project scheduling tools. there are four possible sequencing modes in ms project. suppose b follows...

14
Project Scheduling Tools

Upload: anis-joseph

Post on 01-Jan-2016

219 views

Category:

Documents


0 download

TRANSCRIPT

Project Scheduling Tools

There are four possible sequencing modes in MS Project. Suppose B follows A. FS: Finish Start – Start B after A is completed SS: Start Start – Start A and B at same time FF: Finish Finish – Finish A and B at same time SF: Start Finish – Start A after B is completed

Lags are delays between work on activities

1. Sequencing

FS Sequence - Traditional

A

B E.g. Sand and Paint

A

BLag E.g. Sprinklers and Landscape

SS Sequence

A

B E.g. Plant Lawn

and Flowers

A

BLagE.g. Drywall: Hang

and Tape

FF Sequence

A

B E.g. Olympics

A

B

Lag E.g. Olympics

SF Sequence

A

B E.g. Not Practical

A

B

Lag E.g. Ocean Cruise

2. Activity Uncertainty

PERT assumptions (Richard Schonberger and Ken Mac Crimmon) Beta distribution assumption PERT approximation formula for mean and variance Estimates of a, m, and b

Errors of above up to 30%, but tend to cancel Worse problem is merge event bias

(probability near-critical path becomes critical) – estimates consistently optimistic

Example 2.1

A,1

C,3

D,1

B,2

Critical path is ACD but ABD is near critical. Criticality index: probability path critical.

Use Simulation or Monte Carlo Analysis

Generate random numbers (electronic, formulas, tables,

books) i.e. 28

• Convert to random probabilities i.e. .28 What is probability of probability?

• Convert random probability to random variate. Follows distribution of say actual activity time.

Finding Random Variates, Problem 2.1

B C PMF CDF

Mean – 1 1 2 .3 .3

Mean 2 3 .4 .7

Mean + 1 3 4 .2 .9

Mean + 2 4 5 .1 1.0

Random probability of .28 gives B random variate of 1; .46 gives C value of 3.

Simulation of Problem 2.1

RN B(2) RN C(3) Length Path

.28 1 .46 3 5 ACD

.97 4 .09 2 6 ABD

.63 2 .33 3 5 ACD

.53 2 .76 4 6 ACD

.73 3 .00 5 7 ACD

Expected length = 5.8 > 5 (merge event bias)

Criticality index of ACD = 0.8 or 80%

Project Simulation Simulation includes

GERT – Graphical Evaluation and Review Technique

Crystal Ball – Copy comes with text

Simulation includes Probabilistic branching from node – B may follow A Probabilistic times for activities – various distributions Flexibility in node realization – activity time can = 0 Looping permitted – rework

Critique of Simulation – R. Schonberger recommends intensive critical path scrutiny

3. Limited Resource Scheduling

Resources include labor, material, equipment, space, and money

Money versus time tradeoffs Methods

Crashing – How to shorten activities – cost penalties Resource loading – amount of resource needed per

period. Resource leveling or balancing – evening out resource

use, reacting to limited resources

Simulation programs can help level