PROJECT REPORT
PART A ADMINISTRATIVE REQUIREMENTS
(To completed by the Project Manager)
1 Project Title Mango seedlings Garden
2 Country where project is
located
Tanzania
3 Name of the organization Amani centre for person with Disabilities
4 Name of sponsor The Netherland, Church of Our Saviour
5 Amount requested (also
state currency)
2500 Euro
6 Amount of funds actually
received by the bank of your
organization from the
Church of Our Savior (also
state currency)
2500 Euro
7 When did your bank receive
these funds? 02/05/ 2013
8 Did you encounter any
problems in receiving the
funds by your bank? Please
explain
No problem
9 When did you send the
acknowledgement of receipt
of funds to the Church of
Our Saviour, The Hague,
The Netherlands?
Was this sent by e-mail, by
post or by fax?
18th
January 2013 by e-mail.
10 Name of Project Manager Father Beatus Sewando
11 E-mail address of Project
Manager
PART B. PROJECT IMPLEMENTATION REPORT, as of December 2013
(To be complemented by the Project Manager)
Title of Project Mango seedling garden
Country Where project is located Tanzania
1. STATUS OF THE PROJECT
12 Objectives mentioned in our application have already been achieved as of
December 2013 are income after sold harvested mango fruits and nutrients
from mango itself.
13 Phases/steps enumerated in our application have already been accomplished
as of December 2013 is selling after harvesting.
14
For the first step of Mango trees garden preparation until harvesting process
the funds received from the Church of Our Saviour, The Hague are used.
II. PROJECT RESULTS: PROJECT IMPLEMENTORS, PROJECT
BENEFICIARIES AND THE COMMUNITY
15 The following people are involved in implementing the project Pascal is the fore
man, Festusi Paulo, Deodatusi Elias are the Gardener, Herena Spiriani is the one
who care the project.
16 More than 250 Children with disabilities and their parents, More than 500
villagers and 780 neighbors from different village around Amani Community in
large are the beneficiaries of the project . The additional money that was allocated
to the project was used for treating bad insects.
17 This project desire to remove them from dependence in social and economic
activities and to become productive. And this will lead to Children with
Disabilities and parents or guardians who allocates much resources in terms of
time and finance for caring these groups rather to reallocate those funds in other
development activities which will results to Community and Amani Centre
development.
18 Through this project we expect more than 1000 other persons/ groups to benefit
from the project in the near future because the Project will improve the quality
standard coverage and sustainability of Amani Centre services in the Community
for the disabled persons without too much donor dependence.
111 THE PROJECT AFTER DECEMBER 2013
19 That we still need to do after December 2013 to complete the project
We plan to planting another 400 hundreds Mango seedling at February 2014 rainy
season in order to complete the project.
20 What factor within the community will help contribute to success of the project
- Security for the project
- Caring project
Iv OTHER RELATED INFORMATION
21 Unexpected results of the project and these results affect the project positively
Assessing the provisional of nutrition’s to the pregnant mother for the
development and growth of the children’s, and community inlarge these results
affect project positively.
22 Other related information which is important to forward to the community who
have partly provided funds for this project.
This project desire to remove them from dependence in social and economic
activities and to become productive. And this will lead to parents or guardians
who allocates much resources in terms of time and finance for caring these
groups rather to reallocate those funds in other development activities which will
results to family and National development
V THE PROJECT IN PICTURES
Pictures before the start of the project
Pictures of the completed projects/beneficiaries
I am Father Beatus Sewando, the Project Manager, certify that the above information is correct.
Date 31th Dec 2013.