qhdm vol1 part02 planning octfinal

Upload: sabariqa

Post on 06-Jul-2018

237 views

Category:

Documents


4 download

TRANSCRIPT

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    1/101

     

    Volume 1

    Part 2Planning

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    2/101

    VOLUME 

    PART 

    PLANNING 

    VOLUME 

    Disclaimer

    The 

    State 

    of  

    Qatar 

    Ministry 

    of  

    Transport 

    (MOT) 

    provides 

    access 

    to 

    the 

    Qatar 

    Highway 

    Design 

    Manual 

    (QHDM) 

    and 

    Qatar 

    Traffic 

    Control 

    Manual 

    (QTCM) 

    on 

    the 

    web 

    and 

    as 

    hard 

    copies 

    as 

    Version 

    (1.0) 

    of  

    these 

    manuals, 

    without 

    any 

    minimum 

    liability 

    to 

    MOT. 

    Under 

    no 

    circumstances 

    does 

    MOT 

    warrant 

    or 

    certify 

    the 

    information 

    to 

    be 

    free 

    of  

    errors 

    or 

    deficiencies 

    of  

    any 

    kind. 

    The 

    use 

    of  

    these 

    manuals 

    for 

    any 

    work 

    does 

    not 

    relieve 

    the 

    user 

    from 

    exercising 

    due 

    diligence 

    and 

    sound 

    engineering 

    practice, 

    nor 

    does 

    it 

    entitle 

    the 

    user 

    to 

    claim 

    or 

    receive 

    any 

    kind 

    of  

    compensation for damages or loss that might be attributed to such use. 

    Any future changes and amendments will be made available on the MOT web site. Users of  these 

    manuals 

    should 

    check 

    that 

    they 

    have 

    the 

    most 

    current 

    version. 

    Note: 

    New 

    findings, 

    technologies, 

    and 

    topics 

    related 

    to 

    transportation 

    planning, 

    design, 

    operation, 

    and 

    maintenance 

    will 

    be 

    used 

    by 

    MOT 

    to 

    update 

    the 

    manuals. 

    Users 

    are 

    encouraged 

    to 

    provide 

    feedback  through  the MOT  website  within  a  year  of   publishing  the manuals,  which  will  be 

    reviewed, assessed, and possibly included in the next version. 

    Copyright © 2015. All rights reserved. 

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    3/101

    VOLUME 

    PART 

    PLANNING 

    VOLUME 

    ويه

    ة ار

    ا

    ز

    ‐   Qatar Highway Design Manualدو ط  ر د  اطق و ط)ات و QHDMدو (

    ) ير

    و

    ا

     

     ط

    Qatar Traffic Control Manual ‐ QTCMر

     اار

     ه

    ر

     ط

     كو

     ر

     ا

     ش

     

     

     (

    )1.0دا

     هه

     

     (

     

     

    و

    ؤ

     دا

    ن دو

     ذو

     ة

    ر

    ا

    ز

    او

    ة اأك   إنر

    ا

    ز

    هاتو    ا تا ن ن   قد و  و    ،فوا  فظ ي و

    .اب

     اخط و

     

     ع

      ي

     خ

     ن

     ا 

    س

    ر

    او ئا و جاا ا عإ  ما    ي دا هه اس ا ،ك   لإن اسام 

    ها اسام.   إ ى ن  ا ئا و راضا   ا  ع ي مسا و طا م 

     

     ا

     ن

     ا

     

     

     جو

     .ة

    ر

    ا

    ز

     اص

     ر

     ا

     

     

     

     وة

     ح

     ت

     او

     رات

     غ

     ي

    ن

     أنسف

     

    .دا هه   راإ ثح   

    :مل ظ 

    سم

     ااتوزارة

     واجت

     اة

     اكت

     ار

     ن

     

     خا

     

     ن

     ا

     ك

     و

     

     ا

     

    ق

    طاو

     ا

     و

     غو

     و

     ط

     

     ا

     اة

     ضااو

    و

    او 

    ن

     ا  ة

    ر

    ا

    ز

    ا نإتحا   حار او ذو ،ن ا ك راا  س لخ ،لا دودرو تاو

     احت

     هه

     جا

     

     سف

     ح

     ة

    ر

    ا

    ز

    ا

     

     راحخل

     اودا

     

     ادم

     اار

     ض

     جا

    ر

    وإد

     

     

     و

    .

     

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    4/101

    VOLUME 1 PART 2

    PLANNING

    VOLUME 1 PAGE I

    Contents Page 

    Acronyms and Abbreviations .................................................................................................... vii 

    1  Highway Strategy .............................................................................................................. 1 

    1.1 Introduction .................................................................................................................... 1

    1.2 Vision, Goals, and Objectives.......................................................................................... 1

    1.3 Project Types and Scope ................................................................................................. 3

    1.4 Transportation Planning Process in Qatar ...................................................................... 4

    1.5 Land Use Considerations ................................................................................................ 5

    1.5.1 Land Acquisition .............................................................................................. 5

    1.6 Appraisal ......................................................................................................................... 7

    2  Projects Involving New Roads ........................................................................................... 9 

    2.1 Planning and Design Objectives: Provide Mobility and Accessibility ............................. 92.2 Planning Development Access for New Roads ............................................................... 9

    2.3 Project Development Process......................................................................................... 9

    2.3.1 Development Process for New Road Projects ............................................... 10

    2.3.2 Project Development Process: Design and Build (D&B) ................................ 12

    3  Project Development Process for Interchange Design Studies (Existing Reconstruction or

    New) ............................................................................................................................... 15 

    3.1 Step 1: Establish Data Collection Requirements and Obtain Data ............................... 15

    3.1.1 Develop Interchange Planning and Design Framework ................................ 16

    3.1.2 Stakeholder Involvement .............................................................................. 16

    3.1.3 Develop Project Planning and Design Criteria ............................................... 17

    3.2 Step 2: Confirm Study Approach, Evaluation Criteria, and Decision Process ............... 17

    3.2.1 Determine Evaluation Criteria and Technical Approach ............................... 17

    3.2.2 Develop Design Year Traffic and Select Most Likely Alternatives ................. 18

    3.3 Step 3: Conduct Interchange Type Studies ................................................................... 18

    3.3.1 Concept Engineering Design.......................................................................... 18

    3.3.2 Stakeholder Review and Screening ............................................................... 19

    3.4 Step 4: Functional Geometric Design of Screened Alternatives ................................... 19

    3.5 Step 5: Select Preferred Alternative, Document and Develop Final Engineering

    Plans .............................................................................................................................. 20

    4  Projects Involving Existing Roads .................................................................................... 21 

    4.1 Unique Characteristics of Projects Involving Existing Roads ........................................ 22

    4.2 Design of Reconstruction Projects ................................................................................ 22

    4.2.1 Relationship of Safety Performance to Design Elements .............................. 23

    4.2.2 Risk Management Guidelines ........................................................................ 25

    4.2.3 Reconstruction Design Approach .................................................................. 26

    4.3 Designation of Eligibility for 3R Treatment .................................................................. 27

    4.4 Design of 3R Projects .................................................................................................... 28

    4.4.1 Context Sensitive Safety Enhancements for 3R Projects .............................. 29

    4.4.2 3R Safety Enhancements for Rural Highways ............................................... 294.4.3 3R Safety Enhancements for Urban Roads ................................................... 32

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    5/101

    VOLUME 1 PART 2

    PLANNING

    PAGE II VOLUME 1

    5  Functional Classification as a Primary Design Control...................................................... 33 

    5.1 Qatar Road Classification ............................................................................................. 33

    5.2 Definition of Urban and Rural Roads ........................................................................... 34

    5.3 Functional Classification in Urban Areas ..................................................................... 345.3.1 Expressways .................................................................................................. 34

    5.3.2 Arterials ........................................................................................................ 35

    5.3.3 Collector-Distributor Roads .......................................................................... 36

    5.3.4 Collector Roads ............................................................................................. 36

    5.3.5 Local .............................................................................................................. 38

    5.4 Functional Classification in Rural Areas ....................................................................... 38

    5.5 Special Corridors .......................................................................................................... 39

    5.6 Temporary Roads ......................................................................................................... 40

    5.7 Application of Functional Classification in Design ....................................................... 40

    5.7.1 Key Parameters ............................................................................................. 405.7.2 Network Connections ................................................................................... 46

    5.7.3 Transport Provisions for Non-car Users ....................................................... 50

    6  Design Vehicles............................................................................................................... 53 

    6.1 Introduction ................................................................................................................. 53

    6.2 Vehicle Weights and Dimensions ................................................................................. 53

    6.2.1 Abnormal Loads and High Load Routes ........................................................ 53

    6.3 Typical Design Vehicles ................................................................................................ 54

    6.3.1 Definitions and Principles ............................................................................. 54

    6.3.2 Design Vehicles ............................................................................................. 54

    6.3.3 Swept Path Analysis ...................................................................................... 55

    7  Driver Performance and Human Factors ......................................................................... 59 

    7.1 Introduction ................................................................................................................. 59

    7.2 Qatar Driver Characteristics ......................................................................................... 59

    7.3 The Task of Driving ....................................................................................................... 60

    7.4 Vehicle Guidance ......................................................................................................... 61

    7.4.1 Road Following ............................................................................................. 61

    7.4.2 Car Following ................................................................................................ 61

    7.4.3 Passing Maneuvers ....................................................................................... 61

    7.4.4 Gap Acceptance, Merging, and Other Guidance Activities .......................... 617.5 Information System ..................................................................................................... 61

    7.5.1 Traffic Control Devices ................................................................................. 61

    7.5.2 Road Environment ........................................................................................ 62

    7.6 Information Handling ................................................................................................... 62

    7.6.1 Reaction Time ............................................................................................... 62

    7.6.2 Primacy ......................................................................................................... 62

    7.6.3 Expectancy .................................................................................................... 62

    7.7 Driver Error .................................................................................................................. 63

    7.8 Speed and Design ......................................................................................................... 64

    7.9 Design Assessment ...................................................................................................... 66

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    6/101

    VOLUME 1 PART 2

    PLANNING

    VOLUME 1 PAGE III

    8  Traffic Characteristics...................................................................................................... 67 

    8.1 Introduction .................................................................................................................. 67

    8.2 Traffic Volume .............................................................................................................. 67

    8.2.1 Annual Average Daily Traffic ......................................................................... 678.2.2 Design Hour Traffic ........................................................................................ 67

    8.3 Highway Capacity Concepts .......................................................................................... 69

    8.3.1 Capacity Definition ....................................................................................... 69

    8.3.2 General Characteristics and Application ....................................................... 70

    8.3.3 Level of Service .............................................................................................. 71

    8.3.4 Traffic Operations Analysis ............................................................................ 72

    8.3.5 Level of Service as a Design Control .............................................................. 72

    8.3.6 Influence of Design Features on Capacity ..................................................... 73

    9  Access Control and Access Management ......................................................................... 75 9.1 General Conditions ....................................................................................................... 75

    9.2 Access Management ..................................................................................................... 76

    9.2.1 Basic Principles of Access Management ....................................................... 76

    9.2.2 Access Classifications .................................................................................... 77

    9.2.3 Methods of Controlling Access ................................................................... 77

    9.2.4 Access Management and Safety Performance ............................................. 78

    10  Speed and Design ........................................................................................................... 79 

    10.1 Introduction .................................................................................................................. 79

    10.2 Operating Speed ........................................................................................................... 79

    10.3 Speed Variations ........................................................................................................... 79

    10.4 Design Speed ................................................................................................................ 80

    10.5 Posted Speed ................................................................................................................ 80

    11  Facilities for Pedestrians ................................................................................................. 81 

    11.1 General Considerations ................................................................................................ 81

    11.2 Designing for Pedestrians ............................................................................................. 81

    11.3 Pedestrian Capacity and Pedestrian Facilities .............................................................. 81

    12  Facilities for Cyclists ........................................................................................................ 85 

    13  Parking ........................................................................................................................... 87 

    References ............................................................................................................................... 89 

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    7/101

    VOLUME 1 PART 2

    PLANNING

    PAGE IV VOLUME 1

    Tables

    Table 3.1  Typical Stakeholders and Their Issues for Interchange Projects ....................... 16

    Table 4.1  Relative Relationship of Geometric Design Features to Crash Frequency or

    Severity by Type of Road ................................................................................... 24

    Table 5.1  Key Characteristics of Urban Roads ................................................................... 41

    Table 5.2  Key Characteristics of Rural Roads .................................................................... 43

    Table 5.3  Network Connections for Urban Roads ............................................................. 47

    Table 5.4  Network Connections for Rural Roads .............................................................. 48

    Table 5.5  Transport Provisions for Multimodal Users on Urban Roads ............................ 51

    Table 5.6  Transport Provision for Non-car Users on Rural Roads ..................................... 52

    Table 6.1  Maximum Vehicle Weights and Dimensions ..................................................... 53

    Table 6.2  Typical Design Vehicles ...................................................................................... 55

    Table 8.1  General Definitions of Levels of Service (Uninterrupted Flow) ......................... 71

    Table 8.2  Level of Service and Volume to Capacity (v/c) .................................................. 73

    Table 8.3  Average Control Delay Criteria for Signalized Intersection Levels of Service.... 73

    Table 9.1  Potential Crash Effects of Reducing Access Point Density ................................ 78

    Table 10.1  Relation Between Design and Posted Speeds ................................................... 80

    Table 11.1  Level of Service, Pedestrian Area and Flow Rates ............................................. 82

    Figures

    Figure 3.1  Example Single-line Concept Plan View over Aerial .......................................... 19

    Figure 4.1  Conceptual Relationship between Available Sight Distance and Safety at Crest

    Vertical Curves ................................................................................................... 25

    Figure 4.2  Safety Edge ........................................................................................................ 29

    Figure 4.3  Paved Shoulder and Rumble Strip Example ...................................................... 30

    Figure 4.4  Horizontal Curve Treatments ............................................................................ 31

    Figure 5.1  Urban Road Network ......................................................................................... 34

    Figure 5.2  Expressway with CD Roads ................................................................................ 35

    Figure 5.3  Arterial ............................................................................................................... 36

    Figure 5.4  Collector Road ................................................................................................... 37

    Figure 5.5  Local Road .......................................................................................................... 38

    Figure 5.6  Rural Road Network .......................................................................................... 39

    Figure 5.7  Illustration of a Road’s Mobility Versus Access Functions ................................ 45

    Figure 5.8  Freeway to Freeway Connection ....................................................................... 49

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    8/101

    VOLUME 1 PART 2

    PLANNING

    VOLUME 1 PAGE V

    Figure 5.9 Expressway to Urban Arterial Connection ........................................................ 49

    Figure 5.10  Rural Freeway to Rural Arterial Connection...................................................... 50

    Figure 6.1 Swept Path Parameters for Typical Tractor-Semitrailer Combination .............. 57Figure 7.1 Crash Types and Indicative Fatality Risks at Various Speeds ............................ 65

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    9/101

    VOLUME 1 PART 2

    PLANNING

    PAGE VI VOLUME 1

    This page intentionally left blank.

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    10/101

    VOLUME 1 PART 2

    PLANNING

    VOLUME 1 PAGE VII

    Acronyms and Abbreviations

    AADT annual average daily traffic

    AASHTO American Association of State Highway and Transportation Officials

    ADT average daily traffic

    D&B design and build

    DHV design hour volume

    HCM Highway Capacity Manual (2010)

    HSM Highway Safety Manual  (2010) 

    HV hourly volume

    ITS intelligent transportation system

    km kilometer

    kph kilometers per hour

    LARISA Land Acquisition and Roadway Improvement Strategic Approach

    LOS level of service

    m meter

    MMUP Ministry of Municipality and Urban Planning

    PPD Public Parks Department

    QHDM Qatar Highway Design Manual

    QNRSS Qatar National Road Safety Strategy 

    s second

    3R Resurfacing, Restoration, and Rehabilitation

    TMPQ Transportation Master Plan for Qatar  

    v/c volume to capacity

    vpd vehicles per day

    vph vehicles per hour

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    11/101

    VOLUME 1 PART 2

    PLANNING

    PAGE VIII VOLUME 1

    This page intentionally left blank.

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    12/101

    VOLUME 1 PART 2

    PLANNING

    VOLUME 1 PAGE 1

    1 Highway Strategy

    1.1 IntroductionPlanning for new cities or for transportation projects requires close cooperation among

    town planners, transport planning specialists, and highway engineers. Transportation

    infrastructure serves as the lifeline for the movement of people and goods, and is

    therefore an essential component of good national and town planning practice.

    Transportation infrastructure requires time and resources to construct, but if

    effectively managed, it can promote economic growth and the well-being of Qatar’spopulation. Before construction of any transportation infrastructure, transport

    specialists and town planners should confirm that the facilities will aid the vision and

    goals of Qatar’s growth while adhering to the current and future expansion policies.

    Transportation infrastructure is intended for use by the public, who will have an

    interest in the type of infrastructure provided, its features and characteristics, and the

    timing and schedule of its implementation. The public includes road users, adjacent

    property owners, businesses and local residents, all of whom will have different

    interests and concerns about the project. It is important to identify and involve all such

    stakeholders during the planning stage. This will allow interested parties to express

    their views and concerns, and thus to benefit the users of transportation facilities.

    This section states the vision and objectives of Qatar’s transport strategy, (based on the

    latest Transportation Master Plan for Qatar  (TMPQ), Transport Objectives for Qatar) and

    provides planners and engineers with guidelines to enable the appropriate planning of

    infrastructure projects. In line with the intent of the Qatar Highway Design Manual  

    (QHDM), it promotes the design and construction of highway infrastructure in Qatar to a

    high and common standard, which is a basic component of good planning practice.

    1.2 Vision, Goals, and ObjectivesQatar’s Transport Strategy vision is to “Promote safe, efficient and environmentally

    sustainable transport for people and goods, responding to individuals’ needs for

    mobility and supporting economic growth.”

    The transportation goals for Qatar are categorized into five areas:

    1.  Quality of life and community

    2.  Economy

    3.  Mobility

    4.  Environment

    5.  Finance and governance

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    13/101

    VOLUME 1 PART 2

    PLANNING

    PAGE 2 VOLUME 1

    Goals for each area are translated into objectives and described as follows.

    Quality of Life and Community

    •  Provide an attractive and integrated multi-modal transport system to accomplishthe following:

    −  Serve the anticipated increase in population.

    −  Provide adequate mobility options for people of all social sectors.

    −  Increase transport network access for remote and disadvantaged zones and

    communities.

    •  Implement a transport system with minimum adverse effects on quality of life, such

    as air pollution, noise emission, or barrier effect of infrastructure.

    •  Integrate land use and transport planning.

    •  Respect cultural heritage in alignment and design of transport facilities.

    •  Improve safety by reducing the number and severity of crashes.

    Economy

    •  A smart integrated transport system and an appropriate infrastructure is vital to

    accomplishing the following:

    −  Support the existing and future massive economic and industrial growth.

    −  Implement an efficient movement of goods, services, and passengers.

    •  Provide attractive and equivalent access to education sites by all modes of

    transport.

    Mobility

    •  Identify corridors for large-scale transport of passengers and goods.

    •  Use an integrated transport system to respond to all travel demands.

    •  Employ phased development of transport networks for all modes as the long-range

    forecast transport demand evolves.

    •  Provide an effective traffic management system to eliminate current congestion

    and delays and help avoid over-saturation in the future.

    •  Improve safety (and security) of Qatar’s road transport system as part of the QatarNational Road Safety Strategy (QNRSS)

    •  Achieve high transport awareness and education.

    •  Move away from only meeting demand by provision of additional infrastructure

    and start with managing demand more effectively.

    •  Balance transport modes and minimize conflicts between them.

    •  Improve efficiency and reliability of traffic conditions for motorist and public

    transport users by better information systems.

      Provide accessibility to all highway and transport users.

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    14/101

    VOLUME 1 PART 2

    PLANNING

    VOLUME 1 PAGE 3

    Environment

    •  Consider principles of sustainability when developing Qatar’s integrated transport

    system, now and in the future, particularly an integration of transport development

    with land use development.

    •  Reduce or minimize energy consumption in transport.

    •  Increase awareness of decisions makers and planners about environmental impacts

    of different transport modes.

    •  Raise awareness with general transport users about the impacts of their mobility

    behavior on the natural, manmade, and social environments.

    •  Provide more sustainable options for mobility of Qatar’s residents, such as

    improved public transport services and more attractive bike and pedestrian

    facilities.

    •  Change transport behavior of residents and visitors to more sustainable modes,

    adequate trip lengths, or other preferred options.

    Finance and Governance

    •  Minimize the adverse economic impacts of the car; that is, minimize the costs

    resulting from today’s car-dominated transport system on environment, health,

    and social life.

    •  Achieve a reasonable cost-benefit ratio of investments in the transport system.

    1.3 Project Types and ScopeThere are three basic types of projects that involve highway and transportation

    infrastructure:

    •  New roads

    •  Reconstruction of existing roads

    •  Rehabilitation, restoration, or resurfacing of existing roads (3R)

    New roads may include service roads, minor arterials, or major arterials, any of which

    may involve new intersections with the existing road network. Reconstruction may

    include improvements to existing roads, such as addition of motor vehicle capacity,addition or enhancement of facilities for nonmotorized users, or a combination of

    these. 3R projects are those for which the basic roadway remains, but major repairs to

    the pavement, bridges, or other infrastructure are necessary. Both reconstruction and

    3R projects typically will include replacement or major repair of highway infrastructure

    that has reached the end of its service life or has been damaged by an external event.

    Reconstruction projects may include capacity or other similar improvements.

    All project types require preplanning, but because they all differ in scope and purpose,

    some require greater planning and scrutiny.

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    15/101

    VOLUME 1 PART 2

    PLANNING

    PAGE 4 VOLUME 1

    Road and highway projects that require planning approvals include:

    •  Highway widening

    •  Access to new developments•  Intersection improvements

    •  Proposed new pedestrian and bicycle facilities

    •  New service roads, local roads, and arterials in a new, mixed development, for

    example, retail, commercial, residential, and recreational

    1.4 Transportation Planning Process in QatarQatar is undergoing tremendous economic and industrial growth. That growth has

    resulted in a rapid population increase and the urgent need to develop infrastructure

    projects and major transport projects. The economic and industrial growth are linked

    to the National Vision that aims at transforming Qatar into an advanced country by

    2030, capable of sustaining its own development and providing for a high standard of

    living for all of its people for generations to come.

    The transport strategy developed from the transport master plan  provides direction for

    the planning authority for a systematic approach in the implementation of transport

    infrastructure on the road network. It also calls for the development of an adequate,

    modern, and innovative public transport system to accommodate the future transport

    needs of Qatar.

    The transportation planning process identifies parts of the transport network wherenew investments in transport infrastructure or redesign of existing facilities would be

    beneficial. Proposals are usually developed within the context of master plans.

    The Overseeing Organization’s focus is to deliver transport infrastructure in ways that

    promote sustainable travel and safeguard the efficient and safe functioning of the

    transport system.

    A typical planning process considered by the Overseeing Organization for a transport

    infrastructure project proposed by a developer will involve the following:

    •  Receipt of developer’s application.

    •  Initial review of the project carried out to make sure that local communities are not

    adversely affected by development. This could involve a preapplication meeting

    with the developer to discuss the project details.

    •  Submitting of a formal application by the developer to the Overseeing Organization

    with the supporting information.

    •  Meeting with the developer and agreeing upon the terms of reference and the

    scope of work for the project.

    •  Examination of the project by the Overseeing Organization, which then will advise

    the developer to undertake a transport or traffic impact study for the project.

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    16/101

    VOLUME 1 PART 2

    PLANNING

    VOLUME 1 PAGE 5

    •  Obtaining formal comments from the Overseeing Organizations regarding the

    project and the transport report.

    •  Assessing the proposed land use and the impact of the development on its

    surroundings by considering the impact on transport and the highway network. For

    the planning process, consideration will be given to such, but limited to factors as

    road classification, level of service (LOS), highway design, increased traffic and

    congestion that may harm the economy, and increased crashes.

    •  Reviewing the transport report and, for the final planning approval, achieving

    developer agreement with the appropriate highway infrastructure design.

    •  There is an appeal period and process if an application is refused on technical

    grounds. Further information regarding different types of appeals should be

    addressed to the Overseeing Organization. Scheduling highway planning

    conditions—that is, agreeing upon a time scale in which to implement—will be the

    responsibility of the Overseeing Organization for highway and traffic works.

    1.5 Land Use ConsiderationsThe designer needs to be aware of land ownership issues when developing highway

    plans. The variety of land uses and landowners in Qatar can make the acquisition of

    land for road infrastructure difficult, costly, or not in the interest of the public. In

    particular, the acquisition of areas of special-category lands, such as burial grounds and

    military facilities, will involve additional procedures and may require replacement land

    to be provided.

    It is thus important that, in preparing feasibility studies and concept designs, the

    designer becomes familiar with the land ownership and associated issues near the

    proposed program of work.

    Land uses surrounding a road corridor fundamentally affect the design choices for road

    projects and similarly affect the expected impact of implementation of such a project.

    Consequently, traffic impact studies covering all modes of transport are required for

    new developments in order to assess the following:

    •  The overall transport and environment implications•  The impact of additional traffic on the adjoining highway network

    •  The internal/external site access arrangements

    •  Any need for mitigation measures in support of new development

    1.5.1 Land Acquisition

    As a general practice, the designer should attempt to maintain the existing right-of-way

    corridor when planning for road improvement and design solutions. If design solutions

    cannot be arrived within the existing right-of-way corridor, then additional land may be

    required. In such instance, the acquisition of adjacent properties may assist in

    achieving, geometric improvement solutions for roads and the surrounding links,

    interchanges and intersections, in order to provide a continuation of proposed design

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    17/101

    VOLUME 1 PART 2

    PLANNING

    PAGE 6 VOLUME 1

    solutions. Land acquisition may also assist in meeting project goals of an improved

    vehicular and pedestrian circulation network and meet future demands where poor

    and acceptable conditions are identified.

    A Land Acquisition and Roadway Improvement Strategic Approach (LARISA) can be

    developed to indicate sides of roads where land acquisition should be concentrated

    and to minimize the impact of road corridors to one side versus both sides. This

    approach will efficiently lead the design process in road improvements and design

    solutions.

    LARISA is based on the site survey, existing land and building assessments, and

    identifying project constraints and recommendations.

    1.  Existing Land and Building Survey

    The principles of the site survey are subjective in nature and relative to surrounding

    land uses, building conditions, and heights in comparison to adjacent properties,

    incompatibility, heritage, or cultural landmarks. The site survey may identify the

    following features, and others:

    •  Towers, residential and commercial

    •  Single and multi-family residential

    •  Heritage sites

    •  Rail and metro stations

    •  Vacant land

    2.  Existing Land and Building Assessment

    The building survey shall seek opportunities for parcel acquisition of and vacant lands

    and demolishing buildings that are old or in poor condition. A strategic approach was

    formulated to identify the methods of land acquisition and demolition of structures

    within the corridors. The demolition of adjacent properties should provide sufficient

    room for widening and realigning the road. On the other hand, various constraints may

    limit land acquisition and indicate structures to be avoided. The following are criteria

    to be considered during the assessment:

    •  Likely to be avoided:

    −  Native single-family properties, which should have precedence over the leased

    residential and commercial sites as constrained properties

    −  Buildings that cannot be acquired because of cultural, historical, religious, or

    economic restrictions

    −  Multi-family residential buildings that preserve the character of the residential

    area

    −  Buildings in good condition, developments under construction, or new

    commercial buildings

    −  Sites or buildings that have architectural character suitable for the area

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    18/101

    VOLUME 1 PART 2

    PLANNING

    VOLUME 1 PAGE 7

    −  Shopping malls and large business areas

    −  Parks and recreational areas.

    −  Small strips or sections of land impact on rows of buildings

    •  Likely to be acquired:

    −  Substandard buildings, which are old or in poor condition, and large vacant

    land, which are prime candidates for acquisition to accommodate road

    improvements.

    −  Buildings where land use or occupation compatibilities conflict with

    surrounding uses and are not applicable to the land use plan

    −  Land acquisition on one side of the road only to avoid or minimize impacts to

    the opposite side

    −  Optimal use of buffer zones to avoid land takes on private properties,

    especially with buildings

    3.  Constraints and Recommendations:

    The field investigations shall yield specific recommendations for important buildings,

    significant sites, and strategic existing utilities, which are categorized as constraints.

    Land acquisition and removal of various stretches of roads confined to one side shall

    be considered as part of value engineering approach during strategic planning stage.

    Constraint plans should be developed in the early stages of the project. Restricted

    buildings and sites should be avoided if possible in determining final roadway alignmentoptions or be used as an analysis tool for option development.

    Considerable roadway improvements are needed not only to enhance vehicular and

    pedestrian corridors but also to provide the minimum required space needed to make

    roadway improvements.

    The latest versions of the Ministry of Municipality and Urban Planning (MMUP)

    documents, Guidelines and Procedures for Transport Studies and  Land Acquisition

    Process, outline procedures to be followed for assessing the transport impact of new

    developments and the MMUP land acquisition process in Qatar.

    1.6 AppraisalAs part of the planning process, the highway project appraisal reflects the need for

    balanced improvement across the network. An appraisal is the method of assessing

    whether investing financially in construction of a highway provides value to the

    highway and transport users.

    The planning process identifies parts of the transport network where investments in

    new transport infrastructure or redesign of existing facilities would be beneficial.

    Proposals are usually developed within the context of development plans. The purpose

    of the appraisal is to compare the advantages and disadvantages of various transport

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    19/101

    VOLUME 1 PART 2

    PLANNING

    PAGE 8 VOLUME 1

    infrastructure improvement proposals. Proposals are prioritized based on the costs and

    benefits arising from traffic, economic, environmental, social, and safety effects on the

    community, both in the short and long term.

    The following are the key steps involved in carrying out an appraisal:

    1.  Define objectives and constraints.

    2.  Identify problems.

    3.  Identify solutions and designs. Develop policies or solutions to meet the objectives

    and solve problems.

    4.  Perform measurement and forecasting. Forecasting the outcome for alternative

    plans or scenarios over the life of the project using performance indicators.

    Indicators should be operational (e.g., travel time), environmental (e.g., emissionsand social benefits), or economical (e.g., cost and benefit to the community during

    the life of the project). Benefits are usually referred to as net present benefits, 

    which are the total project benefits minus costs of construction, maintenance, land

    acquisition, and other costs.

    5.  Evaluate the process of applying weights to the indicators identified in step 4.

    Weighting should reflect the Overseeing Organization’s policies, with input from

    stakeholders.

    6.  Select a best-value solution. The highest total benefit that may be approved for

    design completion and construction as appropriate.

    The three levels of appraisal hierarchy are as follows:

    1.  Strategic: The focus is on developing broad options for consideration. Several

    alternative strategic plans should be considered. For example, if a new town is

    being built to provide residential housing, it is at this stage that the planner should

    consider the orientation and the layout of the town’s road network.

    2.  Packages: A package is an alternative means of dealing with particular identified

    problems. The package approach requires the planner to do the following:

    −  Consider the nature of problems and objectives for a particular area.

    −  Relate proposed solutions to the defined problems and objectives−  Consider the impact the solutions have on the area as a whole.

    3.  Alternative: Alternative designs should be conceived within the context of defined

    objectives and objectively identified and described transportation problems.

    Sound appraisals require sound and defensible traffic forecasts. In making these

    choices, reference should be made to the latest version of MMUP’s Guidelines and

    Procedures for Traffic Studies.

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    20/101

    VOLUME 1 PART 2

    PLANNING

    VOLUME 1 PAGE 9

    2 Projects Involving New Roads

    2.1 Planning and Design Objectives: Provide Mobilityand AccessibilityA new road will have one of two basic purposes: to enable new development by making

    the land accessible to the transportation road network, or to enhance the ability to

    travel between two areas or destinations by providing an alternative route to an

    existing route.

    The planning of new roads to serve new development zones should take into account

    the proposed land uses of the new development. The amount of road capacity and the

    types and volume of travel, including pedestrian and cyclist, will be a function of the

    type and density of the development. New road planning and design entails

    development of a suitable road hierarchy classification that can be assigned to roads

    serving both existing and new land uses. A key objective is the designation and ultimate

    acquisition of right-of-way width.

    2.2 Planning Development Access for New RoadsThis section provides planning and design considerations for planning access to

    development by new roads and other transport infrastructure in Qatar to be approved

    by Overseeing Organization for planning and eventually adopted by the Overseeing

    Organization for road works. It includes guidance on the information required to satisfy

    the transport and highway aspects of planning applications with particular regard to

    safety, pedestrians, cyclists, public transport, service and private vehicles, and parking

    standards.

    2.3 Project Development ProcessRoad projects are undertaken to address specific transportation problems, such assafety, capacity, physical features, or accessibility. Generally, road problems fall into

    three categories:

    •  Safety: There is a frequency and pattern of crashes well in excess of what should

    be expected for the location, with such crash experience potentially treatable by

    proven effective countermeasures.

    •  Demand exceeds capacity:  Existing facilities do not meet current or projected

    traffic demand as measured by the desired level of service for the facility.

    •  New development: Access needs to be provided to new developments.

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    21/101

    VOLUME 1 PART 2

    PLANNING

    PAGE 10 VOLUME 1

    These types of problems may be observed for potential road users, be they motorists,

    pedestrians, and cyclists. The problems that a project is intended to address should be

    clearly defined and agreed upon by all stakeholders early in the project development

    process. Therefore, it is important to actively involve stakeholders and seek their inputearly in the project. See also Chapter 1, of Part 20, Context Sensitive Design and

    Solutions,

    2.3.1 Development Process for New Road Projects

    Once a project is planned and recommended for implementation, it goes through the

    following major design phases with specific milestones before implementation:

    scoping, concept design, preliminary design, detailed design, and tenders.

    Construction, operation, and maintenance phases of projects are discussed in other

    manuals. An exception to this process is design and build (D&B) project delivery, in

    which detailed design and construction are combined into a single phase in the project

    development process. See Section 2.3.2 regarding the D&B process.

    1.  Scoping Phase: The project purpose and need, goals, and objectives are defined in

    the scoping phase. Stakeholders are identified, and a project manager is assigned

    to assemble the project team based on the relevant disciplines involved in the

    project. The project team defines project deliverables, estimated budget, and

    schedule for completion of the study and design of the project. The team conducts

    a field investigation of the project to identify potential problems including impacts

    to sensitive sites, constructability issues, level of outreach, and method of project

    delivery.

    2.  Conceptual Design: During the conceptual design, strategies that could address the

    problem including traffic management, alternative transportation routes and

    modes, physical improvements, and other measures are identified, studied,

    analyzed, and evaluated. If all strategies other than physical improvement prove

    insufficient to address the problem, physical improvement will be recommended.

    Relevant information including forecast traffic data and topographic survey

    information will be obtained. Alternative improvement concepts will be

    developed, analyzed, and evaluated based on project goals and objectives, and

    presented to stakeholders. The alternative that meets the project objectives will

    be submitted for approval and advanced to preliminary design. 

    The conceptual engineering design phase will include the following:

    −  Gathering available information on location, size, use of the road, and

    pedestrian, bike, and landscape features; visiting the project site to locate

    sensitive environmental features; and conducting topographic and utility

    surveys.

    −  Conducting traffic counts and analysis and developing design year traffic

    projections. 

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    22/101

    VOLUME 1 PART 2

    PLANNING

    VOLUME 1 PAGE 11

    −  Developing and analyzing alternative conceptual solutions (including

    multimodal opportunities) in coordination with stakeholders; preparing

    conceptual engineering drawings; evaluating concepts; and identifying the

    preferred alternative.

    −  Establishing a workable geometric design for the preferred alternative that will

    work through the final design without major revisions to the horizontal and

    vertical geometry; preparing typical cross sections of structures and other

    features; and identifying landscaping constraints and opportunities.

    −  Establishing the type, size, and length of structures, including bridges, retaining

    walls, box culverts, and other major structures that may be needed.

    −  Performing conceptual design of drainage systems, including watershed

    delineation, storm sewer system layout, culverts, waterway bridges, and

    stormwater management facilities, and utility conflict and mitigationmeasures.

    −  Performing analysis of constructability and maintenance of traffic and

    conceptual design of traffic management and intelligent transportation system

    (ITS) plans.

    −  Establishing limits of right-of-way, identifying land and parcels that need to be

    acquired.

    −  Assessing the environmental impacts of the preferred alternative, obtaining

    stakeholders’ approval, and securing the required permits and approvals.

      Conducting a value engineering review and incorporating its finding into thedesign.

    −  Developing quantities and estimated construction cost for the project, and

    documenting pros and cons of the preferred alternative.

    −  Conducting mandatory reviews and quality controls subject to approval from

    the Overseeing Organization. 

    3.  Preliminary Design: Once the preferred alternative is selected and approved, the

    project will be advanced to preliminary design. The preliminary design phase is very

    important. Sufficient engineering design details of the selected concept will be

    developed and evaluated to verify that there are no unforeseen problems in thedesign. Departures and required permits will be identified and the application

    process will begin. A detailed cost estimate and construction schedule will be

    developed based on the preliminary design plans. The project delivery method, e.g.,

    design, tender, and construct or design and build, will also be decided during the

    preliminary design phase. Engineering activities in this phase include the following:

    −  Design and further refinement of roadway geometry

    −  Design of drainage systems, erosion and sediment controls, and storm water

    management facilities 

      Design of structures and bridges, traffic control features, and ITS−  Design of landscaping features and multi-use paths and trails

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    23/101

    VOLUME 1 PART 2

    PLANNING

    PAGE 12 VOLUME 1

    −  Identification of utility conflicts and relocations options, utility designs, and

    utility field inspection

    −  Conducting constructability analysis, and preparing maintenance of traffic and

    construction staging plans

    −  Conducting and documenting mandatory reviews and quality controls

    −  Obtaining approval for right-of-way expropriations

    −  Revising and updating quantities, cost estimates, and schedule

    −  Applying for and obtaining required permits from the Overseeing Organization 

    4.  Detailed Design: Final design comprises the following activities:

    −  Finalizing the design and producing final plans for roadways, drainage systems,

    erosion and sedimentation control, and stormwater management systems.

    −  Finalizing the design for and producing final plans for structures and bridges,

    traffic control devices/ITS, landscaping, and multi-use facilities, and so on.

    −  Finalizing right-of-way plans; preparing utility impacts analysis, and producing

    utility composite plans for existing utility relocations and for proposed utilities.

    −  Obtaining all required permits.

    −  Performing constructability and maintenance of traffic analyses, and preparing

    construction staging and traffic management plans.

    −  Authorizing right-of-way expropriation and utility relocation or installation, or

    both

    −  Making necessary preparations for construction advertisement and tender.

    5.  Pre-tender Phase: The pre-tender phase includes the following activities:

    −  Prepare construction cost estimate, specifications, and construction schedule

    for the project with sufficient details and milestones based on the final plans

    and quantities.

    −  Secure required permits, certifications, and approvals.

    −  Prepare an overview of the project for the contract department including

    general information, factors considered in preparing cost and schedule, andknown issues that could affect the project, along with supporting

    documentation for cost and schedule.

    2.3.2 Project Development Process: Design and Build (D&B)

    The process for developing plans up to the end of the conceptual design stage for D&B

    projects is generally the same as that for a design, tender, and construct project.

    Limited investigation and engineering and design can be necessary to identify key risks

    and opportunities to be included in the D&B tender. More detailed engineering and

    design is not required prior to tender for a D&B project, as it limits the D&B team’s

    scope for innovation. However, a value engineering study is recommended for large

    projects.

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    24/101

    VOLUME 1 PART 2

    PLANNING

    VOLUME 1 PAGE 13

    Once a decision is made to use the D&B delivery method, the project team will use the

    conceptual engineering plans to develop the tender documents, including project

    limits, scope of work, outline schedule, employer’s requirements, and special

    provisions. A cost estimate will need to be prepared to assess tenders. Rights-of-wayneed to be conservative, within reason, at the concept phase for a D&B project to

    provide bidders scope for innovation.

    Following the concept design, the process for D&B projects differs from the design,

    tender, and construct process. Development of preliminary design and construction

    plans and construction of the project will be the responsibility of the successful D&B

    tenderer’s team. The D&B team will begin mobilization and construction work before

    completion of the design stages.

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    25/101

    VOLUME 1 PART 2

    PLANNING

    PAGE 14 VOLUME 1

    This page intentionally left blank.

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    26/101

    VOLUME 1 PART 2

    PLANNING

    VOLUME 1 PAGE 15

    3 Project Development Processfor Interchange Design Studies(Existing Reconstruction orNew)

    Selecting and designing the best-value interchange combines application of the

    technical background described above with site- or location-specific knowledge and

    data. The importance of interchanges to the functionality of the overall highway

    network demands careful study to determine the best solution. The design process

    starts with an understanding of the basic goals, objectives, and need for the

    interchange project.

    3.1 Step 1: Establish Data Collection Requirements andObtain Data

    At a minimum, the following data and information are necessary to conduct a study to

    determine the appropriate interchange type and to advance it through final

    engineering design:

    •  Design year average daily and design hour traffic forecast for freeway approaches,

    crossroad, ramps, and all peak hours turning movements. If the new interchange is

    within 4 kilometers (km) of an adjacent interchange, traffic forecast data for that

    interchange should be obtained to understand the operational effects on it.

    •  Aerial photography and base-mapping allowing for planning studies at suitable

    scales of typically 1:2500 for concept planning and eventual preliminary

    engineering at 1:1000 and 1:500 scales.

    •  Ownership of land in all quadrants of the proposed location and along the

    crossroad.

    •  Knowledge of important cultural, historic, environmental, mosques, schools, parks

    and public safety facilities, or other lands and land uses near the interchange. Note

    that awareness of these goes beyond potential right-of-way needs and

    encompasses such factors as noise, visual effects, and presence of pedestrians.

    •  Plans and inspection reports for existing highway and bridge infrastructure at the

    proposed location.

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    27/101

    VOLUME 1 PART 2

    PLANNING

    PAGE 16 VOLUME 1

    •  Plans of known utilities, both above and below ground.

    •  Data on soil conditions.

    3.1.1 Develop Interchange Planning and Design Framework

    Key early decisions and actions will affect the progress of the study. The nature of

    interchange projects is that many public, governmental, and private stakeholders may

    have a direct interest in one or more aspects of the study, including regulatory

    permissions and approvals.

    3.1.2 Stakeholder Involvement

    Key stakeholders are any agency or individual with a direct interest because of the

    location of the study, or because of their role in providing information and data, in

    reviewing, in issuing permits, or in accepting and approving the project. Early notice to

    such stakeholders facilitates their input when needed, thus reducing the time and costto complete the project. Early notice and engagement avoids problems associated with

    unforeseen conflicts.

    For major interchange projects or projects in urban areas affecting many stakeholders,

    best practice is to formally engage them in early meetings and dialogue, referred to as

    chartering. Table 3.1 summarizes suggested representative stakeholders and both the

    issues and potential inputs they may provide to the project.

    Table 3.1 Typical Stakeholders and Their Issues for Interchange Projects

    Stakeholder Issue or Concern

    Overseeing Organization:

    Design

    Project is designed in accordance with standards; adequate review and

    approval of Departures.

    Overseeing Organization:

    Traffic

    Project will operate as intended (LOS, safety performance); operation of

    traffic controls.

    Overseeing Organization:

    Construction

    Project bids will be acceptable; constructability within schedule and

    budget.

    Overseeing Organization:

    Maintenance

    Need for maintenance of all project elements, safety of maintenance

    workers.

    Overseeing Organization:

    Public Parks

    Landscaping of public places, planting of trees, traffic island planting, and

    maintenance of landscaping and public parks.

    Transit Agency

    Incorporation of bus stops or light rail/metro stations near interchange

    on crossroad; safety of pedestrians.

    Utilities Need for and timing of relocated utilities.

    Adjacent Landowners

    Potential acquisition, noise from traffic, dust and other impacts of

    construction, changes in access to their properties, visual effects, timing,

    and length of construction.

    Highway Users Safety of the interchange, reductions in delay or travel time after

    construction, detours, or delays during construction.

    Ministry of Environment Protection of proximate environmental resources, permitting, and

    approvals.

    Law Enforcement Ability to enforce traffic laws, safety of the interchange.

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    28/101

    VOLUME 1 PART 2

    PLANNING

    VOLUME 1 PAGE 17

    A chartering meeting may include the following:

    •  Background introduction of the need for the project

    •  Introduction of key project staff, including contact information•  Presentation of the planned public outreach program

    •  Intended schedule for the study, design, and construction

    •  Opportunity for stakeholders to present issues or concerns at the outset

    •  Discussion of issues regarding property or interest that may not be known from

    public records

    3.1.3 Develop Project Planning and Design Criteria

    The entity conducting the study, consulting with appropriate agency stakeholders

    including the Overseeing Organization, should develop, distribute, and present the design

    criteria for the project. These should include design speeds of all elements, design year

    and basis for design year traffic, design LOS for all elements, design vehicles, drainage

    design criteria, and design standards to be used, including specific entrance and exit

    design details. At this stage, criteria determined to be appropriate for use that are outside

    the QHDM-published criteria are understood to be subject to a Departure. Best practices

    are for such criteria to be discussed fully before initiating major work, with concurrence

    from or at least notice to the Overseeing Organization of the reasons for the Departure,

    and agreement to proceed using the proposed criteria.

    3.2 Step 2: Confirm Study Approach, Evaluation Criteria,

    and Decision ProcessThe planning and design framework includes an affirmation of the technical approach to

    the work. This should be as outlined in the scope of work for the project, but before it

    begins, concurrence on methods, data, and necessary assumptions where no data exist

    should be reached. Such methods may include capacity and operational analysis methods

    that are both large- and small-scale, and quantitative safety analyses.

    3.2.1 Determine Evaluation Criteria and Technical Approach

    The key technical factors that will drive the selection of one alternative over another

    should be identified, which should shape the detail and level of effort in addressing

    them. Although every project is unique, the following factors generally will be of

    sufficient importance:

    •  Estimated initial cost of construction

    •  Measures of traffic service, such as travel time, delays, queuing, and LOS

    •  Right-of-way acquisitions, including not only cost but also types of businesses,

    residences, or other uses affected or displaced

    •  Accessibility to side roads and private properties

    •  Environmental issues requiring mitigation

      Assessment of safety performance•  Constructability

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    29/101

    VOLUME 1 PART 2

    PLANNING

    PAGE 18 VOLUME 1

    To the extent possible, those charged with making the final decision on which

    alternative to select should communicate the relative importance of these factors.

    3.2.2 Develop Design Year Traffic and Select Most Likely AlternativesThe next step is to develop design year traffic as intended, and then, with reference to

    the guidance presented in Part 9, identify the most likely reasonable alternatives for

    the location. These will depend on the functional classification of each road, design year

    traffic, general knowledge of the spatial and quadrant-specific requirements for each

    interchange form, and understanding of the most likely or only vertical

    crossroad/freeway relationship.

    For service interchange projects, there may as many as six reasonable options

    representing basic forms and variants thereof. For system interchange projects, at least

    three and often more solutions may be worthy of study.

    3.3 Step 3: Conduct Interchange Type StudiesThe process for efficient and complete interchange studies is stepped and begins with

    as many likely alternatives as are evident, then proceeds through increasing level of

    technical detail to screen those down to a single preferred alternative.

    3.3.1 Concept Engineering Design

    The following is completed is for each concept identified for study:

    •  Size each interchange concept using design year traffic and quick capacitytechniques. Sizing refers to determining the preliminary numbers of lanes for

    ramps, ramp terminal intersections, roundabouts, crossroad bridges, auxiliary lanes

    on freeway.

    •  Develop concept level design in plan view over aerial photography. A sufficiently

    skilled and knowledgeable designer can develop appropriate geometry without

    having to conduct profile studies. The designer can estimate limits of bridges and

    retaining walls, approximate right-of-way, and potential encroachments on

    properties. Figure 3.1 is an example of such a concept.

    •  Using this information, an approximate, comparative construction cost estimatecan be prepared. As the interchanges should be operationally comparable, the

    process of screening focuses on costs, right-of-way, and environmental or special

    local issues.

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    30/101

    VOLUME 1 PART 2

    PLANNING

    VOLUME 1 PAGE 19

    Figure 3.1 Example Single-line Concept Plan View over Aerial

    3.3.2 Stakeholder Review and Screening

    Depending on the project’s sensitivity and importance, conduct external stakeholder or

    public meetings to present the alternatives under consideration and their attributes.

    Such meetings may apprise designers of previously unknown specific issues or impacts

    associated with one or more alternatives.

    Consult with agency and regulatory stakeholders. As a minimum, they should

    communicate fatal flaws or issues that may, if not resolved, present major schedule or

    cost impacts not previously apparent. They may express views representing their

    agency on the alternatives that the Overseeing Organization should consider.

    Decision-makers can then screen the alternatives down to the most reasonable two, or

    at most three.

    For simple two-level service interchange projects, it may be possible to select the best

    value solution. For multilevel system interchanges with complex geometry and

    significant costs, the next step is generally required.

    3.4 Step 4: Functional Geometric Design of ScreenedAlternativesAn alternative proceeding to this stage should have no environmental or other

    problems that would hinder its selection. Assuming more than one alternative remains

    viable, designers next conduct preliminary geometric design studies at an acceptable

    scale as agreed with the Overseeing Organization in three dimensions. Plan view,

    profile in the detailed design stage, and intersection design studies are conducted. The

    latter include details such as intersection or roundabout geometry, left- and right-turn

    lengths, signal phasing, and operations. Concept level bridge studies determine mostlikely type, depths, widths, and ancillary structures such as retaining walls. To facilitate

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    31/101

    VOLUME 1 PART 2

    PLANNING

    PAGE 20 VOLUME 1

    a decision, additional concept studies of drainage, lighting, and signing may be

    conducted. With three-dimensional plans, earthwork can be developed as part of the

    detailed design, enabling firm estimates of right-of-way acquisition. At this stage,

    differences in construction staging or maintenance of traffic along the freeway shouldbe understood and documented.

    This phase of work may include micro-simulation studies of freeway and or crossroad

    operations. These can provide more complete measures of traffic performance, which

    may help differentiate between, say a partial cloverleaf (PARCLO) interchange and a

    diamond, or between a signalized diamond and a roundabout diamond interchange.

    Finally, quantitative safety analyses using the Highway Safety Manual  (HSM; American

    Association of State Highway and Transportation Officials [AASHTO], 2011) can be

    performed to develop comparisons of the difference in predicted crash types and

    severities.

    At this level of design, all necessary significant Departures should be known. They

    should be fully discussed to the point that, should an alternative be selected, there is

    confidence that any Departures associated with it will be found acceptable.

    3.5 Step 5: Select Preferred Alternative, Document andDevelop Final Engineering PlansWith all the above detail, there is sufficient technical information for the Overseeing

    Organization to determine a preferred alternative. Once a decision is made, completion

    of all final engineering plans can proceed.

    Documentation of the recommended plan, including the following, provides the

    background to explain and defend the project:

    •  Stakeholders consulted and their input

    •  Alternatives considered, including summaries of those screened out

    •  Design plans and supporting technical information on alternatives with completed

    functional design

     Construction cost models, assumptions and estimates

    •  Environmental clearances and other permits required or obtained

    •  Departures subject to final approval

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    32/101

    VOLUME 1 PART 2

    PLANNING

    VOLUME 1 PAGE 21

    4 Projects Involving ExistingRoads

    The Overseeing Organization may undertake projects involving existing roads. There

    are four main reasons for such projects, associated with modes of travel:

    •  An observed or expected traffic operational problem, such as bottlenecks or low

    LOS

    •  An observed safety problem, as identified through a science-based assessment of

    crash frequency and severity

    •  An identified need to provide access to a new adjacent development

    •  Pavement or other road infrastructure in a state of disrepair

    Projects involving existing roads are named 3R for Resurfacing, Restoration, and

    Rehabilitation. Examples of 3R projects include:

      Pavement that has reached its useful life and requires complete replacement,including potentially the subgrade, shoulders and curbing

    •  Removal of a bituminous overlay to a concrete pavement and replacement with a

    new overlay

    •  Replacement of roadside barriers such as guardrail

    •  Bridge redecking

    •  Major repairs or replacements to a bridge substructure

    Other certain work efforts related to infrastructure condition are fundamentally

    preventative maintenance activities. These may include minor pavement repairs suchas seal coats, full-width patching, crack sealing, and thin plant mix resurfacing for

    sealing of the pavement surface, correcting minor surface irregularities, and other

    similar repairs. Curb repairs or replacement, replacement of drainage inlets, and other

    similar activities are also fundamentally preventative maintenance in nature. These

    repair types are an important part of the Overseeing Organization’s overall mission.

    Maintenance repair activities are not considered to be 3R or reconstruction projects.

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    33/101

    VOLUME 1 PART 2

    PLANNING

    PAGE 22 VOLUME 1

    4.1 Unique Characteristics of Projects InvolvingExisting RoadsProjects involving existing roads fundamentally differ from those involving new roads

    for several important reasons. First, there is a proven and observable set of traffic

    operational and safety performance measures for an existing road. These should be

    referenced to determine the nature and extent of any problem.

    Second, in most cases there is fixed right-of-way for the existing road, around which

    land development typically has occurred. In urban areas development typically will

    involve buildings and other private infrastructure immediately contiguous with the

    right-of-way. Projects involving existing roads require designers to understand the

    context and to be creative in developing solutions within the right-of-way, because any

    major realignment or widening has the potential for producing substantial impacts to

    many property owners and stakeholders.

    A third unique aspect of projects involving existing roads is they have in place a roadway

    with fixed geometric conditions. The road will have been designed to standards

    employed at the time of its initial construction. Some roads may predate the 1997

    QHDM. As this edition of the QHDM includes some revisions to geometric design

    criteria based on research advances, it is possible that an existing road may have

    geometric features that do not meet the updated, current version of QHDM design

    standards.

    Design standards are a means to an end. The end desired is measurable or expected

    performance with respect to either safety, operations, or both. An existing geometric

    feature or dimension that does not meet current design criteria does not automatically

    require reconstruction to meet such criteria. Such practice is a sub-optimal use of

    resources and may produce unnecessary inconvenience to road users and stakeholders

    affected by construction activities. Decisions under a best-value approach shall be

    based on a review and analysis of the existing roadway’s performance.

    Projects of the above nature will be considered as either 3R projects or reconstruction

    projects. The Overseeing Organization will make the determination for project

    eligibility for 3R treatment using the criteria discussed below.

    4.2 Design of Reconstruction ProjectsReconstruction projects will be those for any of the following:

    •  The demonstrated project need goes beyond mere infrastructure repair, to include

    a known quantitative safety problem or a known operational problem.

    •  The project involves the redesignation or reclassification of a roadway to serve new

    types of trips or travel not previously included along the route, such as bike paths

    or dedicated transit only lanes; widening; conversion of intersection type such as

    roundabout to signalized intersection.

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    34/101

    VOLUME 1 PART 2

    PLANNING

    VOLUME 1 PAGE 23

    •  The project is bridge replacement which specifically includes improvements to

    vertical clearance.

    •  The project converts a temporary road to a permanent road.

    •  The Overseeing Organization determines that the project shall not be eligible for

    3R treatment, as described above.

    Reconstruction projects will involve substantial revision to the functionality and three-

    dimensional character of the road. Reconstruction projects shall be designed and

    reconstructed using the design criteria in the QHDM.

    Challenges unique to reconstruction versus new construction projects include these:

    •  Right-of-way typically is limited, with adjacent development already established.

    Even minor strip acquisitions may create significant damage to adjacent properties,

    in some cases necessitating entire acquisition.

    •  In most cases, it will be necessary to maintain traffic flow along the roadway during

    reconstruction. This includes through traffic, intersection movements, and access

    to business, retail, and residential land uses. Existing underground utilities are in

    place. These constraints will influence the suitability of design solutions, and may

    limit the ability to make more than minor changes to vertical alignment.

    The full design process for new roads applies to reconstruction projects, including

    development of design alternatives and evaluation of potential Departures from

    Standards. Departures may be significant for such projects.

    4.2.1 Relationship of Safety Performance to Design Elements

    The acceptance of Departures from Standards generally will be greater for reconstruction

    projects. A project may be designated for reconstruction based on a review of its crash

    history, but the types and locations of crashes may be such that certain design elements

    or locations along the road may not require full geometric redesign. Thus, for example,

    a decision may be made to flatten a horizontal curve but to retain the vertical

    alignment, even though there are nominally substandard elements.

    Table 4.1 summarizes the known relative importance of roadway elements in safety

    performance, crash frequency, and severity of different roadway types and contexts.

    Not every geometric element is of equal importance in influencing safety performance.

    Moreover, the contribution to safety performance of an element varies by type of road.

    Table 4.1 serves as a reference in making decisions on retaining existing road geometry

    to avoid major costs and conflicts. Refer to the AASHTO HSM (2011) for more details

    on the specific elements and road types.

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    35/101

    VOLUME 1 PART 2

    PLANNING

    PAGE 24 VOLUME 1

    Table 4.1 Relative Relationship of Geometric Design Features to Crash

    Frequency or Severity by Type of Road

    Roadway Design Elements

    Road Type and Intersections

       R   u   r   a    l   2  -    l   a   n   e

       R   u   r   a    l   M   u    l   t   i    l   a   n   e

       M   u    l   t   i    l   a   n   e   U   r    b   a   n

       A   r   t   e   r   i   a    l   s   a   n    d

       C   o    l    l   e   c   t   o   r   s

       F   r   e   e   w   a   y

       U   n   s   i   g   n   a    l   i   z   e    d

       i   n   t   e   r   s   e   c   t   i   o   n

       S   i   g   n   a    l   i   z   e    d

       i   n   t   e   r   s   e   c   t   i   o   n

       R   o   u   n    d   a    b   o   u   t

    Cross Section

    Lane Width     —   — — —

    Cross Slope     — — — — —

    Shoulder Width ✓  ✓  — ✓  — — —

    Shoulder Type (Paved, Unpaved)     —   — — —

    Presence of Rumble Strips ✓  ✓  — ✓  — — —Sideslope     — ✓  — — —

    Clear Zone ✓  ✓  — ✓  — — —

    Presence of Roadside Barrier ✓  ✓  — ✓  — — —

    Presence of Median NA ✓  ✓  ✓  — — —

    Width of Median NA ✓  ✓  ✓  — — —

    Alignment

    Horizontal Curvature (Radius) ✓  ✓  — ✓  NA NA ✓ 

    Length of Curve ✓    —   NA NA NA

    Presence of Spiral ✓    —   NA NA NA

    Superelevation   — — — NA NA NA

    Grade ✓    — — NA NA NA

    Length of Vertical Curve   — — — NA NA NA

    Stopping Sight Distance   — — — NA NA NA

    Presence of Weaving Sections NA NA NA ✓  NA NA NA

    Length of Weaving Sections NA NA NA ✓  NA NA NA

    Location of Ramps (Left vs. Right) NA NA NA ✓  NA NA NA

    Other

    Frequency of Driveways ✓  — ✓  NA NA NA NA

    Frequency of Intersections ✓  ✓  ✓  NA NA NA NA

    Type of Intersections (TrafficControl)

    — — — NA NA NA NA

    Intersection Elements

    Intersection Sight Distance NA NA NA NA ✓  — —

    Number of Legs/Approaches NA NA NA NA ✓  ✓  ✓ 

    Skew Angle NA NA NA NA ✓  ✓  —

    Presence of Left-Turn Lanes NA NA NA NA   ✓  —

    Presence of Right-Turn Lanes NA NA NA NA     —

    KEY: Significant Effect  Minor Effect — No Effect NA Not applicable

    Based on AASHTO HSM (2010).

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    36/101

    VOLUME 1 PART 2

    PLANNING

    VOLUME 1 PAGE 25

    4.2.2 Risk Management Guidelines

    Safety performance related to roadway design elements and dimensions is a

    continuum. One can estimate safety risk by quantifying the three most important

    factors that relate to crash risk on all road types:

    •  How close the dimension or value is to the specified minimum value

    •  Traffic volume exposed to the element

    •  Length of roadway over which the element occurs

    Marginal differences in a design dimension will have at most marginal differences in

    the expected safety performance of the road if any. Figure 4.1 illustrates this concept.

    Source: Fambro, et al. Determination of Stopping Sight Distances, NCHRP Report 400.

    Figure 4.1 Conceptual Relationship between Available Sight Distance and Safety

    at Crest Vertical Curves

    Figure 4.1 is taken from research on SSD and is illustrative only. The concepts below

    apply not only to SSD but also to all other geometric elements.

    Existing values for sight distance that do not meet the standard but are short by only a

    small amount will produce little if any practical increase in actual risk. Only when the

    amount of the deficiency is large might a meaningful increase in crash risk be expected.

    4.2.2.1 Effective vs. Selected Design Speed

    Taking the minimum design value per QHDM standards as a reference point, a useful

    measure of risk is the difference between the “effective” design speed of existing

    geometry for a design element, such as, horizontal or vertical curvature, and the

    selected design speed. This difference is referred to as delta V ( Δ V). Geometry that may

    not meet the minimum standard but that is very close to it, with a small value for delta

    V, can be considered as presenting minimal risk.

  • 8/17/2019 QHDM Vol1 Part02 Planning OctFinal

    37/101

    VOLUME 1 PART 2

    PLANNING

    PAGE 26 VOLUME 1

    The following guidelines apply and may be used in making departure decisions:

    •  Low risk alignment has a Δ V of 10 kilometers per hour (kph) or less.

    •  Moderate risk alignment has a Δ V of 11 kph to 20 kph.•  High risk alignment has a Δ V of greater than 20 kph.

    4.2.2.2 Traffic Volume Exposure

    Substantive safety risk is also proportional to the traffic volume on the roadway. For

    example, the predicted crash frequency per km for a 2-lane rural highway is 0.15 per

    year for a volume of 1,000 vpd, and 2.5 per km for the same road with 15,000 vpd.

    Whatever the effect of a geometric element may be, the risk is clearly different

    depending on the traffic volume exposure. This same concept applies to intersections,

    which are point locations in terms of crash frequency.

    4.2.2.