regulate uncontrolled behaviour during the construction phase, … wef draft scoping... · 2017. 6....
TRANSCRIPT
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 167
regulate uncontrolled behaviour During the Construction Phase, no residence
may be set up on site During the Construction Phase, the appointed
ECO must inspect the construction area for evidence of snares
Loss of vegetation during
construction
Uncontrolled construction beyond the approved development footprint may result in inadvertent damage and could lead to permanent loss of vegetation
DIRECT CUMULATIVE
Localised Long-term Possible Severe HIGH During the Construction Phase, construction activities must be demarcated and vegetation clearing and top soil removal limited to these areas
During the Construction Phase no dense vegetation that resembles indigenous Thicket or Forest may be removed. If deemed unavoidable the appointed ECO must be consulted and an assessment of the vegetation must be undertaken
During the Construction Phase, existing farm tracks or access roads must be used as much as possible
LOW
Disturbance to surrounding
wildlife and fauna
The unregulated clearing of vegetation beyond the development footprint could result in disturbance of specialised faunal habitats and associated species (e.g. wetlands, forests, rocky outcrops, dense woody vegetation and riparian zones), resulting in reduced faunal populations
DIRECT Localised Long-term Possible Severe HIGH No construction, unless authorised by an independent ECO, may be undertaken in an area demarcated in this report as a sensitive area, or its associated buffer
Construction activities must be limited to delineated development areas
LOW
Disturbance of sensitive areas
Uncontrolled construction activities and irresponsible construction of access roads and powerlines routes may contribute to erosion and degradation of water-courses and associated riparian habitats, resulting in permanent habitat degradation
DIRECT Localised and downst
ream
Short to medium term
Possible Severe HIGH Construction through water courses, only where necessary, must occur within the smallest possible construction footprint, preferably during the dry season, and must be immediately followed by erosion stabilisation and re-vegetation (Refer Wetland Impact Assessment). Applicable Water Use Licences must be obtained prior to construction.
MODERATE
WETLAND IMPACT ASSESSMENT
Physical destruction of aquatic habitat
Removal of aquatic habitats due to road construction or installation of powerlines
DIRECT Localised Long-term/ Permanent
Definite Moderately Severe HIGH Existing tracks must be used as far as possible during construction
An ECO must be appointed during the construction phase in order to ensure that unnecessary disturbance to the surrounding environment does not occur.
LOW
Unnecessary loss of species of special concern during construction activities, beyond the construction site.
DIRECT Localised Medium-term Possible Moderately Severe MODERATE A search and rescue must be undertaken prior to construction to ensure that any species of special concern are documented and, where possible, relocated.
LOW
Alteration of the environmental
beyond the development
footprint
Inadvertent or excessive damage and loss of aquatic habitats beyond the development footprint.
DIRECT Localised Short-term Possible Moderately Severe MODERATE Construction activities must be demarcated and vegetation clearing and topsoil removal limited to these areas.
LOW
During the construction of roads, cabling, substation and turbines topsoil clearing, soil storage and soil exposure may result in soil destabilisation and severe soil erosion, locally as well as downstream of construction activities.
DIRECT CUMULATIVE
Regional Long-term Possible Severe HIGH A Stormwater Management Plan must be implemented during the construction phase
Ensure that roads on slopes incorporate storm water retention.
LOW
Loss of wetland Removal of aquatic habitats due to DIRECT Localised Long-term - Definite Moderately Severe HIGH Existing tracks must be used as far as possible LOW
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 168
habitat, ecosystem
services and biodiversity
services due to road construction or installation of
cabling and substation
road construction or installation of cabling and substation.
Permanent during construction An ECO must be appointed during the
construction phase in order to ensure that unnecessary disturbance to the surrounding environment does not occur.
Unnecessary loss of species of special concern during construction activities, beyond the construction site.
DIRECT Localised Medium-term Possible Moderately Severe MODERATE The project sites must be surveyed prior to construction in order to determine whether any flora or fauna of special concern are in the aquatic environment.
LOW
AVIFAUNAL IMPACT ASSESSMENT
Disturbance: WEF The displacement of priority avifauna through the disturbance caused construction activities.
INDIRECT Short-term Project level Probable Moderately Severe MODERATE Construction activity should be restricted to the immediate footprint of the infrastructure, and in particular to the proposed road network. Access to the remainder of the site should be strictly controlled to prevent unnecessary disturbance of priority species.
LOW
Habitat destruction: WEF
The displacement of priority avifauna through habitat destruction during the clearing of turbine platforms in the construction phase.
DIRECT Long-term Project level Possible Moderately Severe MODERATE Removal of natural vegetation must be restricted to a minimum.
Vegetation must be rehabilitated to its former state where possible after construction.
Construction of new roads should only be considered if existing roads cannot be upgraded.
LOW
BAT IMPACT ASSESSMENT
No impacts identified by specialist
PALEONTOLOGICAL IMPACT ASSESSMENT
Destruction of underlying fossils
Underlying fossils destroyed during the excavation phase of turbines construction due to inadequate knowledge of the underlying sediments.
DIRECT Short-term Localised Possible Moderate HIGH The RE and ECO must be made aware of the possibility of the possibility of finding fossils in the Vryheid and Volksrust Formation sediments during excavation of the foundations for the turbines and other infrastructure
A professional palaeontologist must be appointed to monitor possible paleontological findings during the excavation of turbine foundations and infrastructure where turbine positions and infrastructure fall on Vryheid and Volksrust Formation sediments.
LOW
HERITAGE IMPACT ASSESSMENT
Houses and farm walls
All built structures older than 60 years in ages are protected by the KZNHA, damage to these structures will be detrimental to the history of the WEF area
DIRECT CUMULATIVE
Permanent Localised Possible Severe HIGH All houses and walling within 50m of the turbine footprints must be demarcated before any construction activities takes place in the area.
No infrastructure may occur within 20m of walling.
The final layout must be assessed at a desktop level to determine whether or not onsite monitoring will be necessary during the construction phase.
Access roads must be rerouted away from farm buildings.
LOW
Late Iron Age / Historical Period
settlements
Late Iron Age and Historical Period settlements, and walling are protected by the KZNHA. Many of these sites have archaeological deposits, human graves, and other subsurface features which could be lost or damaged during the construction phase.
DIRECT Permanent Localised Possible Severe HIGH All identified sites (see specialist report) must be monitored by an archaeologist during the construction phase.
LOW
Battlefield History On-site areas which form part of the battle site history may be damaged by deviations outside of the current
DIRECT CUMULATIVE
Permanent Localised Possible Severe HIGH Any deviation to the development footprint must to be assessed by an archaeologist.
Relevant sites identified by said archaeologist
LOW
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 169
planned construction areas. will require a metal detector survey. Powerline alternative 1 will require a metal
detector survey by an archaeologist prior to construction.
SOCIO-ECONOMIC IMPACT ASSESSMENT
Construction and upgrading of
roads
An influx of people into the Utrecht area and the expansion of hamlets could cause social pressures in terms of health.
INDIRECT CUMULATIVE
Short-term Localised Probable Very severe HIGH All the project employees should be subject to a health and HIV/AIDS awareness educational programme;
The proponent could initiate programmes aimed at upgrading or lending support to local facilities, e.g. clinics and police stations. Alternatively, the proponent could assist with initiating programmes aimed at encouraging voluntary workers to patrol particular areas (especially during the construction period).
Changes in crime patterns will need to be monitored in consultation with the local police and community policing forums (if these exist);
Specifically for influx management, the consultant recommends that the proponent develops transparent Human Resources (HR) policies and procedures. Such procedures could include a Preferential Procurement Policy in favour of employing the current residents in local communities within 50km of the site such as the Waaihoek Community Trust;
The proponent should develop a Recruitment and Influx Management Plan.
The proponent should develop a Stakeholder Engagement Plan (SEP) which incorporates developing collaborative management strategies for in-migration;
School programmes could be supported or initiated aimed at educating children from an early age about the effects and consequences of crime and social pathologies;
Community out-reach programmes could be supported or initiated to deal with issues related to unsafe sexual practices, sex work, teenage pregnancies and sexual violence; and
Particular roads should be fenced and access to particular road networks should be monitored and controlled. Gates should be considered for particular road networks, and particular access routes should be denied for unauthorised individuals or cars.
LOW
An increase in subsistence farmers adding pressure to the surrounding landscape
INDIRECT CUMULATIVE
Short-term Study Area May Occur Severe MODERATE LOW
Easing unrestricted access to farm roads could lead to an increase in crime (such as stock theft) on farms.
DIRECT Long-term Study Area Probable Very Severe HIGH MODERATE
An increase in crime related to the influx of people in the area
INDIRECT Long-term Localised Probable Very Severe HIGH MODERATE
Health and safety Risk of aircraft collisions with turbines leading to mortalities
DIRECT Long-term Study Area Unlikely Very Severe HIGH The turbines should be accurately positioned to reduce any effects of possible malfunctioning;
If complaints are received, the proponent must investigate and mitigate these issues.
The proponent must follow the manufacturer’s recommendations on frequency and detail of maintenance on the turbine structures to minimise the risk of malfunction;
A Blade Monitoring System must be standard in the turbine technology used in the project;
The proponent should establish safety setbacks, and design the facility in such a manner that no buildings or populated areas lie within the
LOW
Turbine malfunctioning (e.g. blade throw and gearbox failure) could cause safety risks to people onsite.
DIRECT Medium-term Localised Unlikely Severe LOW LOW
Electromagnetic interference leading to communication problems.
DIRECT Medium-term Localised Unlikely Slight LOW LOW
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 170
possible trajectory range of turbine blades; The developer must equip wind turbines with
vibration sensors that can react to any imbalance in the rotor blades and shut down the turbine if necessary;
Regular maintenance work on the turbines is necessary; and
The facility should have warning signs to alert the public of risk.
Increased traffic and related security and safety risks
INDIRECT Short-term Localised Probable Very Severe HIGH Farm-owners should always be consulted (and permission should be given by owners where relevant) prior to the construction or upgrading of any road(s);
Fencing along the access routes should be considered, as well as the construction of cattle grids at road crossings;
Gates should be erected at all the entrances to the WEF and traffic in and out of the project area monitored. This should be discussed with the affected owners;
Traffic calming measures should be implemented and speed limits need to be introduced and managed, especially during the construction period. Traffic should be controlled and regulated, and truck drivers need to be aware of safety regulations through regular briefings and workshops;
It is recommended that the proponent prepares and implements a Community Health and Safety Plan and policy. Such a plan/policy should include traffic safety rules, and would need to enforce particular guidelines, including those related to adequately fencing-off certain infrastructure. This plan should be communicated to all personnel, PAF residents and nearby affected PACs;
Particular criteria need to be developed for the recruitment of security personnel (for the construction phase);
When hiring security personnel, reasonable effort must be made to check whether the potential employees have criminal records or have been part of any other unscrupulous behaviour.
As far as possible, security personnel should be recruited from the surrounding communities. This should allow them to distinguish between the local population and outsiders;
Security personnel need to be properly trained in the use of force and, most importantly, appropriate conduct towards labourers, PAC members and farm-owners;
A code of conduct must be developed for the security personnel; and
All the PAC members and PAF-owners need to be informed about the roles and responsibilities of the security personnel.
LOW
Nuisance impacts (i.e. ambient noise and shadow flickering)
DIRECT Long-term Localised Probable Slight MODERATE The Noise Impact Assessment should be consulted;
LOW
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 171
The Wetland and Hydrological Impact Assessment should be consulted;
Turbines should not be constructed within 500m of households;
The proponent should establish a Grievance Mechanism to allow the PAF-owners and PAC members to lodge any complaints. Management feedback should be provided to claimants within two weeks of claimants submitting formal complaints. Section 7.3 of this report provides a general procedural outline for establishing such a mechanism.
Lightning strikes to turbines which could cause large fires
DIRECT Long-term Study Area May Occur Severe MODERATE An Emergency Preparedness Plan should be developed in case the project gives rise to the need for an emergency response. This plan should include management procedures for fire; (Mainstream has already indicated that they intend to join the local Fire Protection Association in order to obtain their inputs into the management plan)
The site should have warning signs to alert the public of potential fire risks;
Ensure sufficient fire breaks surrounding the WEF in accordance with the Veld Fire Act of 1998;
The proponent developer must follow the manufacturer’s recommendations on frequency and detail of maintenance on the turbine structures. Particular reference is made to the regular maintenance of the gearbox and associated machinery;
Fire-fighting equipment must be kept on site and in proper order to enable immediate responses to fires on site; and
People living and working in the areas along the turbines should be made aware of the dangers of fire and should be informed of the Emergency Preparedness Plan.
LOW
Stimulation of economic growth
Employing local labour could stimulate the local economy
DIRECT CUMULATIVE
Short-term Study Area May Occur Very Beneficial LOW POSITIVE
The proponent should investigate the development of a Skills Development Programme aimed at providing the following programmes to its employees and a selected number of community members: o Core business training; o Learnerships; o Portable skills training; and o At least one community bursary per year.
Employment should be managed by selecting employees according to an electronic selection system that ensures recruitment from local, impacted communities. This should ensure a fair recruitment process.
An Employment Equity Plan should be drafted to provide equal job opportunities. Employment preference should be provided to local residents;
In addition to appropriate HR policies and procedures, a labour desk/employment committee should be established to manage
HIGH POSITIVE
Skills training and further training opportunities could have very positive impacts on the futures on the local people
DIRECT CUMULATIVE
Medium-term Regional May Occur Slightly Beneficial LOW POSITIVE
VERY HIGH POSITIVE
Contributing to local and regional businesses causing an improvement in local GDP
DIRECT INDIRECT
CUMULATIVE
Short-term Regional May Occur Slightly Beneficial LOW POSITIVE
VERY HIGH POSITIVE
Capital investment for farmers to expand their farms leading improved financial security.
INDIRECT Long-term Regional Definite Very Beneficial LOW POSITIVE
VERY HIGH POSITIVE
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 172
and implement labour recruitment policies. This should ensure that recruitment is done in a fair and transparent way, and that job creation opportunities are maximised;
As far as possible, those labourers involved in the construction phase should be incorporated in the permanent staff for the operational phase;
Attention should be paid to employment opportunities for women and disabled persons; and
As far as reasonably possible, a plan for gradual replacement of expats and outsiders by local people should be developed and implemented. This might be unfeasible, however, since the construction period would be short.
Altering the landscape features
Soil erosion leading to a decrease in income due to the deterioration of grazing for cattle
DIRECT CUMULATIVE
Short-term Localised May Occur Severe MODERATE An information centre could enhance the project by educating the public about the need and benefits of wind power;
The proponent could engage with the ELM to establish a tourist route for the area to encompass the turbines on the escarpment with a possible outlook on the escarpment overlooking some of the turbines etc.;
The proponent should engage with the affected farm-owners and tourism businesses in the area to develop mechanisms to link the project with tourist routes and future plans;
The visual and ecological impact assessments should be reviewed and the mitigation measures adopted;
Affected farm-owners should where necessary be involved in the project. Through this process, owners could identify areas which they believe might be susceptible to environmental pollution or destruction, such as erosion, and measures could be discussed to avoid these;
A Grievance Mechanism should be established to allow those affected to voice any issues and/or concerns to the project proponent;
Where necessary, construction areas should be fenced-off and access controlled;
Project benefits or income-restoration measures should be discussed between the farm-owners and the proponent;
Through a (stakeholder engagement plan) SEP, (project affected farms) PAF-owners should be consulted regularly and be allowed to provide feedback on the development regarding relevant matters;
IFC PS 8 recommends that any cultural heritage be identified and protected as far as reasonably possible. For this purposes, an Archaeological Impact Assessment has been drafted. All recommendations made in the latter report should be considered; and
The proponent should rehabilitate or restore degraded areas after the construction period. Such restoration should be discussed with the
LOW
Change in farm-owners’ place attachment
DIRECT Long-term Study Area Probable Moderate MODERATE MODERATE
Effects on the areas tourism potential
DIRECT Long-term Study Area May Occur Moderate MODERATE LOW
Decrease in income related to a decrease in available grazing land for cattle
INDIRECT Short-term Localised May Occur Slight LOW LOW
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 173
affected farm-owners and implemented in such a way as to involve the affected farmers and community members.
VISUAL IMPACT ASSESSMENT
Visual intrusion of construction equipment
The equipment needed to erect the wind turbines during the construction phase may affect the local residents.
DIRECT Short-term Localised Probable Moderate MODERATE Construction must be limited to normal working hours (08:00 till 17:00) to ensure that construction lighting on-site is limited.
LOW
TOURISM IMPACT ASSESSMENT
Ecotourism Ecotourism in the area may be negatively impacted by the WEF through the increase in activity and noise which could chase away birds and animals in the area.
DIRECT CUMULATIVE
Localised Short-term Possible Moderate MODERATE Little can be done to prevent the construction activity from chasing away birds and animals in close proximity to the site, although this is likely to be a short term issue as birds and animals should return after construction is completed.
MODERATE
Heritage tourism The development of the WEF within close proximity of the battlefields memorial sites could negatively affect tourism related to these memorials.
DIRECT Localised Long-term Possible Moderate MODERATE The Heritage Specialist must be consulted to ensure that any heritage sites are available for viewing during the construction phase through the use of buffers.
LOW
NOISE IMPACT ASSESSMENT
No impacts identified by specialist
ISSUE DESCRIPTION OF IMPACT NATURE OF IMPACT
SPATIAL SCALE (EXTENT)
TEMPORAL SCALE (DURATION)
CERTAINTY SCALE (LIKELIHOOD)
SEVERITY / BENEFICIAL SCALE
SIGNIFICANCE PRE-MITIGATION
MITIGATION MEASURES SIGNIFICANCE POST-MITIGATION
OPERATIONAL PHASE
AGRICULTURE & SOILS IMPACT ASSESSMENT
Increase in erosion potential
An increase in hard surfaces (concrete foundations and roads) will increase run-off and potentially lead to soil erosion.
DIRECT CUMULATIVE
Study area Long term Definite Severe MODERATE All run-off water must be collected, channelled and disposed of in an appropriate manner.
Anti-erosion features must be installed where required.
Ensure that all cleared and impacted land is rehabilitated and re-vegetated.
LOW
Establishment of renewable energy infrastructure on agricultural land
Loss of 3ha of high potential agricultural land as a result of new WEF infrastructure development.
DIRECT Localised Long-term Definite Slight LOW Do not fence off any WEF infrastructure. This will allow maximum grazing within current camps.
LOW
Gradual reduction of available agricultural land as a consequence of an increase in renewable energy development in South Africa.
CUMULATIVE National Long-term Probable Moderate LOW • Avoid developing on high potential agricultural land. If unavoidable, ensure that all development footprints are kept at a minimum.
LOW
ECOLOGICAL IMPACT ASSESSMENT
Faunal disturbance due
to noise, vibrations and shadow flicker
caused by turbines
During operation, noise generated by turning rotor blades and turbine generators may deter faunal species from the area or interfere with normal behavioural patterns and communication, leading to reduced ecosystem functioning. This is of particular concern to small faunal species reliant on vocal communication, such as amphibians
DIRECT CUMULATIVE
Project level Unknown Unsure Unknown Unknown Limited mitigation measures are proposed, as it is assumed that faunal species will return once they have become acclimated to the noise, vibration and shadow flicker
• Operational monitoring may be necessary if the result of the faunal site survey (during construction) deems it necessary due to the identification of priority species. If necessary, an operational monitoring programme will be development through consultation between the faunal specialist and the developer.
Unknown
During operation, vibrations generated by the turbines may interfere with the behavioural patterns in species dependant on vibrational communication, which may result in reduced communication
DIRECT Project level Unknown Possible Unknown Unknown LOW
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 174
During operation, shadow flicker created by rotor blade movement may result in changes in predator-prey relationships
DIRECT Project level Unknown Possible Unknown Unknown LOW
Loss of habitat, direct (transformation) or indirect (noise/vibration) and disturbance could lead to faunal groups moving out of the area of disturbance, resulting in reduced habitat availability
DIRECT INDIRECT
CUMULATIVE
Project level Unknown Unsure Unknown Unknown LOW
Narrowing of the Northern Interior Corridor due to
disturbance
Noise and vibrations caused by turbine rotations could deter faunal species from utilising the corridor as intended, thereby resulting in the narrowing of a section of the Northern Interior Corridor, resulting in increased edge effect pressures
INDIRECT CUMULATIVE
Localised Short-term Possible Moderate MODERATE LOW
Increased predation on small faunal
species
Turbine access roads could increase the vulnerability of snakes, lizards and rodents to predation, when traversing roads, resulting in increased population losses
INDIRECT Localised Long-term Possible Low LOW No mitigation possible LOW
Habitat fragmentation
The construction of access roads to turbines could result in reduced area for occupancy, which could, over an extensive period, lead to a decrease in population numbers
INDIRECT CUMULATIVE
Localised Long-term Unlikely Low LOW No mitigation possible LOW
Access roads to turbines may restrict movement between adjacent areas, resulting in reduced genetic transfer and flow between adjacent populations
INDIRECT CUMULATIVE
Project level Long-term Unlikely Low LOW No mitigation possible LOW
WETLAND IMPACT ASSESSMENT
Poor site management
Poor follow-up on the success of post-construction rehabilitation may result in late detection of further loss of aquatic habitats due to changes in the hydrological regime.
DIRECT Regional Long-term Possible Severe HIGH Throughout the life of the project, on-going environmental monitoring of the aquatic systems must be implemented.
Rehabilitation and soil erosion are key elements of post-construction activities that will also need to be monitored.
MODERATE
Poor storm water management during the operation phase may result in late detection of onsite and downstream soil erosion and sedimentation.
DIRECT CUMULATIVE
Regional Long-term Possible Severe HIGH The Stormwater Management Plan must include annual monitoring of evidence of soil erosion associated with the Wind Energy Facility and its activities.
MODERATE
AVIFAUNAL IMPACT ASSESSMENT
Disturbance: WEF The displacement of priority avifauna through disturbance during operational activities Potential disturbance caused by the noise and movement of the turbines cannot adequately be mitigated, but the fact that the turbines are spaced far apart may help to reduce the impact. Habituation might also happen over time.
DIRECT INDIRECT
Long term Project scale Possible Moderately severe MODERATE Vehicle and pedestrian access to the site must be controlled and restricted to access roads to prevent unnecessary disturbance of priority species.
Formal monitoring must be resumed once the turbines have been constructed, as per the most recent edition of the best practice guidelines (Jenkins et al. 2011). The purpose of this would be to establish if displacement of priority species has occurred and to what extent. The exact time when post-construction monitoring should commence, will depend on the construction schedule, and will be agreed upon
LOW
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 175
with the site operator once these timelines have been finalised.
As an absolute minimum, post-construction monitoring must be undertaken for the first two (preferably three) years of operation, and then repeated again in year 5, and again every five years thereafter. The exact scope and nature of the post-construction monitoring will be informed on an on-going basis by the result of the monitoring through a process of adaptive management.
Mortalities due to collisions: WEF
Mortality of priority avifauna through collisions with the turbines
DIRECT Long-term International (due to presence of Palearctic migrants)
Probable Moderately severe MODERATE Formal monitoring must be resumed once the turbines have been constructed, as per the most recent edition of the best practice guidelines (Jenkins et al. 2011). The exact scope and nature of the post-construction monitoring will be informed on an on-going basis by the result of the monitoring through a process of adaptive management. The purpose of this would be (a) to establish if and to what extent displacement of priority species has occurred through the altering of flight patterns post-construction, and (b) to search for carcasses at turbines.
As an absolute minimum, post-construction monitoring must be undertaken for the first two (preferably three) years of operation, and then repeated again in year 5, and again every five years thereafter. The exact scope and nature of the post-construction monitoring will be informed on an on-going basis by the result of the monitoring through a process of adaptive management.
The environmental management plan must provide for the on-going inputs of a suitable experienced ornithological consultant to oversee the post-construction monitoring and assist with the on-going management of bird impacts that may emerge as the post-construction monitoring programme progresses.
Depending on the results of the carcass searches, a range of mitigation measures will have to be considered if mortality levels turn out to be significant, including selective curtailment of problem turbines during high risk periods.
If turbines are to be lit at night, lighting must be kept to a minimum and must not be white light. Flashing strobe-like lights should be used where possible (provided this complies with Civil Aviation Authority regulations).
Lighting of the wind farm (for example security lights) must be kept to a minimum. Lights should be directed downwards (provided this complies with Civil Aviation Authority regulations).
LOW
BAT IMPACT ASSESSMENT
Mortalities due to collisions and barotrauma
Mortality of bats through collisions with turbine blades and through barotrauma caused by the low air pressure caused by the blades.
DIRECT Long-term Regional Probable Severe HIGH Turbines in high sensitivity areas must be removed from the final layout.
Turbines within the medium sensitivity areas must follow a strict curtailment schedule
MODERATE
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 176
development by a bat specialist.
PALEONTOLOGICAL IMPACT ASSESSMENT
No impacts identified by specialist
HERITAGE IMPACT ASSESSMENT
No impacts identified by specialist
SOCIO-ECONOMIC IMPACT ASSESSMENT
Construction and upgrading of
roads
An influx of people into the Utrecht area and the expansion of hamlets
DIRECT INDIRECT
CUMULATIVE
Short-term Study Area Probable Moderate MODERATE All the project employees should be subject to a health and HIV/AIDS awareness educational programme;
The proponent could initiate programmes aimed at upgrading or lending support to local facilities, e.g. clinics and police stations. Alternatively, the proponent could assist with initiating programmes aimed at encouraging voluntary workers to patrol particular areas (especially during the construction period).
Changes in crime patterns will need to be monitored in consultation with the local police and community policing forums (if these exist);
Specifically for influx management, the consultant recommends that the proponent develops transparent Human Resources (HR) policies and procedures. Such procedures could include a Preferential Procurement Policy in favour of employing the current residents in local communities within 50km of the site such as the Waaihoek Community Trust;
The proponent should develop a Recruitment and Influx Management Plan.
The proponent should develop a Stakeholder Engagement Plan (SEP) which incorporates developing collaborative management strategies for in-migration;
School programmes could be supported or initiated aimed at educating children from an early age about the effects and consequences of crime and social pathologies;
Community out-reach programmes could be supported or initiated to deal with issues related to unsafe sexual practices, sex work, teenage pregnancies and sexual violence; and
Particular roads should be fenced and access to particular road networks should be monitored and controlled. Gates should be considered for particular road networks, and particular access routes should be denied for unauthorised individuals or cars.
LOW
An increase in subsistence famers INDIRECT Short-term Study Area May Occur Moderate MODERATE LOW
Easing unrestricted access to farm roads
DIRECT Long-term Study Area May Occur Very Severe HIGH LOW
An increase in crime related to the influx of people in the area
INDIRECT Long-term Localised May Occur Slight LOW LOW
Health and safety Risk of aircraft collisions with turbines
DIRECT Long-term Regional Unlikely Very Severe HIGH The turbines should be accurately positioned to reduce any effects of possible malfunctioning;
If complaints are received, the proponent must investigate and mitigate these issues.
The proponent must follow the manufacturer’s recommendations on frequency and detail of maintenance on the turbine structures to minimise the risk of malfunction;
A Blade Monitoring System must be standard in the turbine technology used in the project;
The proponent should establish safety setbacks, and design the facility in such a manner that no
LOW
Turbine malfunctioning (e.g. blade throw and gearbox failure)
DIRECT Medium-term Localised Unlikely Severe LOW LOW
Electromagnetic interference DIRECT CUMULATIVE
Medium-term Localised Unlikely Slight LOW LOW
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 177
buildings or populated areas lie within the possible trajectory range of turbine blades;
The developer must equip wind turbines with vibration sensors that can react to any imbalance in the rotor blades and shut down the turbine if necessary;
Regular maintenance work on the turbines is necessary; and
The facility should have warning signs to alert the public of risk.
Increased traffic and related security and safety risks
DIRECT INDIRECT
CUMULATIVE
Short-term Localised Probable Very Severe HIGH Farm-owners should always be consulted (and permission should be given by owners where relevant) prior to the construction or upgrading of any road(s);
Fencing along the access routes should be considered, as well as the construction of cattle grids at road crossings;
Gates should be erected at all the entrances to the WEF and traffic in and out of the project area monitored. This should be discussed with the affected owners;
Traffic calming measures should be implemented and speed limits need to be introduced and managed, especially during the construction period. Traffic should be controlled and regulated, and truck drivers need to be aware of safety regulations through regular briefings and workshops;
It is recommended that the proponent prepares and implements a Community Health and Safety Plan and policy. Such a plan/policy should include traffic safety rules, and would need to enforce particular guidelines, including those related to adequately fencing-off certain infrastructure. This plan should be communicated to all personnel, PAF residents and nearby affected PACs;
Particular criteria need to be developed for the recruitment of security personnel (for the construction phase);
When hiring security personnel, reasonable effort must be made to check whether the potential employees have criminal records or have been part of any other unscrupulous behaviour.
As far as possible, security personnel should be recruited from the surrounding communities. This should allow them to distinguish between the local population and outsiders;
Security personnel need to be properly trained in the use of force and, most importantly, appropriate conduct towards labourers, PAC members and farm-owners;
A code of conduct must be developed for the security personnel; and
All the PAC members and PAF-owners need to be informed about the roles and responsibilities of the security personnel.
LOW
Nuisance impacts (i.e. ambient noise DIRECT Long-term Localised Probable Slight MODERATE The Noise Impact Assessment should be LOW
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 178
and shadow flickering) consulted; The Wetland and Hydrological Impact
Assessment should be consulted; Turbines should not be constructed in close
proximity to household buildings; The proponent should establish a Grievance
Mechanism to allow the PAF-owners and PAC members to lodge any complaints. Management feedback should be provided to claimants within two weeks of claimants submitting formal complaints. Section 7.3 of this report provides a general procedural outline for establishing such a mechanism.
Lightning strikes to both turbines and powerlines which could cause large fires
INDIRECT Long-term Study Area May Occur Severe MODERATE An Emergency Preparedness Plan should be developed in case the project gives rise to the need for an emergency response. This plan should include management procedures for fire; (Mainstream has already indicated that they intend to join the local Fire Protection Association in order to obtain their inputs into the management plan)
The site should have warning signs to alert the public of potential fire risks;
Ensure sufficient fire breaks surrounding the WEF in accordance with the Veld Fire Act of 1998;
The developer must follow the manufacturer’s recommendations on frequency and detail of maintenance on the turbine structures. Particular reference is made to the regular maintenance of the gearbox and associated machinery;
Fire-fighting equipment must be kept on site and in proper order to enable immediate responses to fires on site; and
People living and working in the areas along the turbines should be made aware of the dangers of fire and should be informed of the Emergency Preparedness Plan.
LOW
Stimulation of economic growth
Employing local labour DIRECT Short-term Study Area May Occur Moderately Beneficial
LOW POSITIVE
The proponent should investigate the development of a Skills Development Programme aimed at providing the following programmes to its employees and a selected number of community members: o Core business training; o Learnerships; o Portable skills training; and o At least one community bursary per year
(ideally through the Waaihoek Community Trust).
Employment should be managed by selecting employees according to an electronic selection system that ensures recruitment from local, impacted communities. This should ensure a fair recruitment process.
An Employment Equity Plan should be drafted to provide equal job opportunities. Employment preference should be provided to local residents such as the PAF permanent residents and
LOW POSITIVE
Skills training and further training opportunities
DIRECT INDIRECT
CUMULATIVE
Medium-term Regional May Occur Slightly Beneficial LOW POSITIVE
VERY HIGH POSITIVE
Contributing to local and regional businesses
DIRECT CUMULATIVE
Short-term Regional May Occur Slightly Beneficial LOW POSITIVE
VERY HIGH POSITIVE
Capital investment for farmers to expand their farms
DIRECT CUMULATIVE
Long-term Regional Definite Very Beneficial LOW POSITIVE
VERY HIGH POSITIVE
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 179
Waaihoek Community Trust members; In addition to appropriate HR policies and
procedures, a labour desk/employment committee should be established to manage and implement labour recruitment policies. This should ensure that recruitment is done in a fair and transparent way, and that job creation opportunities are maximised;
As far as possible, those labourers involved in the construction phase should be incorporated in the permanent staff for the operational phase;
Attention should be paid to employment opportunities for women and disabled persons; and
As far as reasonably possible, a plan for gradual replacement of expats and outsiders by local people should be developed and implemented. This might be unfeasible, however, since the construction period would be short.
Altering the landscape features
Soil erosion leading to a decrease in income due to the deterioration of grazing for cattle
INDIRECT CUMULATIVE
Medium-term Localised May Occur Severe MODERATE An information centre could enhance the project by educating the public about the need and benefits of wind power;
The proponent could engage with the ELM to establish a tourist route for the area to encompass the turbines on the escarpment with a possible outlook on the escarpment overlooking some of the turbines etc.;
The proponent should engage with the affected farm-owners and tourism businesses in the area to develop mechanisms to link the project with tourist routes and future plans;
The visual and ecological impact assessments should be reviewed and the mitigation measures adopted;
Affected farm-owners should where necessary be involved in the project and in particular the placement of turbines. Through this process, owners could identify areas which they believe might be susceptible to environmental pollution or destruction, such as erosion. Through such consultation, measures could be discussed to avoid soil erosion;
A Grievance Mechanism should be established to allow those affected to voice any issues and/or concerns to the project proponent;
Where necessary, construction areas should be fenced-off and access controlled;
Project benefits or income-restoration measures should be discussed between the farm-owners and the proponent;
Through an SEP, PAF-owners should be consulted regularly and be allowed to provide input into the development;
IFC PS 8 recommends that any cultural heritage be identified and protected as far as reasonably possible. For this purposes, an Archaeological Impact Assessment has been drafted. All recommendations made in the latter report
LOW
Change in farm-owners’ place attachment
DIRECT Long-term Study Area Definite Severe MODERATE MODERATE
Effects on the areas tourism potential
DIRECT Long-term Study Area May Occur Moderate MODERATE LOW
Decrease in income related to a decrease in available grazing land for cattle
INDIRECT Long-term Localised May Occur Slight LOW LOW
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 180
should be considered; and The proponent should rehabilitate or restore
degraded areas after the construction period. Such restoration should be discussed with the affected farm-owners and implemented in such a way as to involve the affected farmers and community members.
VISUAL IMPACT ASSESSMENT
The effect of the WEF of the local sense of place
Visibility of the WEF from the town (Utrecht), surrounding farms and informal settlement influencing the local peoples sense of place.
DIRECT Medium-term Study Area May Occur Severe MODERATE No mitigation possible. MODERATE
Distractions caused by the
WEF
Visibility of turbines from the main road (R34) and secondary farm roads causing distractions while driving.
DIRECT CUMULATIVE
Medium-term Study Area May Occur Severe MODERATE If necessary a viewing area alongside the road should be made available to both local people and passers-by to ensure that they have a safe location from which to view the turbines.
MODERATE
TOURISM IMPACT ASSESSMENT
Ecotourism Ecotourism in the area may be positively / negatively impacted by the WEF through the introduction of a new possible tourist attraction / detraction to the area. The impact depends on the perceptions of the individual tourist.
DIRECT Localised Short-term Possible Moderate MODERATE Little can be done to prevent the activity during deconstruction from chasing away birds and animals in close proximity to the site, although this is likely to be a short term issue as birds and animals should return after deconstruction..
MODERATE
NOISE IMPACT ASSESSMENT
Noise generated by turbines close
to sensitive receptors
The noise generated by turbines can impact people living within 500m of an individual turbine.
DIRECT
Localised Long-term Possible Severe HIGH The specialist report has informed the layout to ensure that turbines do not occur within 500m of households.
No turbines occur in highly sensitive areas
LOW
ISSUE DESCRIPTION OF IMPACT NATURE OF IMPACT
SPATIAL SCALE (EXTENT)
TEMPORAL SCALE (DURATION)
CERTAINTY SCALE (LIKELIHOOD)
SEVERITY / BENEFICIAL SCALE
SIGNIFICANCE PRE-MITIGATION
MITIGATION MEASURES SIGNIFICANCE POST-MITIGATION
DECOMMISSIONING PHASE
AGRICULTURE & SOILS IMPACT ASSESSMENT
No impacts identified by specialist
ECOLOGICAL IMPACT ASSESSMENT
Long-term damage due to
poor rehabilitation
Poor rehabilitation may result in limited re-vegetation and long-term ecological damage
INDIRECT CUMULATIVE
Localised Short-term Probable Moderately severe MODERATE Financial provision should be made for the Decommissioning Phase, which must include costs for landscaping and re-vegetation of the whole development footprint
A Decommissioning Rehabilitation Plan must be developed and include primary objectives of rehabilitation and the latest acceptable methods for implementation
LOW
Poor rehabilitation may result in limited re-vegetation an long-term ecological damage in a nature reserve
INDIRECT CUMULATIVE
Localised Short-term Probable Severe HIGH LOW
Disturbance to surrounding
wildlife and fauna
During decommission, vehicular movement, noise and habitat destruction could result in behavioural disturbance of various faunal species
DIRECT Project level Short-term Possible Moderately severe MODERATE Restrict decommissioning activities to post-dawn and pre-dusk
Decommissioning of the turbines must be undertaken in the shortest time practical
LOW
Poaching Increased activity and presence during the Decommissioning Phase could result in increased poaching of wild animals, resulting in population losses
INDIRECT CUMULATIVE
Localised Short-term Possible Severe HIGH Decommissioning workers must be transported to and from the site
No residence may be set up on site An inspection of the immediate Thicket
vegetation surrounding the turbine sites for evidence of snares must be undertaken by the appointed ECO
LOW
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 181
WETLAND IMPACT ASSESSMENT
Poor rehabilitation
Poor rehabilitation efforts may result in long-term damage to aquatic habitats and severe soil erosion.
DIRECT CUMULATIVE
Regional Long-term Possible Severe HIGH Rehabilitation must be undertaken in the following phases: 1. Removal of top section of the foundation 2. Applying topsoil and re-landscaping the
area to its original condition 3. Stabilising the soil with synthetic materials
or a fast growing plant species 4. Re-vegetate with plants grown from seed
from the surrounding vegetation. A Rehabilitation Plan must be developed by an
independent environmental practitioner in order to fully expand on the steps and implementation of rehabilitation.
MODERATE
AVIFAUNAL IMPACT ASSESSMENT
Disturbance: WEF The displacement of priority avifauna through the disturbance during dismantling activities
DIRECT Short term Project level Probable Moderately severe MODERATE Dismantling activity should be restricted to the immediate footprint of the infrastructure, and in particular to the proposed road network. Access to the remainder of the site should be strictly controlled to prevent unnecessary disturbance of priority species.
LOW
BAT IMPACT ASSESSMENT
No impacts identified by specialist
PALEONTOLOGICAL IMPACT ASSESSMENT
No impacts identified by specialist
HERITAGE IMPACT ASSESSMENT
No impacts identified by specialist
SOCIO-ECONOMIC IMPACT ASSESSMENT
Stimulation of economic growth
Employing local labour DIRECT Short-term Study Area May Occur Very Beneficial LOW POSITIVE
All the project employees should be subject to a health and HIV/AIDS awareness educational programme;
The proponent could initiate programmes aimed at upgrading or lending support to local facilities, e.g. clinics and police stations. Alternatively, the proponent could assist with initiating programmes aimed at encouraging voluntary workers to patrol particular areas (especially during the construction period).
Changes in crime patterns will need to be monitored in consultation with the local police and community policing forums (if these exist);
Specifically for influx management, the consultant recommends that the proponent develops transparent Human Resources (HR) policies and procedures. Such procedures could include a Preferential Procurement Policy in favour of employing the current residents in local communities within 50km of the site such as the Waaihoek Community Trust;
The proponent should develop a Recruitment and Influx Management Plan.
The proponent should develop a Stakeholder Engagement Plan (SEP) which incorporates developing collaborative management strategies for in-migration;
School programmes could be supported or initiated aimed at educating children from an early age about the effects and consequences of crime and social pathologies;
HIGH POSITIVE
Skills training and further training opportunities
DIRECT CUMULATIVE
Medium-term Regional May Occur Slightly Beneficial LOW POSITIVE
VERY HIGH POSITIVE
Contributing to local and regional businesses
DIRECT CUMULATIVE
Short-term Regional May Occur Slightly Beneficial LOW POSITIVE
VERY HIGH POSITIVE
Capital investment for farmers to expand their farms
INDIRECT Long-term Regional Definite Very Beneficial LOW POSITIVE
VERY HIGH POSITIVE
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 182
Community out-reach programmes could be supported or initiated to deal with issues related to unsafe sexual practices, sex work, teenage pregnancies and sexual violence; and
Particular roads should be fenced and access to particular road networks should be monitored and controlled. Gates should be considered for particular road networks, and particular access routes should be denied for unauthorised individuals or cars.
VISUAL IMPACT ASSESSMENT
Visual intrusion of construction equipment
The equipment needed to dismantle the turbines during the decommissioning phase may affect the local residents.
DIRECT Short-term Localised Probable Moderate MODERATE Dismantling must be limited to normal working hours (08:00 till 17:00) to ensure that construction lighting on-site is limited.
LOW
TOURISM IMPACT ASSESSMENT
Ecotourism Ecotourism in the area may be positively / negatively impacted by the deconstruction of the WEF depending on how well the WEF is received by the area in terms of tourism.
DIRECT INDIRECT
CUMULATIVE
Localised Short-term Possible Moderate MODERATE No mitigation required. Refer to Tourism Impact Assessment for international case studies which state the WEF’s are inconsequential and depend entirely on the individuals’ perception of the development.
MODERATE (POSITIVE / NEGATIVE)
Heritage tourism The deconstruction of the WEF within close proximity of the battlefields memorial sites could negatively affect tourism related to these memorials.
DIRECT Localised Long-term Possible Moderate MODERATE The Heritage Specialist must be consulted to ensure that any heritage sites are available for viewing during the decommissioning phase through the use of buffers.
LOW
NOISE IMPACT ASSESSMENT
No impacts identified by specialist
Table 14-3. No-go Impacts Associated with the WEF
ISSUE DESCRIPTION OF IMPACT NATURE OF IMPACT SPATIAL SCALE (SIZE)
TEMPORAL SCALE (DURATION)
CERTAINTY SCALE (LIKELIHOOD)
SEVERITY / BENEFICIAL SCALE
SIGNIFICANCE PRE-MITIGATION
NO-GO OPTION
IN ADDITION TO NONE OF THE NEGATIVE IMPACTS ASSOCIATED WITH THE CONSTRUCTION AND OPERATION OF THE WIND ENERGY FACILITY, AS IDENTIFIED IN THE TABLES ABOVE, THE FOLLOWING IMPACTS HAVE BEEN IDENTIFIED:
No reduction in dependence on fossil-
fuel generated electricity
140MW contribution of renewable energy will be lost. CUMULATIVE International Permanent Definite Moderately Severe HIGH
Increases in the demand for electricity as the South African economy grows will increase the amount of fossil fuels required to generate electricity, placing pressure on non-renewable fossil fuels
DIRECT CUMULATIVE
National Permanent Definite Severe VERY HIGH
No disturbance to wildlife
Avifauna, bats and other wildlife will not be affected by the construction and operation of the wind farm
DIRECT Localised Long-term Definite Moderately Beneficial HIGH POSITIVE
No loss of vegetation Vegetation that would otherwise be lost during the construction of the turbines and other infrastructure would remain intact
DIRECT Localised Long-term Definite Moderately Beneficial HIGH POSITIVE
Socio-economic benefits
None of the farmers involved will acquire the funding related to the WEF development resulting in the anticipated enhancements to their farms not being feasible.
DIRECT
Localised Permanent Definite Severe HIGH
The community will not benefit from the associated WEF funding to local schools, libraries and clinics.
DIRECT CUMULATIVE
Localised Permanent Definite Severe HIGH
-
Coastal & Environmental Services Waaihoek Wind Energy Facility 183
14.6 Appendix F: Specialist Studies Section 14.6.1 Agriculture & Soils Impact Assessment 14.6.2 Ecological Impact Assessment 14.6.3 Wetland and Impact Assessment 14.6.4 Avifaunal Impact Assessment 14.6.5 Bat Impact Assessment 14.6.6 Paleontological Impact Assessment 14.6.7 Heritage Impact Assessment 14.6.8 Socio-economic Impact Assessment 14.6.9 Visual Impact Assessment 14.6.10 Tourism Impact Assessment 14.6.11 Noise Impact Assessment 14.6.12 Biodiversity Offset Plan
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 184
AGRICULTURE & SOILS IMPACT ASSESSMENT
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 185
ECOLOGICAL IMPACT ASSESSMENT
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 186
WETLAND IMPACT ASSESSMENT
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 187
AVIFAUNAL IMPACT ASSESSMENT
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 188
BAT IMPACT ASSESSMENT
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 189
PALEONTOLOGICAL IMPACT ASSESSMENT
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 190
HERITAGE IMPACT ASSESSMENT
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 191
SOCIO-ECONOMIC IMPACT ASSESSMENT
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 192
VISUAL IMPACT ASSESSMENT
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 193
TOURISM IMPACT ASSESSMENT
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 194
NOISE IMPACT ASSESSMENT
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 195
BIODIVERSITY OFFSET PLAN
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 196
14.7 Appendix G: Other Relevant Studies 14.7.1 Engineering Services Report 14.7.2 Geotechnical Report 14.7.3 Transport Plan
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 197
ENGINEERING SERVICES REPORT
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 198
GEOTECHNICAL STUDY
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 199
TRANSPORT PLAN
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 200
14.8 Appendix H: Environmental Management Programme (EMPr) 14.8.1 Environmental Management Programme (EMPr)
-
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 201
Appendix I: CV’s
ALAN CARTER - PHD, CPA (USA) Date and place of birth: 7th July 1959, East London, Eastern Cape, South Africa QUALIFICATIONS Academic
Ph.D. Plant Science (Rhodes University, 1987)
B. Compt. Hons. Accounting Science (University of South Africa, 1997)
B. Com. Financial Accounting (Rhodes University, 1995)
B.Sc. Hons. Plant Science (Rhodes University, 1983)
B.Sc. Plant Science & Zoology (Rhodes University, 1982) Other
Completed American National Standards Institute and British Standards Institute “Environmental Management Systems Lead Auditor Training Course”.
CERTIFICATIONS & MEMBERSHIPS Environmental
Certified Environmental Assessment Practitioner of South Africa (CEAPSA)(since 2012)
Registered as a professional environmental scientist with the South African Council for Natural Scientific Professions (SACNASP) (since 2004).
Certified ISO14001 Environmental Auditor with the Registrar Accreditation Board (RAB) (American National Standards Institute, USA), Quality Systems Association (Australia) (RABQSA) (since 2002).
Professional Member of the South African Institute of Ecologists and Environmental Scientists, South Africa (SAIE&ES) (since 1987).
Member of the South African Bureau of Standards (SABS) Technical Committee TC 207: Environmental Management Systems (since 2002)
Member of the Sustainable Energy Society of South Africa (SESSA) (since 2007) Financial Accounting
Texas State Board of Public Accountancy (TSBPA), USA - Certified Public Accountant (since 1999)
American Institute of Certified Public Accountants (AICPA), USA - Professional Member (since 1999).
South African Institute of Chartered Accountants (SAICA) - Completed three year training certification requirements (completed 1996).
PROFESSIONAL EXPERIENCE
January 2002 – Present: Director (Coastal & Environmental Services, East London, South Africa)
January 1999 – December 2001: Manager (Arthur Andersen LLP, Public Accounting Firm, Chicago, Illinois USA)
December 1996 – December 1998: Senior Accountant/Auditor (Ernst & Young LLP, Public Accounting Firm, Austin, Texas, USA).)
January 1994 – December 1996: Senior Accountant/Auditor (Ernst & Young, Charteris & Barnes, Chartered Accountants, East London, South Africa)