reinforced concrete design (ii) dr. hussain a. jabir · reinforced concrete design (ii) dr. hussain...
TRANSCRIPT
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
1
PRESTRESS CONCRETE
Definition of Prestress:
Pre-stress is defined as a method of applying pre-compression to control the stresses
resulting due to external loads below the neutral axis of the beam tension developed
due to external load which is more than the permissible limits of the plain concrete.
The pre-compression applied (may be axial or eccentric) will induce the compressive
stress below the neutral axis or as a whole of the beam c/s. Resulting either no
tension or compression.
Terminology:
1. Tendon: A stretched element used in a concrete member of structure to impart
prestress to the concrete.
2. Anchorage: A device generally used to enable the tendon to impart and maintain
prestress in concrete.
3. Pretensioning: A method of prestressing concrete in which the tendons are
tensioned before the concrete is placed. In this method, the concrete is introduced
by bond between steel & concrete.
4. Post-tensioning: A method of prestressing concrete by tensioning the tendons
against hardened concrete. In this method, the prestress is imparted to concrete by
bearing.
Materials for prestress concrete members:
1. Cement: The cement used should be any of the following
(a) Ordinary Portland cement.
(b) Rapid hardening Portland cement.
(c) High strength ordinary Portland cement.
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
2
2. Concrete: Prestress concrete requires concrete, which has a high compressive
strength reasonably early age with comparatively higher tensile strength than
ordinary concrete. Minimum cement content of 300 to 360 kg/m3
is prescribed for
the durability requirement.
The water content should be as low as possible.
3. Steel: High tensile steel, tendons, strands or cables.
High strength steel contains:
0.7 to 0.8% carbons,
0.6% manganese,
0.1% silica
Durability, Fire Resistance & Cover Requirements For P.S.C Members:
20 mm cover for pretensioned members
30 mm or size of the cable which ever is bigger for post tensioned members.
If the prestress members are exposed to an aggressive environment, these covers
are increased by another 10 mm.
Necessity of high grade of concrete & steel:
Higher the grade of concrete higher the bond strength which is vital in
pretensioned concrete, Also higher bearing strength which is vital in post-
tensioned concrete. Further creep & shrinkage losses are minimum with high-
grade concrete.
Generally minimum C30 grade concrete is used for post-tensioned & C40
grade concrete is used for pretensioned members.
The losses in prestress members due to various reasons are generally in the range of
250 N/mm2
to 400 N/mm2
. Hence high tensile steel wires are used which varies from
1600 to 2000 N/mm2
.
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
3
Classifications and Types:
Prestressed concrete structures can be classified in a number of ways depending
upon the feature of designs and constructions.
1. Pre-tensioning: In which the tendons are tensioned before the concrete is
placed, tendons are temporarily anchored and tensioned and the prestress is
transferred to the concrete after it is hardened.
2. Post-tensioning: In which the tendon is tensioned after concrete has hardened.
Tendons are placed in sheathing at suitable places in the member before casting
and later after hardening of concrete.
Prestressing Systems:
1. Pretensioning system:
In the pre-tensioning systems, the tendons are first tensioned between rigid
anchor-blocks cast on the ground or in a column or unit –mould types
pretensioning bed, prior to the casting of concrete in the mould. The tendons
comprising individual wires or strands are stretched with constant eccentricity
or a variable eccentricity with tendon anchorage at one end and jacks at the
other. With the forms in place, the concrete is cast around the stressed tendon.
The system is shown in Fig.1 below.
Fig. 1 Prestressing system
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
4
2. Post-tensioned system:
In post-tensioning the concrete unit are first cast by incorporating ducts or
grooves to house the tendons. When the concrete attains sufficient strength, the
high-tensile wires are tensioned by means of jack bearing on the end of the face
of the member and anchored by wedge or nuts. The forces are transmitted to the
concrete by means of end anchorage and, when the cable is curved, through the
radial pressure between the cable and the duct. The space between the tendons
and the duct is generally grouted after the tensioning operation.
Comparative Study: Pretension Vs Post-tensioned Member
Pretension member Post-tensioned member
1. In pretensioned prestress concrete,
steel is tensioned prior to that of concrete.
It is released once the concrete is placed
and hardened. The stresses are transferred
all along the wire by means of bond.
1. Concreting is done first then wires are
tensioned and anchored at ends. The
stress transfer is by end bearing not by
bond.
2. Suitable for short span and precast
products like sleepers, electric poles on
mass production.
2. Suitable for long span bridges
3. In pretensioning the cables are
basically straight and horizontal. Placing
them in curved or inclined position is
difficult. However the wire’s can be kept
with eccentrically. Since cables can not
be aligned similar to B.M.D. structural
advantages are less compare to that of
post-tensioned.
3. The post tensioning cables can be
aligned in any manner to suit the B.M.D
due to external load system. Therefore it
is more economical particularly for long
span bridges. The curved or inclined
cables can have vertical component at
ends. These components will reduce the
design shear force. Hence post-tensioned
beams are superior to pretensioned beams
both from flexural and shear resistances
point.
4. Prestress losses are more compare to
that of post-tensioned concrete.
4. Losses are less compare to pre-
tensioned concrete
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
5
Basic Concept of Pre-stressing
It’s well known that the concrete tensile strength varies from (8 to 14) percent of its
compressive strength. Due to this fact, flexural cracks develop at early stage of
loading. To solve such problem, the concept of pre-stress concrete was developed.
This concept is based on imposing a concentric or an eccentric compressive force in
the longitudinal direction of the structural element. This force will eliminate or
considerably reduce the tensile stresses at the critical sections (mid span and
supports), Figure below. Hence, the cracks will be prevented from developing.
[Nawy, 2003].
Concrete fibber stress distribution in a rectangular girder with straight tendon
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
6
The typical loading history and the corresponding stress distribution across the depth
of the critical section are shown in Figure below;
Load versus deformation (camber or deflection) was, schematically, plotted for
various loading stages due to self-weight effect up to rupture, see below;
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
7
A pre-stressed member, when compared with an equivalent reinforced concrete
member, requires less concrete, and about (1 5/ 𝑡𝑜 1/3) of the amount of reinforcing
steel. The depth of pre-stressed concrete members is usually less than the depth of
the reinforced concrete members for the same span length and loading conditions,
thereby the required casting concrete is less by about (20-25%) than in case of
reinforced concrete but the difference in initial cost is not proportional to the
difference in weight of materials. On the other hand, formwork or mould may be
more expensive, and the additional cost of the pre-stressing operation itself must be
considered. However, there is a little difference in the initial cost of reinforced and
pre-stress concrete, but the indirect savings ( long working live, avoidance of
maintenance, reduction of dead weight imposed on the supporting members … ext)
which accrue from the pre-stressing are often substantial and should be fully taken
into account.
Advantages of Prestressing
Prevents tension cracks under working loads to be used for water and oil tanks
and member subjected to corrosion conditions.
Smaller section will be required for design (the entire section remains
effective for stresses).
Larger span will be possible because of reduction in weight.
Deflection under working loads will be reduced (Cambering of the members).
Prestress reduces diagonal tension stresses at working loads. This led to use of
modified ( I and T sections).
Prestress concrete has more shear resistance, where as shear resistance of
R.C.C is less.
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
8
Analysis of Prestress Member
Basic assumptions
1. Concrete is a homogenous material.
2. Within the range of working stress, both concrete & steel behave elastically,
notwithstanding the small amount of creep, which occurs in both the materials
under the sustained loading.
3. A plane section before bending is assumed to remain plane even after bending,
which implies a linear strain distribution across the depth of the member.
Analysis of prestress member
The stress due to prestressing alone are generally combined stresses due to the action
of direct load bending from an eccentrically applied load. The following notations
and sign conventions are used for the analysis of prestress members.
P: Prestressing force (Negative when compressive). (N)
e: Eccentricity of prestressing force. (mm)
M = P.e : Moment. (N.mm)
A: Cross-sectional area of the concrete member. (mm2)
I: Second moment of area of the section about its centroid. (mm4)
St , Sb: Section modulus of the top & bottom fibre respectively. (mm3)
ftop , fbot: Prestress in concrete developed at the top & bottom fibres. (MPa)
ct, cb: Distance of the top & bottom fibre from the centroid of the section. (mm)
r: Radius of gyration. (mm)
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
9
(i) Concentric tendon
In this case, the load is applied concentrically and a compressive stress of
magnitude (P/A) will act through out the section. Thus the stress will generate in the
section as shown in the figure below.
Stress distribution for Concentric Prestressing
(ii) Eccentric tendon
Direct stress Bending stress Resultant stress
Stress distribution for Eccentric Prestressing
Thus the stresses developed at the top & bottom fibres of the beam can be
written as:
𝑓𝑡𝑜𝑝 = −𝑃
𝐴(1 −
𝑒 𝑐𝑡
𝑟2 ) 𝑓𝑏𝑜𝑡 = −𝑃
𝐴(1 +
𝑒 𝑐𝑏
𝑟2 )
S S
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
10
Flexural Analysis
Pi : Initial prestressing force. (N)
Pe : Effective prestressing force ( after all losses). (N)
f : Stress. (MPa)
Initial Pre-stressed
𝑓𝑖𝑡𝑜𝑝 = −𝑃𝑖
𝐴(1 −
𝑒 𝑐𝑡
𝑟2)
𝑓𝑖𝑏𝑜𝑡 = −𝑃𝑖
𝐴(1 +
𝑒 𝑐𝑏
𝑟2)
Applying Beam Self-weight
𝑓𝑖𝑡𝑜𝑝 = −𝑃𝑖
𝐴(1 −
𝑒 𝑐𝑡
𝑟2) −
𝑀𝑔 𝑐𝑡
𝐼
𝑓𝑖𝑏𝑜𝑡 = −𝑃𝑖
𝐴(1 +
𝑒 𝑐𝑏
𝑟2) +
𝑀𝑔 𝑐𝑏
𝐼
Applying Full Service Loads
𝑓𝑡𝑜𝑝 = −𝑃𝑒
𝐴(1 −
𝑒 𝑐𝑡
𝑟2) −
𝑀𝑔 𝑐𝑡
𝐼−
𝑀𝑠 𝑐𝑡
𝐼
𝑓𝑏𝑜𝑡 = −𝑃𝑒
𝐴(1 +
𝑒 𝑐𝑏
𝑟2) +
𝑀𝑔 𝑐𝑏
𝐼+
𝑀𝑠 𝑐𝑏
𝐼
Asp
e
ct
cb
-Pi/A +Pi.e ct /I
-Pi.e cb /I
−𝑃
𝐴(1 −
𝑒 𝑐𝑡
𝑟2)
−𝑃
𝐴(1 +
𝑒 𝑐𝑏
𝑟2)
-Mg.ct /I
-Mg.cb /I
-Ms.ct /I
-Ms.cb /I
f top
f bot
+ = + + =
Initially
Self wt. Service load
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
11
ACI-Allowable Stresses:
1. Immediately after Pre-stress Transfer;
(a) Ext. fiber stress in compression ………..................................................0.60fci
(b) Ext. fiber stress in compression at end of simply supported member …. 0.70fci
(c) Ext. fiber stress in Tension .......………...................................................0.25√fci
(d) Ext. fiber stress in Tension at end of simply supported member………...0.5√fci
2. At Service Loads
(a) Ext. fiber stress in compression …............0.45fc (Pre-stress+ Sustained load).
(b) Ext. fiber stress in compression …............0.6fc (Pre-stress+ Total load).
(c) Ext. fiber stress in Tension .......………......0.5√fc
3. Permissible Stress in Pre-stressing Tendons
(a) Due to jacking force …………..............................0.94fpy ≤ 0.80fpu
(b) After pre-stress transfer……….............................0.82fpy ≤ 0.74fpu
(c) Post tensioning tendons …………….….................0.7fpu
Example (1): For a simply supported symmetrically I-section beam with the
properties as follow:
I=5×109 mm4 , A=114000mm2 , r2=44000mm2 , h= 610mm , carries uniformly
distributed load (D+L) = 8 kN/m in additional to its own weight over on span length
of 12m, e=130mm , Pi=750kN , Pe=640kN.
Find the flexural stresses at mid-span and at ends due to initial prestress plus self wt.
and due to effective prestress plus full service load.
Solution:
Wg=A.γ = (114000×10-6
).24=2.7 kN/m
Mg=Wg.L2/8
=2.7× (12)2/8=48.6 kN.m
Mid-span stresses due to Initial prestressing and self-weight:
𝑓𝑖𝑡𝑜𝑝 = −𝑃𝑖
𝐴(1 −
𝑒 𝑐𝑡
𝑟2) −
𝑀𝑔 𝑐𝑡
𝐼
= −750000
114000(1 −
130 × 305
44000) −
48.6 × 106 × 305
5 × 109= −0.65 − 2.96 = −3.61 𝑀𝑃𝑎
𝑓𝑖𝑏𝑜𝑡 = −750000
114000(1 +
130 × 305
44000) +
48.6 × 106 × 305
5 × 109= −12.51 + 2.96 = −9.55𝑀𝑃𝑎
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
12
Mid-span stresses after all losses and applying service loads:
Ms=Ws.L2/8
=8×122/8 = 144 kN.m
𝑓𝑡𝑜𝑝 = −𝑃𝑒
𝐴(1 −
𝑒 𝑐𝑡
𝑟2) −
𝑀𝑔 𝑐𝑡
𝐼−
𝑀𝑠 𝑐𝑡
𝐼
= −640000
114000(1 −
130 × 305
44000) −
48.6 × 106 × 305
5 × 109−
144 × 106 × 305
5 × 109
= −0.55 − 2.96 − 8.78 = −12.3 𝑀𝑃𝑎
𝑓𝑏𝑜𝑡 = −640000
114000(1 +
130 × 305
44000) +
48.6 × 106 × 305
5 × 109+
144 × 106 × 305
5 × 109
= −10.68 + 2.96 + 8.78 = 1.03 𝑀𝑃𝑎
At ends:
𝑓𝑖𝑡𝑜𝑝 = −0.65 𝑀𝑃𝑎 𝑓𝑖𝑏𝑜𝑡 = −12.51 𝑀𝑃𝑎
𝑓𝑡𝑜𝑝 = −0.55 𝑀𝑃𝑎 𝑓𝑏𝑜𝑡 = −10.68 𝑀𝑃𝑎
Example (2): For ex. (1) if fci=25MPa, and fc=35MPa. Check the resultant stress
with the ACI permissible stresses.
Solution:
At midspan stresses:
Initially 𝑓𝑖𝑡𝑜𝑝 = −3.61 𝑀𝑃𝑎 (𝐶𝑜𝑚𝑝. ) < 𝐴𝐶𝐼 𝑙𝑖𝑚𝑖𝑡 = 0.6 × 𝑓𝑐𝑖 = −15 𝑀𝑃𝑎 ∴ 𝑂𝐾
𝑓𝑖𝑏𝑜𝑡 = −9.55 𝑀𝑃𝑎 (𝐶𝑜𝑚𝑝. ) < 𝐴𝐶𝐼 𝑙𝑖𝑚𝑖𝑡 = 0.6 × 𝑓𝑐𝑖 = −15 𝑀𝑃𝑎 ∴ 𝑂𝐾
Finally 𝑓𝑡𝑜𝑝 = −12.3 𝑀𝑃𝑎 (𝐶𝑜𝑚𝑝. ) < 𝐴𝐶𝐼 𝑙𝑖𝑚𝑖𝑡 = 0.45 × 𝑓𝑐 = −15.75 𝑀𝑃𝑎 ∴ 𝑂𝐾
𝑓𝑏𝑜𝑡 = 1.03 𝑀𝑃𝑎 (𝑇𝑒𝑛𝑠. ) < 𝐴𝐶𝐼 𝑙𝑖𝑚𝑖𝑡 = 0.5 × √𝑓𝑐 = 2.96 𝑀𝑃𝑎 ∴ 𝑂𝐾
At ends: all stresses are OK with ACI limits.
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
13
Example (3): For ex. (1) calculate stresses at (14⁄ ) span and check them with ACI
limitations.
Example (4): If the tendon profile in ex.(1) is as shown below, calculate stresses at
midspan, at ends and at (14⁄ ) span. Then check the stresses with ACI limitations.
Example (5): For ex. (1), find Pi (Initial prestress force) such that the bottom fiber
stress is finally zero, (15% losses) and check other stresses with ACI limitations.
Example (6): A rectangular concrete beam of cross-section 300 mm deep and 200
mm wide is prestressed by means of 15 wires of 5 mm diameter located 65 mm from
the bottom of the beam and 3 wires of diameter of 5 mm, 25 mm from the top.
Assuming the prestress in the steel Pe =840 MPa, calculate the stresses at the
extreme fibers of the mid-span section when the beam is supporting its own weight
over a span of 6 m. If a uniformly distributed live load of 6kN/m is imposed,
evaluate the maximum working stress in concrete.
centroid tendon
50mm
150mm
12m
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
14
Solution:
Distance of the centroid of prestressing force from the base:
𝒚 = ((15 × 65) + (3 × 275)
18) = 100 𝑚𝑚
Eccentricity, e = 150-100= 50 mm
Prestressing force, P = (840×18×19.7) =3×105 N
Area of concrete section, A = (300 × 200) = 6×104
mm2
Second moment of area, I = 200×3003
/12 = 45×107
mm4
Section modulus (St & S
b) = (45×10
7
/150)=3×106
mm3
Reduce of gyration, r= 86.603 mm, r2=7500 mm
2
Self weight of the beam = (0.2×0.3×24) = 1.44kN/m
Moment due to self weight, Mg = 1.44×(6)2/8 = 6.48 kN.m
Moment due to service load Ms= 6×(6)2/8 = 27 kN.m
𝑓𝑡𝑜𝑝 = −𝑃𝑒
𝐴(1 −
𝑒 𝑐𝑡
𝑟2) −
𝑀𝑔 𝑐𝑡
𝐼−
𝑀𝑠 𝑐𝑡
𝐼
= −3 × 105
6 × 104(1 −
50 × 150
7500) −
6.48 × 106 × 150
45 × 107−
27 × 106 × 150
45 × 107
= −0 − 2.16 − 9 = −11.16 𝑀𝑃𝑎 (Comp.)
𝑓𝑏𝑜𝑡 = −𝑃𝑒
𝐴(1 +
𝑒 𝑐𝑡
𝑟2) +
𝑀𝑔 𝑐𝑡
𝐼+
𝑀𝑠 𝑐𝑡
𝐼
= −10 + 2.16 + 9 = 1.16 𝑀𝑃𝑎 (𝑇𝑒𝑛𝑠. )
+ + + = = _
_
+
_
_ _ _
+ + +
5
5
5
5
0
10 2.16
2.16 9
9
11.16
1.16
Prestress Self wt. Service load Resultant
stress
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
15
Losses in Prestress
The initial prestressing concrete undergoes a gradual reduction with time from the
stages of transfer due to various causes. This is generally defined as total “Loss of
Prestress”. The various losses are explained below:
Types of losses in prestress:
Pretensioning
1. Elastic shortening of concrete (ES).
2. Creep of concrete (CR).
3. Shrinkage of concrete (SH).
4. Relaxation of stress in steel (RE).
Post-tensioning
1. No loss due to elastic shortening if all wires are simultaneously tensioned. If
the wires are successively tensioned, there will be loss of prestress due to
elastic shortening of concrete.
2. Creep of concrete.
3. Shrinkage of concrete.
4. Relaxation of stress in steel.
5. Friction.
6. Anchorage slip (ANC).
1. Loss due to elastic shortening of the concrete
As the prestress force is transferred to concrete, the member shortens and the
prestress steel shortens with it. Hence there is a loss of prestress. The loss of
prestress due to deformation of concrete depends on the modular ratio & the average
stress in concrete at the level of steel, then:
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
16
𝑓𝑐𝑖𝑟 =𝑃𝑖
𝐴+
𝑃𝑖 . 𝑒2
𝐼−
𝑀𝑔. 𝑒
𝐼
𝐸𝑆 = 𝐾𝑒𝑠. 𝐸𝑠.𝑓𝑐𝑖𝑟
𝐸𝑐𝑖
Where:
𝑓𝑐𝑖𝑟: 𝑇ℎ𝑒 𝑠𝑡𝑟𝑒𝑠𝑠 𝑖𝑛 𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒 𝑎𝑡 𝑠𝑡𝑒𝑒𝑙 𝑙𝑒𝑣𝑒𝑙.
𝐾𝑒𝑠 = 1.0 𝑓𝑜𝑟 𝑝𝑟𝑒𝑡𝑒𝑛𝑠𝑖𝑜𝑛𝑒𝑑 𝑚𝑒𝑚𝑏𝑒𝑟.
𝐾𝑒𝑠 = 0.5 𝑓𝑜𝑟 𝑝𝑜𝑠𝑡𝑒𝑛𝑠𝑖𝑜𝑛𝑒𝑑 𝑚𝑒𝑚𝑏𝑒𝑟.
𝐸𝑐𝑖: 𝑀𝑜𝑑𝑢𝑙𝑢𝑠 𝑜𝑓 𝑒𝑙𝑎𝑠𝑡𝑖𝑐𝑖𝑡𝑦 𝑜𝑓 𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒.
𝐸𝑠: 𝑀𝑜𝑑𝑢𝑙𝑢𝑠 𝑜𝑓 𝑒𝑙𝑎𝑠𝑡𝑖𝑐𝑖𝑡𝑦 𝑜𝑓 𝑠𝑡𝑒𝑒𝑙.
If the initial stress in steel is known, the percentage loss of stress in steel due to
elastic deformation of concrete can be computed.
Example (1): (Elastic deformation)
A pre-stressed concrete beam of 8m length, 100 mm wide and 300 mm deep, is pre-
tensioned by straight, wires carrying an initial force of 150kN at an eccentricity of
50 mm. The modulus of elasticity of steel and concrete are 210000 and 35000
N/mm2
respectively. Estimate the percentage loss of stress in steel due to elastic
deformation of concrete if the area of steel wires is 188 mm2
.
Solution:
Wg=A.γ = (0.1×0.3).24=0.72 kN/m
Mg=wg.L2/8
=0.72× (8)2/8=5.76 kN.m
I=100×(300)3/12=225×10
6 mm
4 , 𝑓𝑝𝑖 =
150×103
188= 800 𝑀𝑃𝑎
𝑓𝑐𝑖𝑟 =150000
100 × 300+
150000 × 502
225 × 106−
5.76 × 106 × 50
225 × 106= 5.39 𝑀𝑃𝑎
𝐸𝑆 = 𝐾𝑒𝑠 . 𝐸𝑠 .𝑓𝑐𝑖𝑟
𝐸𝑐𝑖
= 1 × 210000 ×5.39
35000= 32.34𝑀𝑃𝑎
∴ 𝑃𝑒𝑟𝑐𝑒𝑛𝑡𝑎𝑔𝑒 𝑙𝑜𝑠𝑠 𝑜𝑓 𝑠𝑡𝑟𝑒𝑠𝑠 𝑖𝑛 𝑠𝑡𝑒𝑒𝑙 =32.34
800× 100 = 4%
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
17
2. Loss due to creep of concrete
The sustained prestress in the concrete of a prestress member results in creep of
concrete which is effectively reduces the stress in high tensile steel. The loss of
stress in steel due to creep of concrete can be estimated if the magnitude of creep-
coefficient is known, then:
𝐶𝑅 = 𝐾𝑐𝑟 .𝐸𝑠
𝐸𝑐. (𝑓𝑐𝑖𝑟 − 𝑓𝑐𝑑𝑠)
Where:
𝐾𝑐𝑟 = 2.0 𝑓𝑜𝑟 𝑝𝑟𝑒𝑡𝑒𝑛𝑠𝑖𝑜𝑛𝑒𝑑 𝑚𝑒𝑚𝑏𝑒𝑟.
𝐾𝑐𝑟 = 1.6 𝑓𝑜𝑟 𝑝𝑜𝑠𝑡𝑒𝑛𝑠𝑖𝑜𝑛𝑒𝑑 𝑚𝑒𝑚𝑏𝑒𝑟.
𝑓𝑐𝑑𝑠: 𝑆𝑡𝑟𝑒𝑠𝑠 𝑖𝑛 𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒 𝑎𝑡 𝑐. 𝑔. 𝑠. 𝑑𝑢𝑒 𝑡𝑜 𝑠𝑢𝑝𝑒𝑟 − 𝑖𝑚𝑝𝑜𝑠𝑒𝑑 𝑑𝑒𝑎𝑑 𝑙𝑜𝑎𝑑𝑠 𝑎𝑝𝑝𝑙𝑖𝑒𝑑 𝑎𝑓𝑡𝑒𝑟
𝑝𝑟𝑒𝑠𝑡𝑟𝑒𝑠𝑠𝑖𝑛𝑔.
The magnitude of creep coefficient varies depending upon the humidity, concrete
quality, duration of applied loading and the age of concrete when loaded.
Example (2): (Creep)
A post-tension concrete beam, 8m length of a rectangular section, 100 mm wide and
300 mm deep, is pre-stressed by five wires of 7 mm diameter located at an
eccentricity of 50 mm, the initial stress in the wires being 1200 N/mm2
. The
modulus of elasticity of steel and concrete are 210000 and 35000 N/mm2
respectively Estimate the percentage loss of stress in steel due to creep of concrete, if
the beam carrying a dead load of 3kN/m.
Solution:
𝑃𝑖 = 38.5 × 5 × 1200 = 23.1 × 104𝑁
𝑓𝑐𝑖𝑟 =231000
100 × 300+
231000 × 502
225 × 106−
5.76 × 106 × 50
225 × 106= 9 𝑀𝑃𝑎
𝑀𝑑 = 3 ×82
8= 24 𝑘𝑁. 𝑚 𝑓𝑐𝑑𝑠 =
24×106×50
225×106= 5.33 𝑀𝑃𝑎
𝐶𝑅 = 1.6 ×210000
35000× (9 − 5.33) = 35.23 𝑀𝑃𝑎
∴ 𝑃𝑒𝑟𝑐𝑒𝑛𝑡𝑎𝑔𝑒 𝑙𝑜𝑠𝑠 𝑜𝑓 𝑠𝑡𝑟𝑒𝑠𝑠 𝑖𝑛 𝑠𝑡𝑒𝑒𝑙 =35.23
1200× 100 = 2.94%
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
18
3. Loss due to shrinkage of concrete
Factors affecting the shrinkage in concrete:
1. The loss due to shrinkage of concrete results in shortening of tensioned wires &
hence contributes to the loss of stress.
2. The shrinkage of concrete is influenced by the type of cement, aggregate & the
method of curing used.
3. Use of high strength concrete with low water cement ratio results in reduction in
shrinkage and consequent loss of prestress.
4. The primary cause of drying shrinkage is the progressive loss of water from
concrete.
5. The rate of shrinkage is higher at the surface of the member.
6. The differential shrinkage between the interior surfaces of large member may
result in strain gradients leading to surface cracking.
Hence, proper curing is essential to prevent cracks due to shrinkage in prestress
members. In the case of pretensioned members, generally moist curing is restored in
order to prevent shrinkage until the time of transfer. Consequently, the total residual
shrinkage strain will be larger in pretensioned members after transfer of prestress in
comparison with post-tensioned members, where a portion of shrinkage will have
already taken place by the time of transfer of stress. The loss of prestress due to
shrinkage of concrete can be obtained as follow:
𝑆𝐻 = 8.2 × 10−6𝐾𝑠ℎ . 𝐸𝑠 . (1 −0.06
25
𝑉
𝑆) . (100 − 𝑅𝐻)
Where : 𝑅𝐻: 𝑟𝑒𝑙𝑎𝑡𝑖𝑣𝑒 ℎ𝑢𝑚𝑖𝑑𝑖𝑡𝑦
𝑉
𝑆: 𝑣𝑜𝑙𝑢𝑚𝑒 𝑡𝑜 𝑠𝑢𝑟𝑓𝑎𝑐𝑒 𝑟𝑎𝑡𝑖𝑜
𝐾𝑠ℎ = 1.0 𝑓𝑜𝑟 𝑝𝑟𝑒𝑡𝑒𝑛𝑠𝑖𝑜𝑛 𝑚𝑒𝑚𝑏𝑒𝑟, 𝑓𝑜𝑟 𝑝𝑜𝑠𝑡𝑡𝑒𝑛𝑠𝑖𝑜𝑛 𝑚𝑒𝑚𝑏𝑒𝑟 𝑠𝑒𝑒 𝑇𝑎𝑏𝑙𝑒 (1):
𝑻𝒂𝒃𝒍𝒆 (𝟏) 𝑉𝑎𝑙𝑢𝑒𝑠 𝑜𝑓𝐾𝑠ℎ 𝑓𝑜𝑟 𝑝𝑜𝑠𝑡𝑡𝑒𝑛𝑠𝑖𝑜𝑛 𝑚𝑒𝑚𝑏𝑒𝑟
Time after curing to post-
tensioning (days) 1 3 5 7 10 20 30 60
Kes 0.92 0.85 0.8 0.77 0.73 0.64 0.58 0.45
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
19
Example (3): (Shrinkage)
A concrete beam of a rectangular section, 100 mm wide and 300 mm deep is pre-
stressed by a cable carrying an initial pre-stressing force of 300kN. The cross-
sectional area of the cable is 300 mm2
. Calculate the percentage loss of stress in the
cable due to shrinkage of concrete, RH=75%. Assuming the beam to be, (a) pre-
tensioned and (b) post-tensioned.
Assume Es =210 kN/mm
2
, age of concrete at transfer force is 14 days after curing.
Solution:
𝑉
𝑆=
𝐴. 𝐿
𝑃𝑒𝑟𝑚. 𝐿=
𝐴
𝑃𝑒𝑟𝑚.=
100 × 300
2 × (100 + 300)= 37.5 𝑚𝑚
For pre-tension beam:
𝑆𝐻 = 8.2 × 10−6𝐾𝑠ℎ . 𝐸𝑠 . (1 −0.06
25
𝑉
𝑆) . (100 − 𝑅𝐻)
𝑆𝐻 = 8.2 × 10−6 × 1 × 210000 (1 −0.06
25× 37.5) × (100 − 75)
= 39.18 𝑀𝑃𝑎
𝑓𝑝𝑖 =300 × 103
300= 1000 𝑁
∴ 𝑃𝑒𝑟𝑐𝑒𝑛𝑡𝑎𝑔𝑒 𝑙𝑜𝑠𝑠 𝑜𝑓 𝑠𝑡𝑟𝑒𝑠𝑠 𝑖𝑛 𝑠𝑡𝑒𝑒𝑙 =39.18
1000× 100 = 3.92%
For post-tension beam:
Ksh from Table (1) by interpolation=0.694
𝑆𝐻 = 8.2 × 10−6 × 0.694 × 210000 (1 −0.06
25× 37.5) × (100 − 75)
= 27.19 𝑀𝑃𝑎
∴ 𝑃𝑒𝑟𝑐𝑒𝑛𝑡𝑎𝑔𝑒 𝑙𝑜𝑠𝑠 𝑜𝑓 𝑠𝑡𝑟𝑒𝑠𝑠 𝑖𝑛 𝑠𝑡𝑒𝑒𝑙 =27.19
1000× 100 = 2.72%
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
20
4. Loss due to relaxation of stress in steel
Relaxation of a prestressing tendon depends upon the stress level in the tendon.
Basic relaxation values Kre for different kinds of steel are shown in Table (2).
However, because of other prestress losses, there is a continual reduction in
relaxation. The reduction in tendon stress due to elastic shortening of concrete
occurs instantaneously. On the other hand, the reduction of concrete due to creep and
shrinkage takes place in a prolonged period of time. The factor J in equation below
is specified to approximate these effects, then:
𝑅𝐸 = [𝐾𝑟𝑒 − 𝐽(𝑆𝐻 + 𝐶𝑅 + 𝐸𝑆)]𝐶
Where: Kre, J and C are taken from Tables 2 &3.
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
21
5. Loss of stress due to friction
For post-tensioned member friction against the wall of duct result in prestress loss
increases with distance from the jack. The magnitude of loss of stress due to friction
is of following types:
a. Loss due to curvature effect, which depends upon the tendon form or
alignment, which generally follows a curved profile along the length of the
beam.
b. Loss of stress due to wobble effect, which depends upon the local deviations in
the alignment of the cable. The wobble or wave effect is the result of
accidental or unavoidable misalignment, since ducts or sheaths cannot be
perfectly located to follow a predetermined profile throughout the length of
beam.
𝑃𝑥 = 𝑃𝑖. 𝑒−(𝜇𝛼+𝑘𝑥)
or 𝑃𝑥 = 𝑃𝑖. [1 − 𝜇𝛼 − 𝑘𝑥]
where:
𝑃𝑥: 𝑝𝑟𝑒𝑠𝑡𝑟𝑒𝑠𝑠𝑖𝑛𝑔 𝑓𝑜𝑟𝑐𝑒 𝑎𝑡 𝑑𝑖𝑠𝑡𝑎𝑛𝑐𝑒 𝑥 𝑓𝑟𝑜𝑚 𝑒𝑛𝑑
𝑃𝑖: 𝑝𝑟𝑒𝑠𝑡𝑟𝑒𝑠𝑠𝑖𝑛𝑔 𝑓𝑜𝑟𝑐𝑒 𝑎𝑡 𝑡ℎ𝑒 𝑗𝑎𝑐𝑘𝑖𝑛𝑔 𝑒𝑛𝑑
𝜇: 𝑐𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 𝑜𝑓 𝑓𝑟𝑖𝑐𝑡𝑖𝑜𝑛 𝑏𝑒𝑡𝑤𝑒𝑒𝑛 𝑐𝑎𝑏𝑙𝑒 & 𝑑𝑢𝑐𝑡 (𝑐𝑢𝑟𝑣𝑎𝑡𝑢𝑟𝑒 𝑐𝑜𝑒𝑓𝑓. )𝑇𝑎𝑏𝑙𝑒 (4)
𝑘: 𝑓𝑟𝑖𝑐𝑡𝑖𝑜𝑛 𝑐𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 𝑓𝑜𝑟 𝑤𝑎𝑣𝑒 𝑒𝑓𝑓𝑒𝑐𝑡 (𝑤𝑜𝑏𝑏𝑙𝑒 𝑐𝑜𝑒𝑓𝑓. )𝑇𝑎𝑏𝑙𝑒 (4)
𝛼: 𝑐𝑢𝑚𝑢𝑙𝑎𝑡𝑖𝑣𝑒 𝑎𝑛𝑔𝑙𝑒 𝑖𝑛 𝑟𝑎𝑑𝑖𝑎𝑛 𝑡ℎ𝑟𝑜𝑢𝑔 𝑡ℎ𝑒 𝑡𝑎𝑛𝑔𝑒𝑛𝑡 𝑡𝑜 𝑡ℎ𝑒 𝑐𝑎𝑏𝑙𝑒 𝑝𝑟𝑜𝑓𝑖𝑙𝑒 ℎ𝑎𝑠
𝑡𝑢𝑟𝑛𝑒𝑑 𝑏𝑒𝑡𝑤𝑒𝑒𝑛 𝑎𝑛𝑦 𝑡𝑤𝑜 𝑝𝑜𝑖𝑛𝑡𝑠 𝑢𝑛𝑑𝑒𝑟 𝑐𝑜𝑛𝑠𝑖𝑑𝑒𝑟𝑎𝑡𝑖𝑜𝑛
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
22
Table (4) Friction Coefficients for Posttensioning Tendons
Type of Tendon Wobble Coeff. (k) per
meter
Curvature Coeff. (μ)
Tendons in flexible metal
sheathing:
Wire tendons
7-wire strands
High strength bars
0.0033-0.0049
0.0016-0.0066
0.0003-0.0020
0.15-0.25
0.15-0.25
0.08-0.30
Tendons in rigid metal
duct
7-wire strand
0.0007
0.15-0.25
Pregreased tendons
Wire tendon and
7-wire strand
0.001-0.0066
0.05-0.15
Mastic-coated tendons
Wire tendon and
7-wire strand
0.0033-0.0066
0.05-0.15
Example (4): (Friction)
A concrete beam of 10 m span, 100 mm wide and 300 mm deep, is pre-stressed by 3
cables type (7-wire strand in flexible metal sheathing). The area of each cable is 200
mm2
and the initial stress in the cable is 1200 N/mm2
. Cable 1 is parabolic with an
eccentricity of 50 mm above the centroid at the supports and 50 mm below at the
center of span. Cable 2 is also parabolic with zero eccentricity at supports and 50
mm below the centroid at the center of span. Cable 3 is straight with uniform
eccentricity of 50 mm below the centroid. If the cables are tensioned from one end,
estimate the percentage loss of stress in each cable due to friction.
30
0m
m
100mm 10 m
1
2
3
50mm
50mm e=50mm
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
23
Solution:
Equation of parabola is given by: 𝑦 =4𝑒
𝐿2 (𝐿 − 𝑥)
Slope at ends at (𝑥)=0 𝑑𝑦
𝑑𝑥⁄ =
4𝑒
𝐿2(𝐿 − 2𝑥) =
4𝑒
𝐿
For cable 1
𝑒 = 100 𝑚𝑚
𝑠𝑙𝑜𝑝𝑒 𝑎𝑡 𝑒𝑛𝑑𝑠 =4 × 100
10000= 0.04
∴ 𝑐𝑢𝑚𝑢𝑙𝑎𝑡𝑖𝑣𝑒 𝑎𝑛𝑔𝑙𝑒 𝑏𝑒𝑡𝑤𝑒𝑒𝑛 𝑡𝑎𝑛𝑔𝑒𝑛𝑡𝑠, 𝛼 = 2 × 0.04 = 0.08 𝑟𝑎𝑑
For cable 2
𝑒 = 50 𝑚𝑚
𝑠𝑙𝑜𝑝𝑒 𝑎𝑡 𝑒𝑛𝑑𝑠 =4 × 50
10000= 0.02
∴ 𝑐𝑢𝑚𝑢𝑙𝑎𝑡𝑖𝑣𝑒 𝑎𝑛𝑔𝑙𝑒 𝑏𝑒𝑡𝑤𝑒𝑒𝑛 𝑡𝑎𝑛𝑔𝑒𝑛𝑡𝑠, 𝛼 = 2 × 0.02 = 0.04 𝑟𝑎𝑑
Initial pre-stressing force in each cable 𝑃𝑖 = 1200 × 200 = 240000 𝑁
𝑃𝑥 = 𝑃𝑖. 𝑒−(𝜇𝛼+𝑘𝑥) 𝑓𝑜𝑟 𝑠𝑚𝑎𝑙𝑙 𝑣𝑎𝑙𝑢𝑒𝑠 𝑜𝑓(𝜇𝛼 + 𝑘𝑥)𝑤𝑒 𝑐𝑎𝑛 𝑤𝑟𝑖𝑡𝑒:
𝑃𝑥 = 𝑃𝑖. [1 − (𝜇𝛼 + 𝑘𝑥)]
𝜇 = 0.2 , 𝑘 = 0.0041/𝑚 From Table (4)
∴ 𝐿𝑜𝑠𝑠 𝑜𝑓 𝑝𝑟𝑒𝑠𝑡𝑟𝑒𝑠𝑠, 𝑃𝑥 = 𝑃𝑖. [𝜇𝛼 + 𝑘𝑥]
𝐶𝑎𝑏𝑙𝑒 1 = 1200. [0.2 × 0.08 + 0.0041 × 10] = 68.4 𝑀𝑃𝑎 = 5.7%
𝐶𝑎𝑏𝑙𝑒 2 = 1200. [0.2 × 0.04 + 0.0041 × 10] = 58.8 𝑀𝑃𝑎 = 4.9%
𝐶𝑎𝑏𝑙𝑒 3 = 1200. [0 + 0.0041 × 10] = 49.2 𝑀𝑃𝑎 = 4.1%
∴ 𝑇𝑜𝑡𝑎𝑙 𝐿𝑜𝑠𝑠 𝑜𝑓 𝑝𝑟𝑒𝑠𝑡𝑟𝑒𝑠𝑠 𝑑𝑢𝑒 𝑡𝑜 𝑓𝑟𝑖𝑐𝑡𝑖𝑜𝑛 = 5.7 + 4.9 + 4.1 = 14.7%
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
24
6. Loss due to Anchorage slip (ANC)
For the posttensioned member due to the deformation of anchorage fixtures at
transfer of prestress, the magnitude of loss of stress due to the slip in anchorage is
computed as follows:
∆=𝑃𝐿
𝐴𝐸𝑠
Where:
∆: 𝑠𝑙𝑖𝑝 𝑖𝑛 𝑎𝑛𝑐ℎ𝑜𝑟𝑎𝑔𝑒, 𝑚𝑚
𝑃: 𝑃𝑟𝑒𝑠𝑡𝑟𝑒𝑠𝑠 𝑓𝑜𝑟𝑐𝑒 𝑖𝑛 𝑡ℎ𝑒 𝑐𝑎𝑏𝑙𝑒, 𝑁
𝐿: 𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑐𝑎𝑏𝑙𝑒, 𝑚𝑚
𝐴: 𝐶𝑟𝑜𝑠𝑠 𝑠𝑒𝑐𝑡𝑖𝑜𝑛𝑎𝑙 𝑎𝑟𝑒𝑎 𝑜𝑓 𝑡ℎ𝑒 𝑐𝑎𝑏𝑙𝑒, 𝑚𝑚2
𝐸𝑠: 𝑀𝑜𝑑𝑢𝑙𝑢𝑠𝑒 𝑜𝑓 𝑒𝑙𝑎𝑠𝑡𝑖𝑐𝑖𝑡𝑦 𝑜𝑓 𝑠𝑡𝑒𝑒𝑙, 𝑁/𝑚𝑚2
Hence, Loss of stress due to anchorage slip =𝑃
𝐴=
𝐸𝑠∆
𝐿
Example (5): (Anchorage slip)
A concrete beam is post-tensioned by a cable carrying an initial stress of 1000
N/mm2
. The slip at the jacking end was observed to be 5 mm. The modulus of
elasticity of steel is 210 kN/mm2
. Estimate the percentage loss of stress due to
anchorage slip if the length of the beam is 30 m.
Solution:
∴ 𝑙𝑜𝑠𝑠 𝑜𝑓 𝑠𝑡𝑟𝑒𝑠𝑠 𝑑𝑢𝑒 𝑡𝑜 𝑎𝑛𝑐ℎ𝑜𝑟𝑜𝑔𝑒 𝑠𝑙𝑖𝑝 =𝐸𝑠 . ∆
𝐿
=210000 × 5
30000= 35 𝑀𝑃𝑎
∴ 𝑃𝑒𝑟𝑐𝑒𝑛𝑡𝑎𝑔𝑒 𝑙𝑜𝑠𝑠 𝑜𝑓 𝑠𝑡𝑟𝑒𝑠𝑠 =35
1000100 = 3.5 %
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
25
Limiting Maximum Loss
ACI- ACSE Committee recommended the following max. loss estimates
Type of strand Max. loss (MPa)
Stress-relived strand 345
Low-relaxation strand 275
Example (6): For the pre-tensioned beam over a simply supported condition of 20m
length as shown in the figure below and its carrying a service dead load of 7.6 kN/m
and a service live load of 7 kN/m applied at 30 days, fpi=0.75fpu , where
fpu=1860MPa, fci=31 MPa, fc=41MPa, r.h=75%, 12.7mm dia of stress-relived
strands. Es=200000 MPa. Estimate all pre-stress losses.
Solution:
A=286×103 mm
2
I=3.39×1010
mm4
wg=286×103×10
-6×24=6.86 kN/m Mg=6.86×20
2/8=343 kN.m
(1) 𝐸𝑆 = 𝐾𝑒𝑠. 𝐸𝑠.𝑓𝑐𝑖𝑟
𝐸𝑐𝑖
Pi=0.75×1860×1980=2.762×106 N
𝑓𝑐𝑖𝑟 =2.762×106
286×103+
2.762×106×3552
3.39×1010−
343×106×355
3.39×1010= 16.34 𝑀𝑃𝑎
𝐸𝑆 = 1 × 200000 ×16.34
4700√31= 124.9 𝑀𝑃𝑎
650 mm 150 mm
145 mm
175 mm
550 mm
175 mm
Aps=1980 mm2
REINFORCED CONCRETE DESIGN (II) Dr. Hussain A. Jabir
26
(2) 𝐶𝑅 = 𝐾𝑐𝑟 .𝐸𝑠
𝐸𝑐. (𝑓𝑐𝑖𝑟 − 𝑓𝑐𝑑𝑠)
𝑀𝑑 = 7.6 ×202
8= 380𝑘𝑁. 𝑚 𝑓𝑐𝑑𝑠 =
380×106×355
3.39×1010= 3.98 𝑀𝑃𝑎
𝐶𝑅 = 2.0 ×.200000
4700√41× (16.34 − 3.98) = 164.3 𝑀𝑃𝑎
(3) 𝑆𝐻 = 8.2 × 10−6𝐾𝑠ℎ . 𝐸𝑠 . (1 −0.06
25
𝑉
𝑆) . (100 − 𝑅𝐻)
= 8.2 × 10−61 × 200000 × (1 −0.06
25×
286000
3900) . (100 − 75)
= 33.8 𝑀𝑃𝑎
(4) 𝑅𝐸 = [𝐾𝑟𝑒 − 𝐽(𝑆𝐻 + 𝐶𝑅 + 𝐸𝑆)]𝐶
Kre=138, J=0.15 and C=1.45 from Tables 2&3
𝑅𝐸 = [138 − 0.15(33.8 + 164.3 + 124.9)]1.45
𝑅𝐸 = 129.8 𝑀𝑃𝑎
∴ 𝑇𝑜𝑡𝑎𝑙 𝑙𝑜𝑠𝑠𝑒𝑠 = 124.9 + 164.3 + 33.8 + 129.8 = 452.8 𝑀𝑃𝑎 > 345𝑀𝑃𝑎 ∴ 𝑁𝑜𝑡 𝑂𝐾