Rail Electrification in India
‘IR to achieve 100% electrification – Implementation Challenges &
Suggestions’
Mr. Manish Agarwal, Siemens Limited.
Rail Urja Pavilion, Hall No. 16, Elecrama
21st January, 2020
siemens.com/mobilityUnrestricted © Siemens AG 2019
Frei verwendbar © Siemens AG 2019
Page 2 Mobility Division
Overview for Rail Electrification - IR
1
4
3
2
Present
Situation
Need of Indian
Railways
Options
Solutions
• 100% electrified rail network in next two-three years
• 10,500 Crore annual savings after railway goes full electric
• > 30,000 kms to be electrified – project cost to be 30-35K Crores.
• Emphasis on Diesel
• Annual Savings to the tune of INR 10,500 crores envisaged
• Indian Railways could borrow from ADB or equivalent.
• Funds to be made available through LIC , IRFC and internal funding
• Turnkey contract from large EPC players - ongoing
• Larger contract size of 1500-2000 km
• Global players to bring in new methods, Design, mechanized
installation to increase the pace of electrification rapidly.
?
?
Actual Achievements (in RKM) Targets for Rail Electrification in RKM
2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2020-21
1375 1605 2050 4082 5300 Approx. 7500 10319 10500
Frei verwendbar © Siemens AG 2019
Page 3 Mobility Division
Four type of projects, which requires different approaches.
To innovate and improve needs to focus on right settings.
Green Field
Project with
customer who
had no
electrified track
before
Brown Field
Project with
customer who
had electrified
other tracks
before (incl.
Refurbishment)
Upgrade
technology /
speed / capacity
upgrade of
electrified track
Maintenance
(can also incl.
Refurbishment
done my
maintainer)
Components
Needed for green
field, brown field,
upgrade and
maintenance
Green
Field
Brown
Field
Upgrade
Mainte-
nance
Po
ss
ible
so
luti
on
s!
Pro
babili
ty &
Possib
ilities to influence
custo
mers
desig
n
Preferred focus areas for
Indian Market!
Frei verwendbar © Siemens AG 2019
Page 4 Mobility Division
Sicat plattform
Contact line systems for every task – tailored based on requirements
≤ 80 km/h Sicat 3S ‒
≤ 120 km/h Sicat LD ‒
≤ 160 km/h Sicat SD Sicat SR
≤ 200 km/h Sicat SR Sicat LA
≤ 250 km/h Sicat HD Sicat SA / Sicat SX
> 230 km/h ‒ Sicat HA
DC ACRunning speedApart from economy, longevity and
consistently high quality are the key features
of the Sicat contact line systems.
They permit a high running quality, long
service live, low LCC and comply with both
national and international standards.
Siemens – with more than 138 years
experience electrical railways - is releasing
an adjusted OCL system for projects based
on Sicat plattform solution. Therefore all
requirements could be met (e.g. PAN,
environment, operational & RAMS
requirements, …).
c
o
n
si
st
ofSicat 8WL (EN 50119/IEC 60913 tested!)
Sicat CMS, Sicat DMS, Sicat PMS, …
Frei verwendbar © Siemens AG 2019
Page 6 Mobility Division
We electrify rail.
Smart rail electrification
We power rail.
Solutions for
traction power supplies
We make rail smart.
Solutions for rail
electrification of the future
We manage rail.
Solutions for
power system management
Overview
We wire rail.
Solutions for
contact lines
siemens.com/rail-electrification
What may be considered for fast track Rail
Electrification e.g. Modular Aluminum Cantilevers?
Frei verwendbar © Siemens AG 2019
Page 7 Mobility Division
Reasons to adopt….Modular Cantilever
❑ Less number of components, clear interfaces, faster installation & adjustments, lower maintenance
& high availability
Frei verwendbar © Siemens AG 2019
Page 8 Mobility Division
Example: Preassembling of low weight cantilevers with composite
insulators
Delivery (1) or preassembly by installation company (2) – customer’s choice
Preparing for transport, stacked, marked and sorted for easy
installationTransportation on site
1
2
Frei verwendbar © Siemens AG 2019
Page 9 Mobility Division
Example: Installation of low weight preassembled cantilevers with
composite insulators
Prepare
installation
Installation without crane (approx. 35 kg/cantilever),
only 2 workers on platform neededInstallation
Frei verwendbar © Siemens AG 2019
Page 10 Mobility Division
We electrify rail.
Smart rail electrification
We power rail.
Solutions for
traction power supplies
We make rail smart.
Solutions for rail
electrification of the future
We manage rail.
Solutions for
power system management
Overview
We wire rail.
Solutions for
contact lines
siemens.com/rail-electrification
What should be considered to optimize costs
and increase speed of existing lines?
Frei verwendbar © Siemens AG 2019
Page 11 Mobility Division
LCC Cost optimizations in Design, Implementation and
construction of OCL
Lever for Optimization (should be
possible within tender specification!)
⮚ Increase of Span Length
⮚ Increase of Tensioning Length
⮚ System optimization based on TPS network
studies
⮚ Innovative products and components
⮚ Adapt products which require minimum /
zero modification during further upgrade to
high speed
⮚ Digitalization
⮚ Installation plan & technology
Engineering Manufacturing PurchaseAdministration,
Sales
100 %
80 %
60 %
40 %
20 %
70 %
6 %
20 %
36 %
7 %
40 %
3 %
18 %
Cost definition
Cost development
% p
rim
e c
osts
Development process
Source FH Deggendorf &
VDI Richtlinie 2235
»Well done engineering with overall
coordination and logistics concepts will keep
project timeline and budget relaxed ☺
Frei verwendbar © Siemens AG 2019
Page 12 Mobility Division
IR preparedness for Mainline RE // Key concerns
- Funds are available and sanctioned.
- Availability of skilled manpower ?
- Availability of electric locomotives?
- Lack of capacity for production from approved RDSO/ CORE suppliers.
- EPC tenders don’t allow for design flexibility.
- No lever for Design optimization is provided.
- Timelines for execution is limited considering the powerbock activities , especially in hilly terrain.
Frei verwendbar © Siemens AG 2019
Page 13 Mobility Division
Innovations in the field of contact lines –
possible with less restricted specifications
Digitalization in planning, development and
constructionNew models
Assembly
technologyDigitalization in operation
and maintenance
Recording, evaluation and
validation of RAMS/LCC
New overhead line
components
Frei verwendbar © Siemens AG 2019
Page 14 Mobility Division
Smart data opens opportunities –data collection and analysis
Frei verwendbar © Siemens AG 2019
Page 15 Mobility Division
We electrify rail.
Smart rail electrification
We power rail.
Solutions for
traction power supplies
We make rail smart.
Solutions for rail
electrification of the future
We manage rail.
Solutions for
power system management
Overview
We wire rail.
Solutions for
contact lines
siemens.com/rail-electrification
Reliable & approved Sicat components and
systems, domain know-how in overall and
specific engineering disciplines mixed with
a portion of innovation, automation &
digitalization will result in the best in class
life cycle cost optimized contact line
solutions delivered by RE@Siemens!