PT. Bakrie Metal Industries No.Distribution PROCEDURE QUALITY CONTROL Status : INSPECTION & PRODUCT MEASUREMENT No Document : BMI/II/QC/01 Reviewed by Approved by (QC Officer) ( Management Representative ) Revision Notes Revision Date Page Description 1 1 Aug 2003 1 - 4 Purpose dan No. Document 2 1 Apr 2005 3 - 4 (4.2.2) Augment Material Test proses & Flowchart CTE changes to Works Manager 3 1 Aug 2006 2 (4.2.1) Construction and Fabrication, Standard inspection 3 (4.2.2) Material test, (4.2.3) Identification 4 12 Dec 2011 4 1 - 3 (4.3.1) Identification, (5) Reporting test results (4) Procedure: (4.1) General; (4.2) Material Test; (4.3) Incoming Inspection; (4.4) Material in Proses/ WIP Inspection; (4.5) Inspection Finished Goods before being sent to the Warehouse; (4.6) Final Inspection before Delivery.

Upload: ekyharyans

Post on 19-Dec-2015

19 views

Category:

Documents


1 download

DESCRIPTION

QC Procedure

TRANSCRIPT

  • PT. Bakrie Metal Industries

    No.Distribution

    PROCEDURE QUALITY CONTROL

    Status :

    INSPECTION & PRODUCT MEASUREMENT

    No Document : BMI/II/QC/01

    Reviewed by Approved by

    (QC Officer) ( Management Representative )

    Revision Notes Revision Date Page Description

    1 1 Aug 2003

    1 - 4 Purpose dan No. Document

    2 1 Apr 2005

    3 - 4 (4.2.2) Augment Material Test proses & Flowchart

    CTE changes to Works Manager

    3 1 Aug 2006

    2 (4.2.1) Construction and Fabrication, Standard inspection

    3 (4.2.2) Material test, (4.2.3) Identification

    4

    12 Dec 2011

    4

    1 - 3

    (4.3.1) Identification, (5) Reporting test results (4) Procedure: (4.1) General; (4.2) Material Test; (4.3) Incoming Inspection; (4.4) Material in Proses/ WIP Inspection; (4.5) Inspection Finished Goods before being sent to the Warehouse; (4.6) Final Inspection before Delivery.

  • QUALITY CONTROL PROCEDURE No Doc : BMI/II/QC/01 Revision : 4 Inspection & Product

    Measurement Date : 12 December 2011

    Page : 1 of 4

    No.Distribution

    1. PURPOSE To ensure all incoming materials from suppliers, the materials are processed outside,

    Product Return and Customer Property, have been checked or verified before it is approved for use, processed for the production or delivered to the customer.

    To ensure all checks are conducted and recorded properly, according to the procedures and work instructions to meet the specified quality level.

    2. SCOPE This procedure applies to:

    a) Incoming Inspection: Materials suppliers listed in the Approved Vendor List; Materials are processed outside (by supplier); Product Return / product that rejected by customer; Customer Property.

    b) Work Inspection or inspection during the process. c) Finished Goods before being sent to the warehouse. d) Final Inspection before delivery.

    3. RESPONSIBILITY QC section is responsible for checking the material / product according to the scope of the above and provide identification also doing documentation according to activities.

    4. PROCEDURE 4.1 General

    a) Product / Material which is qualified at Incoming Inspection given the identification marks "IQC Pass" on the travel assignment letter and the green line on the side of the stacks.

    b) Qualified in process products which are given the identification marks "" in the product being processed.

    c) Qualified Finished goods are given the identification mark "Line on the side of the stack (Construction Products), and mark () (Fabrication Product)" sign on each product.

    d) Products / materials that does not qualified at Incoming, WIP, or Final Inspection followed up by following the procedure "Control of Product Not Available".

    4.2 Materials Test a) Material test conducted if there is a request from the Customer, there is a new supplier is still

    questionable its material or any projects that are vulnerable to risks caused by the materials that are less good.

    b) Testing conducted by an accredited testing agency such as: LUK & B4T. c) Methods of testing performed by means of: 3 samples / 1 in thickness.

  • QUALITY CONTROL PROCEDURE No Doc : BMI/II/QC/01 Revision : 4 Inspection & Product

    Measurement Date : 12 December 2011

    Page : 2 of 4

    No.Distribution

    d) If the material test results qualified the material is ready to be processed further to produce. e) If not qualified then the NCR will be published and distributed to the Purchasing, then the

    material will be retested again. f) If the second re-test results are also not qualify it will be confirmed with the Works Manager

    for the further specifically accepted or canceled.

    4.3. Incoming Inspection

    NO. INSPECTION STANDARD INSPECTION

    1 Material

    Can be seen on Quality Inspection Plan Summary (BMI/II/QC/03)

    General Tolerance following BMI Standard.

    2 Bolt & Nuts

    3 Consumable Zinc & Alumunium

    4 Consumable Bahan Kimia

    5 Product Return

    6 Customer Property

    7 Consumable Filler Metal

    4.4. Material in Process (WIP) Inspection 4.4.1 Construction and Fabrication

    STANDARD INSPECTION

    NO. PRODUCT PIC STANDARD INSPECTION

    I. Multi Plate

    Can be seen on Quality Inspection Plan Summary (BMI/II/QC/03).

    Can be seen on Quality Inspection Plan Summary (BMI/II/QC/03).

    General Tolerance following BMI Standard.

    II. Base Channel

    III. Anchor Base Channel

    IV. Bridge Deck

    V. Beam Guardrail

    VI. Post & Block Piece Guardrail

    VII. Terminal End Guardrail

    VIII. E 100

    IX. Galvanize

    X. Fabrication

  • QUALITY CONTROL PROCEDURE No Doc : BMI/II/QC/01 Revision : 4 Inspection & Product

    Measurement Date : 12 December 2011

    Page : 3 of 4

    No.Distribution

    4.5. Inspection Finished Goods before being sent to the Warehouse

    STANDARD INSPECTION

    Type of Checked Alat Standard Inspection Sampling/ Frequency

    Remarks

    Appearance

    Visual

    1. Produk is not damaged

    Refer to Work

    Instructions (WI)

    Visual 100%

    Personal In Charge: QC Inspector

    Identification

    1. Stamping atau Metal Tag (Production Code/No. Project , No. Drawing, etc.)

    Dimension

    Inspection gauge

    Must match spesification / Work Instructions (WI)

    1. Dimension

    2. Appearance

    3. Painting, Blasting, Welding Condition, etc.

    4.6. Final Inspection before Delivery

    STANDARD INSPECTION

    Type of Checked Tool Standard Inspection PIC

    Sampling/ Frequency

    Remarks

    Quantity Manual According Delivery List PPC Dispatcher

    Visual 100%

    Final Inspection Proof registered on Inspection Release Certificate (IRC)

    Appearance Visual

    No damage Quality Control

    Inspector Identification Can be clearly seen

    5. REPORTING TEST RESULTS a) All test results of QC Inspector records are stored and maintained within a certain time

    according to procedure "Control of Quality Records". b) QC making the summary rejects that occur during production on "Recapitulation Reject"

    and report the results to the Works Manager. c) Identification of colors used:

  • QUALITY CONTROL PROCEDURE No Doc : BMI/II/QC/01 Revision : 4 Inspection & Product

    Measurement Date : 12 December 2011

    Page : 4 of 4

    No.Distribution

    Green OK / Qualified Yellow On Hold / Rework Red Final Reject

    6. RELATED DOCUMENTS Flowchart of Material test Appendix 10-1

  • FLOWCHART Attachment : 1 Revision : 0 Material Test Date : 1 Apr 2005 Page : 1 of 1

    No.Distribution

    INCOMMINGRAW MATERIAL

    Hasil dapatditerima?

    Not OK

    Selesai

    Selesai

    OK

    PENGUJIAN 1

    PENGUJIAN 2

    PengujianUlang?

    Not OK

    No

    Yes

    Hasil dapatditerima?

    QC/NCR/51

    QC/NCR/51

    Diterima secaraKhusus? Material DitolakNo

    SelesaiYes

    Yes