    1.CALCULATION OF MATERIALS PER 10 cu m. VOLUME OF BRICK

    METRIC BRICKS No. of metric brick having size with mortar 10 cm x 10 cm x 20 cm

    = 10 = 5000 nos.

    0.1 x 0.1 x 0.2

    The size of one metric brick without mortar is 9 cm x 9 cm x 19 cm

    Therefore mortar required per 10 c.m. = 10-(5000 x .09 x .09 x .19) = 2.3 cu m.

    Due to frog filling, brick bonding courses and wastage, etc. increase this quantity by 15%therefore, volume of wet mortar = 2.3 + 2 .3 x .15 = 2.64 cu m

    when dry, increase this quantity by 1/3 = 2.64 + 2.64 x 1/3 = 3.5 cu m

    In case of lime mortar, the above quantity., 3.5 cu m. reaches upto 4.0 cu m. .Such increase

    may be justifies considering the void in surkhi is more, joints are generally thicker and

    additionally, less care is observer towards wastage.

    With second class bricks, the quantity of cement mortar of 4.0 cu m. and lime mortar of 4.2

    cu m. are required according to the shape and size of second class bricks.

  • 7/22/2019 Rate Analysis- Brickwork

    3/13

    TRADITIONAL BRICKS

    No. of traditional bricks having size with mortar 25.4 cm x 12.7 cm x 7.6 cm =

    10 = 4079 nos. , say, 4100 nos.

    0.254 x 0.127 x 0.076

    With this traditional size of bricks, joints are less, and therefore lesser amount of mortarshould be required. But due to larger size of frog and wider area of a brick such variation

    may be minimized.

    TRADITIONAL BRICKS

    No. of traditional bricks having size with mortar 22.9 cm x 11.4 cm x 7.6 cm =

    10 = 5041 nos. , say, 5000 nos. (due to thi

    0.229 x 0.114 x 0.076

    The no. of bricks being same to that of metic brick and the quantity of mortar is also

    same.

    2. FIRST CLASS BRICKWORK IN LIME AND SURKHI MORTAR (1:3 FOUNDATION AND

    PLINTH)

    Consider first 10 c.m.

    Calculation of materials: Lime = 4/4 = 1.0 c.m.

    Surkhi = 1.0 x 3 = 3.0 c.m.

  • 7/22/2019 Rate Analysis- Brickwork

    4/13

    PARTICULARS QUANTITY RATE AMOUNT

    Rs. P.

    (a) Materials - Brick (kiln) 5000 nos. 8p per no. 4000

    metric 20 x 10 x 10 cm

    traditional 25.4 x 12.7 x 7.6 cm 4100 nos.

    22.9 x 11.4 x 7.6 cm 5000 nos.

    Surkhi 3.00 cu m 146.00 per cu m 438

    Lime 1.00 cu m 398.00 per cu m 398

    (b) Labour- Head mason 1/2 no. 38.00 per day 19

    Mason 8 nos. 35 each per day 280

    Mazdoor (2 nos. as bhisti) 10 nos. 20.00 per day 200

    Mazdoor (female) 6 nos. 20.00 per day 120

    Contingencies, T and P, risk etc. L.S 1/2 %(a + b) 27.27 27.27

    Total = 5482.27

    (c) Water charges 1% of the total 54.82

    Total = 5537.09

    (d) Profit and overhead 10% 553.7

    Rate per cu m. = Rs. 609.107 Grand total = 6090.79

  • 7/22/2019 Rate Analysis- Brickwork

    5/13

    3. FIRST CLASS BRICKWORK IN CEMENT MORTAR (1:4) IN SUPER STRUCTURE,

    GROUND FLOOR

    Consider first 10 c.m. Calculation of materials: Cement = 3.5/5 = 0.7 cu m

    Sand =0.7 x 4 = 2.8 cu m

    PARTICULARS QUANTITY RATE AMOUNT

    Rs. P.

    (a) Materials -

    Brick (kiln) - 20cm x 10cm x 10cm 5000 8p per no. 4000

    Sand ( medium) 2.8 cu m 130 per cu m 364

    Cement 0.70 cu m = 21 bags 2.1 bags 73 per bag 1533

    Scaffolding L.S 20 20

    (b) Labour-

    Head mason 1/2 no. 38.00 each per day 19

    Mason 8 nos. 35 each per day 280

  • 7/22/2019 Rate Analysis- Brickwork

    6/13

    Mazdoor (2 nos. as bhisti) 10 nos. 20.00 per day 200

    Mazdoor (female) 7 nos. 20.00 per day 140

    Contingencies, T and P, risk etc. L.S 1/2 %(a + b) 32.78 32.78

    Total = 6588.78

    (c) Water charges 1% of the total 65.88

    Total = 6554.66

    (d) Profit and overhead 10% 655.46

    Rate per cu m. = Rs.721.01 Grand total = 7210.12

    BRICKWORK FOR ADDITIONAL STOREY:

    Labour cost of 1 mason, 3 mazdoors, and a lump sum amount of Rs. 20 for scaffolding per 10

    cu m. volume of work are to be added over the ground floor as illustrated in the next slide.

    According to All India Standard Schedule of Rates an extra overrate of 1% shall be added per

    floor of brickwork, taking each floor to be of average 3m height

  • 7/22/2019 Rate Analysis- Brickwork

    7/13

    4. FIRST CLASS BRICKWORK IN CEMENT MORTAR (1:6) IN SUPER STRUCTURE,

    FIRST FLOOR

    Consider first 10 c.m.

    Calculation of materials: Cement = 3.5/7 = 0.5 cu mSand =0.5 x 6 = 3.0 cu m

    PARTICULARS QUANTITY RATE AMOUNT

    Rs. P.

    (a) Materials -

    Brick (kiln) - 20cm x 10cm x 10cm 5000 8p per no. 4000

    (For 25.4 cm x 12.7 cm x 7.6 cm) 41000 nos.

    (For 22.9 cm x 11.4 cm x 7.6 cm) 5000 nos.

    Sand ( medium) 3 cu m 130 per cu m 390

    Cement 0.50 cu m = 15 bags 15 bags 73 per bag 1095

    Scaffolding L.S 30 30

    (b) Labour-

    Head mason 1/2 no.

    38.00 each per

    day 19

  • 7/22/2019 Rate Analysis- Brickwork

    8/13

    Mason 9 nos.

    35 each per

    day 315

    Mazdoor (2 nos. as bhisti) 13 nos. 20.00 per day 260

    Mazdoor (female) 7 nos. 20.00 per day 140

    Contingencies, T and P, risk etc.

    L.S 1/2 %(a +

    b) 31.24 31.24

    Total = 6280.24

    (c) Water charges 1% of the total 62.8

    Total = 6343.04(d) Profit and overhead 10% 634.3

    Rate per cu m. = Rs.697.73 Grand total = 6977.34

    5.FIRST CLASS BRICKWORK IN PLAIN ARCHES IN SUPERSTRUCTURE SPAN NOT

    EXCEEDING 6M IN CEMENT MORTAR 1:4 INCLUDING CENTERING AND

    SHUTTERING COMPLETE

    PARTICULARS QUANTITY RATE AMOUNT

    Rs. P.

    (a) Materials -

    First class brick (metric) 5000 8p per no. 4000

  • 7/22/2019 Rate Analysis- Brickwork

    9/13

    Sand ( medium) 2.80 cu m 130 per cu m 364

    Cement 0.70cu m = 21 bags 21 bags 73 per bag 1533

    Centring and shuttering -

    Considering a semi circular arch 3.6

    m

    clear span 3.0 m long and .40 m thk.

    area of centring = 3.142 x 1.8 x 3.0

    16.97 sq m

    Brickwork in arch = 3.142 x 2 x .4 x

    3.0

    = 7.54 cu m

    area/ 10 cu m =16.97/ 7.54x10 =22.5

    sqm 22.5 sq m 30.00 per sq m 675

    Scaffolding L.S 25 25

  • 7/22/2019 Rate Analysis- Brickwork

    10/13

    (b) Labour-

    Head mason 1 no. 38.00 each per day 38

    Mason 10 nos. 35 each per day 350

    Mazdoor (2 nos. as bhisti) 22 nos. 20.00 per day 440Contingencies, T and P, risk etc. L.S 1/2 %(a + b) 37.12 37.12

    Total = 7462.12

    (c) Water charges 1% of the total 74.62

    Total = 7536.74

    (d) Profit and overhead 10% 753.67

    Rate per cu m. = Rs.829.04 Grand total = 8290.41

    Extra rate for brickwork (1:4) in plain arches = Rs.527.35 Rs.452.76 = Rs.74.59 cu m

    Extra labour rate for brickwork only = Rs.464.00 Rs.358 = Rs.106 per 10 cu m

    According to IS-1200, the brickwork rate for arches of span not exceeding 6m, hire and

    labour charges for centering and shuttering shall be included in the item and for spans

    exceeding 6m centering and shuttering shall be measured separately.

  • 7/22/2019 Rate Analysis- Brickwork

    11/13

    6.HALF BRICK i.e10 CM BRICK WALL IN CEMENT MORTAR (1:3)WITH PLAIN ARCHES

    WITH H.B NETTING IN EVERY THIRD LAYER(GROUND FLOOR)

    Consider first 10 c.m.

    Calculation of materials: Bricks(metric) = 100 = 5000 nos..10 x .20

    Volume of mortar35% to the volume of work = 100 x .10 x .35 = 3.5 cu m. Due to half

    brickwork, volume of mortar becomes 10% less than 3.5 cu m. = 3.5 0.35 = 3.15 cu m.

    Therefore, cement = 3.15 / 4 = 0.79 cu m

    sand = .79 x 3 = 2.37 cu m.

    Wire netting for every third layer i.e, 30 cm intervals (considering a wall 10m length x

    10m height) = 10 x 10 / .30 = 334 rm, with 10 cm wide area of netting =

    334 x .10 = 33.4 sq m.

    PARTICULARS QUANTITY RATE AMOUNT

    Rs. P.

    (a) Materials -

    Brick (kiln) - 20cm x 10cm x 10cm 5000 8p per no. 4000

    (For 25.4 cm x 12.7 cm x 7.6 cm) 41000 nos.

    (For 22.9 cm x 11.4 cm x 7.6 cm) 5000 nos.

    Sand ( medium) 2.37 cu m 130 per cu m 308.1

  • 7/22/2019 Rate Analysis- Brickwork

    12/13

    Cement (0.79 cu m = 23 bags) 23 bags 73 per bag 1679

    Wire netting 33.4 sq m 30 per sq m 1002

    Scaffolding L.S 25 25

    (b) Labour-

    Head mason 1/2 no.

    38.00 each per

    day 19

    Mason 14 nos. 35 each per day 490

    Mazdoor (2 nos. as bhisti) 21 nos. 20.00 per day 420

    Contingencies, T and P, risk etc.

    L.S 1/2 %(a +

    b) 39.71 39.71

    Total = 7982.81

    (c) Water charges 1% of the total 79.83

    Total = 8062.64

    (d) Profit and overhead 10% 806.26

    Rate per cu m. = Rs.88.69 Grand total = 8868.90

    7. HALF BRICKWORK FOR EACH HIGHER STOREY:

    Labour costs of 3 mazdoors (beldars) is to be added to lift the materials over and above

    the above costs

  • 7/22/2019 Rate Analysis- Brickwork

    13/13

    8.SECOND CLASS BRICKWORK IN MUD MORTAR IN SUPER STRUCTURE,

    GROUND FLOOR

    PARTICULARS QUANTITY RATE AMOUNT

    Rs. P.

    (a) Materials -

    Brick second class ( metric) 5000 8p per no. 4000

    Clay ( selected loamy soil) 4.00 cu m 12.50 per cu m 50

    Scaffolding L.S 25 25

    (b) Labour- Head mason 1/2 no.

    38.00 each per

    day 19

    Mason 8 nos. 35 each per day 280

    Mazdoor (1 nos. as bhisti) 12 nos. 20.00 per day 240

    Contingencies, T and P, risk etc.

    L.S 1/2 %(a +

    b) 28.02 28.02

    Total = 5632.52

    (c) Water charges 1% of the total 56.32

    Total = 5688.84

    (d) Profit and overhead 10% 568.88

    Rate per cu m. = Rs. 625.77 Grand total = 6257.72