RCAF Force Development
Presented by Colonel Steve Chouinard
Director of Air Requirements
3 April 2017
THE AIR FORCE
DEVELOPMENT TEAM
Commander RCAF
LGen Hood
Deputy Comd RCAF
MGen Harris
DG Air FD
BGen lalumiÈre
DAR
Col Chouinard
DAST
Col alexander
DADD
Col Thibert
D Air Prog
Lcol Whalen
• Aircraft (including UAS) • Electronic Warfare Equipment • Support Equipment • Vehicles • Uniforms & Accoutrements
• Modeling & Simulation • Future Air Crew Training • Training contract management
• ie CATS / NFTC / CFTS • International Pilot Training
• Radar Systems • IM/IT Systems • C2 and C4ISR • Cyber / NORAD / NWS
• RCAF Minor Capital Programme Oversight • Minor Requirements Program • Governance
DG Space
BGen Frawley
D Air SP
Col stoltz
CFAWC
Col Truss
DG FCO
MGen pelletier
S&T + DRDC + CORA
MHP
2
RCAF Capability Development Framework
CF-18 Project
Interim Fighter Capability Project
Future Fighter Capability Project
Definition Implementation Delivery
Implementation Delivery
OA Definition Implementation Delivery
Definition
Fighter Capability Plan
OA
4
MHP – CH148 Cyclone
Description: Acquire 28 CH148 Cyclone helicopters (Sikorsky) to provide
a shipborne maritime helicopter capable of conducting Anti-
Submarine Warfare (ASW), Intelligence, Surveillance and
Reconnaissance (ISR), Search and Rescue (SAR) and utility
missions. Project includes ship modifications, training, facility
upgrades and In-Service Support.
Project Milestones
Contract Award Nov 2004
Capability Delivery in Blocks
Block I – Initial Surveillance, ASW and Utility (delivery in progress) Block II – Fully Operationally Capable
Initial Operational Capability 2018
In-Service Support end 2038 (est)
Current Stage: Implementation
CP140 Aurora
AIMP Block III & IV / ASLEP Projects
5
Project Milestones
ASLEP and AIMP Block III – Initial Operational Capability in 2014 with Full Operational Capability by 2019
AIMP Block IV – Initial Operational capability in 2019 with Full Capability in early/mid-2020s
Description: To structurally life-extend and operationally upgrade 14
CP140 Aurora aircraft in order to support operations to
2030. Blocks I and II upgraded legacy and communications
and navigation systems. Block III and ALSEP are
underway and will upgrade all mission and sensor systems
concurrent with structural life extension. Block IV will add a
wideband SATCOM capability as well as Link 16 and a self-
protection suite.
Current Stage: Implementation
CH146 Griffon
Limited Life Extension (GLLE)
Description:
To extend CH146 operating life to 2030+
through the replacement of obsolete avionics,
instrumentation and displays with an integrated
digital systems architecture.
Project Milestones Contract Award 2020 IOC 2024 FOC 2026
Current Stage: Option Analysis
Cormorant Mid-Life Upgrade
(CMLU)
Description:
To extend the operational life of the CH149 to at
least 2040 and provide capability improvements
to enhance its overall mission effectiveness.
7
Project Milestones Definition Approval 2020 Contract Award 2023
Current Stage: Option Analysis
CC144 Challenger
Consolidation Project (CCP)
Description:
To extend Administrative Flight Service
capability for VVIPs and continue Utility Flight
Services (such as Aeromedical Evacuation and
Disaster Assistance Response Team advance
party) as a cost effective alternative to other
RCAF fleets and commercial air.
Project Milestones
Definition Approval 2019
Contract Award 2021
Current Stage: Option Analysis
Joint Unmanned Surveillance
& Target Acquisition System (JUSTAS)
Description:
To provide an all-weather, persistent,
intelligence, surveillance, reconnaissance and
payload delivery capability in support of CAF
domestic and expeditionary operations.
Project Milestones (Ranges) Contract Award 2020-2022
IOC 2025-2028 (1 line of tasking available for operations)
FOC 2026-2029 (3 lines of tasking, aircraft, infrastructure & personnel in-situ)
Current Stage: Option Analysis
Snow and Ice Control Capability
Recapitalization (SNICCR)
Description:
This project will provide high speed snow
removal and de-icing equipment designed for
airfield operation, to replace an aging fleet of
snow and ice control equipment.
Current Stage: Option Analysis
Project Milestones
Definition Jun 17
Implementation May 18
IOC Nov 20
Armament Loader Replacement
(ALR)
Description:
This project will provide a safe and reliable
armament loader fleet capable of supporting
CF188 fighter aircraft operations.
Current Stage: Definition
Project Milestones
Definition / Implementation Jun 17
IOC Aug 18
CMA – Canadian Multi-Mission Aircraft
12
Project Milestones
Initial Operational Capability in early 2030s
Full Operational Capability by mid 2030s
Estimated Life Expectancy 2060
Intent is to pursue opportunities for innovation with industry with a view to building on
the strengths of and lessons learned from AIMP
Description:
To equip the CF with a long-range manned Maritime Patrol,
Anti-Submarine Warfare (ASW) capable, Command and
Control, Communications and Computers (C4) and
Intelligence, Surveillance and Reconnaissance (ISR) aircraft
to complement existing and future ASW and C4ISR
capabilities such as JUSTAS, CH148 Cyclone and space-
based solutions.
Current Stage: Identification
13
Strategic Tanker Transport Capability
(STTC)
Project Milestones
Definition 2020
Contract Award 2022
Description:
This project will replace the existing fleet capability,
including strategic airlift, air-to-air refuelling and VIP
transport after a potential life extension. The platform
will provide air-to-air refuelling for both domestic and
expeditionary coalition operations, while complementing
the strategic airlift capabilities of the CC-177 fleet.
Current Stage: Identification
14
Future Aircrew Training (FAcT)
Current Situation: Options Analysis
Description:
Address the modernization/optimization of the ab initio Pilot,
ACSO and AES Op training to Wings Standard. FAcT is to
implement a relevant, flexible, effective and affordable
solution which modernizes/optimizes the training system to
meet current and future CAF requirements. The solution
must continue and improve upon the training currently
provided by the expiring NFTC and CFTS services contracts
as well as the training currently conducted at 402 Squadron.
Project Milestones
Contract Award: 2021
Initial Operating Capability: 2023
Full Operating Capability: 2027
15
Tactical Integrated Command, Control and Communications (TIC3) Air
Current Situation: Options Analysis
Description:
(1) Replace and modernize RCAF Air Traffic
Management and Air Defence radio networks,
(2) establish domestic Link-16 and Streaming
Video Ground Entry Sites and standardize
deployable Tactical Data Link and Streaming
Video capability, and (3) provide a Link-16
capability to the CC150 Polaris Tankers.
Project Milestones
Contract Award 2018
IOC 2021
FOC 2024
16
CAF PED/DGS-CAN
Description: CAF PED concept to enable the effective use of centralized
PED resources in support of, and responsive to, any
domestic and/or deployed operations
Interoperability with United States, United Kingdom and
Australia (US, UK, AUS, CAN)
Current situation: Research phase
Notional Milestones
DGS-Canada Trial - Oct-May 2018
DGS-Canada IOC - Spring 2018 +
Defence Acquisition Guide
17
http://www.forces.gc.ca/en/business-defence-acquisition-guide-2016/aerospace-systems.page
Minor Capital Projects