pvnavigator, milliken landfill epc rfp site visit, photo ......jan 18, 2016 · the milliken...
TRANSCRIPT
![Page 1: PVNAVIGATOR, Milliken Landfill EPC RFP Site Visit, Photo ......Jan 18, 2016 · the Milliken Landfill in Ontario, CA. PVN is in the Process of Selecting a Construction Contractor](https://reader034.vdocuments.us/reader034/viewer/2022051811/60209a7139f65f45931c3362/html5/thumbnails/1.jpg)
PVNAVIGATOR, LLC
Milliken Landfill Site Solar ProjectEPC RFP Site Visit, Photo Report
WEST COAST1 Pointe Drive, Suite 320Brea, CA 92821714.388.1800
www.PVNavigator.comwww.SafetyMoment.org
GULF COAST15990 N. Barkers Landing Rd., Suite 325Houston, TX 77079713.468.5004
NORTHEAST334 East 9th StreetNew York, NY 10002646.370.4588
January 14, 2016
12KV interconnect switchgear (Preliminary SWGR DIMS = 13’Wx3’D)
Last SCE 12KV Overhead Pole
PVN Proposed Layout of Solar Panel Array
![Page 2: PVNAVIGATOR, Milliken Landfill EPC RFP Site Visit, Photo ......Jan 18, 2016 · the Milliken Landfill in Ontario, CA. PVN is in the Process of Selecting a Construction Contractor](https://reader034.vdocuments.us/reader034/viewer/2022051811/60209a7139f65f45931c3362/html5/thumbnails/2.jpg)
PVNavigator, LLC is Poised to Start Construction on a 3MW PV Solar Installation on the Milliken Landfill in Ontario, CA. PVN is in the Process of Selecting a Construction Contractor. This Deck Describes the RFP Job Walk.
2
South Milliken
Avenu
e
South Haven
Avenu
e
12KV interconnect switchgear (Preliminary SWGR DIMS = 13’Wx3’D)
Last SCE 12KV Overhead Pole
PVN Proposed Layout of Solar Panel Array
![Page 3: PVNAVIGATOR, Milliken Landfill EPC RFP Site Visit, Photo ......Jan 18, 2016 · the Milliken Landfill in Ontario, CA. PVN is in the Process of Selecting a Construction Contractor](https://reader034.vdocuments.us/reader034/viewer/2022051811/60209a7139f65f45931c3362/html5/thumbnails/3.jpg)
On January 12, 2016, PVNavigator, LLC (PVN) and the County of San Bernardino Hosted a Site Visit for Potential Bidders to the Milliken Landfill PV Solar EPC RFP.
3
![Page 4: PVNAVIGATOR, Milliken Landfill EPC RFP Site Visit, Photo ......Jan 18, 2016 · the Milliken Landfill in Ontario, CA. PVN is in the Process of Selecting a Construction Contractor](https://reader034.vdocuments.us/reader034/viewer/2022051811/60209a7139f65f45931c3362/html5/thumbnails/4.jpg)
Over 30 Individuals Representing 22 Firms Participated.
4
![Page 5: PVNAVIGATOR, Milliken Landfill EPC RFP Site Visit, Photo ......Jan 18, 2016 · the Milliken Landfill in Ontario, CA. PVN is in the Process of Selecting a Construction Contractor](https://reader034.vdocuments.us/reader034/viewer/2022051811/60209a7139f65f45931c3362/html5/thumbnails/5.jpg)
PVN’s Robert Potter Briefed All Parties with a Safety Moment and a SOW Presentation Before Entering the Site.
5
![Page 6: PVNAVIGATOR, Milliken Landfill EPC RFP Site Visit, Photo ......Jan 18, 2016 · the Milliken Landfill in Ontario, CA. PVN is in the Process of Selecting a Construction Contractor](https://reader034.vdocuments.us/reader034/viewer/2022051811/60209a7139f65f45931c3362/html5/thumbnails/6.jpg)
Bidders at the SCE Interconnect Location.
6
![Page 7: PVNAVIGATOR, Milliken Landfill EPC RFP Site Visit, Photo ......Jan 18, 2016 · the Milliken Landfill in Ontario, CA. PVN is in the Process of Selecting a Construction Contractor](https://reader034.vdocuments.us/reader034/viewer/2022051811/60209a7139f65f45931c3362/html5/thumbnails/7.jpg)
With the PV Facility Going to be Located on the Landfill’s Top Deck, PVN Answered Questions Such as Landfill OM&M Procedures, and Gas Well Headers & Lines Protection.
7
![Page 8: PVNAVIGATOR, Milliken Landfill EPC RFP Site Visit, Photo ......Jan 18, 2016 · the Milliken Landfill in Ontario, CA. PVN is in the Process of Selecting a Construction Contractor](https://reader034.vdocuments.us/reader034/viewer/2022051811/60209a7139f65f45931c3362/html5/thumbnails/8.jpg)
Potential Bidders Review the Milliken Landfill’s Top Deck…The Main Location for the PV Racks.
8
![Page 9: PVNAVIGATOR, Milliken Landfill EPC RFP Site Visit, Photo ......Jan 18, 2016 · the Milliken Landfill in Ontario, CA. PVN is in the Process of Selecting a Construction Contractor](https://reader034.vdocuments.us/reader034/viewer/2022051811/60209a7139f65f45931c3362/html5/thumbnails/9.jpg)
Potential Bidders Discussed Any Potential Maintenance Costs that Should be Included in their Proposals.
9
![Page 10: PVNAVIGATOR, Milliken Landfill EPC RFP Site Visit, Photo ......Jan 18, 2016 · the Milliken Landfill in Ontario, CA. PVN is in the Process of Selecting a Construction Contractor](https://reader034.vdocuments.us/reader034/viewer/2022051811/60209a7139f65f45931c3362/html5/thumbnails/10.jpg)
PVN’s Robert Potter, Rajeev Sane, and Robert Fritz Closed the Site Visit with a Debriefing and a Q&A Session.
10
![Page 11: PVNAVIGATOR, Milliken Landfill EPC RFP Site Visit, Photo ......Jan 18, 2016 · the Milliken Landfill in Ontario, CA. PVN is in the Process of Selecting a Construction Contractor](https://reader034.vdocuments.us/reader034/viewer/2022051811/60209a7139f65f45931c3362/html5/thumbnails/11.jpg)
11
PVNavigator, LLC Permits, Designs, Builds, Owns and Operates Solar Power Projects on Closed Landfill Cells
![Page 12: PVNAVIGATOR, Milliken Landfill EPC RFP Site Visit, Photo ......Jan 18, 2016 · the Milliken Landfill in Ontario, CA. PVN is in the Process of Selecting a Construction Contractor](https://reader034.vdocuments.us/reader034/viewer/2022051811/60209a7139f65f45931c3362/html5/thumbnails/12.jpg)
The Scope of PVNavigator, LLC’s Capabilities
12