panel. The controlled DC

    output from the AVR panel is connected to the stationary field of the main exciter. The

    output from the rotating armature is connected to the diodes placed along with the

    rotating at the same speed that of the rotating armature of the exciter and generator

    field winding. Thus there is no flow of current between any moving part and stationary

    part and hence they use of brush gear is eliminated. The diodes are arranged on rectifier

    wheels in a three phase configuration .These are protected with fuse and RC network.

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    24/68

    During operation the fuses are monitored with the help of stroboscope. The entire

    arrangement is totally enclosed and the hot air is cooled in two or more cooler arranged

    alongside the exciter.

    Apart from the fuse monitoring unit, other features provided in brushless excitation

    system are ground fault detection,field current measurements etc.

    AUTOMATIC VOLTAGE REGULATOR(AVR):-

    Automatic voltage regulator (AVR) is the heart of excitation system of generator. Now a

    days the AVR uses semiconductor elements to achieve high reliability with very fast

    response. It has two independent channels, the Auto channel with closed loop voltage

    regulation and the Manual channel with open loop regulation. The two channels of thevoltage regulator are designed for operation either on i) a station auxiliary AC power

    supply and ii) power supply from generator terminal or pilot exciter as the case may be.

    Both the auto and manual channels consist of a power part and a control part.

    Some of the salient features of AVR are :

    a) Capability of maintaining constant terminal voltage over a wide operating range

    and maintaining proper share of reactive load among the parallel running

    machines.

    b) Provision for raising the excitation level quickly (field forcing ) in case of fault or

    voltage dip to increase the transient stability limit of the system.

    c) In corporation of suitable circuitry to make the reference voltage as a linear

    function of frequency or turbo generator up to the edge frequency can be set

    depending on the requirement and constant reference voltage beyond edge

    frequency.

    d)

    Provision of automatic follow up circuit to supervise and match the firing angles ofthe pulses in auto-channel and manual channel so that the disturbance on the

    generator terminal is minimum during transfer from auto regulation to manual

    regulation.

    e) Provision of stator current limiter , rotor current limiter and rotor angle limiter

    circuits for optimum utilisation of the lagging and leading reactive capabilities of

    the generator.

    f) Provision of automatic transformer from auto regulation to manual regulation in

    case of measuring PT fuse failure or some internal faults in the auto channel.

    g) Facility for remote control of voltage both in auto and manual channel.

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    25/68

    Generator Cooling and Sealing System:-

    STATOR WATER SYSTEM

    Stator water-cooling is a closed loop system There are two full capacity single stage centrifugal pumps with change over facility

    3Ph.415V A.C motors drive the pumps

    The stator water cooler is shell and tube type heat exchanger

    DM water flows through shell

    There are two mechanical filters and one magnetic filter

    Mechanical filters are of wire mesh type

    Magnetic filter is having permanent magnet

    GAS SYSTEM

    Generator gas system constitutes of hydrogen gas used to cool the rotor and certain

    parts of stator. H-air mixture is explosive. So filling the Generator with H by replacing air

    which is dangerous. So initially air is replaced by CO and since CO is heavier than air COis being filled from the bottom. Purging of air with CO is being done till the purity of CO.

    Cooling fans- Propeller type cooling fans at both the ends of rotor are provided for forced

    circulation of H(H cooled machines ) or air(air cooled machines )inside the generator.

    Fan hubs are made from alloy steel forgoing and are shrunk fitted on the rotor shaft. Thealloy steel cast fan blades are fixed on the fan hub throughout its periphery with the help

    of strength alloy steel non-magnetic conical pins. These fan blades are easily removable

    from the hub. Fan shields are provided to guide the gas flow. Fan shields are fixed to the

    end shields.

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    26/68

    SPECIFICATION OF TURBO GENERATOR:-

    For unit#1 to 4

    KW:210MWp.f:0.85 lag

    KVA:247,000

    Stator voltage:15.75 KV

    Stator ampere:9050 A

    Rotor voltage:310 V

    Rotor ampere:2500A

    Rpm:3000

    Frequency:50 Hz

    Connection: Y Y

    Coolant: Water & Hydrogen

    Gas pressure: 3.5 bar(G)

    Insulation class: F

    Specification: IS:5422

    IEC:34

    For unit#5 and 6

    KW:250MW

    p.f:0.85 lag

    KVA:294100

    Stator voltage:16.5 KV

    Stator ampere:10291 A

    Rotor voltage:292V

    Rotor ampere:2395A

    Rpm:3000

    Frequency:50 Hz

    Connection: Y Y

    Coolant: Hydrogen

    Gas pressure: 3 bar(G)

    Insulation class: F

    Specification: IS:5422

    IEC:34

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    27/68

    For Unit#7 and 8

    KW:500 MW

    p.f:0.85 lag

    KVA:588,000

    Stator voltage:21 KV

    Stator ampere:16,200 A

    Rotor voltage:340 V

    Rotor ampere:4040 A

    Rpm:3000

    Frequency:50 HzConnection: Y Y

    Coolant: Water & Hydrogen

    Gas pressure: 3.5 bar(G)

    Insulation class: F

    Specification: IS:5422

    IEC:34

    SPECIFICATION OF PILOT & MAIN EXCITER(Unit#5 & 6)

    Main Exciter Pilot Exciter

    Apparent Power: -- 35KVA

    Active Power: 1344KW --

    Current: 3200A 105A

    Voltage: 420V 220+/-22V

    Speed: 50/S 50/S

    Freequency: 150Hz 400Hz

    SPECIFICATION OF PMG(Unit#7 & 8):-

    KW:39

    KVA:65

    Volts:220

    Amps:195

    Rpm:3000

    Phase:3

    Coolant: Air

    Insulation Class: F

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    28/68

    Connection: Y Y Y Y

    Y Y Y Y

    Specification: IFC-34

    SPECIFICATION OF BRUSHLESS EXCITER(Unit#7& 8):-

    KW:3780

    Volts DC:600

    Amps DC:6300

    Excitation Volts DC:107

    Excitation Amps DC:142

    Rpm:3000Coolant: Air

    Insulation Class: F

    Specification: IFC-34

    GENERATOR PROTECTION:-

    With the ever increasing size of the generator cost of the

    machine, the expenses for repair and loss of energy during the outage of the machine arevery high. Hence it is necessary to provide a reliable elaborate protection system to

    safeguard against damage and loss of generation and ensure long life of the machine.

    Generator protection concerns especially the electrical protection of machines and

    associated circuits. The purpose of generator protection is to provide protection against

    abnormal operating condition and during fault condition. In the first case the machine

    and the associated circuit may be in order but the operating parameters (load, frequency,

    temperature) and beyond the specified limits. Such abnormal running condition wouldresult in gradual deterioration and ultimately lead to failure of the generator. It may be

    possible to correct the running of the generator. It may be possible to correct the running

    condition after the protective relay gives an alarm, there by avoiding the loss of revenue

    and damage of the machine. In the later case , it is necessary to restrict the damage of

    the machine and associate circuit to a minimum by taking it out from the service.

    PROTECTION UNDER ABNORMAL RUNNING CONDITIONS: -

    a)Over current protection:The over current protection is used in generator protection

    against external fault as back up protection. Normally external short circuits are cleared

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    29/68

    by protection of the faulty section and are not dangerous to the generator. If this

    protection fails the short circuit current contributed by the generator is normally higher

    than the rated current of the generator and caused over heating of the stator, hence the

    generators are provided with back up over current protection which is usually definitetime lag over current relay.

    b)Over load protection: Persistent over load in rotor and stator circuit cause heating of

    winding and temperature rise of the machine. Permissible duration of the stator and

    rotor over load depends upon the class of insulation, thermal time constant, cooling of

    the machine and is usually recommended by the manufacturer. Beyond these limits the

    running of the machine is not recommended and over load protection thermal relays fed

    by current transformer or thermal sensors are provided.

    c)Over voltage protection: The over voltage at the generator terminals may be caused

    by sudden drop of load and AVR malfunctioning. High voltage surges in the system

    (switching surges or lightning) may also cause over voltage at the generator terminals.

    Modern high speed voltage regulators adjust the excitation current to take care against

    the high voltage due to load rejection. Lightning arresters connected across the

    generator transformers terminals take care of the sudden high voltages due to external

    surges. As such no special protection against generator high voltage may be needed.Further protection provided against high magnetic flux takes care of dangerous increase

    of voltage.

    d)High flux density:High flux density in the machine causes saturation core leading to

    over heating in the iron core of both the generator and the transformer due to increased

    iron losses and additional losses from the eddy currents. High magnetic flux density may

    occur because of over excitation at no load or due to low frequency running. A relay

    which operates on V/f (volts per Hz) basis is recommended as a preventive measure forprotection against high flux densities.

    e)Unbalance loading protection:Unbalance loading is caused by single phase short

    circuit out side the generator, opening of the one of the contacts of the generator circuit

    breaker snapping of conductors in the switchyard or excessive single phase load.

    Unbalance load produces ve phase sequence current which cause over heating of the

    rotor surface and mechanical vibration. Normally 10% of unbalance is permitted provided

    phase current do not exceed the rated values. For ve phase sequence currents above5-10% of rated value dangerous over heating of rotor is caused and protection against

    this is an essential requirement. The relay provided for this is an inverse characteristic

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    30/68

    with definite minimum time delay relay connected to a network which segregates the

    ve sequence current from the positive and zero sequence currents. The I2t

    characteristics of the relay is matched to the rotor heating characteristic.

    f)Loss of excitation protection:The loss of excitation in a synchronous machine may be

    caused by tripping of field circuit breaker or trouble in AVR. On loss of excitation the

    generator starts drawing reactive power from the grid instead of supplying it. The power

    factor of the generator becomes capacitive and as a result of this asynchronous running

    ( higher slip frequency) over heating of the rotor surface takes place. In case the

    generators connected to the system can not supply this reactive power there will be large

    voltage drop in the system leading to instability. The protection provided against loss of

    excitation is by an off-set Mho relay. Its operating characteristics is so chosen that duringextremely low excitation faults within the tripping zone.

    g) Loss of prime mover protection:In the event of loss of prime mover the generator

    operates as a motor and drives the prime mover itself. In some cases this condition could

    be very harmful as in the case of steam turbine sets where steam acts as coolant,

    maintaining the turbine blades at a constant temperature and the failure of steam results

    in over heating due to friction and windage loss with subsequent distortion of the turbine

    blade. This can be sensed by a power relay with directional characteristics and themachine can be taken out of bar under the condition. Because of the same reason a

    continuous very low level of output from the thermal sets are not permissible. The

    generator breaker is tripped under this condition by the use of a relay measuring the

    electrical power output of the generator designed to operate when the power output

    faults below selected pre-set value.

    h)Pole slip protection:A generator may loss synchronism with system without losing the

    excitation. In this condition the machine may be subjected to severe mechanical torqueand oscillation with consequent variation of current, voltage and power factor. If the

    angular displacement of the rotor exceeds the stable limit, the rotor will slip a pole pitch.

    If the disturbance persist the machine must be isolated from the system to prevent

    damage to the generator and to minimize power system disturbance. The pole slipping

    protection relay operates on the criteria that the angle of the generator EMF exceeds a

    certain fixed value with the operation of the reverse power relay. The occurrence of

    these criteria are counted and the machine is tripped out after a certain number of

    oscillations. These relays are capable of detecting the first pole slip condition when a slip,

    corresponding to the speed of pole slipping is in the range of +0.1% to +10% on a 50Hz

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    31/68

    basis. The protection must remain inoperative for steady state lading, power switching

    and correctly cleared system fault condition.

    PROTECTION UNDER FAULT CONDITION:-

    a)Stator short circuit: Short circuits are among the faults which cause the heaviest

    damage to the generator. Not only do they result in thermal damages such as the

    welding of the core laminations and burning of the winding but also result in possible

    mechanical damage like deformation of the ends of the coil. Very fast operating

    protection is required , otherwise the damage may be beyond repair. Differential

    protections, inter turn short circuit protections are the main protection against shortcircuits in stator winding. As back up protection for the same faults, minimum impedance

    and over current protections are used.

    b)Differential protection: The protection is used for detection of internal faults in a

    specified zone defined by the CTs supplying the differential relay. For an unit connected

    system separate differential relays are provided for generator, generator transformer

    and unit transformer in addition to the overall differential protection. In order to restrict

    damage very high differential relay sensitivity is demanded but sensitivity is limited by CTerrors, high inrush current during external fault and transformer tap changer variations.

    c) Inter turn fault protection: Inter turn faults comprise of insulation failure between

    turns of the same winding or between the parallel winding of the same phase which can

    not be detected by longitudinal differential protection. Inter turn faults have commonly

    been disregarded on the basis that if the occur the will quickly develop into earth faults

    or phase to phase faults which will be detected by the sensitive protections provided for

    these faults. With this idea sometimes no specific protection for inter inter-turn fault isprovided. However considering the risk of severe damage to the machine before the

    faults convert into above types of faults inter turn fault protection is recommended, In

    large machine as all the three windings are brought out separately it is possible to

    employ a system to transverse differential protection consisting of balanced current

    arrangement between current transformers connected in the line ends of the windings in

    which current in the parallel paths of the windings are compared. A bias system is always

    used as it is not possible to guarantee in advance that exact current sharing between

    windings take place.

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    32/68

    d) Back-up impedance protection: This protection is basically designed as back up

    protection for the part of the installation situated between the generator and the

    generator and unit transformers. A back up protection in the form of minimum

    impedance measurement is used, in which the current windings are connected to theCTs in the neutral connection of the generator and its voltage windings through a PT to

    the phase to phase terminal voltage. The pick up impedance is set to such a value that it

    is only energised by short circuits in the zone specified above does not respond to faults

    beyond the transformers.

    e) Stator earth fault protection: The earth fault protection is the protection of the

    generator against damages caused by the failure of insulation to earth. Present practice

    of grounding the generator neutral is so designed that the earth fault current is limitedwithin 5 and 10 AMPs. Fault current beyond this limit may caused serious damage to the

    core laminations. This leads to very high eddy current loss with resultant heating and

    melting of the core.

    f) 95% stator earth fault protection: Inverse time voltage relay connected across the

    secondary of the high impedance neutral grounding transformer relay is used for

    protection of around 95% of the stator winding against earth fault.

    g)100% stator earth fault protection:earth fault in the entire stator circuits are detected

    by a selective earth fault protection covering 100% of the stator windings. This 100% E/f

    relay monitors the whole stator winding by means of a coded signal current continuously

    injected in the generator winding through a coupling. Under normal running condition

    the signal current flows only in the stray capacitances of the directly connected system

    circuit. In case of an earth fault , this capacitance is bypassed and the monitoring current

    which is determined mainly by the resistance to earth increases. This increased current

    value and reproduction of the signal code are used for the operation of the relay.

    h)Rotor earth fault protection: Normally a single rotor earth fault is not so dangerous as

    the rotor circuit is unearthed and current at fault point is zero. So only alarm is provided

    on occurrence of first rotor earth fault. On occurrence of the second rotor earth fault

    between the points of fault the field winding gets short circuited. The current in field

    circuit increases, resulting in heating of the field circuit and the exciter. But the more

    dangerous is disturbed symmetry of magnetic circuit due to partial short circuited coils

    leading to mechanical unbalance. Severe vibration may seriously damage the machine.Thus the protection circuit should be so designed as to give an alarm in case of

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    33/68

    development of 1st

    rotor earth fault and it should trip the machine on the occurrence of

    2nd

    earth fault.

    GENERATOR OPERATION:-

    The operation of the generator is concerned with the basic processes of synchronization,

    loading , voltage maintenance, stability and safe tripping/shutting down of the machine.

    In the power system the generator is required to operate in parallel with other running

    machines and to share both active and reactive power demand of the system.

    Synchronization of generator: The process of interconnection of the generator with the

    grid to which a number of generators are already connected is known as synchronization.

    For successful synchronization and parallel operation of the generator the voltage,frequency and phase sequence of the incoming generator must be same as that of the

    grid(running system ). To determine the exact instant of synchronism synchroscope with

    three lamps is provided at the generator control desk. In some machine auto

    synchronization facility is also provided. Before rolling of the TG to match the speed of

    the machine corresponding to the grid frequency and increasing generator terminal

    voltage readiness of the machine itself and it is various auxiliaries are to be ensure. The

    synchronization process is to be in close co-ordination with the mechanical system of the

    power house. In general following operation and checking are to be carried out in steps

    before synchronization of the generator.

    Before machine starts rolling check and ensure-

    Generator auxiliary system:-

    a)The lube oil flow to generator bearings is adequate with correct pressure and

    temperature and there is no oil leakage.

    b)Casing H pressure is adequate and with required purity. There is no sign of drop in gas

    pressure. The machine may be synchronized at a lower H pressure within allowable limit

    but in that case load is to be restricted as per the manufacturers recommendation.

    Hydrogen extractor fan is in service.

    c)Stator cooling water flow is established and distillate conductivity is below 5 micro

    mho-cm.

    d)Generator exciter end bearing pedestal insulation is clean and free from dust , dirt or

    oil.

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    34/68

    Generator bus duct:

    All the inspection windows are properly closed and there is no oil or water dropping over

    the duct. The dehumidifier blower is off.

    Neutral grounding transformer(NGT):

    a)All the doors are properly closed and locked.

    b)There is no drop of oil or water on the cubicle.

    Generator P.T and surge protection cubicles:

    a)All PT drums are completely rotated towards/inserted in service position and locked in

    that position and doors are properly closed.

    b)PT fuses are o.k. and tightly inserted within the grips. Door for the box containing fuses

    and terminal strip is closed.

    ELECTRICAL PROTECTION AND SAFETY INTERLOCKS:

    Various failsafe protection

    and safety interlocks are provided in the power plant for safe starting, running and

    shutting down of electrical equipments. These interlocks play vital role to prevent or

    reduce damage of costly equipments during internal fault or fault in connected system/

    equipments operational error as well as for safety of personnel and the system as a

    whole.

    GENERATOR

    In general, it is based if generator protection relays initiate non-sequential

    trip mode(Class A) for unit isolation. However, sequential tripping (Class B) provides a

    better means of tripping a steam turbine generator on some abnormal operating

    condition where delayed tripping of the generator will not result in increased damage to

    the turbine, generator or other electrical equipment. The reason for sequentially tripping

    a steam turbine generator is to avoid the over-speed condition that results when the

    generator main breaker is tripped while steam is supplied to the turbine.

    Proper control logic is critical to the design of a sequential tripping scheme

    switches, trip oil system pressure switches etc) which is supervised by an electrical LowForward Power relay/ Reserve Power relay. This relay is normally set to detect very low

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    35/68

    power levels and incorporates a brief time delay of the order of few seconds for added

    security.

    It has been recommended that generator protective relays, initiates non-sequentialtrip mode for isolation of the unit due to electrical faults. Only devices protecting unit

    from an abnormal mechanical operating condition or an abnormal (not faulted) electrical

    condition or normal shut down should initiate a sequential trip.

    Class ALockout Relay will operate for the following conditions indicating major

    electrical faults in the Generator stator, Generator rotor, Generator Transformer and

    Unit Auxiliary Transformers and excitation transformer and associated field Breaker

    Cubicle and similar other faults as detailed below:

    a) Generator stator differential relay operated.

    b) Generator stator inter-turn differential relay operated.

    c) Generator Transformer differential operated

    d) Generator Transformer overall differential relay operated

    e) Unit auxiliary transformer differential relay operated

    f) Generator stator E/F relay(0-95%)operated

    g)

    Generator stator E/F relay (95-100%) operatedh) Generator rotor earth fault relay operated

    i) Loss of excitation relay operated

    j) Generator transformer restricted E/F relay operated

    k) Generator over voltage relay operated

    l) Generator reverse power relay operated

    m)Generator transformer over-fluxing relay operated

    n) Generator transformer back-up E/F relay operated

    o)

    UAT back-up E/F relay operated

    p) Back-up distance relay operated

    q) Generator negative sequence relay operated

    r) Bus differential protection relay operated

    s) GT buchholz relay operated

    t) UAT buchholz relay operated

    u) Thyristor bank failure

    v) Generator Neutral isolator open

    w)EBP pressed

    x) GT SPR(Sudden pressure relay)

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    36/68

    Class-Blockout relay will operate for the following conditions:

    a)Boiler tripb) Turbine trip

    c)UAT backup O/C relay operated

    d)AVR protection

    Class-Clockout relay will operate for the following conditions:

    a)Back-up distance relay operated stage I

    b)Generator negative sequence stage I

    c)GT breaker protection

    d)GT winding temperature/ oil temperature operated

    e) Under frequency relay operated

    Unit trip sequence:

    The difference sequence of tripping shall be as mention below:

    a)Boiler to Turbine to Generator

    b)Turbine to Generator

    c)Generator to Turbine

    Generator field breaker interlocks:

    Generator field breaker can only be closed if the

    following per missives are available

    a)Turbine is running at its rated speed(3000 rpm for thermal machine with

    +/- tolerance).

    b)To be detected by speed switch contact at ATRS cubicle

    c)All generator class-A lockout relay are in reset condition

    d)Field flushing system is healthy

    Generator field breaker trip interlocks:

    Generator field breaker can trip through the

    following initiating contacts:

    a)Class-A relays operated

    Generator field breaker manual trip block interlocks:When generator is in service

    manual tripping of field breaker is not permitted owing to loss of excitation and

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    37/68

    subsequent harmful effects on the machine. Operation of F8S relay indicate that

    generator is in service(connected in the grid) with its own breaker of bus coupler breaker.

    One NC contact of F8S relay is used in series with the manual tripping circuit of the field

    breaker.

    Generator field breaker auto-trip block interlocks:

    When generator is in service, auto

    tripping (through Class-A lockout contacts) of field breaker is permitted only after

    opening of generator breaker or transfer B/C breaker as case may be and there by

    drop out of F8S relay to avoid momentary loss of excitation and subsequent harmful

    effect on the machine.

    Single Line Diagram Of Generating Station(unit#5 and 6)

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    38/68

    SINGLE LINE DIAGRAM OF GENERATING STATION(UNIT-7)

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    39/68

    GENERATOR TRANSFORMER

    Transmission of power at generated voltage is not economical. The need for transformers

    is paramount for a power system considering the fact that transmission losses are

    minimum for high voltages where as a distribution has to be done at the relatively safe

    voltage. In essence the transformer transforms a voltage and current one level to a

    voltage and current at another level while keeping the frequency and power level

    unaltered. So generator output voltage is step up to the transmission voltage system

    voltage by a transformer known as Generator transformer(GT). Capacity of generator

    transformer is determined based on the MVA capacity of generator. The open type

    terminals of the HV bushing of the generator transformer are connected to switchyard

    conductor through GCB. The LV terminals are kept suitably enclosed to facilitatedconnection to generator bus duct. Cooling method adopted is OFAF.

    In MTPS Unit#1 to 6, GTs are single 3 phase transformer and in phase II, GTs are a bank

    of three single phase transformers . The only step up transformer is GT in this station.

    GENERATOR TRANSFORMER

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    40/68

    Specification of GT:-

    Unit# 1 to 4

    Make: BHELType of cooling: ONAN/ONAF/OFAF

    Rating of HV(MVA): 150/200/250

    Rating of LV(MVA): 150/200/250

    Frequency(Hz): 50

    Phase: 3

    Connection symbol: YNd1

    No Load Voltage of HV(KV): 240

    No Load Voltage of LV(KV): 15.75

    Line Current of HV(Amp): 301/482/602

    Line Current of LV(Amp): 3505/7340/9175

    Temperature rise of oil(C): 40 over ambient of 50C

    Temperature rise of winding(C): 45 over ambient of 50C

    Weight:

    Core and windings(kg): 139000

    Complete Transformer including oil(kg): 38070Transport(kg): 237100

    Insulation level: HV SI 750 LI 1050

    LV LI 95 AC 50

    H.V.N LI 170 AC 70

    Unit# 5 and 6

    Make: BHELType of cooling: ONAN/ONAF/OFAF

    Rating of HV(MVA): 109/252/315

    Rating of LV(MVA): 109/252/315

    Frequency(Hz): 50

    Phase: 3

    Connection symbol: YNd1

    No Load Voltage of HV(KV): 220

    No Load Voltage of LV(KV): 16.5

    Line Current of HV(Amp): 757.77

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    41/68

    Line Current of LV(Amp): 11022.14

    Temperature rise of oil(C): 40 over ambient of 50C

    Temperature rise of winding(C): 45 over ambient of 50C

    Weight:Core and windings(kg): 165000

    Complete Transformer including oil(kg): 253250

    Transport(kg): 180000

    Oil quantity(lit): 57000

    Insulation level: HV SI 750 LI 1050

    LV LI 95 AC 50

    H.V.N LI 170 AC 70

    Unit#7 and 8

    Make: BHEL

    Type of cooling: ONAN/ONAF/OFAF

    Rating of HV(MVA): 120/160/200

    Rating of LV(MVA): 120/160/200

    Frequency(Hz): 50

    Phase: 1

    Connection symbol: YNd11

    No Load Voltage of HV(KV): 420/3

    No Load Voltage of LV(KV): 21

    Line Current of HV(Amp): 824.79

    Line Current of LV(Amp): 9523.8

    Temperature rise of oil(C): 40 over ambient of 50C

    Temperature rise of winding(C): 45 over ambient of 50C

    Weight:Core and windings(kg): 153520

    Complete Transformer including oil(kg): 257500

    Transport(kg): 174900

    Oil quantity(lit): 56220

    Insulation level: HV SI 1180 LI 1425-AC 38

    CHOPPED LI 1570

    LV 125-AC 50

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    42/68

    UNIT TRANSFORMER:

    There is one unit transformer for each unit in phase ii. There are some machines whose

    operating voltage is 11kv.To supply these machines we have to step down the generating

    voltage. These can be done by unit transformer by tapping from generating terminal.

    Unit transformer step down the voltage 21kv to 11 kv. This is a three phase transformer.

    But, in case of unit#1to 6 there is no need of UT, because there is only two

    voltage level-6.6kv and 415v.

    Specification of UT:-

    Make: BHEL

    Type of cooling: ONAF/ONAN

    Rating of HV(MVA): 45/36

    Rating of LV(MVA): 45/36

    Frequency(Hz): 50

    Phase: 3

    Connection symbol: Dyn1

    No Load Voltage of HV(KV): 21

    No Load Voltage of LV(KV): 11.5Line Current of HV(Amp): 1238.64

    Line Current of LV(Amp): 2261.87

    Temperature rise of oil(C): 40 over ambient of 50C

    Temperature rise of winding(C): 45 over ambient of 50C

    Weight:

    Core and windings(kg): 40065

    Complete Transformer including oil(kg): 86205

    Transport(kg): 50000

    Oil quantity(lit): 25580

    Insulation level: HV LI 125-AC 50

    LV LI 75-AC 28

    Unit Auxiliary Transformer:

    The normal source of HV power to unit auxiliaries is unit auxiliary transformer. The sizing

    of the UAT is usually based on the total connected capacity of running unit auxiliaries i.eexcluding the stand by drives. It is safe and desirable to provide about 20% excess

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    43/68

    capacity than calculated. With the help of UAT we stepped down the generated 15.75kv

    (in case of unit#1to4) and 16.6 kv(in case of unit#5,6) into 6.6kv to supply the 6.6kv

    auxiliary drives. But, in case of phase II UAT is used to stepped down the 11kv voltage

    into 3.3kv to supply the 3.3 kv machines and its high voltage terminal is connected to aUT and there is two UAT for each UT.

    Specification of UAT:-

    For Unit# 1to 4

    Make: Atlanta Electrical Pvt.Ltd.

    Type of cooling: ONAF/ONAN

    Rating of HV(MVA): 16/12.50Rating of LV(MVA): 16/12.50

    Frequency(Hz): 50

    Phase: 3

    Connection symbol: Dyn11

    No Load Voltage of HV(KV): 15.7

    No Load Voltage of LV(KV): 6.9

    Line Current of HV(Amp): 586.5 /458.2

    Line Current of LV(Amp): 1338.8/1045.9

    Temperature rise of oil(C): 40C

    Temperature rise of winding(C): 45C

    Weight:

    Core and windings(kg): 14300

    Weight of oil(kg): 8600

    Total weight(kg): 30500

    Oil quantity(litre): 7650Insulation Level:

    HV : 95 KVP 38 KV rms

    LV : 30 KVP 20 KV rms

    For Unit#5 and 6

    Make: BHEL

    Type of cooling: ONAF/ONAN

    Rating of HV(MVA): 20/16

    Rating of LV(MVA): 20/16

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    44/68

    Frequency(Hz): 50

    Phase: 3

    Connection symbol: Dyn11

    No Load Voltage of HV(KV): 16.5No Load Voltage of LV(KV): 6.9

    Line Current of HV(Amp): 699.81/559.85

    Line Current of LV(Amp): 1673.479/1338.783

    Temperature rise of oil(C): 50C

    Temperature rise of winding(C): 55C

    Weight:

    Core and windings(kg): 20600

    Weight of oil(kg): 15050

    Total weight(kg): 46300

    Oil quantity(litre): 16900

    Insulation Level:

    HV : 95 KVP 38 KV rms

    LV : 30 KVP 20 KV rms

    For Unit#7 and 8

    Make: BHEL

    Type of cooling: ONAF/ONAN

    Rating of HV(MVA): 16/12.50

    Rating of LV(MVA): 16/12.50

    Frequency(Hz): 50

    Phase: 3Connection symbol: Dyn1

    No Load Voltage of HV(KV): 11

    No Load Voltage of LV(KV): 3.45

    Line Current of HV(Amp): 839.78/656.08

    Line Current of LV(Amp): 2677.57/2091.85

    Temperature rise of oil(C): 40C

    Temperature rise of winding(C): 45C

    Weight:

    Core and windings(kg): 16700

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    45/68

    Weight of oil(kg): 9800

    Total weight(kg): 40000

    Oil quantity(litre): 11000

    Insulation Level:HV : LI 75 KVP AC 28 KV rms

    LV : LI 40 KVP AC 10 KV rms

    DISTRIBUTION TRANSFORMER

    To supply the 415v rated motors we use this distribution transformer which actually

    steps down the 6.6kv supply into 415v.Some of the distribution transformer are dry type

    i.e natural cooling system is used here.For each unit(1 to 6) there are 8 distribution

    transformer inside plant.

    :RATING:

    Make: BHEL

    Type of Cooling: AN

    Rating(KVA): 1250

    Rated Current H.V(Amps): 109.4

    Rated Current L.V(Amps): 1666.7Vector Group: DyN11

    Model: CAST RESIN DRY TYPE

    Freequency: 50Hz

    Temperature Rise Over 500c Ambient

    at 85.5% rated voltage: 800c

    Insulation level H.V: 75KVp/28KV rms

    Insulation Class: F

    Weight(Kg): 5500

    STATON SERVICE TRANSFORMER(SST):

    Normal source to the station auxiliaries and stand by source to the unit auxiliaries during

    start up and after tripping of the unit is Station Service transformer. Quantity of station

    Service transformers and there capacity depends upon the unit sizes and numbers. Each

    station service transformer shall be one hundred percent stand by of the other. Station

    service transformers shall cater to the simultaneous load demand due to start up power

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    46/68

    requirements for the largest unit, power requirement for the station auxiliaries required

    for running the station and power requirement for the unit auxiliaries of a running unit in

    the event of outage of the unit source of supply. There is three SST for unit#1 to 4 and

    two SST for unit#5 and 6.Its steps down 220 kv grid voltage to 6.6 kv voltage and supplytwo board-CAB(Common Auxialiary Board) and SEB(Start-up Emergency Board).

    For unit#1 to 4

    Make: BHEL

    Type of cooling: ONAF/ONAN

    Rating of HV(MVA): 31.5/25.2

    Rating of LV(MVA): 31.5/25.2

    Frequency(Hz): 50

    Phase: 3

    Connection symbol: YNyn0d1

    No Load Voltage of HV(KV): 230

    No Load Voltage of TV(KV): 11

    No Load Voltage of LV(KV): 6.6

    Line Current of HV(Amp): 79.1

    Line Current of TV(Amp): 2635.8Temperature rise of oil(C): 40

    Temperature rise of winding(C): 45

    Weight:

    Core and windings(kg): 34400

    Weight of oil(kg): 29550

    Total weight(kg): 214000

    For unit#5 and 6

    Make: BHEL

    Type of cooling: ONAF/ONAN

    Rating of HV(MVA): 40/25

    Rating of LV(MVA): 25/15.625

    Frequency(Hz): 50

    Phase: 3

    Connection symbol: YNyn0yn0

    No Load Voltage of HV(KV): 230

    No Load Voltage of LV1(KV): 6.9

    LV2(KV): 6.9

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    47/68

    Line Current of HV(Amp): 100.408/62.755

    Line Current of LV1(Amp) and LV2: 2091.848/1307.405

    Temperature rise of oil(C): 40

    Temperature rise of winding(C): 45Weight:

    Core and windings(kg): 48000

    Weight of oil(kg): 46000

    Total weight(kg): 132000

    But in case of phase II this scheme is different and this is elaborated below-

    STATION TRANSFORMER (ST):

    Normal source to the station auxiliaries and stand by source to the unit auxiliaries during

    start up and after tripping of the unit is Station transformer. Quantity of station

    transformers and there capacity depends upon the unit sizes and numbers. Each station

    transformer shall be one hundred percent stand by of the other. Station transformers

    shall cater to the simultaneous load demand due to start up power requirements for the

    largest unit, power requirement for the station auxiliaries required for running the

    station and power requirement for the unit auxiliaries of a running unit in the event of

    outage of the unit source of supply. We have two station transformer in 400kv

    switchyard. It steps down the 400kv grid voltage to 11kv voltage.

    STATION AUXILIARY TRANSFORMER(SAT):

    Station auxiliary transformer is also a step down transformer. It steps down 11kv voltage

    to 3.3kv voltage. It is mainly used to supply the 3.3 kv machines. Its high voltage is

    connected to the secondary of the ST. Its use is similar to the UAT at starting condition

    and tripping condition. There is two SAT for each ST.

    Specification of ST:-

    Make: BHEL

    Type of cooling: ONAN/ONAF

    Rating of HV(MVA): 72/90

    Rating of LV(MVA): 72/90

    Frequency(Hz): 50

    Phase: 3

    Connection symbol: Yn0 Yn0 Yn0

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    48/68

    No Load Voltage of HV(KV): 400

    No Load Voltage of LV1(KV): 11.5

    LV2(KV): 11.5

    Line Current of HV(Amp): 130Line Current of LV1(Amp): 2261.9

    LV2(Amp): 2261.9

    Temperature rise of oil(C): 40

    Temperature rise of winding(C): 45

    Weight:

    Core and windings(kg): 9769

    Weight of oil(kg): 58450

    Total weight(kg): 214000

    Oil quantity(litre): 67180

    Insulation level:

    HV : LI 1300-AC38

    LV 1: LI 75- AC28

    LV2: LI 75-AC28

    Specification of SAT:-Make: BHEL

    Type of cooling: ONAN/ONAF

    Rating of HV(MVA): 16/12.50

    Rating of LV(MVA): 16/12.50

    Frequency(Hz): 50

    Phase: 3

    Connection symbol: DyN1

    No Load Voltage of HV(KV): 11

    No Load Voltage of LV(KV): 3.45

    Line Current of HV(Amp): 839.78/656.08

    Line Current of LV(Amp): 2677.57/2091.85

    Temperature rise of oil(C): 40

    Temperature rise of winding(C): 45

    UST & SST:- There are other two types of step-down 3 phase transformer for internaloperation, known as UST and SST. UST is fed from UT switch board and SST is fed from ST

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    49/68

    switch board. These are dry type cast resin transformer. The voltage ratio is 11KV/433V

    for both the transformer. Air natural cooling and Dyn1 connection is used.

    NGT (NEUTRAL GROUNDING TRANSFORMER):The NGT is used to prevent the generator from earth faults. It comprises of primary

    winding and secondary winding, the secondary winding is connected with a low value

    resistance. When ever a earth fault arises heavy current flows to the primary winding and

    as a result an emf is induced in the secondary. The voltage drop across the resistance is

    sensed by the NGT relay and it actuates to actuate the GCB(generator circuit breaker)

    and thus the generator is tripped. Basically NGT is a step-down(21KV/220V) transformer.

    TRANSFORMER AUXILARIES:

    For proper functioning of the transformer it is provided with several auxiliaries sub

    systems. Basically they are:

    COOLING SUB SYSTEM:

    Considering the substantial amount of load delivered by a power transformer a

    proper cooling system has to be in place in order to prevent any hazards. Mostly,

    OFAF(Oil Forced Air Forced) or ONAF(Oil Natural Air Forced) schemes are used.

    There are radiators and fans as well. For OF type cooling butterfly valve is kept to

    pump oil.

    CONSERVETOR:

    Since the oil plays a major role in the cooling of a transformer hence it has to be

    maintained. The conservator preserves the oil of the transformer while expansion

    of oil. BUCHHOLZ RELAY:

    It is a protective device used only in oil immersed transformer. It provides

    protection against two types of fault, incipient faultand severe fault. Under

    incipient fault it gives an alarm and under severe fault it trips the transformer from

    the line by using two floats which acts as a switch. It is universally use for

    transformer having rating more than 750 KVA.

    BREATHER:

    The breather basically absorbed any moisture that may be caused due to

    vaporization of the oil in transformer. It contains silica gel, which changes colour

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    50/68

    from blue to off-white as it absorbs moisture. Thus it provides an indicator

    mechanism for the quality of the oil.

    PROTECTION MECHANISMS:

    There are temperature sensors, which can alarm if the temperature rises beyond acertain limit. Also the water supply gets activated in case of hazards like fire.

    There are also kept RTD(resistance temperature detector) and PRV(pressure relief valve)

    for safety.

    SWITCHYARDIt is a switching station ,which has the following credits:

    Main link between generating plant and transmission system, which has a

    large influence on the security of the supply.

    Step-up and/or step-down the voltage levels depending upon the Network node.

    SwitchingON/OFF reactive power control devices, which have effect on quality of

    power.

    In MTPS has mainly two switchyards. one is 220KV and another one is 400KV.

    These two switchyards are of three bus system(also called, one and half bus system).

    1. Main bus I

    2. Main bus II

    3.

    Transfer bus

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    51/68

    Single Line Diagram of 220kv switchyard

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    52/68

    Single Line Diagram Of 400kv Switchyard

    EQUIPMENTS COMMONLY FOUND IN SWITCHYARD:-

    1. Circuit Breakers

    2. Current Transformer

    3. Potential Transformer

    4. Capacitor Voltage Transformer

    5. Isolator

    6. Earth Switch

    7. Lightning Arrester

    8. Wave traps

    9. Bus bar & Clamp fittings

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    53/68

    1. CIRCUIT BREAKERS:-

    It is an on-load switch which can break the circuit under any fault

    condition which can damage other instrument in the station. It works automatically and

    also manually.There are mainly two types CB are used. These are a). SFgas CB, b). Vacuum Circuit

    Breaker.

    In the 220KV switchyard we have SF CBs (single break) and in the 33kv switchyard we

    have VCB.

    In the 400kv switchyard we have double break SF CB. This type of CB arrangement

    consist of i) gradient capacitor, ii) break, iii) pre-insert resistor. The gas is put inside the

    circuit breaker by force under high pressure. When if the gas gets decreases there is a

    motor connected to the circuit breaker. The motor starts operating if the gas went lower

    than 20.8 bar. There is a meter connected to the breaker so that it can be manually seen

    if the gas goes low. The circuit breakers use the SFgas to reduce the torque produce in it

    due to any fault in the line. The circuit breaker has a direct link with the instruments in

    the station, when any fault occur alarm bell rings.

    In a single break type only the bus bar end is isolated but in a double break type, both

    bus bar(source) and cable (load) ends are broken.

    CIRCUIT BREAKER

    (Double Break) (Single Break)

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    54/68

    2. CURRENT TRANSFORMER:-

    Current transformers are basically used to take the reading of the currents entering the

    station. This transformer steps down the current from 1600amps to 1 amp. This is done

    because we have no instruments to measure such type of huge amount current. This

    type of transformer are used to i) protection & ii) measurement purpose.

    There are 5 cores used in this type of CT.

    CURRENT TRANSFORMER

    3.POTENTIAL TRANSFORMER:-

    Potential transformers serve a number of functions in a power system.

    They are required for the operation of many types of instrumentations and relay

    protective systems. They are mainly used to step down the high magnitude of voltage to

    a save value to incorporate measuring and protection logics. They measures voltage and

    in conjunction with CT, they measure power. They feed synchronizing equipments. They

    can be used as coupling capacitor in power line carrier network.This is used in 220KV

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    55/68

    Switchyard.

    (POTENTIAL TRANSFORMER)

    4. CAPACITOR VOLTAGE TRANSFORMER(CVT):-

    A capacitor voltage transformer (CVT) is a

    transformer used in power system to step down extra high voltage signals and provide

    low voltage signal either for measurement or to operate protective relay. Inits most basic form it consist of three parts: two

    capacitor across which the voltage signal is split, an

    inductive element used to tune device to the supply

    frequency and a transformer to isolate and further step

    down voltage for instrumentation and protective relay.

    The device has at least four terminals, a high voltage

    terminal for connection of high voltagesignal, a ground

    terminal and at least one set of secondary terminals for

    connecting to the instrumentation and protective relay.

    CVTs are typically single phase device used for measuring voltage in excess of one

    hundred kilovolts where the use of voltage transformer would be uneconomical. In

    practice the first capacitor, C1 is often replaced by a stack capacitor connected in series.

    This result in large voltage drop across the stack of capacitor that replaced the first

    capacitor and a comparatively small voltage drop across the second capacitor, C2 and

    here the secondary terminals.

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    56/68

    5.ISOLATOR:-

    Basically an isolator is off-load switch. The use of this isolator is to protect

    the transformer from the other instrument in the line. The isolator isolates the extra

    voltage to the ground and thus any extra voltage cannot enter the line. Thus an isolator isused after the bus for protection also. Two isolator must be kept in both side of a

    breaker.

    Type of isolator used in 220KV:

    i)Central Rotate Double Break

    (CRDB)

    Types of isolator used for 400KV:

    i) HCB(horizontal central break)

    ii) pantograph

    HCB Pantograph isolator

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    57/68

    6. EARTH SWITCH:-

    Earth switch discharges the capacitive voltage stored in line on

    generator side in isolated system just after opening of CB and isolator. When earth switch

    is connected to the isolated but un-discharged system it discharges the stored energy tothe earth, so that maintenance work can be carried out either in line or in generator side.

    Earth switch should be operated only when the isolators are open. In MTPS all earth

    switches can be operated manually.

    EARTH SWITCH

    7. LIGHTENING ARRESTOR:-

    Lightening arrestors are the instruments that are used in the

    incoming feeders so that to prevent the high voltage entering the main station.

    This high voltage is very dangerous to the instruments used in the substation. Even

    the instruments are very costly, so to prevent any damage lightening arrestors are

    used. The lightening arrestors do not let the lighting to fall on the station. If some

    lightening occurs the arrestors pull the lightening and ground it to the earth. In any

    sub-station the main important is of protection which is firstly done by these

    lightening arrestors. The lightening arrestors are grounded to the earth so that it

    can pull the lightening to the ground. The lightening arrestors work with an angle

    of 30to 45making a cone.In 400kv switchyard gap-less arrestor are used & gap

    less material is ZnO.

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    58/68

    LIGHTENING ARRESTOR WAVE TRAP

    8.Wave Traps:-

    Wave trap is nothing but a L-R circuit which can trap the high frequency

    communication signals sent on the line from the remote substation and diverting

    them to the telecom/tele protection panel in the substation control room (through

    coupling capacitor and LMU).This is relevant in Power Line carrier

    Communication(PLCC) systems for communication among various substation

    without dependence on the telecom company network. The signals are primarily

    tele protection signals and in addition , voice and data communication signals

    through same power line.

    The wave trap offers high impedance to the high frequency communication signals

    thus obstructs the flow of these signals in to the substation busbars. If there were

    not to be there, then signal loss is more and communication will be

    ineffective/probably impossible. The total systems occurs by using

    modulation/demodulation factors through transmitter and receiver.

    9.Bus bar & Clamp fittings:-

    The bus is a line in which the incoming feeders come into and get into the

    instruments for further step up or step down. There may be double line in the bus

    so that if any fault occurs, other can works. Thus the supply will not stop.

    In MTPS there have two switchyards with three bus.

    i)Main bus-1 & ii)Main bus2Buses are main source of power in power system grid the

    generators or the alternator are connected in parallel to the main bus 1 or 2 to supply the

    power in the grid.

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    59/68

    iii)Transfer busUsually there is no power at the time of normal operation in a transfer

    bus of a generating station. When there is a fault in certain line so power cannot be

    transferred to a main bus. So transfer bus is used to transfer the power from one main

    bus to other main bus.In MTPS 220KV switchyard has 31no.of Bay.Among them six for GT,twelve for Line,five

    for SST,two for 80MVA Transformer,four for Bus coupler,two for Bus tie and 400KV

    switchyard has 10 no. of bay. Among them four line bay, two for GT, two for ST, one for

    bus-tie and another one is bus coupler. Mainly bus coupler is used to maintain the supply

    under fault conditions of a breaker.

    10.INSULATORS:-

    The overhead line conductors are bare and not covered with any

    insulating materials. The line conductors are therefore, secured to the supporting

    structures by means of insulating fixtures, called insulators, in order that there is no

    current leakage to the earth through the supports. Insulators are mounted on the cross-

    arms and the line conductors are attached to the insulator so as to provide the

    conductors proper insulation and also provide necessary clearance between conductors

    and metal works. The insulators must provide proper insulation and necessary clearance

    against the highest voltage in worst atmospheric conditions to which the line is likely tobe subjected. The insulator also prevent short circuiting between the different phase

    conductors and provide necessary mechanical support for the line conductors. Thus the

    insulators undoubtly one of the most important and vulnerable links in transmission and

    distribution of overhead transmission and distribution.

    In MTPS switchyards mainly disc type, string type, pin type insulators are used.

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    60/68

    RATINGS

    SF6 CIRCUIT BREAKER(Single Break)

    Rated voltage :245KVRated Impulse withstand voltage :1050 KV

    Rated power frequency voltage :460 KVp

    Rated frequency :50 Hz

    Rated normal current :2000 A

    Rated short time current :40 KA

    Rated short-circuit duration :1 s

    First pole to clear factor :1.3

    Symmetrical :40 KA

    Breaking capacityequivalent :19000 MVA

    Asymmetrical :46.4KA

    Rated making current :100 KAp

    Rated pressure of hydraulic operated mechanism gauge :250-350 bar

    Rated pressure of SF at 20C(gauge) :6.5 bar

    Weight of complete breaker :4051kg

    Weight of SF gas :25 kgRated trip coil voltage :220V(DC)

    Rated closing coil voltage : 220V(DC)

    SF CIRCUIT BREAKER(Double Break)

    Rated voltage :420 KV

    Rated Impulse withstand voltage :1050/1425 KVp

    Rated power frequency voltage :520/610 KV

    Rated frequency :50 Hz

    Rated normal current :3150 A

    Rated short time current :40 KA

    Rated short-circuit duration :1 s

    First pole to clear factor :1.3

    Symmetrical :40 KABreaking capacityequivalent :29000 MVA

    Asymmetrical :52.5 KA

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    61/68

    Rated making current :100 KAp

    Rated pressure of hydraulic operated mechanism gauge :313 3 bar

    Rated pressure of SF at 20C(gauge) :7.5 bar

    Weight of complete breaker :9181 kgWeight of SF gas :57.5 kg

    Rated trip coil voltage :220+ 20

    -10 Volt DC

    Rated closing coil voltage : 220+ 20

    -10 Volt DC

    CENTRAL ROTATE DOUBLE BREAK ISOLATOR

    Make :H.L.M.Industries

    Type :CRDB

    Volt(kv) :245

    BIL(kv) :1250

    STC(kA/sec) :40

    Curent(Amp) :1250

    Type of Drive :Motor

    Motor Voltage(AC)(V) :415

    Control Ckt. Voltage(D.C)(V) :230

    HORIZONTAL CENTRAL BREAK ISOLATOR

    Type :HCB

    Volt( KV) :420

    BIL (KV) :1425

    Switching Impulse(KV) :1050/1245

    P(KV) :610

    STC(KA/sec) :40

    Weight of isolator(kg) :1950 approx

    Frequency(Hz) :50

    Current(A) :2000

    Type of drive :Motor

    Motor voltage(AC)(V) :415

    Control voltage(DC)(V) :220

    Weight of drive(kg) :100

    PANTOGRAPH TYPE ISOLATOR

    Type :Pantograph

    Volt( KV) :420

    BIL (KV) :1425

  • 5/20/2018 REPORT ON MEJIA THERMAL POWER PLANT(DVC)

    62/68

    Switching Impulse(KV) :1050/1245

    P(KV) :610

    STC(KA/sec) :40

    Weight of isolator(kg) :1950 approx

    Frequency(Hz) :50

    Current(A) :2000

    Type of drive :Motor

    Motor voltage(AC)(V) :415

    Control voltage(DC)(V) :220

    Weight of drive(kg) :100

    EARTHING SWITCH

    Type :Telescopic

    Volt( KV) :420

    BIL (KV) :1425

    STC(KA/sec) :40

    Weight of isolator(kg) :78/pole

    Frequency(Hz) :50

    Current(A) :2000

    Type of drive :Motor

    Motor voltage(AC)(V) :415

    Control voltage(DC)(V) :220

    Weight of drive(kg) :100

    PROTECTION OF SWITHYARD:-

    The main protections are given to line & bus-bars under different faults are

    1.Distance protection:- In this type, the relay operates when the ratio of the voltage &

    current changes beyond a specified limit.

    2.Over current protection:- All buses have a specific limit to flow the current, if current is

    more beyond this limit, then the o/c relay will operate.

    3.Over voltage protection:- Same as o/c protection ,all buses have a specific limit to

    withstand a maximum voltage, if this voltage is over, then the over voltage relay will

    operate.

    4.Earthfault protection:- Earth fault protection is one of the main protection of the lines.

    If there occ