real solutions presentation 2008 03

Upload: walaywan

Post on 14-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 Real Solutions Presentation 2008 03

    1/84

    11Bowlby & Associates, Inc.

  • 7/29/2019 Real Solutions Presentation 2008 03

    2/84

    22Bowlby & Associates, Inc.

    Bill BowlbyBill Bowlby

    J im OzmentJ im Ozment

    DarleneDarleneReiterReiter

    DougDougDelaney,Delaney,

    TDOTTDOT

  • 7/29/2019 Real Solutions Presentation 2008 03

    3/84

    33Bowlby & Associates, Inc.

    But, first, a word from our sponsorBut, first, a word from our sponsor

    NHI Course 142051,NHI Course 142051,

    Highway Traffic NoiseHighway Traffic NoiseUpcoming sessionsUpcoming sessions

    Nevada, Apr. 1Nevada, Apr. 1--33 public seats availablepublic seats available

    Alabama, Apr. 15Alabama, Apr. 15--1717

    Alaska, May 13Alaska, May 13--1515

    www.nhi.fhwa.dot.govwww.nhi.fhwa.dot.gov

  • 7/29/2019 Real Solutions Presentation 2008 03

    4/84

    44Bowlby & Associates, Inc.

    Real Solutions FormatReal Solutions Format

    Challenge encounteredChallenge encountered

    How was the challenge addressed?How was the challenge addressed?How was the challenge resolved?How was the challenge resolved?

    Lessons learnedLessons learnedQuestion and answer opportunityQuestion and answer opportunity

  • 7/29/2019 Real Solutions Presentation 2008 03

    5/84

    55Bowlby & Associates, Inc.

    TopicsTopics

    FHWA noise regulations and TDOTFHWA noise regulations and TDOT

    noise policy revisionsnoise policy revisionsType II needs assessmentType II needs assessment

    Type II prioritizationType II prioritizationType II program and pilot projectsType II program and pilot projects

  • 7/29/2019 Real Solutions Presentation 2008 03

    6/84

    66Bowlby & Associates, Inc.

    BackgroundBackground

    There was a need to address longThere was a need to address long--

    standing neighborhood concerns for noisestanding neighborhood concerns for noisebarriers on existing highwaysbarriers on existing highways

    New TDOT Commissioner and staff wereNew TDOT Commissioner and staff werecommitted to working with the publiccommitted to working with the public

    Ability to use FederalAbility to use Federal--aid funding (80% ofaid funding (80% of

    total cost) was essentialtotal cost) was essential

  • 7/29/2019 Real Solutions Presentation 2008 03

    7/84

    77Bowlby & Associates, Inc.

    OurOur Marching OrdersMarching Orders

    FHWAFHWA Noise Standards,Noise Standards, 23 CFR 77223 CFR 772

    TDOT Guidelines on Highway TrafficTDOT Guidelines on Highway Traffic

    Noise Abatement, revised in 2006 asNoise Abatement, revised in 2006 as

    TDOT Policy on Traffic Noise AbatementTDOT Policy on Traffic Noise Abatement

  • 7/29/2019 Real Solutions Presentation 2008 03

    8/84

    88Bowlby & Associates, Inc.

    23 CFR 772 Project Categories:23 CFR 772 Project Categories:

    Type I ProjectsType I ProjectsFederal or FederalFederal or Federal--aidaid

    highway project for:highway project for: Construction on newConstruction on new

    locationlocation

    Major change toMajor change toalignment, or addition ofalignment, or addition of

    throughthrough laneslanes

    Noise analysis isNoise analysis is

    requiredrequired

  • 7/29/2019 Real Solutions Presentation 2008 03

    9/84

    99Bowlby & Associates, Inc.

    23 CFR 772 Project Categories:23 CFR 772 Project Categories:

    Optional Type II ProjectsOptional Type II Projects

    Federal orFederal orFederalFederal--aid highwayaid highwayprojectproject solely forsolely fornoise abatementnoise abatement ononan existing highwayan existing highway

  • 7/29/2019 Real Solutions Presentation 2008 03

    10/84

    1010Bowlby & Associates, Inc.

    To qualify for FederalTo qualify for Federal--aid for a Typeaid for a Type

    II project, a neighborhood mustII project, a neighborhood must

    prepre--datedate initialinitial highway construction,highway construction,

    andand

    not have been previously studied for anot have been previously studied for a

    Type I project where a barrier was foundType I project where a barrier was foundto not be feasible and reasonableto not be feasible and reasonable

  • 7/29/2019 Real Solutions Presentation 2008 03

    11/84

    1111Bowlby & Associates, Inc.

    Challenge: TDOT Noise PolicyChallenge: TDOT Noise Policy

    needed updatingneeded updatingHow challenge was addressed:

    2003 Bowlby & Associates study reviewedTDOTs and others policies, andrecommended changes, including new

    reasonableness method

    How challenge was resolved:

    Subsequent analysis, briefings, discussionsand decision-making led to new policy

  • 7/29/2019 Real Solutions Presentation 2008 03

    12/84

    1212Bowlby & Associates, Inc.

  • 7/29/2019 Real Solutions Presentation 2008 03

    13/84

    1313Bowlby & Associates, Inc.

    Policy ChangesAbatement not

    reasonable foruses constructedafter date ofpolicy adoption

    TDOT will

    undertake publiceducation effort

  • 7/29/2019 Real Solutions Presentation 2008 03

    14/84

    1414Bowlby & Associates, Inc.

    Policy Change:

    New Cost-Reasonableness MethodResulting Ranges of Allowable Costs

    per Benefitted Residence

    Development DateFull Range of

    Allowable Costs

    Typical Cost

    Range

    Pre-date Highway or

    New Alignment

    $30,000 - $42,000 $30,000 - $34,000

    Post-date Highway $15,000 - $27,000 $15,000 - $19,000

  • 7/29/2019 Real Solutions Presentation 2008 03

    15/84

    1515Bowlby & Associates, Inc.

    Phases of TDOT Type II ProgramPhases of TDOT Type II Program

    Development and ImplementationDevelopment and Implementation

    Statewide Type II Noise Barrier NeedsStatewide Type II Noise Barrier Needs

    Assessment StudyAssessment Study

    Type II Noise Barrier Prioritization StudyType II Noise Barrier Prioritization Study

    Type II Noise Barrier Program, startingType II Noise Barrier Program, starting

    with Pilot Projectswith Pilot Projects

  • 7/29/2019 Real Solutions Presentation 2008 03

    16/84

    1616Bowlby & Associates, Inc.

    20032003--20042004

    Goal: orderGoal: order--ofof--magnitude program costmagnitude program cost

    Focus on limitedFocus on limited--access highwaysaccess highways

    Phase 1: Statewide Type II NoisePhase 1: Statewide Type II Noise

    Barrier Needs Assessment StudyBarrier Needs Assessment Study

  • 7/29/2019 Real Solutions Presentation 2008 03

    17/84

    1717Bowlby & Associates, Inc.

    Needed relatively simple, quick and inexpensive,Needed relatively simple, quick and inexpensive,yet accurateyet accurate

    Had to identify previous Type I project areasHad to identify previous Type I project areas

    where barriers werewhere barriers were not reasonablenot reasonable

    Had to identify planned widenings that wouldHad to identify planned widenings that would

    require Type I studies (TIP, Long Range Plan)require Type I studies (TIP, Long Range Plan)

    Challenges forChallenges for

    Statewide Needs AssessmentStatewide Needs Assessment

  • 7/29/2019 Real Solutions Presentation 2008 03

    18/84

    1818Bowlby & Associates, Inc.

    How Challenges Were AddressedHow Challenges Were Addressed

    Locate residentialLocate residential

    development alongdevelopment alongroads sectionsroads sections

    Electronic mappingElectronic mapping

    WebWeb--based aerialbased aerial

    photosphotos

    WindshieldWindshield fieldfieldreview with GPSreview with GPS

  • 7/29/2019 Real Solutions Presentation 2008 03

    19/84

    1919Bowlby & Associates, Inc.

    How Challenges Were AddressedHow Challenges Were Addressed

    Residential development date analysis: DidResidential development date analysis: Didany of the development predate initialany of the development predate initial

    highway construction?highway construction?

  • 7/29/2019 Real Solutions Presentation 2008 03

    20/84

    2020Bowlby & Associates, Inc.

    How Challenges Were AddressedHow Challenges Were Addressed

    Simplified FHWA TNM (Traffic NoiseSimplified FHWA TNM (Traffic Noise

    Model) modeling and simplifyingModel) modeling and simplifyingassumptionsassumptions

    Is the residential area impacted?Is the residential area impacted?

    Is a barrier acoustically feasible?Is a barrier acoustically feasible?

    Would barrier cost beWould barrier cost be reasonablereasonable??

  • 7/29/2019 Real Solutions Presentation 2008 03

    21/84

    2121Bowlby & Associates, Inc.

    Challenge: Keeping track ofChallenge: Keeping track of

    everythingeverythingDuring the studyDuring the study

    Easy documentation and referenceEasy documentation and reference PerformingPerforming what ifwhat ifanalysesanalyses

    After the studyAfter the study

    Answering queries from citizens, legislators, andAnswering queries from citizens, legislators, and

    internal managementinternal management

    How challenge was addressed and resolvedHow challenge was addressed and resolved Developed prototype TDOT Traffic Noise ProgramManagement GIS

  • 7/29/2019 Real Solutions Presentation 2008 03

    22/84

    2222Bowlby & Associates, Inc.

    Prototype TDOT Traffic NoisePrototype TDOT Traffic Noise

    Program Management GISProgram Management GIS

    Data implementedData implemented inin

    ArcViewArcView 8.0,with the ESRI8.0,with the ESRI

    ArcGIS StreetMap USAArcGIS StreetMap USA

    8.3 component8.3 componentLinked to ExcelLinked to Excel

    spreadsheet forspreadsheet forrecalculation analysisrecalculation analysis

  • 7/29/2019 Real Solutions Presentation 2008 03

    23/84

    2323Bowlby & Associates, Inc.

  • 7/29/2019 Real Solutions Presentation 2008 03

    24/84

    2424Bowlby & Associates, Inc.

  • 7/29/2019 Real Solutions Presentation 2008 03

    25/84

    2525Bowlby & Associates, Inc.

    Analysis Areas (excluding Type I)Analysis Areas (excluding Type I) 212212

    minusminus TIPTIP 2424

    minusminus PostPost--dated highwaydated highway 6868

    PrePre--dated highway (eligible fordated highway (eligible for

    consideration)consideration)

    120120

    minusminus Not impactedNot impacted 1010

    minusminus Not feasibleNot feasible 55

    minusminus Not reasonableNot reasonable 6969

    Qualified (impacted, feasible, reasonable)Qualified (impacted, feasible, reasonable) 3636

    Statewide Needs Assessment ResultsStatewide Needs Assessment Results

  • 7/29/2019 Real Solutions Presentation 2008 03

    26/84

    2626Bowlby & Associates, Inc.

    TotalTotal order of magnitudeorder of magnitudecost was $32cost was $32

    millionmillionMany areasMany areas on the bubbleon the bubble(between $34,000(between $34,000

    and $37,000 per benefitted residence)and $37,000 per benefitted residence)Many LongMany Long--Range Plan projects adjacent toRange Plan projects adjacent to

    eligible areaseligible areas

    TDOTTDOTs Commissioner decided to initiates Commissioner decided to initiate

    Type II ProgramType II Program

    Statewide Needs Assessment ResultsStatewide Needs Assessment Results

  • 7/29/2019 Real Solutions Presentation 2008 03

    27/84

    2727Bowlby & Associates, Inc.

    20042004--20052005

    Goals:Goals:

    Detailed analysis to identify and help decideDetailed analysis to identify and help decide

    on program scheduling for qualified areason program scheduling for qualified areas

    Development of a Public Response PlanDevelopment of a Public Response Plan

    Phase 2: Type II Noise BarrierPhase 2: Type II Noise Barrier

    Prioritization StudyPrioritization Study

  • 7/29/2019 Real Solutions Presentation 2008 03

    28/84

    2828Bowlby & Associates, Inc.

    Challenge: What criteria should beChallenge: What criteria should be

    considered in deciding which projectsconsidered in deciding which projectsto fund first?to fund first?

    Did not want a ranking of areasDid not want a ranking of areasFactors to considerFactors to consider

    FirstFirst--row sound levelrow sound level Number of firstNumber of first--row impactsrow impacts

    Number of nonNumber of non--firstfirst--row benefitsrow benefits

    Cost per benefitted residenceCost per benefitted residence

    Size and cost of projectSize and cost of project

  • 7/29/2019 Real Solutions Presentation 2008 03

    29/84

    2929Bowlby & Associates, Inc.

    Analysis StepsAnalysis Steps

    Residential development date verificationResidential development date verification

    (majority of residences in first two rows(majority of residences in first two rowsmust premust pre--date initial road)date initial road)

    Noise impact verification / noiseNoise impact verification / noisemeasurementsmeasurements

    SiteSite--specific TNM noise modelingspecific TNM noise modeling

    Updating of TDOT Noise Management GISUpdating of TDOT Noise Management GIS

  • 7/29/2019 Real Solutions Presentation 2008 03

    30/84

    3030Bowlby & Associates, Inc.

    Challenge: Obtaining residentialChallenge: Obtaining residential

    construction date informationconstruction date informationNot all data bases onlineNot all data bases online

    How challenge was addressed:How challenge was addressed: Used onUsed on--line resources where availableline resources where available

    Repeated requests in some countiesRepeated requests in some countiesHow challenge was resolved:How challenge was resolved:

    Most data were obtainedMost data were obtained

    In one case, had to use old aerialIn one case, had to use old aerial

    photography and USGS mapsphotography and USGS maps

  • 7/29/2019 Real Solutions Presentation 2008 03

    31/84

    3131Bowlby & Associates, Inc.

    Some OnSome On--line County GIS Systemsline County GIS Systems

    Were Very UsefulWere Very Useful

  • 7/29/2019 Real Solutions Presentation 2008 03

    32/84

    3232Bowlby & Associates, Inc.

    Using County GIS DXF Files for TNMUsing County GIS DXF Files for TNM

  • 7/29/2019 Real Solutions Presentation 2008 03

    33/84

    3333Bowlby & Associates, Inc.

    Type II Prioritization Study ResultsType II Prioritization Study Results

    Analysis AreasAnalysis Areas 159159minusminus PostPost--dated highwaydated highway 7272

    PrePre--dated highway (eligible for consideration)dated highway (eligible for consideration) 8787

    minusminus Not feasibleNot feasible 55

    minusminus Not eligible land useNot eligible land use 55

    minusminus Low densityLow density 1919

    Areas where measurements conductedAreas where measurements conducted 5858

    minusminus Not impactedNot impacted 1414

    Detailed TNM ModelingDetailed TNM Modeling 4444minusminus Not reasonableNot reasonable 2323

    Qualified (impacted, feasible, reasonable)Qualified (impacted, feasible, reasonable) 2121

  • 7/29/2019 Real Solutions Presentation 2008 03

    34/84

    3434Bowlby & Associates, Inc.

    Challenge: Barrier programmingChallenge: Barrier programming

    Who should be involved in programmingWho should be involved in programming

    process (planning, design, projectprocess (planning, design, project

    management)?management)?

    Political issuesPolitical issues should projects be spreadshould projects be spread

    across the stateacross the states four regions?s four regions?Future Type I projectsFuture Type I projects some Type II areas aresome Type II areas are

    planned to be widened in 10planned to be widened in 10--15 years15 years

    Uncertainties on projecting funding into theUncertainties on projecting funding into thefuturefuture

  • 7/29/2019 Real Solutions Presentation 2008 03

    35/84

    3535Bowlby & Associates, Inc.

    Challenge: Barrier programming (con.)Challenge: Barrier programming (con.)

    Combining adjacent areas for constructionCombining adjacent areas for construction Economies of scaleEconomies of scale

    Minimize construction duration and lane closuresMinimize construction duration and lane closures

    Allocating fundingAllocating funding banking over several yearsbanking over several years(large projects require(large projects require bankingbanking funds for twofunds for two

    or more years)or more years)Balancing projectsBalancing projects phasing for a mix of planningphasing for a mix of planning& engineering, ROW & utilities, and construction& engineering, ROW & utilities, and construction

    Many factors are dynamic, such as wideningMany factors are dynamic, such as wideningschedules and fundingschedules and funding

  • 7/29/2019 Real Solutions Presentation 2008 03

    36/84

    3636Bowlby & Associates, Inc.

    How Challenges Were AddressedHow Challenges Were Addressed

    List of qualified Type II areas was notList of qualified Type II areas was not

    assigned a numerical orderassigned a numerical orderList is dynamic and is reviewed andList is dynamic and is reviewed and

    updated periodicallyupdated periodically

    TDOT environmental division staffTDOT environmental division staff

    requested that a project manager berequested that a project manager be

    assigned to the Type II Program and allassigned to the Type II Program and allprojects within the programprojects within the program

  • 7/29/2019 Real Solutions Presentation 2008 03

    37/84

    3737Bowlby & Associates, Inc.

    How Challenges Were ResolvedHow Challenges Were Resolved

    SelectedSelected top 3top 3areas for pilot programareas for pilot program

    Did not publish a singleDid not publish a single listlistof rankingsof rankingsAssigned an overall program managerAssigned an overall program manager

    (Ann Andrews)(Ann Andrews)Will consider each of the issues whenWill consider each of the issues when

    projects are being programmedprojects are being programmed

    h ll d f if

  • 7/29/2019 Real Solutions Presentation 2008 03

    38/84

    3838Bowlby & Associates, Inc.

    Challenge: Need for uniformChallenge: Need for uniform

    and consistent TDOT responsesand consistent TDOT responsesto abatement requeststo abatement requests

    Hundreds of residential groupings alongHundreds of residential groupings alonglimited access roadway system, notlimited access roadway system, not

    including previously studied Type I areasincluding previously studied Type I areasNeed to be prepared to respond quicklyNeed to be prepared to respond quickly

    and uniformly to inquiries from the publicand uniformly to inquiries from the public

    and public officialsand public officials

  • 7/29/2019 Real Solutions Presentation 2008 03

    39/84

    3939Bowlby & Associates, Inc.

    How Challenge Was Addressed:How Challenge Was Addressed:

    Public Response Plan was developedPublic Response Plan was developedFigures, tables and decision info for eachFigures, tables and decision info for each

    residential area in binders and the GISresidential area in binders and the GISSet of standardized response lettersSet of standardized response letterstailored to specific situations, withtailored to specific situations, with

    supporting info attached:supporting info attached: Area not impactedArea not impacted

    Residences postResidences post--date highwaydate highwayType I areaType I area

    Barrier not feasible or reasonableBarrier not feasible or reasonable

  • 7/29/2019 Real Solutions Presentation 2008 03

    40/84

    4040Bowlby & Associates, Inc.

    Phase 3: Type II ProgramPhase 3: Type II Program

    and Pilot Projectsand Pilot Projects

  • 7/29/2019 Real Solutions Presentation 2008 03

    41/84

    4141Bowlby & Associates, Inc.

  • 7/29/2019 Real Solutions Presentation 2008 03

    42/84

    4242Bowlby & Associates, Inc.

  • 7/29/2019 Real Solutions Presentation 2008 03

    43/84

    4343Bowlby & Associates, Inc.

  • 7/29/2019 Real Solutions Presentation 2008 03

    44/84

    4444Bowlby & Associates, Inc.

  • 7/29/2019 Real Solutions Presentation 2008 03

    45/84

    4545Bowlby & Associates, Inc.

  • 7/29/2019 Real Solutions Presentation 2008 03

    46/84

    4646Bowlby & Associates, Inc.

  • 7/29/2019 Real Solutions Presentation 2008 03

    47/84

    4747Bowlby & Associates, Inc.

    Type II Pilot ProgramType II Pilot Program

    First Year ProgramFirst Year Program

    funded at $3 million forfunded at $3 million for

    three pilot projectsthree pilot projects

    starting in 2005starting in 2005--20062006

    Similar funding levelSimilar funding levelanticipated for futureanticipated for future

    years (total of $25years (total of $25million)million)

  • 7/29/2019 Real Solutions Presentation 2008 03

    48/84

    4848Bowlby & Associates, Inc.

    II--65,65, WoodlandWoodland--inin--WaverlyWaverly, Nashville, Nashville

  • 7/29/2019 Real Solutions Presentation 2008 03

    49/84

    4949Bowlby & Associates, Inc.

    II--55 NB,55 NB,

    MemphisMemphis

  • 7/29/2019 Real Solutions Presentation 2008 03

    50/84

    5050Bowlby & Associates, Inc.

    II--40, Sudekum40, Sudekum

    Homes, NashvilleHomes, Nashville

    Ch llChallenge Obt i i id tObtaining residents

  • 7/29/2019 Real Solutions Presentation 2008 03

    51/84

    5151Bowlby & Associates, Inc.

    Challenge:Challenge: Obtaining residentsObtaining residents

    opinions regarding a proposed barrieropinions regarding a proposed barrierDiffering demographicsDiffering demographics

    Differing levels of communityDiffering levels of communityproactiveness, priorities, and interestsproactiveness, priorities, and interests

    OutsidersOutsidersattending meetingsattending meetingsHow challenge was addressed:How challenge was addressed:

    Demographics of affected residencesDemographics of affected residences

    should be considered in developing a planshould be considered in developing a plan

    for obtaining residentsfor obtaining residents opinionsopinions

    H Ch ll W R l dH Ch ll W R l d

  • 7/29/2019 Real Solutions Presentation 2008 03

    52/84

    5252Bowlby & Associates, Inc.

    How Challenge Was ResolvedHow Challenge Was Resolved

    Regular community meetings worked wellRegular community meetings worked wellin one area where residents were highlyin one area where residents were highly

    involved in the projectinvolved in the projectMailMail--back surveys were used in two areasback surveys were used in two areas

    Poor attendance at meeting in one areaPoor attendance at meeting in one area

    Outsiders attending and voting in the otherOutsiders attending and voting in the otherareaarea

    A second mailA second mail--back survey was sent viaback survey was sent viacertified mail in one area before deciding ifcertified mail in one area before deciding ifthe actual residents wanted the barrierthe actual residents wanted the barrier

  • 7/29/2019 Real Solutions Presentation 2008 03

    53/84

    5353Bowlby & Associates, Inc.

    First Pilot AreaFirst Pilot Area

  • 7/29/2019 Real Solutions Presentation 2008 03

    54/84

    5454Bowlby & Associates, Inc.

    M ti i N i hbMeetings in Neighbors H tHouses at

  • 7/29/2019 Real Solutions Presentation 2008 03

    55/84

    5555Bowlby & Associates, Inc.

    Meetings in NeighborsMeetings in Neighbors Houses atHouses at

    Several Stages in the ProcessSeveral Stages in the Process

    P d B i E l i d tProposed Barrier Explained to

  • 7/29/2019 Real Solutions Presentation 2008 03

    56/84

    5656Bowlby & Associates, Inc.

    Proposed Barrier Explained toProposed Barrier Explained to

    Residents with FiguresResidents with Figures

  • 7/29/2019 Real Solutions Presentation 2008 03

    57/84

    5757Bowlby & Associates, Inc.

    and Photosand Photos

  • 7/29/2019 Real Solutions Presentation 2008 03

    58/84

    5858Bowlby & Associates, Inc.

  • 7/29/2019 Real Solutions Presentation 2008 03

    59/84

    5959Bowlby & Associates, Inc.

    Input Sought onInput Sought on

    Noise BarrierNoise BarrierFinishes,Finishes,

    Colors, andColors, andOther ConcernsOther Concerns

  • 7/29/2019 Real Solutions Presentation 2008 03

    60/84

    6060Bowlby & Associates, Inc.

    Challenge: Avoiding tree removalChallenge: Avoiding tree removal

  • 7/29/2019 Real Solutions Presentation 2008 03

    61/84

    6161Bowlby & Associates, Inc.

    How Challenge Was Addressed:How Challenge Was Addressed:

    Extensive field review and investigationExtensive field review and investigation

  • 7/29/2019 Real Solutions Presentation 2008 03

    62/84

    6262Bowlby & Associates, Inc.

    How Challenge Was Resolved:How Challenge Was Resolved:

    Could not save all theCould not save all the

    treestrees No easements could beNo easements could be

    obtained due to historicobtained due to historic

    nature of areanature of area

    Others had to be leftOthers had to be left

    along with old controlalong with old controlaccess fenceaccess fence

  • 7/29/2019 Real Solutions Presentation 2008 03

    63/84

    6363Bowlby & Associates, Inc.

    Groundbreaking day arrivesGroundbreaking day arrives

  • 7/29/2019 Real Solutions Presentation 2008 03

    64/84

    6464Bowlby & Associates, Inc.

    with exhibitswith exhibits

  • 7/29/2019 Real Solutions Presentation 2008 03

    65/84

    6565Bowlby & Associates, Inc.

    press coveragepress coverage

  • 7/29/2019 Real Solutions Presentation 2008 03

    66/84

    6666Bowlby & Associates, Inc.

    neighborsneighbors remarksremarks

  • 7/29/2019 Real Solutions Presentation 2008 03

    67/84

    6767Bowlby & Associates, Inc.

    and shovelsand shovels

  • 7/29/2019 Real Solutions Presentation 2008 03

    68/84

    6868Bowlby & Associates, Inc.

    The Finished ProjectThe Finished Project

  • 7/29/2019 Real Solutions Presentation 2008 03

    69/84

    6969Bowlby & Associates, Inc.

    D di ti CDedication Ceremon AA

  • 7/29/2019 Real Solutions Presentation 2008 03

    70/84

    7070Bowlby & Associates, Inc.

    Dedication CeremonyDedication CeremonyAA

    December 21December 21stst Christmas PresentChristmas Present

  • 7/29/2019 Real Solutions Presentation 2008 03

    71/84

    7171Bowlby & Associates, Inc.

    Very Happy NeighborsVery Happy Neighbors

  • 7/29/2019 Real Solutions Presentation 2008 03

    72/84

    7272Bowlby & Associates, Inc.

    Countdown begins for the last panelCountdown begins for the last panel

  • 7/29/2019 Real Solutions Presentation 2008 03

    73/84

    7373Bowlby & Associates, Inc.

  • 7/29/2019 Real Solutions Presentation 2008 03

    74/84

    7474Bowlby & Associates, Inc.

  • 7/29/2019 Real Solutions Presentation 2008 03

    75/84

    7575Bowlby & Associates, Inc.

    It fits !!It fits !!

    Nothing like a round of applauseNothing like a round of applause

  • 7/29/2019 Real Solutions Presentation 2008 03

    76/84

    7676Bowlby & Associates, Inc.

    Nothing like a round of applauseNothing like a round of applause

    after a State DOT projectafter a State DOT project

  • 7/29/2019 Real Solutions Presentation 2008 03

    77/84

    7777Bowlby & Associates, Inc.

    Ongoing Type II ProgramOngoing Type II Program

    PilotsPilots

    II--55, Memphis: rejected by neighbors55, Memphis: rejected by neighbors II--40, Sudekum Homes: construction contract40, Sudekum Homes: construction contract

    has been lethas been let

    Anderson CountyAnderson County

  • 7/29/2019 Real Solutions Presentation 2008 03

    78/84

    7878Bowlby & Associates, Inc.

    Lessons LearnedLessons LearnedThe process takes time, but it worksThe process takes time, but it works

    Management/oversight: Very important toManagement/oversight: Very important to

    have an experienced project managerhave an experienced project managerassigned to the Type II programassigned to the Type II program

    Project development: Early and continualProject development: Early and continualinvolvement of all affected staff is essentialinvolvement of all affected staff is essential

    d ( )

  • 7/29/2019 Real Solutions Presentation 2008 03

    79/84

    7979Bowlby & Associates, Inc.

    Lessons Learned (con.)Lessons Learned (con.)

    ProgrammingProgramming

    Many factors affect what can be programmedMany factors affect what can be programmedand whenand when

    Many of these factors are dynamic andMany of these factors are dynamic and

    require continual rerequire continual re--assessment of plansassessment of plans

    Staging of projects can help spread out theStaging of projects can help spread out the

    loadload

    L L d ( )

  • 7/29/2019 Real Solutions Presentation 2008 03

    80/84

    8080Bowlby & Associates, Inc.

    Lessons Learned (con.)Lessons Learned (con.)

    Public InputPublic Input Develop public involvement plan with consideration ofDevelop public involvement plan with consideration of

    demographics of affected residentsdemographics of affected residents Do not expect to be able to anticipate what the publicDo not expect to be able to anticipate what the publicwantswants

    Public ResponsePublic Response Clear and consistent responses to local officials,Clear and consistent responses to local officials,representatives and members of the public arerepresentatives and members of the public areimportantimportant

    Engage the public the best you can, being honestEngage the public the best you can, being honestwith expectationswith expectations

    Follow through on promisesFollow through on promises

    d ( )L L d ( )

  • 7/29/2019 Real Solutions Presentation 2008 03

    81/84

    8181Bowlby & Associates, Inc.

    Lessons Learned (con.)Lessons Learned (con.)

    Ongoing CommunicationOngoing Communication

    Use the Public Relations office often andUse the Public Relations office often andeffectivelyeffectively

    WellWell--defined open communication systemdefined open communication system

    between residents and TDOT helped projectbetween residents and TDOT helped projectproceed smoothly and eliminated issuesproceed smoothly and eliminated issues

    during constructionduring construction

    S d C l iS d C l i

  • 7/29/2019 Real Solutions Presentation 2008 03

    82/84

    8282Bowlby & Associates, Inc.

    Summary and ConclusionsSummary and Conclusions

    TDOT was willing to address longTDOT was willing to address long--standingstanding

    traffic noise problems along its highwaystraffic noise problems along its highways

    Statewide needs assessment was critical forStatewide needs assessment was critical for

    decisiondecision--makersmakers

    Prototype Traffic Noise Management GISPrototype Traffic Noise Management GISwas and is still very helpfulwas and is still very helpful

    Programming of projects is complexProgramming of projects is complexThe first pilot project seems to be a successThe first pilot project seems to be a success

  • 7/29/2019 Real Solutions Presentation 2008 03

    83/84

    8383Bowlby & Associates, Inc.

    Acknowledgments to Tennessee DOT andAcknowledgments to Tennessee DOT andthe Federal Highway Administration forthe Federal Highway Administration for

    funding, assistance, and support for allfunding, assistance, and support for all

    aspects of our workaspects of our work

  • 7/29/2019 Real Solutions Presentation 2008 03

    84/84

    Questions?Questions?

    Bill BowlbyBill Bowlby

    [email protected]@bowlbyassociates.com615615--771771--3006 ext 2253006 ext 225

    Darlene ReiterDarlene [email protected]@bowlbyassociates.com

    615615--771771--3006 ext 2263006 ext 226

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]