ps2 - managing the next step for pan-starrs
TRANSCRIPT
Panoramic Survey Telescope and Rapid Response System
PS2: Managing the Next Stepin the Pan-STARRS Wide Field Survey System
William S. Burgett Pan-STARRS Project Manager
Pan-STARRS Wide Field High Resolution Survey System
• Time domain astronomy → “Rapid Response” needed for follow-up
– Transient objects, e.g., Supernovae– Moving objects– Variable objects
• Static sky science– Stack (co-add) repeated scans to form ultra-deep static
sky images
• Pan-STARRS PS-4 system concept― Four 1.8m R-C + corrector lenses
• Distributed aperture concept yields ~4m capability• Simpler fabrication, reduced cost compared to larger
monolithic system → less risk (wide field optics already difficult enough!)
– 7 deg2 FOV per telescope, 4 1.4 Gigapixel cameras– Sited in Hawaii (excellent site characteristics)– A ~ 50 m2 deg2
– R ~ 24 in 30 s integration → 7000 deg2/night– All sky + deep field surveys in g, r, i, z, y and w filters
Pan-STARRS Development and Evolution
• Design, development, infrastructure, and testing(2003-2006)
• PS1– Integration and Commissioning
(2006 – 2008, 2009)– 3.5 year mission (2010 – 2013)
• PS2, PS1+2 (2009 – 2014+)– Improved telescope/optics– Improved camera/CCDs– Multiple tel/cam control
• PS-4– Development and
Construction (2014 – 2017)– PS-4 10-yr Mission (2017-2026)
TC 3 360 Mpix
GPC 1 1.4 Gpix
GPC 1, 2, 3, 45.6 Gpix
GPC 1 & 2 2.8 Gpix
PS1 + PS2
Management Basics
• Buy-in to the management plan– Requires commitment at all levels above and below project manager– Most reasonable plans can succeed if there is buy-in– Without buy-in, even the “perfect” plan will fail
• Successful project execution is TEAM sport
• Successfully and efficiently managing any project requires tight organization– Well-defined authorities, roles, responsibilities, and work plan
• Successful project execution is TEAM sport– Good documentation
Management Basics
• Buy-in to the management plan– Requires commitment at all levels above and below project manager– Most reasonable plans can succeed if there is buy-in– Without buy-in, even the “perfect” plan will fail
• Successful project execution is TEAM sport
• Successfully and efficiently managing any project requires tight organization– Well-defined authorities, roles, responsibilities, and work plan
• Successful project execution is TEAM sport– Good documentation – Common mistakes and misunderstanding
• “If the other person/team isn’t doing it, why should I/we?”• “Do you want product/progress or do you want documentation?”• “All we need to do is maintain Wiki pages.”• “We can wait to write the documentation until we have everything else done.”
Management Basics
• Buy-in to the management plan– Requires commitment at all levels above and below project manager– Most reasonable plans can succeed if there is buy-in– Without buy-in, even the “perfect” plan will fail
• Successful project execution is TEAM sport
• Successfully and efficiently managing any project requires tight organization– Well-defined authorities, roles, responsibilities, and work plan
• Successful project execution is TEAM sport– Good documentation
• “If the other person/team isn’t doing it, why should I/we?”• “Do you want product/progress or do you want documentation?”• “All we need to do is maintain Wiki pages.”• “We can wait to write the documentation until we have everything else done.”
– Configuration management– Communication
• Two-way street both vertically and laterally
Acronyms/AbbreviationsEIS: Environmental Impact StatementIPP: Image Processing PipelineMOPS: Moving Object Processing SWA&E: Architectural & EngineeringObs/Tel: Observatory & TelescopeOCS/TCS: Obs/Tel Control SWDB: DatabaseDev Sup: Development SupportEng Sup: Engineering Sup
Pan-STARRS Organization (as of 2009)
Business OfficeAdmin/Fiscal Lead
IPP SubsystemLead
Principal Investigator
Project Management OfficeProject Manager
Deputy Project Manager (vac)Chief Engineer & Test Manager (vac)
OCS/TCS SubsystemLead
DB SubsystemLead
SW Dev SupSubcontractor
Science Design CommitteeProject Scientist (Chair)
A&ESubcontractor
ConstructionSubcontractors
Eng SupIfA Instr Div &Subcontractor
FiltersSubcontractor
OpticsSubcontractor
Tel StructureSubcontractor
DetectorsSubcontractor
ShuttersSubcontractor
Eng SupIfA Instr Div
Obs/Tel SubsystemLead
Civil Construction OfficeConstruction Manager
Camera SubsystemLead
MOPS SubsystemLead
EIS & PermittingSubcontractor
Pan-STARRS Subsystems
Image Processing Pipeline:Processes the pixels and finds the objects in the images
Publishes Science Products Subsystem:Ingests the data and serves it to the user
Observatory, Telescope, & Instrumentation SW: Controls the System
Moving Objects Processing SW: Calculates orbits for SS objects
Management Basics
• Buy-in to the management plan– Requires commitment at all levels above and below project manager– Most reasonable plans can succeed if there is buy-in– Without buy-in, even the “perfect” plan will fail
• Successful project execution is TEAM sport
• Successfully and efficiently managing any project requires tight organization– Well-defined authorities, roles, responsibilities, and work plan
• Successful project execution is TEAM sport– Good documentation – Common mistakes and misconceptions
• “If the other person/team isn’t doing it, why should I/we?”• “Do you want product/progress or do you want documentation?”• “All we need to do is maintain Wiki pages.”• “We can wait to write the documentation until we have everything else done.
– Configuration management– Communication
• Managing expectations– Providing transparency to team and sponsors, – Initially setting realistic goals– Maintaining the discipline to avoid requirements/scope creep
Pan-STARRS: An Academically-based Science Project
• Academically-based projects requiring initial R&D leading to a production or operations end goal often have some unique challenges
• Management tools such as Earned Value (EV) very useful for controlling management issues and assessing performance, but …
– Difficult to implement when R&D is a major component of the SOW– Requires significant commitment from those providing the inputs
• Regardless of management plan and tools, never allow “the perfect to be the enemy of the good enough”
– Not as easy as it sounds!
• Pan-STARRS management– Well known to Air Force Research Laboratory sponsor (AFRL)
• Plan subject to direct oversight and approval• Frequently reviewed
– Not as well known outside AFRL sponsor • Has been subject to some anecdotal, often inaccurate comments or
perceptions– Several reviews by external advisory committees
Principles of Risk Management
• Risk Management– Assessment– Control– Mitigation– Quantitative foundations, but
nearly impossible to eliminate all subjectivity
• Risk categories– Technical– Schedule– Budget
• Consequence and Probability of Occurrence Levels used for Pan-STARRS
– Low– Medium– High
Impact Risk Matrix
High LH MH HH
Med LM MM HM
Low LL ML HL
Consequence Prob. of Occur. Low Med High
Impact Risk (or simply, Risk)
• Consequence of adverse event weighted by probability of occurrence• Common to have related sequence of low consequence, low probability events pose a High cumulative risk• Often adequate to approximate Risk above to Low, Medium, and High
Primary Factors Creating Risk
• Budget– Technical component or features not mature so require development or repair
beyond that planned– Poor schedule estimates– Unknown costs, i.e., no work element with associated costs for material, fabrication,
equipment, or personnel
• Schedule– Unknown tasks– Poor estimate of duration
• Technical– Poor design– Initial design validation revealing problems– System HW does not perform properly– Lack of tools to test and analyze performance– Requirements/scope creep
PS2 Risk Assessment: Overview
• The Technical and Schedule risks for PS2 are simply not the same as for PS1– Same experienced team for PS2 that designed & commissioned PS1– Commissioning tasks known and necessary tools now exist– Most significant risk reduction factor for PS2 was successfully completing PS1
• Low Technical risk for the overall system concept and performance – Designs are mature and validated by PS1 system performance plus the known
characteristics of the PS2 as-builts
• Low Schedule risk for the telescope and associated testing through at least SAT– Virtually all long lead fabrication will be complete by January 1, 2013– Serious delays now unlikely in the final delivery of the telescope structure– Machine shop hours, engineering, and construction material contingency for relatively
minor additional fabrication
PS2 Risk Assessment: Overview (contd.)
• Medium Schedule risk for GPC2– Unavoidable delays in some areas of electronics fab/assembly due to funding
slowing– Delays in CCD delivery now producing noticeable adverse consequence
• Overall technical performance still looks promising – Remove GPC2 from Telescope SAT critical path (CP) by using 16-OTA TC3
• Other Schedule contingencies– 75 days in the schedule for weather, installation, integration, and commissioning
delays• Weather contingency based on 10-year historical Haleakala meteorological data
– Substantial schedule contingency has been included for SW tasks
Lessons Learned from PS1
• The overall Pan-STARRS design was validated and is sound – It is not always sufficiently appreciated or is forgotten that so many aspects of
the PS1 design were completely new, and yet PS1 works as designed for the most part
– The design is tightly coupled to the specified capability requirements
• The deviations in PS1 performance from the capability requirements and goals are mostly due to fabrication issues, not design issues
– Some important design iterations for PS2 to further improve performance
• Complete fabrications and development prior to commissioning– Staffing critical mass
• We learned what needed to be improved for PS2 and how to do it
PS2 Improvements Relative to PS1
• Better telescope (provided by AMOS of Liège, Belgium)– Actively cooled drives with increased performance margin, – Cooled primary mirror assembly (PMA)– Better M2 support– A stiffer truss providing increased margin against vibration– Better M1 figure control utilizing 36 active figure controllers (PS1 has 12)– Improved cable wrap (balanced and powered)– Better overall reliability not only due to intrinsic design but better quality control of as-
built components– Better accessibility for more efficient maintenance and repair
• Better optics– Full aperture testing critical
• Better filters
• Significant reduction of ghosting and scattered light
AMOS PS2 Telescope on Factory Floor in Liège
AMOS PS2 Telescope
PS2 Improvements Relative to PS1• Better CCDs (provided by MIT Lincoln Laboratory)
– Reduced “burn trails/persistence”– Reduced defects – Improved CTE– Reduced/eliminated amplifier glow– Eliminated corner problem– Reduced device cross talk by using only 2-phase devices– Better AR coatings – Increased full well – Improved linearity
• Better package and mounting to FP
• Better camera electronics – Reduced cross talk with new cable routing – Reduced read noise– Improved thermal control
• Mature image processing due to the efforts of the SW engineers on the PS1 Science Consortium team
PS2 Milestone Schedule as of October 2012• The on-site delivery of the telescope structure Mar 2013
• The on-site delivery of the 16-OTA TC3 camera Mar 2013
• Completion of the optics & instrument integration with the telescope Apr 2013
• The Site Acceptance Testing (SAT) of the telescope May 2013
• The start of post-SAT telescope commissioning, i.e., testing that does Jun 2013not involve direct participation by the telescope vendor
• The on-site delivery and integration of GPC2 Jul 2013
• The return of GPC2 Oahu for final tuning early Oct 2013– Includes focal plane metrology to match the physical detector
surface to the actual optical focal surface determined from the preliminary collimation and alignment
– Possible replacement of some devices, if necessary
• Subsequent return of GPC2 to the summit mid Nov 2013
• Final collimation and alignment Nov-Dec 2013
• The successful simultaneous operation of PS1+PS2 using OTIS Dec 2013
• Beginning of science operations Jan 2014
Summary
• We are confident that the PS2 system will perform noticeably better than PS1, and that commissioning will proceed much more efficiently than for PS1
• We are not over-confident with respect to our costs or schedule– We fully recognize that unanticipated issues will arise, and some of those may incur
delays or added expense• Case in point: 2-month delay by UH in securing approval and availability of funds
for observatory renovations– We monitor, attempt to control, and revise as necessary full WBS and schedule often
to incorporate updates, identify risk points, prepare contingencies• Much more informal than formal process for Pan-STARRS
• As of October 2012, the critical path to operational readiness is GPC2 completion due to CCD delivery schedule
– MIT Lincoln Laboratory fabrication schedule remains challenging• Has shown commendable commitment and effort to produce devices that will be
significant upgrade to those used in GPC1• Unfortunately, Schedule Risk now Medium so necessary to begin executing
contingency plan– Telescope SAT will be conducted with 16-OTA TC3