regional competitiveness operational programme 11 th sectoral monitoring committee meeting
DESCRIPTION
REGIONAL COMPETITIVENESS OPERATIONAL PROGRAMME 11 TH SECTORAL MONITORING COMMITTEE MEETING. 13 November 2012 – Ankara. Agenda For the 11 th Sectoral Monitoring Committee Meeting For the Regional Competitiveness Operational Programme in Turkey ( 13 November 201 2 , 09 :30 ). - PowerPoint PPT PresentationTRANSCRIPT
REGIONAL COMPETITIVENESS REGIONAL COMPETITIVENESS OPERATIONAL PROGRAMMEOPERATIONAL PROGRAMME
1111THTH SECTORAL MONITORING COMMITTEE SECTORAL MONITORING COMMITTEE MEETINGMEETING
13 November 2012 – Ankara
1.Opening statements – by the Head of the Operating Structure and by the Commission (HoS + EC)2.Approval of the Minutes of the last meeting and the agenda of the Meeting (HoS + EC)3.Information on audit related issues(Audit Authority + EC)4.Information on programming (OS)- 1st project package- 2nd project package- 3rd project package (OS+EIF)- 4th project package5.Information on implementation (OS)- Tendering and contracting- Implementation-Absorption (n+3), procurement plans and disbursement forecasts-Updated payment forecast and payment cycle for 2012 (OS+NAO)6. Information on technical assistance and communication activities (OS)7. Information on Monitoring Report and Monitoring Sheets (OS)8. Information on follow-up of conferral of management audit findings of the DG REGIO (OS+EC)9.Information on the revision and extension of the Operational Program for years 2012/2013 (OS +EC+ Strategic Coordinator)10. Indicative date for the next Sectoral Monitoring Committee (HoS + EC) 11. AOB
AgendaFor the 11th Sectoral Monitoring Committee Meeting
For the Regional Competitiveness Operational Programme in Turkey(13 November 2012, 09:30)
2
PROGRAMMINGPROGRAMMING-1st project package1st project package-2nd project package2nd project package-3rd project package3rd project package-4th project package4th project package-Overall AssessmentOverall Assessment
SSTATE TATE of of PLAY PLAY - 1st PACKAGE of - 1st PACKAGE of PROJECTSPROJECTS
TOTAL BUDGET: 99.402.500 €
TOTAL OPERATIONS: 11
APPROVED OPERATIONS: 10
First Submission of the Documents – 26.02.2010 Admissibility Letter – 23.04.2010 Comments from the EC – 11.10.2010 Second Submission of the Documents – 29.07.2011 Comments from the EC – 22.03.2012 Meeting with EC representatives – 14.09.2012 Unofficial Submsission of revised docs. – 22.10.2012 Third Submission of the Documents – Q4th 2012 /
Q1st 2013
SSTATE OF PLAY TATE OF PLAY IIN SECOND N SECOND PROJECT PACKAGE PROJECT PACKAGE
Prioritized Projects by the call: 47Current Number of Projects: 38 Approved Projects: 29 OIS in Preparation: 9Total Budget ofApproved Projects: € 202,962,882
Name of Proposal Location Submission Date
Approval Date
1-Expansion of Elazığ Enterprise Development Center Elazığ 17.07.2012 30.07.2012
2-Amasya Natural Stone Centre of Excellence Amasya 24.07.2012 01.08.2012
3-Whey Powder Production Plant Trabzon 02.05.2012 11.10.2012
4-Maraş Business Development Center MaraşSent to EUD via e-mail 24.08.2012
via e-mail 29.08.2012
5-Bafra Business and Export Development Unit SamsunSent to EUD via e-mail 16.07.2012
via e-mail 27.08.2012
6-Revitalization of the Tourism Sector in Siirt SiirtSent to EUD via e-mail 17/08/2012
via e-mail 07.11.2012
7-Bitlis (Eren) Centre for Business Support Bitlis 26.09.2012 via e-mail 09.11.2012
OPERATIONS APPROVED SINCE THE LAST SMC MEETINGOPERATIONS APPROVED SINCE THE LAST SMC MEETING
8
Measure Name of the Proposal ERA Status Submission Date
1.3
Establishment and Operationalisation of an Applied R&D and Service Centre, specialised on Food Industry, at Çankırı Karatekin University
Çankırı Karatekin University
Waiting EUD’s comments 23.08.2012
1.1 Yozgat Business Support Office
Yozgat Chamber of Commerce and Industry
OIS in preparation November 2012
2.1
Establishment and Operationalisation of a Lab Services Unit at the Hazelnut Research Station in Giresun
Hazelnut Research Station OIS in preparation November 2012
SECOND PROJECT PACKAGE – PLANNING
9
SECOND PROJECT PACKAGE – PLANNING
Measure Name of the Proposal ERA Estimated Submission Date
1.4 Ardahan Yalnızçam Winter Sports Tourism Development Operation
Ardahan Special Provincal Administration
1st Quarter of 2013
2.2Development of Dairy Products Cluster in Eastern Anatolia Through a Market Oriented Strategy
Governorate of Kars 1st Quarter of 2013
1.3 Erzurum Ataturk University – Design and Innovation Centre Atatürk University 1st Quarter of
2013
1.4 Kommagene Nemrut Tourism Oriented Revival Project (KN-TOC)
Governorate of Adıyaman
1st Quarter of 2013
1.1
Establishment of cold storage house by using renewable energy (soil solar) and Apricot Clustering Valley for apricot processing SMEs
Governorate of Malatya and Malatya Commodity Exchange
1st Quarter of 2013
2.1 Increasing Regional Competitiveness in Kars, Ağrı, Ardahan and Iğdır Provinces Kars Governorate 1st Quarter of
2013
SSTATE OF PLAY TATE OF PLAY IIN N THIRDTHIRDPROJECT PACKAGE PROJECT PACKAGE
11
THIRD PROJECT PACKAGE - STATE OF PLAY
Results as of October 2012*Total Volume: > EUR 320 million
80% absorption on available funds
Total Number of Loans: >4,300172% of the target
Total Number of SMEs: >4,000160% of the target
* Indicative due to late reporting by FIs
SSTATE OF PLAY TATE OF PLAY IIN N THE FOURTHTHE FOURTHPROJECT PACKAGE PROJECT PACKAGE
PRIORITIZED LIST OF PROJECTS IN 4TH PACKAGE (IND. 117.000.000 €)PRIORITIZED LIST OF PROJECTS IN 4TH PACKAGE (IND. 117.000.000 €)# Measure Title of the Operation End Recipient of
Assistance Status Indicative Budget (€)
1 1.1 Processing and Storing of Sea Food North Anatolia Dev.Agency (KUZKA) Q1st of 2013 9.500.000
2 1.3 Establishment of Nanotechnology and Nonwoven R&D Centre
Silkroad Dev.Agency (İKA) Q1st of 2013 7.000.000
3 1.1 Samsun Logistics Center Middle Blacksea Dev.Agency (OKA)
Q2nd of 2013 42.000.000
4 2.2 Turkish Cluster Academy MoSIT-DG for Industrial Zones Q1st of 2013 4.500.000
5 1.1 The Common Use Workshop Project Eastern Anatolia Dev.Agency (DAKA)
Q4tht of 2012 6.668.645
6 1.3 Shoe-making Training and Design Centre and Shared-use Workshop
Eastern Mediterranian Dev.Agency (DOĞAKA) Q1st of 2013 6.471.000
7 1.1 Establishment of a Enterprise Development Center in Gümüşhane
Eastern Blacksea Dev.Agency (DOKA) Q4tht of 2012 6.000.000
8 1.1 Establishment of Enterprise Development Center (İŞGEM) in Bingöl Fırat Dev.Agency (FKA) At EUD 6.158.044
9 1.3 Carpet Incubator Centre Silkroad Dev.Agency (İKA) Q1st of 2013 5.000.000
10 1.1 Şanlıurfa Cotton Licensed Warehouse TOBB Q4tht of 2012 7.147.000
11 1.1 Sivas Industry Incubator Center Project (ISGEM)
Middle Anatolia Dev.Agency (ORAN) Q4tht of 2012 7.137.800
12 1.4 Kars City with its Historical Identity Serhat Dev.Agency (SERKA) Q1st of 2013 9.500.000
OPERATIONS SUBMITTED BY THE NATIONAL PUBLIC BODIESOPERATIONS SUBMITTED BY THE NATIONAL PUBLIC BODIES (IND. 19 mil € )(IND. 19 mil € )
# Measure Title of the Operation End Recipient of Assistance Location Indicative
Budget (€)
1 1.4 Sustainable Tourism Development in Kaçkar Mountains National Park
Ministry of Forestry and Hydraulic Works
Rize 9.500.000
2 1.4 Increasing Tourism Capactity in Şanlıurfa
Ministry of Culture and Tourism Şanlıurfa 9.500.000
OVERALL ASSESSMENTOVERALL ASSESSMENT
Total Number of Operations : 66Total Number of approved operations: 41Operations in preparation: 25 Total Volume of Budget: ind. € 575 mil.
WHOLE OPERATION PROTFOLIO WHOLE OPERATION PROTFOLIO (Total Budget: ind. 575 MEUR)
PROGRESS PROGRESS BY PRIORITY AXESBY PRIORITY AXES
Priority 1: Improvement of Business Environment(Budget. ind 530 MEUR)
PROGRESS PROGRESS BY PRIORITY AXESBY PRIORITY AXES
Priority 2: Strengthening of Enterprise Capacity and Foster Entrepreneurship (Budget ind. 45 MEUR)
MEASURE BASED PROJECTS IN TARGET REGIONMEASURE BASED PROJECTS IN TARGET REGION
15 Growth Centers
Provinces not covered:•Artvin•Iğdır•Ağrı •Şırnak•Kilis•Tunceli
1.1 1.3 1.4 2.1 2.2
IIMPLEMENTATMPLEMENTATIIONON-Tendering and contractingTendering and contracting-ImplementationImplementation-Absorption (n+3), procurement plans and disbursement Absorption (n+3), procurement plans and disbursement forecastsforecasts-Updated payment forecast and payment cycle for 2012Updated payment forecast and payment cycle for 2012
0
20
40
60
80
100
PN Shortlisting Evaluation Award Signature
33
6 6 5 6
70
47
9889
82
4 617
24
2 22012201320142015
0
5
10
15
20
25
2 2
5 46 5
18
23 22
19
11
1 2
10
2
Until Today
2013
2014
2015
87.761.650,50
158.729.201,00
51.523.063,0097.092,00
Until Today201320142015
€ 298 million is foreseen to be contracted until April, 2015.
Realised and Realised and ForeseenForeseen Contracted BudgetContracted Budget
FinalizedFinalized ContractsContracts
Totally 7 contracts
Type of Contracts
Works SupervisionTechnical assistance
/ FW Supply
Total(euros)
Number of Contracts
0 0 2 5 7
Budget(euros) 0 0 187.968 865.470 1.053.438
26
Contracts under Implementation Contracts under Implementation
Totally 17 contracts
Type of Contracts Works Supervision Technical
assistance Supply DirectGrant
Total(euros)
Number of Contracts 6 4 5 0 2 17
Budget(euros) 18.162.683 1.947.225 18.298.195 0 48.300.000 86.708.213
27
Projects coming to ImplementationProjects coming to Implementation Totally 32 project-111 components Totally 32 project-111 components
Type of Components Works Supervision Technical
assistance Supply Total # of comp. Budget (€)
2012 0 0 2 0 4 2.322.360
1st Q / 2013 0 1 1 0 2 2.788.060
2nd Q / 2013 1 2 2 1 6 14.229.924
3rd Q / 2013 14 13 7 10 44 91.159.775
4th Q / 2013 7 7 9 8 31 55.589.604
2013 22 23 19 19 83 163.767.363
2014 2 1 11 10 24 51.523.063
2015 0 0 0 2 2 97.092
Total # of comp. 24 24 32 31 111 217.709.878
Budget (€) 81.267.407 9.775.364 64.109.697 62.557.410 217.709.878
28
DISBURSEMENT FORECAST AND N+3 GAP FOR RCOP 2007-2013 PROGRAMMING PERIOD
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 TOTAL PRIORITY I 27,200,000 13,855,000 4,756,534 44,532,876 94,465,212 20,479,394 4,977,469 0 210,266,484Measure 1.1. 1,601,961 23,886,601 67,542,485 14,965,712 4,441,933 112,438,693Measure 1.2. 27,200,000 13,855,000 41,055,000Measure 1.3. 3,154,573 16,266,288 19,772,855 3,589,687 483,438 43,266,840Measure 1.4. 4,379,987 7,149,871 1,923,994 52,098 13,505,951PRIORITY II 1,219,338 1,678,497 5,073,770 6,108,603 561,479 128,268 0 14,769,954
Measure 2.1. 380,537 1,020,000 2,582,093 2,174,728 6,157,358Measure 2.2. 838,801 658,497 2,491,677 3,933,874 561,479 128,268 8,612,596
PRIORITY III 59,577 1,636,302 1,165,757 3,485,134 1,317,339 1,103,725 574,974 9,342,807
Measure3.1. 59,577 1,636,302 1,165,757 2,807,548 676,167 462,553 396,474 7,204,377Measure 3.2. 677,586 641,172 641,172 178,500 2,138,430OHTER (non approved project)
0 0 16,284,211 0 50,000,000 105,000,000 90,404,165 0 261,688,376
1st PP 0 0 0 0 10,000,000 10,000,000 5,404,165 25,404,165
2nd PP 0 0 0 0 20,000,000 60,000,000 50,000,000 130,000,000
3rd PP 16,284,211 16,284,211
4th PP 0 0 0 0 20,000,000 35,000,000 35,000,000 90,000,000TOTAL (per year)
TOTAL (cumulative expenditure forecast )
27,259,577 43,970,217 67,855,215 120,946,995 272,838,148 399,982,746 496,067,621 496,067,621 496,067,621
Allocated fund for RCOP 41,900,000 43,500,000 54,800,000 71,430,000 88,020,000 89,016,597 91,720,588 480,387,185
N+3 Expenditure Requirements (per year)
41,900,000 43,500,000 54,800,000 71,430,000 88,020,000 89,016,598 91,720,588 0 480,387,186
Pre-finance* 42,060,000 22,215,000 64,275,000
Expenditure paid and declared cumulative
-160,000 21,125,000 75,925,000 147,355,000 235,375,000 324,391,598 416,112,186 480,387,186 480,387,186
N+3 Gap 27,419,577 22,845,217 -8,069,785 -26,408,005 37,463,148 75,591,148 79,955,435 15,680,435 15,680,435
Disbursement Forecast (EU Contribution) -October
27,259,577 16,710,640 23,884,998 53,091,780 151,891,153 127,144,598 96,084,876 496,067,621
DISBURSEMENT FORECAST GRAPHOCTOBER, 2012
TECHNICAL ASSISTANCE ACTIVITIESTECHNICAL ASSISTANCE ACTIVITIES
31
Main activities July – November 2012Main activities July – November 2012
On the job support to the Departments of RCP-CID
Preparation of Tender Dossiers
Training and capacity building for RCP-CID and ERAs
Technical Technical AAssistance on ssistance on IInstitutional nstitutional BBuilding uilding for the for the IImplementation of mplementation of RCOPRCOP
32
Training and capacity buildingTraining and capacity building to RCP-CID to RCP-CID
Trainings to RCP-CID: Insurance Workshop for FCD staff (29 August
2012) Procurement of Supplies Training (19 October
2012) Team Building Event (03 November 2012)
Internships2 internships delivered to PolandOrganization of additional 9 internships before the
end of 2012: four to Hungary and five to Latvia33
Training and capacity buildingTraining and capacity building to ERAs to ERAs
Trainings to ERAs Training on Procurement (24-27 September 2012)Training on Project Implementation (8- 11 October 2012)
Preparation of Guidelines for ERAs:Procurement GuidelinesImplementation Guidelines
34
Planned tPlanned training and capacity buildingraining and capacity building
5 trainings for RCP-CID:Leadership & HR Management
Training (2 remaining modules – 4 days)Programme and Contract management
for works and supervision contracts IPA major projects, Feasibility and Cost-
Benefit AnalysisProject management (soft skills)
35
Main activities planned for December 2012 Main activities planned for December 2012 to June 2013to June 2013Support to the Departments of RCP-CIDCompletion of Revision of RCP-CID manualsPreparation of remaining ToRs within the new TA
Plan (2012-2017)Completion of training and capacity building for
RCP-CID staff and ERAsSupport to pipeline development (OIS)Preparation of Tender DossiersStudy visits and internshipsOrganization of the 4th and 5th Study Visits, (Ireland and Hungary)
36
COMMUNICATION ACTIVITIESCOMMUNICATION ACTIVITIES
37
MONITORING REPORT MONITORING REPORT AND MONITORING SHEETSAND MONITORING SHEETS
39
OVERALL PROGRAMME PROGRESSOVERALL PROGRAMME PROGRESS
40
YEARS 2007-2013
Total Allocation (1)
Allocation per Approved
Operations(2)
Allocation per Project
Pipeline*
% of total allocation
([2/1]*100)
Available Allocation
(3)=(1)-(2)Commitments
Rate of Commitments
(% of total allocation)
Disbursement
Rate of Disbursement
(% of commitments)
Financial Progress
(Disbursement% of total allocation)
PRIORITY 1 480,666,206 275,643,537 514,046,635 57 205,022,669 70,719,016 15 50,270,337 71 10
Measure 1.1 243,730,279 150,822,585 248,074,401 62 92,907,694 8,349,647 3 850,857 10 0.3
Measure 1.2 98,300,000 48,300,000 98,300,000 49 50,000,000 48,300,000 49 48,300,000 100 49
Measure 1.3 81,785,729 58,767,538 109,519,998 72 23,018,191 14,069,370 17 1,119,479 8 1
Measure 1.4 56,850,198 17,753,414 58,152,236 31 39,096,784 0 0 0 0 0
PRIORITY 2 58,798,737 27,387,130 37,657,080 47 31,411,607 10,761,705 18 1,754,217 16 3
Measure 2.1 26,842,945 10,749,121 14,575,321 40 16,093,824 6,874,190 26 447,690 7 2
Measure 2.2 31,955,792 16,638,009 23,081,759 52 15,317,783 3,887,515. 12 1,306,527 34 4
PRIORITY 3 25,696,477 11,464,810 23,864,120 45 14,231,667 6,280,928 24 2,666,631 42 10
Measure 3.1 21,764,120 9,364,810 21,764,120 43 12,399,310 6,280,928 29 2,666,631 42 12
Measure 3.2 3,932,357 2,100,000 2,100,000 53 1,832,357 0 0 0 0 0
TOTAL 565,161,420 314,495,477 575,567,835 56 250,665,943 87,761,649 16 54,691,184 62 10
* Project pipeline consists of both approved and non-approved projects (totally 66 projects). For non-approved projects, budgets are indicative.
FOLLOW-UP OF CONFERRAL OF FOLLOW-UP OF CONFERRAL OF MANAGEMENT AUDMANAGEMENT AUDIIT T FINDINGS OF FINDINGS OF
THE DG REGIOTHE DG REGIO
41
AREA:AREA: Formal establishment of accountability, responsibility, delegated responsibility and any necessary related authority for all tasks and positions throughout the organisation.
SUMMARY FINDING RECOMMENDATI
ON/FOLLOW UP
ACTIONS
CURRENT STATUS
A smooth transition of all tendering and contracting files should be safeguarded among the MoSIT and CFCU upon the conferral of the tendering, contracting and financial management functions. According to the first addendum (December 2010) of the initial Cooperation Agreement, there were specific provisions arranging in detail the handover of the public procurement documents according to the status of the tenders/contracts managed by CFCU. However, in a second addendum (May 2011), it is stated that following the accreditation and conferral of management powers, all the contractual responsibilities should be undertaken by the Ministry of Science, Industry and Technology. This uncertainty put into question the effective functioning of the management and control system concerning tendering, contracting and financial management.
Specific provisions arranging in detail the transition of the tendering, contracting and financial management files should be laid down in an agreement between the two institutions.
The handover process of tendering files of the projects which were carried out by the CFCU has been achieved.
Following Contracts were signed by CFCU and handed over to the MoSIT with the transfer of tendering and contracting files. All these contracts totally 5 projects / 12 contracts are currently under implementation.
1- MoSIT (TA)(1 contract)
2- MoE [TA and Supply-1 (2 lots)] (3 contracts)
3- TOBB [TA and Supply-1 (3 lots)] (4 contracts)
4- KOSGEB (Supervision)(1 contract)
5- TDZs [Supervisions (Erciyes, Fırat, Gaziantep)] (3
contracts)
42
AREA:AREA: Internal audit including handling of audit reports and recommendations
SUMMARY FINDING RECOMMENDATION
/FOLLOW UPACTIONS
CURRENT STATUS
The set up and functioning of theinternal audit function in theMinistry of Science, Industry andTechnology has weakened since theinitial conferral of managementdecision and is considered as animportant weakness in the currentmanagement and control system.No IPA related, internal auditactivity was carried out, norplanned, in 2011.The requirement of CommissionRegulation (EC) No 718/2007Article 28(2)(k): The operatingstructure shall be responsible formanaging and implementing theprogramme or programmesconcerned in accordance with theprinciple of sound financialmanagement. For those purposes, itshall carry out a number offunctions that include: ensuringinternal audit of its differentconstituting bodies; in the currentsituation it is not fulfilled.
Recruitment and retainment of qualified internal auditors should be given the highest priority.
Internal audit training programmes, in accordance with international internal audit standards should be implemented and further intensified.
IPA related internal audit work should be regularly performed. Relevant follow-up information should be provided to the Commission concerning- recruitment- training- audit workcarried out.
A detailed audit plan for 2012 including the follow-up of previous internal audit findings should be submitted to the Commission.
One of the two auditors who is responsible from the audit of the RCP-CID participated to a language education at a foreign country, but also three additional Auditors -who are capable to perform audits on the IPA issues as of their language skills- were recruited within the Internal Audit Unit. So, there are 5 internal auditors in the Ministry who can perform IPA audits, totally.
Studies on preparation of the Training Strategy Document for EU funded projects were finalised and submitted to the HOS. One of the internal auditors participated to a seminar on “the fight against fraud and irregularities with regard to EU funds” which was held by the Ministry of EU on 29-30 May 2012. The audit on "Reporting Irregularities"and ‘’Follow up of Previous Internal Audit Findings’’ located in the 2012 Internal Audit Program started on 16.07.2012 and it is on-going.
43
Conferral of Management Decision of the DG REGIO AREA:AREA: Security procedures (IT) and Evaluation
SUMMARY FINDING RECOMMENDATION
/FOLLOW UPACTIONS
CURRENT STATUS
At Strategic Coordinator level the horizontal Integrated Monitoring Information System (IMIS) is still not functioning and the Commission has been made aware of technical problems. In parallel, the Ministry of Science, Industry and Technology plans to develop an individual Management Information System addressing specific implementation and financial reporting needs at a measure, project and contract level. The integration between the IMIS, the MIS and the accounting system should be given a priority and proper procedures should be added in the manual of procedures. The finalisation of the MIS is foreseen for the end of 2013, in the meantime an alternative information system will be used. The requirement of Commission Regulation (EC) No 718/2007 Article 28(2)(i): The operating structure shall be responsible for managing and implementing the programme or programmes concerned in accordance with the principle of sound financial management. For those purposes, it shall carry out a number of functions that include: setting up, maintaining and updating the reporting and information system; in the current situation only partly fulfilled.
The technical problems with the IMIS system should be solved with the highest priority.
Possible interfaces should be developed between the different systems in order to prevent double entry of data and similar entry mistakes. Priority should be given to the finalisation of the MIS. Relevant follow-up information should be provided to the Commission concerning
- The functioning of the IMIS System
- the planning and progress concerning the interfaces
- progress of the MIS
- Training provided.
The Tender Notice of MIS of MoSIT was published on 21.08.2012
The ToR is designed for preventing the duplications for users while entering data for the MIS and IMIS. The shortlisting of the tender have been started on 25th September 2012. File Server was established in the RCP-CID by March 2012, which ensures data archiving and hierarchical electronic document sharing.
A training programme about the content of IMIS was delivered to the end recipients of the first project package and selected end recipients from the second project package on 11 October 2012 within the scope of the ERA Implementation Training Programme. Currently, IMIS has been fully functional and accessible for the MoSIT and the end recipients of assistance. Up to date, operation pages have been created for 39 operations which were approved by EC/EUD and data entry has been in progress. In parallel, studies towards the improvement of Data Entry Forms are also ongoing.
In order to prepare disbursement plan and n+3 table in computerized manner a short term IT expert was recruited. A special software and trainings on usage of the software programme were delivered by the IT STE. Producing other financial reports in the same way is under process.
44
THANK YOU FOR YOUR ATTENTION
Ministry of Science, Industry and TechnologyRegional Competitiveness Programme
Coordination and Implementation Directorate
e-mail: [email protected] Web adress: ipa.sanayi.gov.tr