rate build up for construction materials

Upload: akintonde-oyewale

Post on 07-Jul-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/18/2019 Rate Build Up For Construction Materials.

    1/4

    A

      SITE CLEARANCE

    10hrs of unskilled labour 10 125 1250

    Add 25% p&oh 0.25 312.5

    1562.5 1562.5

    EXCAVATION OF VEGETABLE TOPSOIL

      Excvtn of veg. Topsoil 150mm deep

    (0.45hrs/m sq) 0.45 125 56.25

    Add 25% p&oh 0.25 14.0625

    70.3125 70.3125

    TRENCH EXCAVATION

    Excvt trnch. For ground beam

    (2.2hrs/m cube of unskilled labour) 2.2 125 275

    Add 25% p&oh 0.25 68.75

    343.75 343.75

    excvtn of wk. Space 2.2 125 275

    Add 25% p&oh 0.25 68.75

    343.75 343.75

    EARTHWORK SUPPORT

    Cost of 3.6m x 0.3m plank (1.08m sq) 800

    no. Of plank in 1m sq 1.85

    cost of 1m sq of plank 740

    cost of transportation 50

    790

    Add 7.5% waste 0.075 59.25

    849.25

    Labour for fixing and striking

    (1.5hrs of unskilled labour) 1.5 125 187.5

    (2hrs of skilled labour) 2 250 500

    1536.75

    Add 25% P&oh 0.25 384.1875

    1920.938 1920.938

    PROTECTION

    Allow for keeping the site free from water 20000

    WHEEL AND SPREAD

     Wheel and spread top soil 150mm deep

    (1hr of unskilled labour) 1 125 125

    Spread and level

    (1.5hrs of unskilled) 1.5 125 187.5

    312.5

    Add 25% profit & O/h 0.25 78.125

    390.625 390.625

    REMOVAL OF SURPLUS SOIL

    Remove surplus soil 1.5hrs of unsilled labour 1.5 125 187.5

     Add 25% profit & O/h 0.25 46.875

    234.375 234.375

    J BACKFILLING

    Backfilling of excavated material 1.50 man hour

    spread and level exc. Mat. 0.75 man hour

    2.25 man hour@ 125/h 2.25 125 281.25

    Add 25% profit and O/h 0.25 70.3125

    351.5625 351.5625

  • 8/18/2019 Rate Build Up For Construction Materials.

    2/4

    K FILLING TO MAKE UP LEVEL

    5 Cubic meter of sharp sand 15000

    1cubic met o 3000

    T/4 300mm of sharp sand 0.3 900

    20% Consolidation 0.2 180

    0.45 man hour labour 0.45 125 56.25

    1136.25

    Add 25% profit and O/h 0.25 284.0625

    1420.313 1420.313

    L LEVEL AND COMPACT

    LEVEL AND COMPACT FDN. TRENCH 0.75 man hour

    ( for skilled & unskilled) 0.75 375 281.25

    Add 25% profit and O/h 0.25 70.3125

    351.5625 351.5625

    M ANTI TERMITE SOLUTION

    4 litres of anti-termite soln. 2000

    0.5 litres needed/m sq 250

    0.2 hrs of skilled labour 0.2 250 50

    Add 25% profit & O/h 1.25 300

    375 375

    N CONCRETE BLINDING

    I CUBIC METER OF CEMENT= 28 BAGS @1600 28 1600 44800

    LOADING AND OFF-LOADING 3000

    10 CUBIC METER OF AGG. @ N5,249 10 5249 52490

    11 CUBIC METER OF CONCRETE 11 100290

    1 CUBIC METER OF CONRETE = 9117.273

    Add 40% void 0.4 3646.909

    Add 0.75 man-hour labour rate 0.75 375 281.25

    13045.43

    Add 25% profit and O/h 0.25 3261.358

    16306.79 16306.79

    P DITTO CONCRETE OVER DAMP PROOF

    I CUBIC METER OF CEMENT= 28 BAGS @1600 28 1600 44800LOADING AND OFF-LOADING 3000

    10 CUBIC METER OF AGG. @ N5,249 10 5249 52490

    11 CUBIC METER OF CONCRETE 11 100290

    1 CUBIC METER OF CONRETE = 9117.273

    Add 40% void 0.4 3646.909

    Add 0.75 man-hour labour rate 0.75 375 281.25

    13045.43

    Add 25% profit and O/h 0.25 3261.358

    16306.79

    GROUND BEAM IN-SITU REINFORC ED CONCRETE 1:2:4 - 19mm agg.

      er of ceme METER OF CEMENT @ N1600 28 1600 44800

     TRANSPORT/CARRIAGE 28 100 2800

     1 CUBIC METER OF CEMENT 47600

    fine agg.

     5 cubic meter of sand 15000

     2 cubic meter of sharp sand 6000

    Coarse agg.

  • 8/18/2019 Rate Build Up For Construction Materials.

    3/4

    1 cubic meter of granite 7853

    4cubic meter of granite 31414

     7 cubic meter of concrete 7 85014

    1 cubic meter of concrete 12144.86

    Add 40% for waste/compaction 0.4 4857.943

     5.42 man hour labour@N375 5.42 375 2032.5

    19035.3Add 25% profit and O/h 0.25 4758.825

    23794.13 23794.13

    RAFT SLAB

     DITTO AS DESCRIBED ABOVE

    1 cubic me UBE OF METER @N1600 28 1600 44800

     TRANSPORT/CARRIAGE 28 100 2800

    FINE AGG.

      5 CUBIC METER 15000 6000

     2CUBIC METER OF SHARP SAND

      COARSE AGG.

     1 CUBIC METER OF GRANITE 7853

     4CUBIC METER OF GRANITE 31414

    7 CUBIC METER OF CONCRETE 7 85014

     1 CUBIC METER OF CONCRETE 12144.86

     Add 40% for waste/compaction 0.4 4857.94

     5.42 man hour labours@N 375 5.42 375 2032.5

    (For skilled and unskilled) 19035.3

     Add 25% profit and O/h 0.25 4758.825

    23794.13 23794.13

     ENTRANCE SLAB

     Ditto for entrance step 23794.13

      10- 20mm reinforcement  1 ton of Y10mm reinforcement 185000

      Carriage/loading/off-loading 1000

    186000

      Off- cut (5% waste) 0.05 9300

    195300

      5Kg of binding wire 2500

      6hrs of labour 6 250 1500

      199300

      1 kg of reinforcement 1000 199.3

      Add 25% profit/Oh 0.25 49.825

    249.125 249.125

      12-16mm reinforcemnt for raft slab  1 ton of Y10mm reinf. 185000

      Carriage/loading/off-loading 1000

     

    Off-cut (5% waste) 9300

      5kg of binding wire 2500

      6hrs of labour 6 250 1500

    199300

    1 kg of reinforcement 199.3

     Add 25% O/H and profit 0.25

  • 8/18/2019 Rate Build Up For Construction Materials.

    4/4

      FORMWORK

      cost of 3.6x0.3m plank (1.08m2) 800

      No. Of planks in 1m2 of formwork 0.93 plank

      cost of 1m2 of plank 740

      cost of transportation 50

      Add 7.5% for waste 59.25

      cost of vertical supports 50x75mm plank 300

      1.5hrs of unskilled labour for fixing/striking 1.5 125 187.5

      2.0hrs of skilled labour 2 250 500

      Allow for 1 pound of nail 200

      2036.75

      Allow for 25% O/h and profit 0.25 509.1875

    2545.938 2545.938

      EDGES OF RAFT FLOOR SLAB

      3.6m length of 300x25mm plank 800

      1m length of plank 3.6 222.2222

      cost of 0.1hr of skilled labour 0.1 250 25

    247.2222

      Add 25% profit and O/h 0.25 61.80556

    309.0278 309.0278

    DAMP PROOF MEMBRANE

    COST OF 1000mm guage polythene material/sq m

    (2 layers) 600

    0.2hrs of skilled labour 0.2 250 50

    650

    Add profit & O/h 25% 0.25 162.5

    812.5 812.5

     PROTECTION 100 100