8/18/2019 Rate Build Up For Construction Materials.
1/4
A
SITE CLEARANCE
10hrs of unskilled labour 10 125 1250
Add 25% p&oh 0.25 312.5
1562.5 1562.5
EXCAVATION OF VEGETABLE TOPSOIL
Excvtn of veg. Topsoil 150mm deep
(0.45hrs/m sq) 0.45 125 56.25
Add 25% p&oh 0.25 14.0625
70.3125 70.3125
TRENCH EXCAVATION
Excvt trnch. For ground beam
(2.2hrs/m cube of unskilled labour) 2.2 125 275
Add 25% p&oh 0.25 68.75
343.75 343.75
excvtn of wk. Space 2.2 125 275
Add 25% p&oh 0.25 68.75
343.75 343.75
EARTHWORK SUPPORT
Cost of 3.6m x 0.3m plank (1.08m sq) 800
no. Of plank in 1m sq 1.85
cost of 1m sq of plank 740
cost of transportation 50
790
Add 7.5% waste 0.075 59.25
849.25
Labour for fixing and striking
(1.5hrs of unskilled labour) 1.5 125 187.5
(2hrs of skilled labour) 2 250 500
1536.75
Add 25% P&oh 0.25 384.1875
1920.938 1920.938
PROTECTION
Allow for keeping the site free from water 20000
WHEEL AND SPREAD
Wheel and spread top soil 150mm deep
(1hr of unskilled labour) 1 125 125
Spread and level
(1.5hrs of unskilled) 1.5 125 187.5
312.5
Add 25% profit & O/h 0.25 78.125
390.625 390.625
REMOVAL OF SURPLUS SOIL
Remove surplus soil 1.5hrs of unsilled labour 1.5 125 187.5
Add 25% profit & O/h 0.25 46.875
234.375 234.375
J BACKFILLING
Backfilling of excavated material 1.50 man hour
spread and level exc. Mat. 0.75 man hour
2.25 man hour@ 125/h 2.25 125 281.25
Add 25% profit and O/h 0.25 70.3125
351.5625 351.5625
-
8/18/2019 Rate Build Up For Construction Materials.
2/4
K FILLING TO MAKE UP LEVEL
5 Cubic meter of sharp sand 15000
1cubic met o 3000
T/4 300mm of sharp sand 0.3 900
20% Consolidation 0.2 180
0.45 man hour labour 0.45 125 56.25
1136.25
Add 25% profit and O/h 0.25 284.0625
1420.313 1420.313
L LEVEL AND COMPACT
LEVEL AND COMPACT FDN. TRENCH 0.75 man hour
( for skilled & unskilled) 0.75 375 281.25
Add 25% profit and O/h 0.25 70.3125
351.5625 351.5625
M ANTI TERMITE SOLUTION
4 litres of anti-termite soln. 2000
0.5 litres needed/m sq 250
0.2 hrs of skilled labour 0.2 250 50
Add 25% profit & O/h 1.25 300
375 375
N CONCRETE BLINDING
I CUBIC METER OF CEMENT= 28 BAGS @1600 28 1600 44800
LOADING AND OFF-LOADING 3000
10 CUBIC METER OF AGG. @ N5,249 10 5249 52490
11 CUBIC METER OF CONCRETE 11 100290
1 CUBIC METER OF CONRETE = 9117.273
Add 40% void 0.4 3646.909
Add 0.75 man-hour labour rate 0.75 375 281.25
13045.43
Add 25% profit and O/h 0.25 3261.358
16306.79 16306.79
P DITTO CONCRETE OVER DAMP PROOF
I CUBIC METER OF CEMENT= 28 BAGS @1600 28 1600 44800LOADING AND OFF-LOADING 3000
10 CUBIC METER OF AGG. @ N5,249 10 5249 52490
11 CUBIC METER OF CONCRETE 11 100290
1 CUBIC METER OF CONRETE = 9117.273
Add 40% void 0.4 3646.909
Add 0.75 man-hour labour rate 0.75 375 281.25
13045.43
Add 25% profit and O/h 0.25 3261.358
16306.79
GROUND BEAM IN-SITU REINFORC ED CONCRETE 1:2:4 - 19mm agg.
er of ceme METER OF CEMENT @ N1600 28 1600 44800
TRANSPORT/CARRIAGE 28 100 2800
1 CUBIC METER OF CEMENT 47600
fine agg.
5 cubic meter of sand 15000
2 cubic meter of sharp sand 6000
Coarse agg.
-
8/18/2019 Rate Build Up For Construction Materials.
3/4
1 cubic meter of granite 7853
4cubic meter of granite 31414
7 cubic meter of concrete 7 85014
1 cubic meter of concrete 12144.86
Add 40% for waste/compaction 0.4 4857.943
5.42 man hour labour@N375 5.42 375 2032.5
19035.3Add 25% profit and O/h 0.25 4758.825
23794.13 23794.13
RAFT SLAB
DITTO AS DESCRIBED ABOVE
1 cubic me UBE OF METER @N1600 28 1600 44800
TRANSPORT/CARRIAGE 28 100 2800
FINE AGG.
5 CUBIC METER 15000 6000
2CUBIC METER OF SHARP SAND
COARSE AGG.
1 CUBIC METER OF GRANITE 7853
4CUBIC METER OF GRANITE 31414
7 CUBIC METER OF CONCRETE 7 85014
1 CUBIC METER OF CONCRETE 12144.86
Add 40% for waste/compaction 0.4 4857.94
5.42 man hour labours@N 375 5.42 375 2032.5
(For skilled and unskilled) 19035.3
Add 25% profit and O/h 0.25 4758.825
23794.13 23794.13
ENTRANCE SLAB
Ditto for entrance step 23794.13
10- 20mm reinforcement 1 ton of Y10mm reinforcement 185000
Carriage/loading/off-loading 1000
186000
Off- cut (5% waste) 0.05 9300
195300
5Kg of binding wire 2500
6hrs of labour 6 250 1500
199300
1 kg of reinforcement 1000 199.3
Add 25% profit/Oh 0.25 49.825
249.125 249.125
12-16mm reinforcemnt for raft slab 1 ton of Y10mm reinf. 185000
Carriage/loading/off-loading 1000
Off-cut (5% waste) 9300
5kg of binding wire 2500
6hrs of labour 6 250 1500
199300
1 kg of reinforcement 199.3
Add 25% O/H and profit 0.25
-
8/18/2019 Rate Build Up For Construction Materials.
4/4
FORMWORK
cost of 3.6x0.3m plank (1.08m2) 800
No. Of planks in 1m2 of formwork 0.93 plank
cost of 1m2 of plank 740
cost of transportation 50
Add 7.5% for waste 59.25
cost of vertical supports 50x75mm plank 300
1.5hrs of unskilled labour for fixing/striking 1.5 125 187.5
2.0hrs of skilled labour 2 250 500
Allow for 1 pound of nail 200
2036.75
Allow for 25% O/h and profit 0.25 509.1875
2545.938 2545.938
EDGES OF RAFT FLOOR SLAB
3.6m length of 300x25mm plank 800
1m length of plank 3.6 222.2222
cost of 0.1hr of skilled labour 0.1 250 25
247.2222
Add 25% profit and O/h 0.25 61.80556
309.0278 309.0278
DAMP PROOF MEMBRANE
COST OF 1000mm guage polythene material/sq m
(2 layers) 600
0.2hrs of skilled labour 0.2 250 50
650
Add profit & O/h 25% 0.25 162.5
812.5 812.5
PROTECTION 100 100