Report from MIPO

Executive Board Meeting

Roy Preece

23rd May 2014

Page 2: Report from MIPO Executive Board Meeting Roy Preece 23 rd May 2014

Organisation

• Project Manager: R. Preece (Chair)• Spokesperson: K. Long• US Map Director : M. Palmer• MICE-US Construction Project Manager: A. Bross• Experimental Integration Scientist: P. Hanlet• MICE-UK Capital Project Associate: A. Grant• Accelerator Integration Scientist: J. Pasternak• MICE-US Financial Manager: P. Garbincius• MICE-UK Principal Investigator: P. Soler

• All meeting minutes can be found on the MIPO WIKI - http://micewww.pp.rl.ac.uk/projects/mipo/wiki• Agenda is changeable – focusing on the hot topics of the moment and future• Meets every two weeks

Page 3: Report from MIPO Executive Board Meeting Roy Preece 23 rd May 2014

Milestone TrackerDashboard link - http://micewww.pp.rl.ac.uk/dashboard/Version at this link has no been updated yet

Baseline Date May 13

Oct 13 Feb 14 Mar 14 Apr 14 May 14 6 7 8 9 10 11 12 13

Step IV Top Level MilestonesSS#2 Mechanically installed in MICE Hall 02/12/13 02/12/13 24/04/14 24/04/14 07/05/14 09/05/14AFC installed in R9 ready for field mapping 10/12/13 10/12/13 23/05/14 23/05/14 30/05/14 23/05/14Downstream Solenoid arrives at RAL 03/01/14 08/05/14 08/05/14 08/05/14 16/05/14 30/04/14SS#1 Mechanically installed in MICE Hall 13/01/14 13/01/14 01/10/14 01/10/14 21/11/14 21/11/14AFC#1 ready for installation in MICE Hall 16/01/14 16/01/14 18/07/14 18/07/14 14/08/14 14/08/14West Mezz build Complete - milestone 04/02/14 04/02/14 25/03/14 19/03/14South side yoke material delivered 15/04/14 15/04/14 15/07/14 15/07/14 11/08/14 11/08/14Rack Room 2 BPG work Complete 23/04/14 23/04/14 24/06/14 24/06/14 09/07/14 12/05/14South side return yoke installation complete 04/06/14 04/06/14 03/09/14 03/09/14 12/11/14 12/11/14Compressor services Complete 30/06/14 30/06/14 30/06/14 30/06/14 20/08/14 20/08/14North side yoke material delivered 15/07/14 15/07/14 15/07/14 15/07/14 15/12/14 15/12/14Compressors ready for Cooling channels tests 04/09/14 04/09/14 13/10/14 13/10/14 19/01/15 19/01/15Rack Room Complete 12/09/14 12/09/14 13/11/14 13/11/14 02/02/15 02/02/15North side return yoke installation complete 17/10/14 17/10/14 05/11/14 05/11/14 23/02/15 23/02/15Combined magnet operational tests complete 30/01/15 30/01/15 18/02/15 18/02/15 13/05/15 13/05/15MICE step IV installation complete 30/01/15 30/01/15 25/02/15 25/02/15 04/03/15 04/03/15

Step V Top Level MilestonesLH2 absorber #2 at RAL (KEK) 28/09/12 28/09/15 28/09/15 28/09/15 28/09/15 28/09/15AFC#2 ready for installation in MICE Hall 28/10/13 28/10/13 29/10/14 29/10/14 29/10/14 29/10/14Amplfier#2 installation complete 26/08/14 26/08/14 26/08/15 26/08/15 26/08/15 26/08/15Cavity & RFCC module #1 delivered to RAL 03/01/17 06/03/18 06/03/18 06/03/18 06/03/18 06/03/18MICE step V installation complete 26/06/17 28/08/18 28/08/18 28/08/18 28/08/18 28/08/18

Change since last update Reduction Date No Change Date 1 - 2 weeks Date 2 - 4 Weeks Date 1 -2 months Date 2+ months Date Complete Date

23/10/13

31/01/14

11/05/14

19/08/14

27/11/14

07/03/15

15/06/15

1 2 3 4 5 6 7 8 9 10 11 12 13 14

Step IV Milestones SS#2 Mechanically installed in MICE HallAFC installed in R9 ready for field mappingDownstream Solenoid arrives at RALSS#1 Mechanically installed in MICE HallAFC#1 ready for installation in MICE HallWest Mezz build Complete - milestoneSouth side yoke material deliveredRack Room 2 BPG work CompleteSouth side return yoke installation completeCompressor services CompleteNorth side yoke material deliveredCompressors ready for Cooling channels testsRack Room CompleteNorth side return yoke installation completeCombined magnet operational tests completeMICE step IV installation complete

UK-US Project teams working on expedited scenario

Page 4: Report from MIPO Executive Board Meeting Roy Preece 23 rd May 2014

Recent progress

• Commissioning Plan proposed by MAP has been accepted by Magnet task force, led by Jaroslaw

• USS training in the morning• DSS training in the afternoon• Re-cool overnight and stabilise

• Bring all magnets up together• Day for AFC to re-cool

• Partial Return Yoke• Purchase order for the JFE iron is out.• South side materials milestone mid August• Purchase orders for the lower sections, in to trench, are out.• Some materials are on site

• Lithium Hydride Absorber• Transfer of ownership • Top level STFC approval letter required

• Magnet power break out box• Proposal by the Electrical group to have power break out boxes• All mode changes can be made at these positions• A meeting to discuss will be organised by Andy N

Page 5: Report from MIPO Executive Board Meeting Roy Preece 23 rd May 2014

Recent progress

• Step V cost and schedule• Discussions next week during the MAP collaboration meeting• Gain an expedited schedule, cost profile and risk transfer document• This is a RLSR recommendation

• Assumptions document• Preparation will continue• To define who owns or is responsible for areas of the experiment, eg spares for

detectors, operational gasses / cryogens……

• MTA testing• There will be a team from the UK attending the RF workshop at Fermi Lab• While there they will help and take part in the MTA testing

• Focus Coil• Mapping equipment is at RAL, arrangements underway for mapping.

• FC#1 will be used in Step IV (Unless FC#2 sufficiently outperforms FC#1 and it can be installed to the experiment without disrupting or extending the current schedule for the construction of Step IV.

• FC#1 will be mapped in Flip mode (current mode) and then in Solenoid mode• If required, FC#1 will be re-trained in Flip mode and will be the first mode used

in the experiment