Page 1: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

PS Planning

Fernando Pedrosa

Page 2: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

2

Table of Contents

• Progress report on the activities between 23th January to 6th February 2020

• Works foreseen for the next 2 weeks

06-Feb-2020

Page 3: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

3

23rd January 2020As performedAs presented the 23rd January 2020

06-Feb-2020

Page 4: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

4

24th January 2020As performedAs presented the 23rd January 2020

06-Feb-2020

Page 5: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

5

27th January 2020As performedAs presented the 23rd January 2020

06-Feb-2020

Page 6: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

6

28th January 2020As performedAs presented the 23rd January 2020

06-Feb-2020

Page 7: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

7

29th January 2020As performedAs presented the 23rd January 2020

06-Feb-2020

Page 8: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

8

30th January 2020As performedAs presented the 23rd January 2020

06-Feb-2020

Page 9: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

9

31st January 2020As performedAs presented the 23rd January 2020

06-Feb-2020

Page 10: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

10

3rd February 2020As performedAs presented the 23rd January 2020

06-Feb-2020

Page 11: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

11

4th February 2020As performedAs presented the 23rd January 2020

06-Feb-2020

Page 12: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

12

4th February 2020As performedAs presented the 23rd January 2020

06-Feb-2020

Page 13: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

13

6th and 7th February 2020 F61 line works

• Equipment installation

10 MHz water manifold installation (SS11, SS46, SS51, SS56)

Amplifiers cabling for the pickups systems

TE-MSC works to complete the connection of all MUs and Straight section

equipment

“Carotage” for the RF rigid line + RF rigid installation

PS SWY

activities in

the next slide

06-Feb-2020

Page 14: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

14

6th February 2020

• LV consolidation

• LT smoothing

• Overhead crane

modifications

• BTP Alignment

• Installation of the cooling

manifold for the PSC10

SS11

• PSC10 SS36 internal

cabling

• CV works – magnet

valves modification

• TE-MSC works to

complete the connection

of all MUs and Straight

section equipment

06-Feb-2020

Page 15: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

15

7th February 2020

• LV consolidation

• BTP vacuum closure, leak

detection and pump down

• LT Smoothing

• Overhead crane

modifications

• Installation of the cooling

manifold for the PSC10

SS11

• PSC10 SS36 internal cabling

• CV BTP water line pressure

test (access only to the ext.

gallery needed)

• CV works – magnet valves

modification

• TE-MSC works to complete

the connection of all MUs

and Straight section

equipment

We will re-install the SMH16 the 13/02/2020, so all works that

require the opening of the vacuum must be completed by the

11/02/2020

If your activity doesn’t appear in these slides or is not yet approved

in IMPACT please contact me as soon as possible

06-Feb-2020

Page 16: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

16

10th February 2020

F61 line works

• Equipment installation

10 MHz water manifold installation (SS66)

Amplifiers cabling for the pickups systems

TE-MSC works to complete the connection of all MUs and Straight section

equipment

MU93 repair

Asbestos pipe removedPS SWY

activities in

the next slide

06-Feb-2020

Material to be removed from

this area before Monday (RF,

VSC, MSC, …)

Page 17: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

17

10th February 2020

• LV consolidation

• BI line alignment

• VSC works to close the

F16 line in the PS SWY +

LT (including leak

detection and pump

down)

• Beam stoppers

connection to the services

• F16 + LT MSC equipment

connection to the services

• F16 BLMs installation

• F16.QDN163 re-

installation + alignment

• Re-install the stairs that

were removed to allow

the LT smoothing

• Finish the vacuum pump

down and start the BTP

smoothing

06-Feb-2020

Page 18: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

18

11th February 2020

F61 line works

• Equipment installation

10 MHz water manifold installation (SS66)

Amplifiers cabling for the pickups systems

TE-MSC works to complete the connection of all MUs and Straight section

equipment

MU93 repair

MU97 damper installation

Asbestos pipe removed

PS SWY

activities in

the next slide

06-Feb-2020

Page 19: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

19

11th February 2020

• LV consolidation

• BI line alignment

• VSC works to close the

F16 line in the PS SWY +

LT (including leak

detection and pump

down)

• Beam stoppers

connection to the services

• F16 + LT MSC equipment

connection to the services

• F16 BLMs installation

• BTP smoothing

06-Feb-2020

Page 20: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

20

12th February 2020

F61 line works

• Equipment installation

10 MHz water manifold installation (SS66)

Amplifiers cabling for the pickups systems

TE-MSC works to complete the connection of all MUs and Straight section

equipment

MU93 repair

SS93 BPM installation

Asbestos pipe removed

PS SWY

activities in

the next slide

06-Feb-2020

Page 21: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

21

12th February 2020

• LV consolidation

• BI line alignment

• VSC works to close the

F16 line in the PS SWY +

LT (including leak

detection and pump

down)

• Beam stoppers

connection to the services

• F16 + LT MSC equipment

connection to the services

• F16 BLMs installation

• BTP smoothing

06-Feb-2020

Page 22: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

22

13th and 14th February 2020

F61 line works

• Equipment installation

10 MHz water manifold installation (SS66)

Amplifiers cabling for the pickups systems

TE-MSC works to complete the connection of all MUs and Straight section

equipment

MU93 repair

Asbestos pipe removedPS SWY

activities in

the next slide

06-Feb-2020

Page 23: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

23

13th February 2020

• LV consolidation

• BI line vacuum

connection, leak detection

and pump down

• VSC works to close the

F16 line in the PS SWY +

LT (including leak

detection and pump

down)

• Beam stoppers

connection to the services

• F16 + LT MSC equipment

connection to the services

• F16 BLMs installation

• SMH16 installation

• PR20 vacuum closure,

leak detection and pump

down

• Scaffolding installation

• BTP smoothing

• Start the MU27 re-

installation

All material that cannot be removed with the MU27

installed must be removed from the PS SWY outer

side before this date

06-Feb-2020

Page 24: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

24

14th February 2020

• LV consolidation

• BI line vacuum

connection, leak detection

and pump down

• VSC works to close the

F16 line in the PS SWY +

LT (including leak

detection and pump

down)

• Beam stoppers

connection to the services

• F16 + LT MSC equipment

connection to the services

• F16 BLMs installation

• BTP smoothing

• PR20 vacuum closure,

leak detection and pump

down

• Finish the MU27 re-

installation

06-Feb-2020

Page 25: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

25

17th to 21st February 2020

F61 line works

• Equipment installation

Amplifiers cabling for the pickups systems

TE-MSC works to complete the connection of all MUs and Straight section

equipment

Asbestos pipe removed

PS SWY

activities in

the next slide

06-Feb-2020

Page 26: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

26

17th February 2020

• LV consolidation

• SEH23 installation +

alignment

• Vacuum leak detection

and pump down of PR20

• MU27 alignment

• PSC10 SS36 cooling

manifold installation

06-Feb-2020

Page 27: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

27

18th February 2020

• LV consolidation

• Vacuum leak detection

and pump down of PR20

• Install the stairs on top of

MU27 that allow crossing

between inner and outer

side of the ring

• TE-MSC works to

connect the MU27 and

the straight sections that

are missing

• TE-VSC works to close

the PR30 sector

• PSC10 SS36 cooling

manifold installation

06-Feb-2020

Page 28: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

28

19th February 2020

• LV consolidation

• TE-MSC works to

connect the MU27 and

the straight sections that

are missing

• TE-VSC works to close

the PR30 sector

• Vacuum leak detection

and pump down of PR20

• PSC10 SS36 cooling

manifold installation

06-Feb-2020

Page 29: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

29

20th February 2020

• LV consolidation

• PR20 Vacuum sector

bake-out

• PR30 leak detection and

pump down

• PSC10 SS36 cooling

manifold installation

06-Feb-2020

Page 30: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

30

21st February 2020

• LV consolidation

• PR20 Vacuum sector

bake-out

• PR30 leak detection and

pump down

• PSC10 SS36 cooling

manifold installation

06-Feb-2020

Page 31: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

31

TT2

All renovated magnets are aligned with the

exception of:

• BHZ377 and BHZ378

• FTA line magnets (9020, 30 and 40)

• FTN.QFO415

• TT10 line magnets

06-Feb-2020

Page 32: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

32

TT2

• Cabling campaigns

• WIC installation

• Minor maintenance activities

• Alignment of the remaining magnets if time allows

06-Feb-2020

Page 33: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

B.151• EN-EL works to

power the 40, 80

and 200 MHz

systems from the

new power source

• EN-EL works to

power the TE-MSC

workshop from a

new power source

06-Feb-2020

Page 34: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

B.269 - Report• BLM system installation in the racks

• AC cabling

• Smoke detection installed

06-Feb-2020

Page 35: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

B.269 – Next 2 weeksIn the coming 2 weeks we will have some co-activity in the building and a

dedicated VIC is needed for all the works starting on week 7 (EN-EL cabling,

IT-CS and EN-EL power)

Note:

Planning and conditions agreed in the VIC must be respected – any change

needed must be re-discussed and documented

C17 +

additional

cabling

campaign

EN-EL works

to power the

racks

CV pipes inspection and repairs

06-Feb-2020

Page 36: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

B.355 – Next 2 weeks

EN-EL general

services renovation

EN-CV works in the new PS

CV cooling station

06-Feb-2020

Page 37: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

37

B.359 – next 2 weeks

TE-ABT control works

06-Feb-2020

Page 38: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

AOB – 5 weeks without access to the PS SWY

06-Feb-2020

Page 39: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment

AOB

Sector under vacuum

• SS70 to SS80

• SS01 to SS10

06-Feb-2020

Page 40: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment