ral network upgrade - cern · 2021. 3. 23. · modest upgrade plans to make use of planned 100gb/s...

16
RAL Network Upgrade Alastair Dewhurst

Upload: others

Post on 10-Jun-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: RAL Network Upgrade - CERN · 2021. 3. 23. · Modest upgrade plans to make use of planned 100Gb/s LHCOPN link were scheduled for 2020. Covid-19 meant many plans were delayed/put

RAL Network

Upgrade

Alastair Dewhurst

Page 2: RAL Network Upgrade - CERN · 2021. 3. 23. · Modest upgrade plans to make use of planned 100Gb/s LHCOPN link were scheduled for 2020. Covid-19 meant many plans were delayed/put

Motivation

In the last few years the RAL Tier-1 network has struggled to deliver what was required of it. Modest upgrade plans to make use of planned 100Gb/s LHCOPN link

were scheduled for 2020.

Covid-19 meant many plans were delayed/put on hold. Opportunities for projects that could spend money.

We had access to a pot of money to build a: “World Class Laboratory” (WCL). Additional £400k to upgrade the RAL Tier-1 network.

Also, a recent security breach at a different UK research council has led to greater scrutiny of the network design/separation.

2

Alastair Dewhurst, 23rd March 2021

Page 3: RAL Network Upgrade - CERN · 2021. 3. 23. · Modest upgrade plans to make use of planned 100Gb/s LHCOPN link were scheduled for 2020. Covid-19 meant many plans were delayed/put

RAL Campus Upgrades Several planned upgrades to the campus network were also

expedited as a result of the WCL funds.

The RAL Campus offsite connection is being upgraded from 100Gbps to 200Gbps This is a resilient link 2 x 200Gbps active/passive) Physical connections done 17th - 18th March. Due to go into production March 31st.

New Fortinet 4201F Firewall Partially moved into production (IPv6) in February 2021, however intermittent

packet loss with Telephone network has meant IPv4 has not been migrated. Due for completion end of April. Access to some Tier-1 services currently passes through the firewall.

New 100Gbps capable core switches. Delivered in March 2021, in production in Q3 2021.

Alastair Dewhurst, 23rd March 2021

3

Page 4: RAL Network Upgrade - CERN · 2021. 3. 23. · Modest upgrade plans to make use of planned 100Gb/s LHCOPN link were scheduled for 2020. Covid-19 meant many plans were delayed/put

Tier-1 Network The RAL Tier 1 currently connects to:

The world via Janet via the RAL Campus Network.

Tier 0s and other Tier 1s via the LHCOPN via a private router (OPNR).

Tier 2s via Janet via a private router (OPNR).

Currently the Tier 1 provides compute, storage and services over both IPv4 and IPv6 on a single L2 segment. 3× IPv4 subnets (one for LHCOPN) 2× IPv6 subnets (one for LHCOPN)

Routing to deal with this is a little arcane… 3+1 physical routers ~7 virtual routers Nodes have ~16 IPv4 and ~8 IPv6 routing table entries More default route (gateway) options than subnets

4

Alastair Dewhurst, 23rd March 2021

Page 5: RAL Network Upgrade - CERN · 2021. 3. 23. · Modest upgrade plans to make use of planned 100Gb/s LHCOPN link were scheduled for 2020. Covid-19 meant many plans were delayed/put

Tier-1 NetworkRAL Campus & JanetLHCOPN

Alastair Dewhurst, 23rd March 2021

Page 6: RAL Network Upgrade - CERN · 2021. 3. 23. · Modest upgrade plans to make use of planned 100Gb/s LHCOPN link were scheduled for 2020. Covid-19 meant many plans were delayed/put

Tier-1 Subnets3 x Tier 1 subnets:

OPN: 130.246.176.0/22

Services: 130.246.180.0/22

Compute: 130.246.216.0/21

Subnet design was done a decade before services like CMS AAA were thought of.

6

130.246.128.0/20

130.246.192.0/20

130.246.188.0/22

130.246.208.0/21

Alastair Dewhurst, 23rd March 2021

Page 7: RAL Network Upgrade - CERN · 2021. 3. 23. · Modest upgrade plans to make use of planned 100Gb/s LHCOPN link were scheduled for 2020. Covid-19 meant many plans were delayed/put

Designing a new Tier-1 Network

We decided to build a new network for the RAL Tier-1 with a Spine / Leaf topology. New CTA Tape system is on a separate network pod.

Wanted to provide a uniform experience for end users: Dual Stack everywhere.

All machines accessible to the outside world will be on the LHCOPN and LHCONE.

We choose a single vendor (Mellanox) with the Cumulus OS for all systems. Also required storage and CPU nodes to come with Mellanox NICs.

Hardware purchased in the last two years can be easily added to new network: Review other hardware on case by case basis.

7

Alastair Dewhurst, 23rd March 2021

Page 8: RAL Network Upgrade - CERN · 2021. 3. 23. · Modest upgrade plans to make use of planned 100Gb/s LHCOPN link were scheduled for 2020. Covid-19 meant many plans were delayed/put

SCD Super Spine

In 2018 RAL Scientific Computing department deployed a Super Spine. Design to move data between big SCD

projects (bypassing site core).

3 Tier, Spine/leaf architecture following data centre best practises.

16 x Mellanox SN2700 switches in 4 blocks. 32 x 100Gb/s each

8

Alastair Dewhurst, 23rd March 2021

Page 9: RAL Network Upgrade - CERN · 2021. 3. 23. · Modest upgrade plans to make use of planned 100Gb/s LHCOPN link were scheduled for 2020. Covid-19 meant many plans were delayed/put

Tier-1 Network Design9

CTA

200Gb/sCloud

200Gb/s

Super Spine

JASMIN 400Gb/s

Tier-1 Spine

100Gb/s to CERN

200Gb/s to JANET

400Gb/s to Site Core

400Gb/s

~40PB storage 42k CPU cores

Legacy

Tier-1

Alastair Dewhurst, 23rd March 2021

Page 10: RAL Network Upgrade - CERN · 2021. 3. 23. · Modest upgrade plans to make use of planned 100Gb/s LHCOPN link were scheduled for 2020. Covid-19 meant many plans were delayed/put

10

Alastair Dewhurst, 23rd March 2021

Page 11: RAL Network Upgrade - CERN · 2021. 3. 23. · Modest upgrade plans to make use of planned 100Gb/s LHCOPN link were scheduled for 2020. Covid-19 meant many plans were delayed/put

Joining the LHCONE11

Tier-1 Spine

RAL Tier-2 has been connected to the LHCONE since September 2019

Before the Tier-1 joins we will need to switch T1E Router to peer with CERN.

LHCONE will work as a backup in the event the OPN link is cut.

Alastair Dewhurst, 23rd March 2021

Page 12: RAL Network Upgrade - CERN · 2021. 3. 23. · Modest upgrade plans to make use of planned 100Gb/s LHCOPN link were scheduled for 2020. Covid-19 meant many plans were delayed/put

Time Line

1)Build new Tier-1 Network Vendors are currently doing all installation and cabling inside the data centre.

Vast majority done this week, completion by April 14th.

Dedicated contractor effort to configure setup. Target completion mid May (4 weeks work).

2)Switch Peering from OPNR to TIE Router.

3)Announce 130.246.216.0/21 and 2001:630:58:1820/64 to LHCOPN.

4)Announce 130.246.216.0/21 and 2001:630:58:1820/64 to LHCONE.

5)Migrate older hardware to new network. Q3 2021

12

Alastair Dewhurst, 23rd March 2021

Mid

May -

June

Page 13: RAL Network Upgrade - CERN · 2021. 3. 23. · Modest upgrade plans to make use of planned 100Gb/s LHCOPN link were scheduled for 2020. Covid-19 meant many plans were delayed/put

Future plans

The new network should be in place this summer ready for other hardware/service to be migrated in the autumn.

The hardware shouldn’t change during Run 3. 4 x 100Gb/s leaf links with 25Gb/s links to CPU/Storage nodes should

be more than sufficient for Run 3.

Given current pricing trends, we would hope to upgrade to 2 x 100Gb/s LHC OPN links in the second half of Run 3. Cost halves every ~4 years.

In 2026 during LS3, when the warranty expires on current hardware, we would expect to replace 100Gb/s capable spine switches with 400Gb/s capable ones.

13

Alastair Dewhurst, 23rd March 2021

Page 14: RAL Network Upgrade - CERN · 2021. 3. 23. · Modest upgrade plans to make use of planned 100Gb/s LHCOPN link were scheduled for 2020. Covid-19 meant many plans were delayed/put
Page 15: RAL Network Upgrade - CERN · 2021. 3. 23. · Modest upgrade plans to make use of planned 100Gb/s LHCOPN link were scheduled for 2020. Covid-19 meant many plans were delayed/put

SCD Super Spine

Alastair Dewhurst, 22nd September 2020

15

Page 16: RAL Network Upgrade - CERN · 2021. 3. 23. · Modest upgrade plans to make use of planned 100Gb/s LHCOPN link were scheduled for 2020. Covid-19 meant many plans were delayed/put

y = 5115 . e -0.17x

LS3