Podium and auditorium front Back brown panels to be re-covered with lighter material. Remove lattice walls; replace with one half-wall planter in front of
organ in lighter wood; Possibly use some of the podium wood for this?
Add quality silk plants for planter (screening wall for organist). Put a baby grand piano on the right side open on the carpet. Install doors to hide the back entry area. Remove large front podium on platform; replace with one or two
step open carpeted platform. Repair and install “pony wall” behind readers between platform floor
and wall. Signs with more modern lettering; location of signs to be
determined.
Committee Investigations
Podium and auditorium frontCosts:
Contractor costs estimated $375 - $500 a day;
10 -12 days $10,000
Materials for podium repair, swing doors to back, wall behind platform, repair drywall holes $ 4,800
Podiums or desks to be discussed as the best option on the platform along with more greenery $1,500?
Committee Investigations
Auditorium and foyer lighting Chandelier lighting preference is choice A or B
(wider light source)
Cost for auditorium, foyer ceiling and wall: $ 4,171.83 6 chandeliers, 2 sconces, ceiling fixtures
(chains provide flexibility in hanging)
Cost: $ 3180.40
Couple floods/recessed cans over stairsCost:
$ 40.00
Retain cove lighting Retain some floods by church front?
Committee Investigations
Seating Upholstered chairs (back and seat); wooden arms + legs
Including hymnal rack
Assume 32” back; longer seat with trampoline seat (improved after theater seating)
Not fixed seating; allow flexibility
Cost: (approx. $156/seat x 100) $ 15,600
Committee Investigations
Carpet Close loop weave estimate with pad (commercial grade)
Cost per square yard: $22.00 - $35.00Cost to carpet foyer, hall stairs + auditorium:
$7000 to $10,000
May consider Readers’ Rooms, Children’s Room, Counting Room, etc.
Committee Investigations
Painting costsInside auditorium brick $1,960
Outside foyer brick $710
Back wall painting $ 565
Main ceiling and beams $5,410
Total for all $8,645
$200 coupon available to us $8,445
Committee Investigations
(Prices include prime and block fill bricks, 2 top coats for bricks; back wall 3 top coats; sanding ceiling and priming with 2 coats.)
Committee Investigations
Back seating area Create a moveable ¾ long wall to define the front auditorium into a
more intimate space; allow space for wheelchair Seating; Add greenery, a few love seats or upholstered chairs, 6-top
tables; ability to use space for business meetings, After church meetings, Wednesday meetings, or open for lectures or
expanded congregation Foyer bench seats
Committee Investigations
Other ideas shared Paint walls or ceilings a cream color Replace windows Make basement accessible Type of sign (Plexiglas, wood, metal?) Re-panel foyer wood wall or wallpaper Few bench seats instead of having all chairs in auditorium Upstairs bathroom wheelchair accessibility – Combine upstairs
bathrooms to have one larger bathroom; Make the hall wider upstairs.
Committee Investigations
Sunday School Construction of painted walls to separate rooms along parallel walls
and bring color to the space. A few paintings and timelines for rooms. Add lamps to bring color and intimacy to the space instead of
fluorescents. Add some bookshelves (one per room) Replace aqua plastic chairs with upholstered benches in center of
room A couple of loveseats/couches for high school/college class space;
some pillows for younger classes Possibly replace tables? Not sure Do something with windows (paint outside well white?) Some greenery/silk plants or trees
Decorator’s Observations
Painting interior walls and ceiling A lighter color would give a more transcendent look and
feeling of a modern church. Would give us the best value for our money.
Example of church with light interior
Decorator’s Observations
Seating According to the decorator, current seating is not a major
problem. Keep theater seating in the front. Move the rows farther apart to give a feeling of more space and
make it easier to move through the seating.
Lighting Replace light fixtures with more something more contemporary.
Podium + Auditorium Front Replace fabric covering the speakers with new
fabric or with metal or wooden frets. Remove the lattice panels on either side of the
podium. Reduce podium size horizontally
Classical molding could be included in the front with the painting.
Color Current appearance is very brown. Color can be brought into the church with pulpit
fabric, carpeting, and paint. According to decorator seating could be reupholstered, but current gold color is okay.