r.bailey, january 2008 procedures phase a pilot physics run (43 to 156 bunches) oplhccwg document...
TRANSCRIPT
R.Bailey, January 2008R.Bailey, January 2008
ProceduresProcedures
Phase APilot physics run (43 to 156 bunches)
OP LHCCWG Document statusJanuary 2008
A.1 injection and first turn Magali Brennan Released
A.2 circulating beam, RF capture Magali Gianluigi In work
A.3 450 GeV, initial commissioning Verena Rhodri Under Approval
A.4 450 GeV, optics meas Stefano Frank Released
A.5 450 GeV, increase intensity Laurette Jan In work
A.6 450 GeV, two beam operation Walter/Verena Ralph Engineer check
A.7 450GeV, collisions Magali Helmut In work
A.8 snapback and ramp Reyes Mike In work
A.9 top energy checks with beam Walter Frank Engineer check
A.10 top energy, collisions Reyes Helmut In work
A.11 squeeze Stefano Massimo Released
A.12 experimental magnets Delphine Helmut In work
R.Bailey, January 2008R.Bailey, January 2008
Getting ready for beam (situation end of 2007)Getting ready for beam (situation end of 2007)
Power tests of the magnet Power tests of the magnet circuitscircuits
Guess based on latest info from Katy et al
Sector Cool down Power tests When ready
12 11 - 16 17 - 29 July
23 08 - 13 14 - 24 June
34 14 - 19 20 - 27 July
45 19 - 24 25 - 28 July
56 05 - 09 10 - 21 May/June
67 08 - 13 14 - 21 May/June
78 04 - 09 10 - 21 May/June
81 06 - 11 12 - 24 June
For the other accelerator For the other accelerator systemssystems Finish installationFinish installation Component testsComponent tests Individual system testsIndividual system tests Integration into operationIntegration into operation
Readiness reviewsReadiness reviews
Dry runsDry runs
Machine checkoutMachine checkout
Take over finished sectors Take over finished sectors for operational testingfor operational testing
R.Bailey, January 2008R.Bailey, January 2008
Injection and first turn / Circulating beam
Phase Step Activity Who (OP +)
A.1
A1.1 Commission injection region: beam 2, 1 pilot BT BI
A1.2 Threading around the ring: beam 2 BT BI AP
A1.3 Commission injection region: beam 1 BT BI
A1.4 Threading around the ring: beam 1 BT BI AP
A1.5 Check interleaved threading: beam 1 and beam 2 OP
Phase Step Activity Who (OP +)
A.2
A2.1 Instrumentation and corrector checks (Interleaved) CO BI
A2.2 Establish closed orbit (One beam at a time) OP
A2.3 Measurements with few turns (One beam at a time) AP
A2.4 Offsets between different sectors (Interleaved) OP
A2.5 RF observation equipment (One beam at a time) RF
A2.6 SPS-LHC Energy matching (Mostly interleaved) RF
A2.7 Synch Loop commissioning and beam capture (Interleaved) RF
R.Bailey, January 2008R.Bailey, January 2008
450 GeV, initial commissioning
Phase Step Activity Who (OP +)
A.3
A3.1 Final RF commissioning with Pilot Intensity RF
A3.2 BCTFR and BPM checks with Pilot Intensity BI
A3.3 First Commissioning of Beam Dumping System (pilot) BT BI ATB
A3.4 Commission systems with higher intensity (3 x 1010) BT BI RF
A3.5 Establish cycling machine (3 x 1010) OP
A3.6 Lifetime optimisation (3 x 1010) OP
A3.7 Further commissioning of beam instrumentation (3 x 1010) BI
A3.8 Basic optics checks in addition to LOCO Results (3 x 1010) AP BI RF
A3.9 Further commissioning of beam dumping system (3 x 1010) BT BI
A3.10 Commission feedback systems (3 x 1010) RF BI
A3.11 Rough Setting up of the TDI (3 x 1010) BT
R.Bailey, January 2008R.Bailey, January 2008
450 GeV, optics meas
Phase Step Activity Who (OP +)
A.4
A4.1 Measurement and correction of the closed orbit AP BI
A4.2 Measurement and correction of the linear optics AP BI
A4.3 Measurement and correction of the aperture AP
A4.4 Detailed RF measurements RF
A4.5 Measurement of the momentum aperture AP
A4.6 Collimators and protection devices for energy ramp Coll
A4.7 Measurements of the global non-linear optics AP
A4.8 Commissioning of the non-linear correctors AP
A4.9 Commissioning of bumps in the IR's AP
A4.10 Detailed injection matching AP BT
A4.11 Detailed beam loss studies BI Coll
A4.12 Tracking errors: measurements and corrections OP PO
R.Bailey, January 2008R.Bailey, January 2008
450 GeV, increase intensity
Phase Step Activity Who (OP +)
A.5
A5.1 Tuning of injection protection (up to 4 bunches, 1e10 p+/bunch) BT BI CO
A5.2 Commissioning of the beam dumping system (43 bunches) BT BI AP RF
A5.3 Check Beam Instrumentation and beam parameters (43 bunches) BI
A5.4 Check MPS functionality of BLM (43 bunches) BI
A5.5 Setting-up of RF (43 bunches) RF
A5.6 Setting-up of the ring betatron and momentum collimation (43b) Coll
A5.7 Re-check and optimize injection settings (43b, 4e10 p+/bunch) BT
A5.8 Check some of the previous steps with 43b, 4e10 p+/bunch BT BI RF
A5.9 Check intensity dependence of safe beam flag CO
A5.10 Check beam load on cryogenics and vacuum system Cryo Vac
A5.11 Fine tuning of injection (156b, 1e10 p+/bunch to 9e10 p+/bunch) PO
A5.12 Commission beam dump system (156 bunches) BT BI CO
A5.13 Check Beam Instrumentation and beam parameters (156b) BT BI AP RF
A5.14 Setting-up of the RF (156 bunches) RF
A5.15 Setting-up of the betatron and momentum collimation (156b) Coll
A5.16 Setting-up of the transfer line collimators (156 bunches) BT Coll
R.Bailey, January 2008R.Bailey, January 2008
450 GeV, two beam operation / 450GeV collisions
Phase Step Activity Who (OP +)
A.6
A6.1 Preparation OP
A6.2 Optimize correctors settings OP
A6.3 IR set up: separation bumps, SIS limits (first part) AP
A6.4 IR set up: aperture measurements with separation on Coll
A6.5 IR set up: separation bumps, SIS limits (second part) AP
A6.6 IR set up: triplet alignment checks (k modulation) AP
A6.7 Fine tune RF phase to guarantee collisions at IP AP
A6.8 Set up of two beam collimators (TCTVB) Coll
A6.9 Equalize beam characteristics OP
A6.10 Multi-bunch operation: initially 12 bunches AP
A6.11 Equalize beam characteristics AP
Phase Step Activity Who (OP +)
A.7
A7.1 Get Beams into Collision in the X,Y plane OP
A7.2 Measure and correct longitudinal position RF
A7.3 Monitor lifetime, beam losses and keep background low and stable OP
A7.4 Monitor luminosity during the fill provided by the experiments OP
R.Bailey, January 2008R.Bailey, January 2008
Snapback and ramp / Top energy checks
Phase Step Activity Who (OP +)
A.8
A8.1 Separation scans (simple orthogonal separation for commissioning) AP
A8.2 Ramp single beam; ring 1 MA RF BI
A8.3 Post Ramp analysis RF AP
A8.4 Beam at Intermediate Intensity AP BT
A8.5 Iterate OP
A8.6 Commission collimators in the ramp Coll
A8.7 Commission feedback using PLL BI
Phase Step Activity Who (OP +)
A.9
A9.1 Measure and correct closed orbit after ramp AP BI Coll
A9.2 Measure & correct linear optics, verify reproducibility cycle - cycle AP
A9.3 Optimize beam extraction AP BT
A9.4 Check apertures and adjust collimators, including tertiaries AP BI Coll
A9.5 Characterize & optimize beam conditions: emittances, lifetimes AP
A9.6 Pre squeeze optics checks AP
A9.7 Measure & correct global non-linear optics AP
R.Bailey, January 2008R.Bailey, January 2008
Top energy, collisions / Squeeze
Phase Step Activity Who (OP +)
A.10
A10.1 Get Beams into Collision in the X,Y plane OP
A10.2 Measure and correct longitudinal position RF
A10.3 Monitor lifetime, beam losses and keep background low and stable OP
A10.4 Separation scans (simple orthogonal separation for commissioning) AP
A10.5 Monitor luminosity during the fill provided by the experiments OP
A10.6 Waist measurement AP
A10.7 Measure b* AP
A10.8 Optimize Luminosity: beam-beam transfer function AP
A10.9 Absolute luminosity determination: beam parameters AP
A10.10 Absolute luminosity determination: Van de Meer AP
Phase Step Activity Who (OP +)
A.11
A11.1 Beam-based calibration and settings of collimators Coll
A11.2 Load magnet settings into hardware AP
A11.3 Running the betatron squeeze AP
A11.4 Preparation to bring the beams in collision AP
R.Bailey, January 2008R.Bailey, January 2008
Experimental magnets
Phase Step Activity Who (OP +)
A.12
A12.1 Switch ON Alice solenoid with beams circulating at 450Gev
A12.2 Ramp Alice solenoid to nominal current
A12.3 Switch ON Atlas solenoid + toroids, beams circulating at 450Gev
A12.4 Ramp Atlas solenoid and toroids to nominal current
A12.5 Switch ON CMS solenoid, beams circulating at 450Gev
A12.6 Ramp CMS to nominal current
A12.7 The orbit measurement and corrections has to be repeated with the crossing angle ON, in phase B of the beam commissioning : CMS magnet will create an orbit distortion that will not be negligible
A12.8 Take a reference orbit for both beams
A12.9 Dump beams in LHC
A12.10 Switch ON LHCb magnets and the compensators
A12.11 Switch on ALICE magnets and compensators
R.Bailey, January 2008R.Bailey, January 2008
Readiness reviews
Phase Need to check readiness of Max beam Who (OP +)
A.2
Closed orbit systemSector offset toolsRF beam observationEnergy matching toolsRF loops
Pilot
COBIAPRF
Phase Need to check readiness of Max beam Who (OP +)
A.1
Injection region equipment (magnetic and TDI)BTVsThreadingBPMFast BCT
PilotBTBI
Phase Need to check readiness of Max beam Who (OP +)
A.3
RF systemsBeam dump with pilotTDIBCTTune meter and PLLWire scannersSynchrotron lightRest Gas Ionisation monitorMulti turn acquisitionFeedback systems
3 1010
RFATBBIBT
R.Bailey, January 2008R.Bailey, January 2008
Readiness reviews
Phase Need to check readiness of Max beam Who (OP +)
A.4
At 450GeV Tune Coupling Beta beating Dispersion Aperture Momentum aperture Q’ Q’’ Non linear correctors Separation bumpsCollimators and protection devices for rampTracking between sectors
3 1010
APBIRFCollBTPO
Phase Need to check readiness of Max beam Who (OP +)
A.5
Injection protection devicesMachine protection systemsBeam dump with multi bunchesBI with multi bunchesRF with multi bunchesCollimationBeam loads on cryogenicsBeam loads on vacuum
43 / 156 4 1010
BT BI MPCORFCollCryoVac
R.Bailey, January 2008R.Bailey, January 2008
Readiness reviews
Phase Need to check readiness of Max beam Who (OP +)
A.6
Injection with 2 beamsSeparation bumpsBI with 2 beamsRF with 2 beamsBeam dump with 2 beamsAperture
43 / 156 4 1010
BTBIRFAPColl
Phase Need to check readiness of Max beam Who (OP +)
A.7Beams in collisionLongitudinal adjustment
43 / 156 4 1010
APRF
Phase Need to check readiness of Max beam Who (OP +)
A.8
Ramp progressively to intermediate energies toolsBIFeedbacksTrackingBeam dumpCollimators
43 / 156 4 1010
APFidel teamRFBIBTColl
R.Bailey, January 2008R.Bailey, January 2008
Readiness reviews
Phase Need to check readiness of Max beam Who (OP +)
A.9
At top energy Tune Coupling Beta beating Dispersion Aperture Momentum aperture Q’ Q’’ Non linear correctors Separation bumps
43 / 156 4 1010
APBICollBT
Phase Need to check readiness of Max beam Who (OP +)
A.10
Beams in collision toolsLongitudinal adjustmentLuminosity optimisationWaist measurementBeta measurement
43 / 156 4 1010
RFAP
Phase Need to check readiness of Max beam Who (OP +)
A.11Squeeze progressively to lower betaCollimators
43 / 156 4 1010
CollAP
R.Bailey, January 2008R.Bailey, January 2008
Extended LTCExtended LTC
Provisionally (RB, PC, OB, SM last week)Provisionally (RB, PC, OB, SM last week) March 3-7March 3-7 5 principal topics5 principal topics
Issues for injection into part of the machine (Mike)Issues for injection into part of the machine (Mike) Access, interlocks, RP, impact on hwc etcAccess, interlocks, RP, impact on hwc etc
From hwc to full machine commissioning (Gianluigi)From hwc to full machine commissioning (Gianluigi) Dry runs, machine checkout, overview of beam commissioning plansDry runs, machine checkout, overview of beam commissioning plans
Readiness and beam plans for accelerator systems (Roger)Readiness and beam plans for accelerator systems (Roger) Injection, extraction, RF, collimation etcInjection, extraction, RF, collimation etc
Readiness and beam plans for AP and BI systems (Oliver)Readiness and beam plans for AP and BI systems (Oliver) Aperture, beta beating, dispersion, optics etcAperture, beta beating, dispersion, optics etc
Readiness and beam plans for control systems (Jorg)Readiness and beam plans for control systems (Jorg) LSA, logging, post mortem, fixed displays etcLSA, logging, post mortem, fixed displays etc
R.Bailey, January 2008R.Bailey, January 2008
LHCCWG topics 2008LHCCWG topics 2008
0 crossing angle filling schemes 0 crossing angle filling schemes WernerWerner Feb 12Feb 12 Parameters and tolerancesParameters and tolerances MassimoMassimo ?? 75ns (and 25ns) operation75ns (and 25ns) operation ?? ??