propositions s and z · • 66 schools, 2030 classrooms – july 2014 to march 2016 2,000 hottest...

24
Propositions S and Z Board of Education Meeting June 7, 2016 Lee Dulgeroff, Chief, Facilities Planning and Construction Julie Martel Executive Director, Facilities Planning and Design

Upload: others

Post on 27-May-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Propositions S and Z · • 66 schools, 2030 classrooms – July 2014 to March 2016 2,000 Hottest Classrooms - Complete • Install air conditioning in remaining qualifying spaces

Propositions S and Z

Board of Education Meeting June 7, 2016

Lee Dulgeroff, Chief, Facilities Planning and

Construction

Julie MartelExecutive Director, Facilities Planning

and Design

Page 2: Propositions S and Z · • 66 schools, 2030 classrooms – July 2014 to March 2016 2,000 Hottest Classrooms - Complete • Install air conditioning in remaining qualifying spaces

Outline

• Propositions S and Z progress and Financial Status

• Current and Planned Projects

• Issuance Capacity

• Program Plan

• Next Steps

2Artist’s rendering of Ocean Discovery Institute’s Living Lab

Page 3: Propositions S and Z · • 66 schools, 2030 classrooms – July 2014 to March 2016 2,000 Hottest Classrooms - Complete • Install air conditioning in remaining qualifying spaces

Props. S and Z Progress

Construction projects:

• 116 in design and bid phase

• 22 in construction

• 103 completed

Campus Upgrades:

• 53 new classroom buildings

• 371 portables removed/replaced

• 21 Career Technical Education facilities

3

New Academy of Business Building at Clairemont High School

Page 4: Propositions S and Z · • 66 schools, 2030 classrooms – July 2014 to March 2016 2,000 Hottest Classrooms - Complete • Install air conditioning in remaining qualifying spaces

i21 Classroom Technology

4

Interactive classrooms (i21) and technology infrastructure

• i21 Five-year plan completed

− 5,477 i21 classrooms with Promethean boards

− All K-12 students have access to devices

• Technology Infrastructure Program (cables,

routers, switches, access points, etc.):

− $47.7M in E-Rate funds awarded for tech infrastructure – projects completed

− $43.5M in E-Rate funds awarded for tech infrastructure – projects in progress

− $11M in E-Rate funds awarded in December 2015 for tech infrastructure – projects in planning phase

• Online Learning Centers

Morse HS Online Learning Center

Page 5: Propositions S and Z · • 66 schools, 2030 classrooms – July 2014 to March 2016 2,000 Hottest Classrooms - Complete • Install air conditioning in remaining qualifying spaces

Air Conditioning

5

• 66 schools, 2030 classrooms– July 2014 to March 2016

2,000 Hottest Classrooms - Complete

• Install air conditioning in remaining qualifying spaces at schools with classroom AC– Design: 43 projects, 818 spaces in progress– DSA submittals: In progress– Construction: summer 2016 – summer 2017

Academic/Support Spaces

• Air conditioning in all qualifying spaces in remaining district schools – Design: 68 projects, 2865 spaces in progress– DSA submittal: starting summer 2016– Construction: starting winter 2016 - 2019

HVAC Phase 2 – Climate Zone 1 and 2

Roof-top Air Conditioning Equipment

Page 6: Propositions S and Z · • 66 schools, 2030 classrooms – July 2014 to March 2016 2,000 Hottest Classrooms - Complete • Install air conditioning in remaining qualifying spaces

Sustainability/Solar

6

Solar panels on carport structures at new Salk Elementary School

◦ E.B. Scripps ES, Mira Mesa HS, Morse HS,

Nye ES, Penn ES, Serra HS, Tierrasanta ES,

Zamorano ES

Solar Plan Phase II: PV at 8 to 12 high

energy-use schools in 2017

• 30 schools currently being considered• Site selection: July 2016• Construction Starting: 2017

Solar Plan Phase I: Photovoltaic (PV) at eight high energy-use schools

• Construction: Starts summer 2016

Page 7: Propositions S and Z · • 66 schools, 2030 classrooms – July 2014 to March 2016 2,000 Hottest Classrooms - Complete • Install air conditioning in remaining qualifying spaces

Sustainability/Solar

Phase I and II Project Totals:

− $40M estimated installation cost− 10.5M kWH estimated annual production− $2.8M estimated energy cost offset annually

7

Solar Plan Phase II: PV at 8 to 12 high energy-use schools in 2017

Page 8: Propositions S and Z · • 66 schools, 2030 classrooms – July 2014 to March 2016 2,000 Hottest Classrooms - Complete • Install air conditioning in remaining qualifying spaces

Charter School Projects

Feasibility Studies and Site Master Plans– Albert Einstein– Darnall– Keiller– Tubman Village– Arroyo Paseo– High Tech International– Innovations

Design– Audeo Charter School – Gompers Preparatory Academy – Health Sciences HS and Middle College– Iftin– King/Chavez– Museum– Preuss– San Diego Cooperative Charter School – San Diego Global Vision Academy ES– San Diego Global Vision Academy MS

Construction– O’Farrell Community School

HVAC Completed– Darnall– Holly Drive– Keiller– Iftin– Tubman Village

$ 40.4M Expended to Date

Site Discretionary Spending Summary– Allocated -- $5.2M– Expended -- $3.5M

8

New School Buildings at O’Farrell

Page 9: Propositions S and Z · • 66 schools, 2030 classrooms – July 2014 to March 2016 2,000 Hottest Classrooms - Complete • Install air conditioning in remaining qualifying spaces

Communications and Stakeholder Engagement

• 272 stakeholder meetings

– Site Master Planning

– Design Task Force

– Joint-Use fields

– High school field use policies

– Environmental studies

• 70 groundbreakings and dedications

• Ongoing updates to cluster councils, community groups, City of San Diego colleagues, and industry professionals

• Project updates, meetings and events posted on district website and social media

• Regular updates in district’s “Unified Vision” e-newsletter (more than 60,000 subscribers)

9

Dedication of new field at Oak Park Elementary School

Page 10: Propositions S and Z · • 66 schools, 2030 classrooms – July 2014 to March 2016 2,000 Hottest Classrooms - Complete • Install air conditioning in remaining qualifying spaces

Emerging Business OutreachEmerging Business Enterprises (EBE) Contract Awards

10

Business Classification2016

Market Capacity

2016 EBE Goals

% of dollars awarded*

Disabled Veteran-Owned Business Enterprise (DVBE) 2.26% 5% 7.57%

Minority-owned Business Enterprise (MBE) 1.89% 6% 17.66%

Women-owned Business Enterprise (WBE) 0.59% 3% 2.41%

Small Business Enterprise (SBE) 16.41% 40% 38.12%

EBE Goal 44%**

Total EBE Participation 42.55%*** Period of performance: Jan. – March 2016; five projects awarded** Some firms have multiple EBE certifications so total EBE numbers does not reflect the sum of EBE categories

Page 11: Propositions S and Z · • 66 schools, 2030 classrooms – July 2014 to March 2016 2,000 Hottest Classrooms - Complete • Install air conditioning in remaining qualifying spaces

Micro-Projects Program (MPP)

11

Local small business owners are sought for “MPP” Program projects

• Program to award projects under $15,000 to Emerging Business Enterprises

−FY 2015-16 (as of March 2016)

20 MPP contracts awarded

$184,619 to certified Small Business Enterprises

3 are also certified DisabledVeteran-Owned

7 are also certified Minority-Owned

5 are also certified Woman-Owned

Page 12: Propositions S and Z · • 66 schools, 2030 classrooms – July 2014 to March 2016 2,000 Hottest Classrooms - Complete • Install air conditioning in remaining qualifying spaces

Project Stabilization Agreement (PSA)

12

• Since inception of the PSA

− 75 projects awarded

− 6073 total workers employed

− Worker participation ZIP code map

posted on district website

Category GoalCumulative

Actual

Residents of Targeted ZIP Codes 35% 27%

Residents of SDUSD ZIP Codes 70% 38%

Residents of County ZIP Codes 100% 96%

http://www.sandi.net/cms/lib/CA01001235/Centricity/Domain/138/Cumulative%20Workers%20by%20Zipcode%20102913.pdf

Page 13: Propositions S and Z · • 66 schools, 2030 classrooms – July 2014 to March 2016 2,000 Hottest Classrooms - Complete • Install air conditioning in remaining qualifying spaces

Financial Status Props. S and Z

• Program budget: $5.1B(including state matching funds

of approximately $200M)

− Total revenue $2B

− Expenditures

$1.15B expended to date

$120.8M expended in FY 2015-16

$230M work in progress

− Successful financial and performance audits13

Concrete walkway at University City HS

Page 14: Propositions S and Z · • 66 schools, 2030 classrooms – July 2014 to March 2016 2,000 Hottest Classrooms - Complete • Install air conditioning in remaining qualifying spaces

Props. S and Z - Categories

• $1.15B total expenditures

– Major repair replacement

– Student learning

– Access/code compliance

– Neighborhood schools

– Health, safety, and security

– Accommodate enrollment

– Replace inadequate buildings

– Special education

– Energy efficiency

– Site discretionary

14

MRR, $92.1

Student Learning,

$436.3Student Health

/ Safety, $226.6

Code Compliance,

$173.0

Neighborhood Schools , $79.2

Energy Efficiency ,

$2.9

Replace Inadequate Buildings,

$69.8

Accommodate Enrollment,

$47.0

Site Discretionary,

$21.5

Special Education,

$0.8

Page 15: Propositions S and Z · • 66 schools, 2030 classrooms – July 2014 to March 2016 2,000 Hottest Classrooms - Complete • Install air conditioning in remaining qualifying spaces

Estimated Future Revenues

Issue bonds at least cost to taxpayers

• Prop. Z future proceeds

− Issuances every two years (approx. $450-500M) Current Interest Bonds (CIBs)

− Long-term bonds used for facility

capital projects

− Short-term bonds for technology

devices and equipment

• Prop. S future proceeds

− Bond Issuance every two years (approx. $100M)

− Next issuance closes May 2016

• Potential for 2016 state bond (matching funds for modernization and new

construction)

15

Pershing Middle School Whole Site Modernization

Page 16: Propositions S and Z · • 66 schools, 2030 classrooms – July 2014 to March 2016 2,000 Hottest Classrooms - Complete • Install air conditioning in remaining qualifying spaces

Planned Projects

16

Page 17: Propositions S and Z · • 66 schools, 2030 classrooms – July 2014 to March 2016 2,000 Hottest Classrooms - Complete • Install air conditioning in remaining qualifying spaces

Planned Projects

17

Page 18: Propositions S and Z · • 66 schools, 2030 classrooms – July 2014 to March 2016 2,000 Hottest Classrooms - Complete • Install air conditioning in remaining qualifying spaces

Planned Projects

18

Page 19: Propositions S and Z · • 66 schools, 2030 classrooms – July 2014 to March 2016 2,000 Hottest Classrooms - Complete • Install air conditioning in remaining qualifying spaces

Planned Projects

19

Page 20: Propositions S and Z · • 66 schools, 2030 classrooms – July 2014 to March 2016 2,000 Hottest Classrooms - Complete • Install air conditioning in remaining qualifying spaces

Planned Projects

20

Page 21: Propositions S and Z · • 66 schools, 2030 classrooms – July 2014 to March 2016 2,000 Hottest Classrooms - Complete • Install air conditioning in remaining qualifying spaces

Planning Facilities

• Academic Program Alignment

• Priority Clusters and Current Successful Programs

• Innovation/On-line Learning Centers

• Wellness Centers

• Learning Environments for Today and Tomorrow

21

Page 22: Propositions S and Z · • 66 schools, 2030 classrooms – July 2014 to March 2016 2,000 Hottest Classrooms - Complete • Install air conditioning in remaining qualifying spaces

Props. S and Z Plan –2015-2021

22

• Repair and renovate schools $1,249.6M

• Maximize state matching funds, i.e., College, Career, and Technical Education

and Overcrowded Relief Grant projects – Received $72M

• Board and Superintendent priority projects

− Classroom technology $108.6M

− Air conditioning $221.6M

− Safety and Security $269.2M

− Sustainability $40M

• Pro Rata share for charter

schools $196M

• Project Plan – Attachment 1

Collaborative spaces plan for Mann Middle School

Page 23: Propositions S and Z · • 66 schools, 2030 classrooms – July 2014 to March 2016 2,000 Hottest Classrooms - Complete • Install air conditioning in remaining qualifying spaces

Props. S and Z Committees

23

• Props. S and Z Independent Citizens’ Oversight Committee

• Prop. Z Charter School Facilities Committee

− Regular meetings since April 2, 2013

− Facilities Planning and Construction staff support and facilitation

ICOC members visit the new

Jonas Salk Elementary

School.

Page 24: Propositions S and Z · • 66 schools, 2030 classrooms – July 2014 to March 2016 2,000 Hottest Classrooms - Complete • Install air conditioning in remaining qualifying spaces

24

Questions and Comments

San Diego Unified student participants in ACE Mentoring Program

tour Props. S and Z construction projects