pt-boq gmp-r00 04012015

19
Total PT-BOQ GMP-R00 04012015 1 146,060.20 Piping & Fitting 1.00 Job 146,060.20 2 1,486,358.80 Piping & Fitting 1.00 Job 1,326,358.80 Pump 1.00 Job 160,000.00 3 1,289,053.60 Piping & Fitting 1.00 Job 1,169,053.60 Pump 1.00 Job 120,000.00 4 608,865.40 Piping & Fitting 1.00 Job 608,865.40 5 2,275,318.60 Piping & Fitting 1.00 Job 355,318.60 Blower 1.00 Job 1,920,000.00 6 96,496.40 Piping & Fitting 1.00 Job 96,496.40 7 440,128.00 Piping & Fitting 1.00 Job 440,128.00 8 433,851.60 Piping & Fitting 1.00 Job 383,931.60 Valve 1.00 Job 49,920.00 9 85,818.24 Float 1.00 Job 85,818.24 10 1,090,194.00 HDPE Cover Sheet 1.00 Job 1,090,194.00 11 1,199,900.00 HDPE Lining 1.00 Job 1,199,900.00 12 163,511.51 Pump House Floor 1.00 Job 45,526.52 Pump House Roof 1.00 Job 117,984.98 13 76,474.07 Pump House Floor 1.00 Job 11,827.26 Pump House Roof 1.00 Job 64,646.82 14 76,474.07 Pump House Floor 1.00 Job 11,827.26 Pump House Roof 1.00 Job 64,646.82 15 PUMP LIST FOR SCRUBBER 530,000.00 Pump 1.00 Job 530,000.00 BREATHE PIPING SYSTEM PUMP HOUSE PM001, PM002 PUMP HOUSE PM003 PUMP HOUSE PM004 BILL OF QUANTITY DATE 4 January 2015 AMOUNT REMARK Q'ty PROJECT : PT WILMAR-GMP MILL PADANG DESCRIPTION ITEM UNIT HDPE LINING EFFLUENT AND SLUDGE PIPING SYSTEM INFLUENT PIPING SYSTEM TIE IN SYSTEM HDPE COVER SHEET FLOATING SYSTEM PIPING GAS TO GENERATOR SYSTEM PIPING GAS TO FLARE SYSTEM BIO SCRUBBER TO CHILLER PIPING GAS SYSTEM MAIN PIPING GAS SYSTEM

Upload: andre-gazali-malik

Post on 21-Dec-2015

214 views

Category:

Documents


1 download

DESCRIPTION

halooo

TRANSCRIPT

Page 1: PT-BOQ GMP-R00  04012015

Total PT-BOQ GM P-R00 04012015

1 146,060.20

Piping & Fitting 1.00 Job 146,060.20

2 1,486,358.80

Piping & Fitting 1.00 Job 1,326,358.80

Pump 1.00 Job 160,000.00

3 1,289,053.60

Piping & Fitting 1.00 Job 1,169,053.60

Pump 1.00 Job 120,000.00

4 608,865.40

Piping & Fitting 1.00 Job 608,865.40

5 2,275,318.60

Piping & Fitting 1.00 Job 355,318.60

Blower 1.00 Job 1,920,000.00

6 96,496.40

Piping & Fitting 1.00 Job 96,496.40

7 440,128.00

Piping & Fitting 1.00 Job 440,128.00

8 433,851.60

Piping & Fitting 1.00 Job 383,931.60

Valve 1.00 Job 49,920.00

9 85,818.24

Float 1.00 Job 85,818.24

10 1,090,194.00

HDPE Cover Sheet 1.00 Job 1,090,194.00

11 1,199,900.00

HDPE Lining 1.00 Job 1,199,900.00

12 163,511.51

Pump House Floor 1.00 Job 45,526.52

Pump House Roof 1.00 Job 117,984.98

13 76,474.07

Pump House Floor 1.00 Job 11,827.26

Pump House Roof 1.00 Job 64,646.82

14 76,474.07

Pump House Floor 1.00 Job 11,827.26

Pump House Roof 1.00 Job 64,646.82

15 PUMP LIST FOR SCRUBBER 530,000.00

Pump 1.00 Job 530,000.00

BREATHE PIPING SYSTEM

PUMP HOUSE PM001, PM002

PUMP HOUSE PM003

PUMP HOUSE PM004

BILL OF QUANTITY

DATE 4 January 2015

AMOUNT REMARKQ'ty

PROJECT : PT WILMAR-GMP MILL PADANG

DESCRIPTIONITEM UNIT

HDPE LINING

EFFLUENT AND SLUDGE PIPING SYSTEM

INFLUENT PIPING SYSTEM

TIE IN SYSTEM

HDPE COVER SHEET

FLOATING SYSTEM

PIPING GAS TO GENERATOR SYSTEM

PIPING GAS TO FLARE SYSTEM

BIO SCRUBBER TO CHILLER PIPING GAS SYSTEM

MAIN PIPING GAS SYSTEM

Page 2: PT-BOQ GMP-R00  04012015

Total PT-BOQ GM P-R00 04012015

9,998,504.49

1,499,775.67

11,498,280.17

OVERHEAD COST 15%

TOTAL AMOUNT

GRAND TOTAL AMOUNT

Page 3: PT-BOQ GMP-R00  04012015

01-TIE IN SYSTEM3/19

PT-BOQ GM P-R00 04012015

DATE

TOTAL

Unit Rate Sub Total Unit Rate Sub Total AMOUNT

TIE IN SYSTEM

1 Piping & Fitting

1.1 HDPE Pipe ø160 mm., PN6.3, PE100 200.00 m. 479.00 95,800 143.70 28,740 124,540

1.2 Tees way ø160 mm., PN6.3, PE100 1.00 Ea. 1,220.00 1,220 366.00 366 1,586

1.3 HDPE Stubend ø160 mm with flange 11.00 Ea. 1,394.00 15,334 418.20 4,600 19,934

Total 146,060

TOTAL AMOUNT 146,060

OVERHEAD COST 15% 21,909

GRAND TOTAL AMOUNT 167,969

4 January 2015

ITEM DESCRIPTION QT'Y UNITMATERIAL COST LABOUR COST

REMARK

PROJECT : PT WILMAR-GMP MILL PADANG

Page 4: PT-BOQ GMP-R00  04012015

02-INFLUENT PIPING SYSTEM4/19

PT-BOQ GM P-R00 04012015

DATE

TOTAL

Unit Rate Sub Total Unit Rate Sub Total AMOUNT

INFLUENT PIPING SYSTEM

1 Piping & Fitting

1.1 HDPE Pipe ø110 mm., PN6.3, PE100 420.00 m. 228.00 95,760 68.40 28,728 124,488

1.2 HDPE Pipe ø200 mm., PN6.3, PE100 318.00 m. 746.00 237,228 223.80 71,168 308,396

1.3 Stainless steel Pipe ø200 mm. SCH 10S 6.00 m. 9,740.00 58,440 2,922.00 17,532 75,972

1.4 Stainless steel Pipe ø300 mm. SCH 10S 18.00 m. 14,500.00 261,000 4,350.00 78,300 339,300

1.5 Tees way ø110 mm., PN6.3, PE100 3.00 Ea. 356.00 1,068 106.80 320 1,388

1.6 Tees way ø200 mm., PN6.3, PE100 2.00 Ea. 1,308.00 2,616 392.40 785 3,401

1.7 Stainless steel Reducing Tees ø300x200 mm. SCH 10S 7.00 Ea. 9,500.00 66,500 2,850.00 19,950 86,450

1.8 Stainless steel Reducing Tees ø300x150 mm. SCH 10S 3.00 Ea. 9,500.00 28,500 2,850.00 8,550 37,050

1.9 Crosses ø200 mm., PN6.3, PE100 3.00 Ea. 1,740.00 5,220 522.00 1,566 6,786

1.10 Concentric reducers ø200x110 mm., PN6.3, PE100 9.00 Ea. 672.00 6,048 201.60 1,814 7,862

1.11 Concentric reducers ø225x200 mm., PN6.3, PE100 12.00 Ea. 309.00 3,708 92.70 1,112 4,820

1.12 Concentric reducers ø250x200 mm., PN6.3, PE100 2.00 Ea. 530.00 1,060 159.00 318 1,378

1.13 Stainless steel Excentric reducers ø200x150 mm. 2.00 Ea. 4,500.00 9,000 1,350.00 2,700 11,700

1.14 Stainless steel Concentric reducers ø200x150 mm. 2.00 Ea. 4,000.00 8,000 1,200.00 2,400 10,400

1.15 HDPE Pipe ø110 mm Segmented Elbow 90° PN6.3,PE100 6.00 Ea. 294.00 1,764 88.20 529 2,293

1.16 HDPE Pipe ø200 mm Segmented Elbow 90° PN6.3,PE100 10.00 Ea. 1,134.00 11,340 340.20 3,402 14,742

1.17 Stainless steel ø200 mm Elbow 45° 2.00 Ea. 4,500.00 9,000 1,350.00 2,700 11,700

1.18 Stainless steel ø200 mm Elbow 90° 2.00 Ea. 5,000.00 10,000 1,500.00 3,000 13,000

PROJECT : PT WILMAR-GMP MILL PADANG 4 January 2015

ITEM DESCRIPTION QT'Y UNITMATERIAL COST LABOUR COST

REMARK

Page 5: PT-BOQ GMP-R00  04012015

02-INFLUENT PIPING SYSTEM5/19

PT-BOQ GM P-R00 04012015

DATE

TOTAL

Unit Rate Sub Total Unit Rate Sub Total AMOUNT

PROJECT : PT WILMAR-GMP MILL PADANG 4 January 2015

ITEM DESCRIPTION QT'Y UNITMATERIAL COST LABOUR COST

REMARK

1.19 Stainless steel ø300 mm Elbow 90° 2.00 Ea. 7,500.00 15,000 2,250.00 4,500 19,500

1.20 HDPE Stubend ø110 mm PN6.3,PE100 with flange 18.00 Ea. 639.00 11,502 191.70 3,451 14,953

1.21 HDPE Stubend ø160 mm PN6.3,PE100 with flange - Ea. 1,278.00 - 383.40 - -

1.22 HDPE Stubend ø225 mm PN6.3,PE100 with flange 12.00 Ea. 2,381.00 28,572 714.30 8,572 37,144

1.23 Stainless steel flange ø150 mm 7.00 Ea. 2,050.00 14,350 615.00 4,305 18,655

1.24 Stainless steel flange ø200 mm 27.00 Ea. 3,150.00 85,050 945.00 25,515 110,565

1.25 Stainless steel flange ø300 mm 6.00 Ea. 5,400.00 32,400 1,620.00 9,720 42,120

1.26 Stainless stee Blind flange ø200 mm 1.00 Ea. 4,150.00 4,150 1,245.00 1,245 5,395

1.27 Stainless stee Blind flange ø300 mm 2.00 Ea. 6,500.00 13,000 1,950.00 3,900 16,900

1.28 HDPE Pipe 110 mm Support 87.00 Ea. 550.00 47,850 165.00 14,355 62,205

1.29 HDPE Pipe 200 mm Support 18.00 Ea. 750.00 13,500 225.00 4,050 17,550

Total 1,326,359

2 Pump

2.1 Centrifugal Pump 2.00 set 75,000.00 150,000 5,000.00 10,000 160,000

Total 160,000

TOTAL AMOUNT 1,486,359

OVERHEAD COST 15% 222,954

GRAND TOTAL AMOUNT 1,709,313

Page 6: PT-BOQ GMP-R00  04012015

03-EFFLUENT AND SLUDGE PIPING 6/19 PT-BOQ GM P-R00 04012015

DATE

TOTAL

Unit Rate Sub Total Unit Rate Sub Total AMOUNT

EFFLUENT AND SLUDGE PIPING SYSTEM

1 Piping & Fitting

1.1 HDPE Pipe ø110 mm., PN6.3, PE100 222.00 m. 228.00 50,616 68.40 15,185 65,801

1.2 HDPE Pipe ø160 mm., PN6.3, PE100 744.00 m. 479.00 356,376 143.70 106,913 463,289

1.3 HDPE Pipe ø200 mm., PN6.3, PE100 100.00 m. 746.00 74,600 223.80 22,380 96,980

1.4 Tees way ø160 mm., PN6.3, PE100 2.00 Ea. 763.00 1,526 228.90 458 1,984

1.5 Concentric reducers ø225x160 mm., PN6.3, PE100 1.00 Ea. 360.00 360 108.00 108 468

1.6 Concentric reducers ø250x200 mm., PN6.3, PE100 5.00 Ea. 530.00 2,650 159.00 795 3,445

1.7 HDPE Pipe ø110 mm Segmented Elbow 90° PN6.3,PE100 8.00 Ea. 294.00 2,352 88.20 706 3,058

1.8 HDPE Pipe ø160 mm Segmented Elbow 90° PN6.3,PE100 5.00 Ea. 636.00 3,180 190.80 954 4,134

1.9 HDPE Stubend ø110 mm PN6.3,PE100 with flange 4.00 Ea. 639.00 2,556 191.70 767 3,323

1.10 HDPE Stubend ø160 mm PN6.3,PE100 with flange 5.00 Ea. 1,278.00 6,390 383.40 1,917 8,307

1.11 HDPE Stubend ø200 mm PN6.3,PE100 with flange 6.00 Ea. 2,281.00 13,686 684.30 4,106 17,792

1.12 Stainless steel Pipe ø150 mm. SCH 10S 6.00 m. 7,300.00 43,800 2,190.00 13,140 56,940

1.13 Stainless steel Pipe ø200 mm. SCH 10S 12.00 m. 9,740.00 116,880 2,922.00 35,064 151,944

1.14 Stainless steel Tees way ø150 mm. SCH 10S 1.00 Ea. 4,800.00 4,800 1,440.00 1,440 6,240

1.15 Stainless steel Tees way ø200 mm. SCH 10S 6.00 Ea. 6,500.00 39,000 1,950.00 11,700 50,700

1.16 Stainless steel Reducing Tees ø200x100 mm. SCH 10S 4.00 Ea. 6,500.00 26,000 1,950.00 7,800 33,800

1.17 Stainless steel Reducing Tees ø200x150 mm. SCH 10S 1.00 Ea. 6,500.00 6,500 1,950.00 1,950 8,450

1.18 Stainless steel Excentric reducers ø200x150 mm. 1.00 Ea. 4,500.00 4,500 1,350.00 1,350 5,850

PROJECT : PT WILMAR-GMP MILL PADANG 4 January 2015

ITEM DESCRIPTION QT'Y UNITMATERIAL COST LABOUR COST

REMARK

Page 7: PT-BOQ GMP-R00  04012015

03-EFFLUENT AND SLUDGE PIPING 7/19 PT-BOQ GM P-R00 04012015

DATE

TOTAL

Unit Rate Sub Total Unit Rate Sub Total AMOUNT

PROJECT : PT WILMAR-GMP MILL PADANG 4 January 2015

ITEM DESCRIPTION QT'Y UNITMATERIAL COST LABOUR COST

REMARK

1.19 Stainless steel ø150 mm Elbow 90° 6.00 Ea. 4,000.00 24,000 1,200.00 7,200 31,200

1.20 Stainless steel ø200 mm Elbow 90° 1.00 Ea. 5,000.00 5,000 1,500.00 1,500 6,500

1.21 Stainless steel flange ø100 mm 4.00 Ea. 1,400.00 5,600 420.00 1,680 7,280

1.22 Stainless steel flange ø150 mm 24.00 Ea. 2,050.00 49,200 615.00 14,760 63,960

1.23 Stainless steel flange ø200 mm 15.00 Ea. 3,150.00 47,250 945.00 14,175 61,425

1.24 Stainless stee Blind flange ø200 mm 3.00 Ea. 4,150.00 12,450 1,245.00 3,735 16,185

1.25 HDPE Pipe 110 mm Support 36.00 Ea. 550.00 19,800 165.00 5,940 25,740

Total 1,169,054

2 Pump

2.1 Centrifugal Pump 2.00 set 55,000.00 110,000 5,000.00 10,000 120,000

Total 120,000

TOTAL AMOUNT 1,289,054

OVERHEAD COST 15% 193,358

GRAND TOTAL AMOUNT ########

Page 8: PT-BOQ GMP-R00  04012015

04-M AIN PIPING GAS SYSTEM 8/19 PT-BOQ GM P-R00 04012015

DATE

TOTAL

Unit Rate Sub Total Unit Rate Sub Total AMOUNT

MAIN PIPING GAS SYSTEM

1 Piping & Fitting

1.1 HDPE Pipe ø250 mm., PN6.3, PE100 366.00 m. 1,171.00 428,586 351.30 128,576 557,162

1.2 Tees way ø250 mm., PN6.3, PE100 1.00 Ea. 2,114.00 2,114 634.20 634 2,748

1.3 HDPE Pipe ø250 mm Segmented Elbow 90° PN6.3,PE100 2.00 Ea. 1,822.00 3,644 546.60 1,093 4,737

1.4 HDPE Stubend ø250 mm PN6.3,PE100 with flange 9.00 Ea. 3,262.00 29,358 978.60 8,807 38,165

1.5 Blind flange ø250 mm 2.00 Ea. 2,328.00 4,656 698.40 1,397 6,053

Total 608,865

TOTAL AMOUNT 608,865

OVERHEAD COST 15% 91,330

GRAND TOTAL AMOUNT 700,195

PROJECT : PT WILMAR-GMP MILL PADANG 4 January 2015

ITEM DESCRIPTION QT'Y UNITMATERIAL COST LABOUR COST

REMARK

Page 9: PT-BOQ GMP-R00  04012015

05-BIO SCRUBBER TO CHILLER 9/19 PT-BOQ GM P-R00 04012015

DATE

TOTAL

Unit Rate Sub Total Unit Rate Sub Total AMOUNT

BIO SCRUBBER TO CHILLER PIPING GAS SYSTEM

1 Piping & Fitting

1.1 HDPE Pipe ø250 mm., PN6.3, PE100 78.00 m. 1,171.00 91,338 351.30 27,401 118,739

1.2 Tees way ø250 mm., PN6.3, PE100 7.00 Ea. 2,114.00 14,798 634.20 4,439 19,237

1.3 HDPE Pipe ø250 mm Segmented Elbow 90° PN6.3,PE100 14.00 Ea. 1,822.00 25,508 546.60 7,652 33,160

1.4 HDPE Stubend ø160 mm PN6.3,PE100 with flange 4.00 Ea. 1,278.00 5,112 383.40 1,534 6,646

1.5 HDPE Stubend ø250 mm PN6.3,PE100 with flange 40.00 Ea. 3,262.00 130,480 978.60 39,144 169,624

1.6 Concentric reducers ø250x160 mm., PN6.3, PE100 4.00 Ea. 1,133.00 4,532 339.90 1,360 5,892

1.7 Concentric reducers ø250x200 mm., PN6.3, PE100 2.00 Ea. 777.00 1,554 233.10 466 2,020

Total 355,319

2 Blower

2.1 Blower 2.00 set 950,000.00 1,900,000 10,000.00 20,000 1,920,000

Total 1,920,000

TOTAL AMOUNT 2,275,319

OVERHEAD COST 15% 341,298

GRAND TOTAL AMOUNT 2,616,616

PROJECT : PT WILMAR-GMP MILL PADANG 4 January 2015

ITEM DESCRIPTION QT'Y UNITMATERIAL COST LABOUR COST

REMARK

Page 10: PT-BOQ GMP-R00  04012015

06-PIPING GAS TO FLARE SYSTEM 10/19 PT-BOQ GM P-R00 04012015

DATE

TOTAL

Unit Rate Sub Total Unit Rate Sub Total AMOUNT

PIPING GAS TO FLARE SYSTEM

1 Piping & Fitting

1.1 HDPE Pipe ø200 mm., PN6.3, PE100 72.00 m. 746.00 53,712 223.80 16,114 69,826

1.2 HDPE Pipe ø200 mm Segmented Elbow 90° PN6.3,PE100 2.00 Ea. 1,134.00 2,268 340.20 680 2,948

1.3 HDPE Stubend ø200 mm PN6.3,PE100 with flange 8.00 Ea. 2,281.00 18,248 684.30 5,474 23,722

Total 96,496

TOTAL AMOUNT 96,496

OVERHEAD COST 15% 14,474

GRAND TOTAL AMOUNT 110,971

PROJECT : PT WILMAR-GMP MILL PADANG 4 January 2015

ITEM DESCRIPTION QT'Y UNITMATERIAL COST LABOUR COST

REMARK

Page 11: PT-BOQ GMP-R00  04012015

07-PIPING GAS TO GENERATOR 11/19 PT-BOQ GM P-R00 04012015

DATE

TOTAL

Unit Rate Sub Total Unit Rate Sub Total AMOUNT

PIPING GAS TO GENERATOR SYSTEM

1 Piping & Fitting

1.1 Stainless steel Pipe ø125 mm. SCH 10S 40.00 m. 3,500.00 140,000 1,050.00 42,000 182,000

1.2 Stainless steel Pipe ø200 mm. SCH 10S 30.00 m. 5,000.00 150,000 1,500.00 45,000 195,000

1.3 Stainless steel Concentric reduers ø200x125 mm 2.00 Ea. 1,900.00 3,800 570.00 1,140 4,940

1.4 Stainless steel ø200 mm Elbow 90° 2.00 Ea. 4,900.00 9,800 1,470.00 2,940 12,740

1.5 Stainless steel Tees way ø200 mm 1.00 Ea. 5,800.00 5,800 1,740.00 1,740 7,540

1.6 Stainless steel flange ø125 mm 8.00 Ea. 1,530.00 12,240 459.00 3,672 15,912

1.7 Stainless steel flange ø200 mm 6.00 Ea. 2,820.00 16,920 846.00 5,076 21,996

Total 440,128

TOTAL AMOUNT 440,128

OVERHEAD COST 15% 66,019

GRAND TOTAL AMOUNT 506,147

PROJECT : PT WILMAR-GMP MILL PADANG 4 January 2015

ITEM DESCRIPTION QT'Y UNITMATERIAL COST LABOUR COST

REMARK

Page 12: PT-BOQ GMP-R00  04012015

08-BREATHE PIPING SYSTEM12/19

PT-BOQ GM P-R00 04012015

DATE

TOTAL

Unit Rate Sub Total Unit Rate Sub Total AMOUNT

BREATHE PIPING SYSTEM

1 Piping & Fitting

1.1 Neodrain Pipe HDPE ø150 mm. 414.00 m. 598.00 247,572 179.40 74,272 321,844

1.2 Crosses ø150 mm. Neodrain 3.00 Ea. 920.00 2,760 276.00 828 3,588

1.3 Socket ø150 mm. Neodrain 8.00 Ea. 195.00 1,560 58.50 468 2,028

1.4 HDPE Pipe ø160 mm., PN6.3, PE100 48.00 m. 479.00 22,992 143.70 6,898 29,890

1.5 HDPE Stubend ø160 mm PN6.3,PE100 with flange 16.00 Ea. 1,278.00 20,448 383.40 6,134 26,582

Total 383,932

2 Valve

2.1 Butterfly Valve ø150 mm. 8.00 set 4,800.00 38,400 1,440.00 11,520 49,920

Total 49,920

TOTAL AMOUNT 433,852

OVERHEAD COST 15% 65,078

GRAND TOTAL AMOUNT 498,929

PROJECT : PT WILMAR-GMP MILL PADANG 4 January 2015

ITEM DESCRIPTION QT'Y UNITMATERIAL COST LABOUR COST

REMARK

Page 13: PT-BOQ GMP-R00  04012015

09-FLOATING 13/19 PT-BOQ GM P-R00 04012015

DATE

TOTAL

Unit Rate Sub Total Unit Rate Sub Total AMOUNT

FLOATING SYSTEM

1 Float

1.1 Polystyrene Floats (0.4x0.4 m.) 108.00 ม. 350.00 37,800 50.00 5,400 43,200

1.2 HDPE Material Float Cover 1.5 mm (Seam Weld & Install) 196.42 ตร.ม. 95.00 18,660 45.00 8,839 27,498

1.3 HDPE Float welding (Extrude Weld) 126.00 ม. - - 120.00 15,120 15,120

Total 85,818

TOTAL AMOUNT 85,818

OVERHEAD COST 15% 12,873

GRAND TOTAL AMOUNT 98,691

PROJECT : PT WILMAR-GMP MILL PADANG 4 January 2015

ITEM DESCRIPTION QT'Y UNITMATERIAL COST LABOUR COST

REMARK

Page 14: PT-BOQ GMP-R00  04012015

10-HDPE COVER SHEET 14/19 PT-BOQ GM P-R00 04012015

DATE

TOTAL

Unit Rate Sub Total Unit Rate Sub Total AMOUNT

HDPE COVER SHEET

1 HDPE Cover Sheet

1.1 HDPE Material cover sheets (Seam Weld & Install) 1.5 mm 7,787.10 ตร.ม. 95.00 739,775 45.00 350,420 1,090,194

Total 1,090,194

TOTAL AMOUNT 1,090,194

OVERHEAD COST 15% 163,529

GRAND TOTAL AMOUNT 1,253,723

PROJECT : PT WILMAR-GMP MILL PADANG 4 January 2015

ITEM DESCRIPTION QT'Y UNITMATERIAL COST LABOUR COST

REMARK

Page 15: PT-BOQ GMP-R00  04012015

11-HDPE LINING 15/19 PT-BOQ GM P-R00 04012015

DATE

TOTAL

Unit Rate Sub Total Unit Rate Sub Total AMOUNT

HDPE LINING

1 HDPE Lining

1.1 HDPE Material cover sheets (Seam Weld & Install) 1.0 mm 9,230.00 ตร.ม. 85.00 784,550 45.00 415,350 1,199,900

Total 1,199,900

TOTAL AMOUNT 1,199,900

OVERHEAD COST 15% 179,985

GRAND TOTAL AMOUNT 1,379,885

PROJECT : PT WILMAR-GMP MILL PADANG 4 January 2015

ITEM DESCRIPTION QT'Y UNITMATERIAL COST LABOUR COST

REMARK

Page 16: PT-BOQ GMP-R00  04012015

12-PUM P HOUSE PM 001,PM 002 16/19 PT-BOQ GM P-R00 04012015

DATE

TOTAL

Unit Rate Sub Total Unit Rate Sub Total AMOUNT

PUMP HOUSE PM001, PM002

1 Pump House Floor

1.1 Excavating 3.00 cu.m. - - 125.00 375 375

1.2 Compacted Sand 3.75 cu.m. 500.00 1,875 150.00 563 2,438

1.3 Concrete 240 ksc (cubic) 6.90 cu.m. 2,500.00 17,250 750.00 5,175 22,425

1.4 DB 12 mm SD30 497.28 kg 30.00 14,918 9.00 4,476 19,394

1.5 Wire 14.92 kg 60.00 895 - - 895

Total 45,527

2 Pump House Roof

2.1 SQ Pipe 125x125x6 mm 390.60 kg 38.00 14,843 11.40 4,453 19,296

2.2 SQ Pipe 100x100x3.2 mm 285.60 kg 38.00 10,853 11.40 3,256 14,109

2.3 Rafter C-100x50x5x7.5 mm 224.64 kg 38.00 8,536 11.40 2,561 11,097

2.4 Purlin C-100x50x5x7.5 mm 767.52 kg 38.00 29,166 11.40 8,750 37,915

2.5 Metal Sheet 68.40 sq.m. 400.00 27,360 120.00 8,208 35,568

Total 117,985

TOTAL AMOUNT 163,512

OVERHEAD COST 15% 24,527

GRAND TOTAL AMOUNT 188,038

PROJECT : PT WILMAR-GMP MILL PADANG 4 January 2015

ITEM DESCRIPTION QT'Y UNITMATERIAL COST LABOUR COST

REMARK

Page 17: PT-BOQ GMP-R00  04012015

13-PUM P HOUSE PM 003 17/19 PT-BOQ GM P-R00 04012015

DATE

TOTAL

Unit Rate Sub Total Unit Rate Sub Total AMOUNT

PUMP HOUSE PM003

1 Pump House Floor

1.1 Excavating 1.00 cu.m. - - 125.00 125 125

1.2 Compacted Sand 1.00 cu.m. 500.00 500 150.00 150 650

1.3 Concrete 240 ksc (cubic) 1.84 cu.m. 2,500.00 4,600 750.00 1,380 5,980

1.4 DB 12 mm SD30 124.32 kg 30.00 3,730 9.00 1,119 4,848

1.5 Wire 3.73 kg 60.00 224 - - 224

Total 11,827

2 Pump House Roof

2.1 SQ Pipe 125x125x6 mm 260.40 kg 38.00 9,895 11.40 2,969 12,864

2.2 SQ Pipe 100x100x3.2 mm 142.80 kg 38.00 5,426 11.40 1,628 7,054

2.3 Rafter C-100x50x5x7.5 mm 168.48 kg 38.00 6,402 11.40 1,921 8,323

2.4 Purlin C-100x50x5x7.5 mm 336.96 kg 38.00 12,804 11.40 3,841 16,646

2.5 Metal Sheet 38.00 sq.m. 400.00 15,200 120.00 4,560 19,760

Total 64,647

TOTAL AMOUNT 76,474

OVERHEAD COST 15% 11,471

GRAND TOTAL AMOUNT 87,945

PROJECT : PT WILMAR-GMP MILL PADANG 4 January 2015

ITEM DESCRIPTION QT'Y UNITMATERIAL COST LABOUR COST

REMARK

Page 18: PT-BOQ GMP-R00  04012015

14-PUM P HOUSE PM 004 18/19 PT-BOQ GM P-R00 04012015

DATE

TOTAL

Unit Rate Sub Total Unit Rate Sub Total AMOUNT

PUMP HOUSE PM004

1 Pump House Floor

1.1 Excavating 1.00 cu.m. - - 125.00 125 125

1.2 Compacted Sand 1.00 cu.m. 500.00 500 150.00 150 650

1.3 Concrete 240 ksc (cubic) 1.84 cu.m. 2,500.00 4,600 750.00 1,380 5,980

1.4 DB 12 mm SD30 124.32 kg 30.00 3,730 9.00 1,119 4,848

1.5 Wire 3.73 kg 60.00 224 - - 224

Total 11,827

2 Pump House Roof

2.1 SQ Pipe 125x125x6 mm 260.40 kg 38.00 9,895 11.40 2,969 12,864

2.2 SQ Pipe 100x100x3.2 mm 142.80 kg 38.00 5,426 11.40 1,628 7,054

2.3 Rafter C-100x50x5x7.5 mm 168.48 kg 38.00 6,402 11.40 1,921 8,323

2.4 Purlin C-100x50x5x7.5 mm 336.96 kg 38.00 12,804 11.40 3,841 16,646

2.5 Metal Sheet 38.00 sq.m. 400.00 15,200 120.00 4,560 19,760

Total 64,647

TOTAL AMOUNT 76,474

OVERHEAD COST 15% 11,471

GRAND TOTAL AMOUNT 87,945

PROJECT : PT WILMAR-GMP MILL PADANG 4 January 2015

ITEM DESCRIPTION QT'Y UNITMATERIAL COST LABOUR COST

REMARK

Page 19: PT-BOQ GMP-R00  04012015

DATE

TOTAL

Unit Rate Sub Total Unit Rate Sub Total AMOUNT

PUMP LIST FOR SCRUBBER

1 Pump

1.1 Scrubber Recirculation Pump 2.00 set 125,000.00 250,000 5,000.00 10,000 260,000

1.2 Settled Waste Transfer Pump 1.00 set 85,000.00 85,000 5,000.00 5,000 90,000

1.3 Scrubbing Water Supply Pump 1.00 set 85,000.00 85,000 5,000.00 5,000 90,000

1.4 Spent Wash Removal Pump 1.00 set 85,000.00 85,000 5,000.00 5,000 90,000

Total 530,000

TOTAL AMOUNT 530,000

OVERHEAD COST 15% 79,500

GRAND TOTAL AMOUNT 609,500

PROJECT : PT WILMAR-GMP MILL PADANG 4 January 2015

ITEM DESCRIPTION QT'Y UNITMATERIAL COST LABOUR COST

REMARK