project name environment clearance for it-ites project...

70
Project Name Environment Clearance for IT-ITES Project 8(b) Project Proponent Balaji IT Parks Pvt. Ltd. Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh Environment Consultant Aplinka Solutions & Technologies Pvt. Ltd, Noida Uttar Pradesh 22 APPENDIX II FORM-1 A (Only for construction projects listed under item 8 of the Schedule) CHECK LIST OF ENVIRONMENTAL IMPACTS (Project proponents are required to provide full information and wherever necessary attach explanatory notes with the Form and submit along with proposed Environmental Management Plan & Monitoring Programme). 1. LAND ENVIRONMENT Attach panoramic view of the project site and the vicinity 1.1. Will the existing land use get significantly altered from the project that is not consistent with the surroundings? (Proposed land use must conform to the approved Master Plan / Development Plan of the area. Change of land use if any and the statutory approval from the competent authority are submitted). Attach Maps of (i) site location, (ii) surrounding features of the proposed site (within 500 meters) and (iii) the site (indicating levels & contours) to appropriate scales. If not available attach only conceptual plans. The project is an IT/ITES project located at plot no. 13B, Techzone, Greater Noida, Uttar Pradesh. The project site is comes under Greater Noida Industrial Development Authority. The Greater Noida Authority have allotted the land to Ms. Balaji IT Parks (P) Ltd vide letter no. IND/IT/2007/521 dated 29/03/2007 for the development of IT/ITES Park. The land falls under the IT/ITES zone as per the Master Plan of Greater Noida 2021. No Change of Landuse is required. The project proponent is providing commercial, institutional activities, auditorium, 1 & 2 BHK dwelling units and separate individual plots. The project is over a plot area of 84,994.92 sq. m. with built up area 183433.115 sq. m. The land documents (Allotment letter & Deeds) are attached as Annexure 1. The site location plan is attached in Annexure 2.

Upload: others

Post on 20-Jun-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

22

APPENDIX II

FORM-1 A(Only for construction projects listed under item 8 of the Schedule)

CHECK LIST OF ENVIRONMENTAL IMPACTS

(Project proponents are required to provide full information and wherever necessary

attach explanatory notes with the Form and submit along with proposed

Environmental Management Plan & Monitoring Programme).

1. LAND ENVIRONMENT

Attach panoramic view of the project site and the vicinity

1.1. Will the existing land use get significantly altered from the project that is not

consistent with the surroundings? (Proposed land use must conform to the approved

Master Plan / Development Plan of the area. Change of land use if any and the

statutory approval from the competent authority are submitted).

Attach Maps of (i) site location, (ii) surrounding features of the proposed site (within

500 meters) and (iii) the site (indicating levels & contours) to appropriate scales. If

not available attach only conceptual plans.

The project is an IT/ITES project located at plot no. 13B, Techzone, Greater Noida, UttarPradesh. The project site is comes under Greater Noida Industrial Development Authority.The Greater Noida Authority have allotted the land to Ms. Balaji IT Parks (P) Ltd vide letterno. IND/IT/2007/521 dated 29/03/2007 for the development of IT/ITES Park. The land fallsunder the IT/ITES zone as per the Master Plan of Greater Noida 2021. No Change of Landuseis required.

The project proponent is providing commercial, institutional activities, auditorium, 1 & 2BHK dwelling units and separate individual plots. The project is over a plot area of 84,994.92sq. m. with built up area 183433.115 sq. m. The land documents (Allotment letter & Deeds)are attached as Annexure 1. The site location plan is attached in Annexure 2.

Page 2: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

23

The required maps are attached as follows.(i) Site location, (Annexure-2)(ii) Surrounding features of the proposed site (within 500 meters) (Annexure-3)(iii) 30 meter radius map (Annexure-4)(iv) 15 Km Radius Map (Annexure 5)

Site Location: The site is located at Plot No. 13B, Techzone, Greater Noida, Uttar Pradesh.The project site is connected to Yamuna express way. The coordinates for location of theproject are present in Table 1.

Table 1: Latitude and Longitude of the Project Site

S. No. Description of Point Latitude Longitude

1. A 28022’ 55.39’’ N 77031’ 1.37” E2. B 280 22’ 57.29” N 770 30’ 55.95” E3. C 28023’ 03.20”N 770 30’ 55.53” E4. D 280 23’ 06.73” N 77031’ 04.43” E5. E 280 22’ 57.98”N 77031’ 06.58” E6 F 280 22’ 56.86”N 77031’ 5.49” E

Source: Site visit by Team.Surrounding Features: The surrounding features of the project site are presented in Table 2.S. No. Surrounding Features Aerial Distance & Direction from the

Project Site

1 Jaganpur Afjalpur Village Approx. 0.37 Km. towards SSE direction3 Yamuna River Approx. 1.95 km towards NWW direction3 Yamuna express way Approx. 1.30 km towards East direction from

project site4 Yatharth Wellness Hospital and

Trauma Centre Approx. 7.37 km towards North direction

Page 3: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

24

1.2. List out all the major project requirements in terms of the land area, built up area,

water consumption, power requirement, connectivity, community facilities, parking

needs etc.

The major project requirements are as follows.Area Requirements: The project will be developed on a net plot area of 63814.35 sq.m. Thetotal built-up area proposed is 183433.155 sq.m and total proposed FAR is 1,29,745.507sq.m. The proposed ground coverage of is 18870.064 sq.m. The other details of arearequirements are given is Table- 3.

Table – 3: Area Statement

S. No. Particular Total AreaIn terms of

percentage of plotarea

1. Total Plot area 84,994.92 1002. Area Left for Future Planning 21180.573. Net Plot Area 63814.354. Permissible FAR (1.875% of plot area) 1,59,365.475. Proposed FAR (1.871% of plot area) 1,29,745.5076. Permissible Ground Coverage (30% of

Net Plot area) 24,441.25

7. Achieved Ground Coverage (29.57% ofNet plot area) 18870.064 29.57

8. Open Area 44944.2869. Green Area 22500 35.2510. Area Under Surface Parking 6140 9.62

11. Area Under pavements/roads/services 16304.286 25.54

12. Basement Area 40626.74713. Additional FAR & Non FAR 13060.86114. Built Up Area 183433.11515. Maximum height of building 49 m

Page 4: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

25

Table 4: Built Up Area Details

Water Requirement:

Construction Phase: The water requirement during the construction phase comprisesmainly of two parts i.e. fresh water for labourers and treated water for buildingconstructions. It is estimated approx. 3.75 KLD of fresh water will be required for drinkingpurpose which will be imported in form of bottled cans from the local fresh water supplierduring the days of construction.About 183 KL of water will be required for construction purpose of the building. The treatedwater requirement will be met by the treated water from the nearby CSTP, which will bebrought by the private water tank.Operation Phase: It is estimated that the total water demand during the operation phasewill be 898 KLD. The fresh water requirement for permanent staff, floating population andfor food court is calculated to 453 KLD, whereas the treated wastewater proposed to be usedis approx. 445 KLD which includes water requirement for flushing, horticulture, HVAC andDG set cooling.Power Requirements:

The power supply shall be supplied by Noida Power Corporation Limited. The demand loadfor the project is 12,160 KW.There is provision of 7 Number of DG sets for power back up in the project. The DG sets willbe equipped with acoustic enclosure to minimize noise generation and adequate stack heightfor proper dispersion. The power requirements during operation Phase are given in Table 5.

S. No. Particulars Area (in m2)

1 FAR 129745.507

2 Additional FAR & Non FAR 13060.861

3 Basement Area 40626.747

Total 183433.115

Page 5: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

26

Table-5: Power Requirement for Construction Phase

Parameters Operation Phase

Power requirement 12,160 KW (demand load)Supply by Noida Power Corporation LimitedBack-up power supply 7 nos. of DG sets; (5 nos. X 2000) KVA & (2 Nos. X 1000) KVAParking Requirements:

Adequate provision for car/vehicle parking will be made at the project site. There will besufficient parking provisions within the project premises. The required and proposed parkingis given in Table 6.

Table 6: Parking Requirement for the Proposed IT/ITES Project

MOEF & CC PARKING REQUIREMENT

For Residential units 1 ECS / 100 m2 FAR area 159 ECSFor WTC One D 1 ECS/ 50 m2 FAR area 1,670 ECSFor WTC One E 1 ECS/ 50 m2FAR area 127 ECSFor Cubit 1 ECS/ 50 m2FAR area 427 ECSFor Auditorium 1 ECS/15 Seats 48 ECSTotal Proposed Parking 2,431 ECSAS PER GREATER NOIDA BYELAWS:

Total required parking 1 ECS/ 80 m2 of PermissibleFAR

1,992 ECS

PARKING PROPOSED:

Surface Parking (20 sq. m/ECS) 307 ECS

Basement Parking (Mechanical) (@16 sq. m. / ECS) 2125 ECS

Total Proposed Parking 2432 ECS

Source: (i) MoEF&CC Norms (ii) Greater Noida Bye Laws (iii) M/s Balaji IT Parks (P) Ltd.

Connectivity and Community Facility Requirement: Community facilities like hospitals,school, place of worship, etc. are available in near vicinity of the project site. The sector

Techzone is fast developing and has good connectivity through 60 meter wide sector roads.The Site Plan is attached as (Annexure-6)

Page 6: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

27

1.3 What are the likely impacts of the proposed activity on the existing facilities

adjacent to the proposed site? (Such as open spaces, community facilities details of the

existing land-use, disturbance to the local ecology).

The proposed site is a vacant land with scanty vegetation. No negative impact is anticipatedof the activity on the existing facilities adjacent to the site such as open spaces & communityfacilities. The project activities will be confined in the site only. The project will not have anyadverse impact on the surrounding environment. The existing landuse of the area is IT/ITESand projects 100% conforms to the existing landuse. There will be no major disturbance tolocal ecology as no tree felling is involved rather; the project has a proposal of green areadevelopment, which will increase the aesthetic value of the area. Total Green areadevelopment will be done on the 22500 sq. m. Plantation will be done on both sides of roadsalong the periphery of the plot area.1.4 Will there be any significant land disturbance resulting in erosion, subsidence &

instability? (Details of soil type, slope analysis, vulnerability to subsidence, seismicity

etc may be given).

The proposed activity will not affect any significant land disturbance resulting in soil erosion,subsidence and instability. The area is not susceptible to erosion. The excavated earthmaterial will be utilized at the site for leveling, and backfilling. Top soil will be carefullystock piled and covered with tarpaulins. The same shall be used for green area development.There are no buildings or structures at the site, so no demolition work will be required.Land/soil environment may be affected due to activities like site preparation, excavation,material handling & storage etc. during construction phase. Proper drainage system shall beprovided to deal with the storm water in case of rain.Soil type: A quantitative assessment of the particle in size distribution the soil was made bywet sieve analysis and sedimentation analysis using hydrometer, as per procedures laiddown is IS: 2720 Part IV. The particle sizes were designated according to the scale given in IS:1498 and the soil type in the area is found to be loam. The project site is located in highseismic risk (Zone IV) by national standards.

Page 7: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

28

Figure 1: Seismic Zone ClassificationSource: Building Materials and Technology Promotion Council

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

28

Figure 1: Seismic Zone ClassificationSource: Building Materials and Technology Promotion Council

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

28

Figure 1: Seismic Zone ClassificationSource: Building Materials and Technology Promotion Council

Page 8: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

29

Flood Plain: The project lies near the Yamuna River & site is flat and protected by 5meter high flood protection embankment and no incidence of flooding and waterlogging is envisaged by the project.1.5 Will the proposal involve alteration of natural drainage systems? (Give

details on a contour map showing the natural drainage near the proposed project

site)

As per contour plan the area can be categorized as a plain land as it is having relativerelief of less than 5 meter. The project is not likely to alter or obstruct any naturaldrainage courses.There is no natural watercourse passing through the project site. Hence, the projectdoes not involve alteration of natural drainage systems. As a result of excavation oftopsoil during construction phase, the impact on drainage pattern, and run offcharacteristics will be restricted to the project area. Proper rain water drainage facilitywill be provided and the run-off generated will be storing in underground water tank &reusing.

1.6. What are the quantities of earthwork involved in the construction activity-

cutting, filling, reclamation etc. (Give details of the quantities of earthwork

involved, transport of fill materials from outside the site etc?)

The total excavated earth quantity is estimated to be approximately 1,42,000 cubic

meters. Excavation will be carried out for foundation & basement work. The totalexcavated earth material will be reused for the purpose of back-filling & leveling of lowlying areas and developing landscape. There will be no transport of earth materialoutside the project site.1.7. Give details regarding water supply, waste handling etc during the

construction period.

The water requirement during the construction phase comprises mainly of two parts i.e.fresh water for labourers and treated water for building constructions. It is estimatedapprox. 3.75 KLD of fresh water will be required for drinking purpose which will be

Page 9: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

30

imported in form of bottled cans from the local fresh water supplier during the days ofconstruction. It is envisaged that approx. 183 KL of treated water will be required forthe building constructions. The treated water requirement will be met by the treatedwater from nearby CSTP which will be brought by the private water tank.The solid waste generated during the construction phase mainly comprises of concretewashout cement residue, litters, packaging waste, masonry blocks, scraps etc. Thegenerated waste will be recycled and re-used to raise the level of the site.Conclusively, it can be stated that impacts may be confined to small area (mainly toproject site) and for short duration. Proposed mitigation plan suggests maximum re-useof construction waste on site, removal of non-reusable waste from the site and its

proper disposal, which would reduce the impact significantly.1.8 Will the low lying areas & wetlands get altered? (Provide details of how low

lying and wetlands are getting modified from the proposed activity).

There are no low-lying areas present at the project site. However river Yamuna flowsabout 1.5 Km from project site but the project site is protected by 5 meter highembankment, so, there will be no impact.1.9 Whether construction debris & waste during construction cause health

hazard? (Give quantities of various types of wastes generated during construction

including the construction labour and the means of disposal).

During the construction phase, there is no such waste generated, which can cause healthhazard. The surplus earth and the fertile topsoil will be used for developing landscape.Construction debris will be collected and stored at earmarked place for reuseimmediately from the construction site and no accumulation shall be allowed.Labour hutments with basic amenities (Mobile toilets, waste bins, electricity, cookingand bathing facility, primary treatment etc) will be provided during construction.

Page 10: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

31

2. WATER ENVIRONMENT

2.1 Give the total quantity of water requirement for the proposed project with

the breakup of requirements for various uses. How will the water requirement

met? State the sources & quantities and furnish a water balance statement.

Water Management:

Construction Phase: The water requirement during the construction phase comprisesmainly of two parts i.e. fresh water for labourers and treated water for buildingconstructions. It is estimated approx. 3.75 KLD of fresh water will be required fordrinking purpose which will be procured from the local suppliers. About 183 KL of

water will be required for construction purpose of the building. The treated waterrequirement will be met by the treated wastewater from the nearby CSTP, which will bebrought by the private water tank.Operation Phase: It is estimated that the total water demand during the operationphase will be 898 KLD. The fresh water requirement for permanent staff, floatingpopulation and for food court is calculated to 453 KLD, whereas the treated waterrequirement is approx. 445 KLD which includes water requirement for flushing,horticulture, HVAC and DG set cooling. Detailed Water Requirement is given in Table 7.

Table 7: Water Calculation

S.No.

Description Rate ofwaterdemand(lpcd)

TotalOccupancy

FreshWater(KLD)

TreatedWater(KLD)

Total waterrequirement

(KLD)

WasteWater

Generation(KLD)

1 MainDwellingUnits (1BHK+ 2 BHK) 86 1266 76.21 32.66 108.88 93.63

2 Visitors 15 127 1.33 0.57 1.90 1.633 Staff 45 63 1.99 0.85 2.85 2.454 WTC One D 45 8349 262.9

9 112.71 375.70 323.10

5 WTC One E 45 637 20.07 8.60 28.67 24.666 Gallery 45 720 22.68 9.72 32.40 27.867 Cubit 45 2134 67.23 28.81 96.04 82.60

Page 11: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

32

8 HVAC LS 170 1709 DG Cooling 0.9

l/kva/hr

59 59

10 Landscape 1 l/sq.m.

22500 23 23

11 Total 453 445 897.44 556Source:(i) Manual on norms and standards for environment clearance of large construction projects,

Ministry of Environment and Forests, Government of India (iii) National Building Code of India, 2005,

The water balance diagram during the non-rainy is shown below in Figure 2:

Figure 2: Water Balance Diagram (Non-rainy Season)

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

32

8 HVAC LS 170 1709 DG Cooling 0.9

l/kva/hr

59 59

10 Landscape 1 l/sq.m.

22500 23 23

11 Total 453 445 897.44 556Source:(i) Manual on norms and standards for environment clearance of large construction projects,

Ministry of Environment and Forests, Government of India (iii) National Building Code of India, 2005,

The water balance diagram during the non-rainy is shown below in Figure 2:

Figure 2: Water Balance Diagram (Non-rainy Season)

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

32

8 HVAC LS 170 1709 DG Cooling 0.9

l/kva/hr

59 59

10 Landscape 1 l/sq.m.

22500 23 23

11 Total 453 445 897.44 556Source:(i) Manual on norms and standards for environment clearance of large construction projects,

Ministry of Environment and Forests, Government of India (iii) National Building Code of India, 2005,

The water balance diagram during the non-rainy is shown below in Figure 2:

Figure 2: Water Balance Diagram (Non-rainy Season)

Page 12: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

33

The water balance diagram during the rainy season is shown below in Figure 3:

Figure 3: Water Balance Diagram (Rainy Season)

2.2 What is the capacity (dependable flow or yield) of the proposed source of

water?

The total water requirement of the project will be 898 KLD. The fresh water requiredwill be 453 KLD and recycled wastewater used will be 445 KLD. It is expected thatapproximately 445 KLD of treated waste water will be recovered from the STP of

Capacity (670 KLD) which will be recycled for flushing, horticulture, DG set cooling &HVAC within the IT/ITES Project. The required fresh water will be provided by GreaterNoida Industrial Development Authority.2.3 What is the quality of water required, in case; the supply is not from a

municipal source? (Provide physical, chemical, biological characteristics with

class of water quality)

The water supply is from Greater Noida Industrial Development Authority. The datafrom the secondary source shows that all the parameters are well within thepermissible limits and water can be used for drinking and domestic purposes. The

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

33

The water balance diagram during the rainy season is shown below in Figure 3:

Figure 3: Water Balance Diagram (Rainy Season)

2.2 What is the capacity (dependable flow or yield) of the proposed source of

water?

The total water requirement of the project will be 898 KLD. The fresh water requiredwill be 453 KLD and recycled wastewater used will be 445 KLD. It is expected thatapproximately 445 KLD of treated waste water will be recovered from the STP of

Capacity (670 KLD) which will be recycled for flushing, horticulture, DG set cooling &HVAC within the IT/ITES Project. The required fresh water will be provided by GreaterNoida Industrial Development Authority.2.3 What is the quality of water required, in case; the supply is not from a

municipal source? (Provide physical, chemical, biological characteristics with

class of water quality)

The water supply is from Greater Noida Industrial Development Authority. The datafrom the secondary source shows that all the parameters are well within thepermissible limits and water can be used for drinking and domestic purposes. The

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

33

The water balance diagram during the rainy season is shown below in Figure 3:

Figure 3: Water Balance Diagram (Rainy Season)

2.2 What is the capacity (dependable flow or yield) of the proposed source of

water?

The total water requirement of the project will be 898 KLD. The fresh water requiredwill be 453 KLD and recycled wastewater used will be 445 KLD. It is expected thatapproximately 445 KLD of treated waste water will be recovered from the STP of

Capacity (670 KLD) which will be recycled for flushing, horticulture, DG set cooling &HVAC within the IT/ITES Project. The required fresh water will be provided by GreaterNoida Industrial Development Authority.2.3 What is the quality of water required, in case; the supply is not from a

municipal source? (Provide physical, chemical, biological characteristics with

class of water quality)

The water supply is from Greater Noida Industrial Development Authority. The datafrom the secondary source shows that all the parameters are well within thepermissible limits and water can be used for drinking and domestic purposes. The

Page 13: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

34

detailed characteristics of the water will be given in the Environmental Impactassessment report.

2.4 How much of the water requirement can be met from the recycling of

treated wastewater? (Give the details of quantities, sources and usage).

Details of Dual Plumbing: - There will be a dual plumbing system for use of water fordifferent applications thus saving on the high quality water. Installation of dualplumbing for using recycled water will reduce the demand on freshwater. There will betwo pipe lines, one supplying freshwater for drinking, cooking etc. And other for supplyof recycled water for flushing, landscape etc. this will result in saving of fresh waterdemand and life of existing sewerage will be improved.It is expected that the project will generate approx. 445 KLD of wastewater which willbe treated in the STP of capacity 670 KLD. The Dual Plumbing Plan is attached as(Annexure-7)

2.5 Will there be diversion of water from other users? (Please assess the

impacts of the project on other existing uses and quantities of consumption).

No, there is no diversion of water from other users. Rise in water demand is a localphenomenon but the project would have limited regional impact on water reserves.2.6 What is the incremental pollution load from wastewater generated from

the proposed activity? (Give details of the quantities and composition of

wastewater generated from the proposed activity).

Approximately, 445 KLD (80% fresh + 100% flushing) of sewage will be generatedduring the operational phase from domestic use and other commercial uses. Thissewage generated will be treated in well-designed sewage treatment plant. Thecomposition of waste water characteristic contains following.

Table 8: Composition of Waste Water Characteristic

Parameters

Value

Expected wastewater

characteristics

Treated wastewater

characteristics

pH 7.5-8.5 6.0-8.5

Page 14: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

35

BOD 250- 450 mg/l Less than 10 mg/l

Suspended solids 250-400 mg/l Less than 20 mg/l

COD 600-800 mg/l Less than 60 mg/l

Oil and grease 50-100 mg/l Less than 10 mg/l

Detergents 50-100 mg/l Less than 10 mg/l

2.7 Give details of the water requirements met from water harvesting? Furnish

details of the facilities created.

The rainwater harvesting will help in meeting the required water by collection andreuse. As such, the Ground water level is about 3-5 meter at the project site henceground water recharge is not proposed, however it will be collected in an underwatertank for fire fighting and as required.Water Harvesting: Rainwater from roofs will be taken to collection/desilting chamberslocated on ground. These collection chambers are interconnected to the filter pitthrough pipes. The filter pit will be circular in shape and will be back-filled with gradedmaterial, boulder at the bottom, gravel in the middle and sand at the top. The watercollected will be used for creating surface storages for utilization in non-rainy season(Table 9).

Table 9: Annual Recharge Potential (After Construction)

S.

No.Particular Area (m2)

Runoff

CoefficientRainfall

Harvesting

Potential (m3)

1. Roof top Area 18870.064 0.8 0.7 10567.24

Source: (i) CGWB Manual, (ii) Handbook on Hydrogeology

Taking retention time of 15 minutes; 2642 m3 of rain water will be collected into tanksfrom the rooftop.A detailed “Storm Water Management” has been developed. This will incorporate bestmanagement practices which will include following:

Regular inspection and cleaning of storm drains. Clarifiers or oil/water separators shall be installed in all the parking areas. Cover waste storage areas.

Page 15: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

36

Avoid application of pesticides and herbicides before wet season. Secondary containment and dykes in fuel/oil storage facilities. Conducting routine inspections to ensure cleanliness. Preparation of spill response plans, particularly for fuel and oil storage areas. Provision of slit traps in storm water drains.

2.8 What would be the impact of the land use changes occurring due to the

proposed project on the runoff characteristics (quantitative as well as qualitative)

of the area in the post construction phase on a long-term basis? Would it

aggravate the problems of flooding or water logging in any way?No adverse impacts are envisaged due to the project on the runoff characteristics of thearea as adequate arrangements will be made to trap the rainwater and suitable stormwater drainage system will be provided. During the post-construction phase, runofffrom the project shall not be allowed to stand or enter into the roadside or nearby drain.Adequate measures shall be taken to collect such run off and either shall be reused.Suitable garlanding drain as per the existing contours of the plot will be developed. Noproblem of flooding and water logging is envisaged as excess run-off will be drained toground water.2.9 What are the impacts of the proposal on the ground water? (Will there be

tapping of ground water; give the details of ground water table, recharging

capacity, and approvals obtained from competent).

The Ground water level is about 3-5 meter at the project site hence ground waterrecharge is not proposed, however it will be collected in an underwater tank andutilized for fire fighting and as required (During Operational Phase). The building

structure will have rainwater-harvesting infrastructure. The rainwater harvestingfacility will used to fulfill the water requirement of the proposed IT/ITES Project, whichwill not have any negative impact on the ground water. Water requirement will bereduced by recycling of treated water. Further ground water will not used during

construction phase. Rather, it will be supplied by the STP treated water suppliers.

Page 16: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

37

2.10 What precautions/measures are taken to prevent the run-off from

construction activities polluting land & aquifers? (Give details of quantities and

the measures taken to avoid the adverse impacts).

To prevent degradation and maintain the quality of the water source, adequate controlmeasure has been proposed to check the surface run-off. Following managementmeasures are being suggested to protect the water quality for the further constructionphase: -

Avoiding excavation during monsoon season. Care will be taken to avoid soil erosion. The storm water disposal system for the proposed IT/ITES Project shall be self-sufficient to avoid any collection/ stagnation and flooding of water. Maximumharvesting will be done within the site.

2.11 How is the storm water from within the site managed? (State the provisions

made to avoid flooding of the area, details of the drainage facilities provided

along with a site layout indication contour levels).

The storm water disposal system for the proposed IT/ITES Project shall be self-sufficient to avoid any collection/stagnation and flooding of water. Maximum harvestingwill be done within the site.A detailed “Storm Water Management Plan” will be developed. The plan will incorporatebest management practices which will include following: Rain water outlets/ spouts will be provided in terrace for taking out rainwater. The rainwater collected through channels and catch basins will be collected in anunderground water tank for future use. Regular inspection and cleaning of storm drains. A grating at the main entrance will be provided to prevent entry of outside rainwaterto the premises. All road crossings for services shall be provided with RCC Hume pipe and manholesfor the ease of maintenance and to avoid any digging of roads.

Page 17: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

38

2.12 Will the deployment of construction laborers particularly in the peak

period lead to unsanitary conditions around the project site (Justify with proper

explanation).

Labour hutments will be provided for housing of construction labours. All the basicneeds (drinking water, electricity, etc) will be provided along with rest shelters, washplace, mobile toilets will be provided to labourers on the project site. Portable toiletswith soak pit facility will be provided to treat the wastewater generated duringconstruction phase. The environmental management of labour hutments will be lookedafter by the safety health and environmental division of the company.

2.13 What on-site facilities are provided for the collection, treatment & safe

disposal of sewage? (Give details of the quantities of wastewater generation,

treatment capacities with technology & facilities for recycling and disposal).

During operation, 445 KLD of wastewater will be generated, which will be treated in thesewage treatment plant & part of the treated wastewater from STP will be utilized forflushing, green area development, HVAC & DG cooling. Details of the quantities ofwastewater generation, treatment capacities with technology & facilities for recyclingand disposal are given in Table 11.

Table 11: Sewage Quantity, Treatment, Reuse & Disposal

Parameters Details

Quantity of

sewage669 KLD

Collection of

sewage

Sewage generated during the operation phase will be collected

through underground sewerage system (pipe drain) for treatment

in STP.

Treatment of

sewage

Sewage will be treated up to the tertiary level in a SewageTreatment Plant (STP) of Capacity 800 KLD of MBBR Technology.

Reuse/recycle

and Disposal of

treated sewage During normal operations treated sewage will be recycled and reusedfor flushing, green area development, HVAC & DG cooling.

Page 18: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

39

2.14. Give details of dual plumbing system if treated waste is used for flushing of

toilets or any other use.

There will be a dual plumbing system for use of water for different applications thussaving on the high quality water. Installation of dual plumbing for using recycled waterwill save the potable water from authorized private water agency. There will be twopipe lines, one supplying freshwater for drinking, cooking etc. and other for supply ofrecycled water for flushing, landscape irrigation, etc. This will result in saving freshwater demand and life of existing sewerage will be improved.3. VEGETATION

3.1 Is there any threat of the project to the biodiversity? (Give a description of

the local ecosystem with its unique features, if any).

The the area is protected by a 5 meter high embankment which has been made byGNIDA. The project site contains only grasses and small bushy shrubs such as DubGrass, Congress grass, Madar, Dhatura, Kurri, and cucurbits. The avian and mammalsspecies like large egret, Crow, Bank Mayna and Cows, & Bufflaows, are observed at theproject site. The flora and fauna found are of common occurrence in the flood plainecosystem of Yamuna. No threatened, rare, endangered or endemic species wereobserved during the survey in core zone. There is no ecologically sensitive area within15 km of the project site. The details received in site survey, it can be stated that thedevelopment of proposed IT/ITES project doesn’t pose any threat to the biodiversity.3.2 Will the construction involve extensive clearing or modification of

vegetation? (Provide a detailed account of the trees & vegetation affected by the

project).

There are only two trees along the project boundary within the core zone and these willbe preserved. Grasses and shrubs will be cleared during construction phase. Further asthe project related activities (during construction and operation) are confined withinthe project premises, no cutting of tree in the project area is anticipated.

Page 19: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

40

3.3 What are the measures proposed to be taken to minimize the likely

impacts on important site features (Give details of proposal for tree plantation,

landscaping, creation of water bodies etc. along with a layout plan to an

appropriate scale?).

Extensive plantation and green area and landscape development in the area of 30438sq. m is planned. This is here by ensured that the indigenous / local plants will beplanted all around the periphery of the project area and along the roadsides; as per theGuidelines for the development of Greenbelt by CPCB. Plantation would be of flowering,evergreen, broadleaf trees that provide adequate shade. Following species arerecommended for plantation. The landscape plan is attached as Annexure-8

Table 12: List of Plants/ Trees Species

S.No.

BinomialName

FamilyCommonName

LocalName

Height(Meters)

Flowering Season

CrownShape

1Acacia nilotica(Linn) Willd. Mimosceae

IndianGum- Babul 8 Aug-JAN. Spreading

2

Alstoniascholaris (linn.)R. Br. Apocynaceae

Chattiyan 15 Dec - Mar. Round

3Cassia siameaLamk

Caesalpinaceae

Ironwoodtree Minjri 10 Aug - May Oblong

4Citrusaurantium Linn Rutaceae Limbu 5 Sept - Nov

Round/Oblong

5Ixora arboreaRoxb Rubiaceae 6

Throughout theyear

Oblong tospreading

6Lagerstroemiaspeciosa (Linn) Lythraceae

QueencrapeMyrte Jarool 10

April -June. Oblong

7Mimusop selengiLinn Sapotaceae Bakuli Bakul 10 Jan.- Mar.

Oblong /Round

8Morus albaLinn. Moraceae Tuti Tut 8 Feb.- June Oblong

9 Psidium Myrtaceae Guava Amrud 5 Oblong

Page 20: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

41

S.No.

BinomialName

FamilyCommonName

LocalName

Height(Meters)

Flowering Season

CrownShape

guayavaLinn. tree

10Saraca asokaRoxb.De Wilde

Caesalpinaceae Ashok 5 Dec. - May Spreading

11

SpathaodeacampanulataBeauv

Bignoniaceous

IndianTulipTree 12 Nov. - Jan.

Oblong/Round

12

Thespesiapopuleneoides(Roxb) Kostel Malvaceae

UmbrellaTree

Parespipal 10

Throughthe year Round

Source: Guidelines for developing greenbelt- CPCB-2007Table 13: Shrubs for Green Belt Development

S.No.

Binomial Name FamilyCommonName

HindiName

Height(Meter)

Flowering

Season

CrownShape

1BougainvilleaspectabilisWilld Nyctaginvillea

Bougainvillea

KagjiPhul 8

Throught theyear

Oblong/Round

2Hamelia patensJacq Rubiaceae

Scarletbush 3 Oct.- Jan Round

3Lawsonia inermisLinn Lythraceae Henna

Mehendi 5

April -July Round

4Nerium indicumMill Apocynaceae

Pinkoleander Kaner 5

Throughout theyear

Oblong /Round

5

Tabernaemonatana divaricataLinn Apocynaceae Tagar 3

Throught theYear Round

6Tecoma stansLinn. Bingnoniaceae 5

Feb -April Oblong

7

Thevetiaperuviana (Pers.)Merrill. Apocynaceae

Yellowoleanner

PilaKaner 6

Round/Oblong

Source: Guidelines for developing greenbelt- CPCB-2007

Page 21: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

42

4. Fauna

4.1 Is there likely to be any displacement of fauna- both terrestrial and aquatic

or creation of barriers for their movement? Provide the details.

Cat, Dog, Cow, Rat, Mouse, Aves, Crow, Sparrow, Baya, Parrot, Pigeon etc. are found on& near the site. No displacement of fauna is envisaged due to proposed IT/ITESProject. The project site is free of nesting, roasting foraging habitat of wild animalsfurther there is no proposal of creation of any barrier for terrestrial or aquatic fauna,hence it can be inferred that the proposed IT/ITES project is not going to disturb themovement of fauna.4.2 Any direct or indirect impacts on the avifauna of the area? Provide details.No direct impact on avifauna is envisaged. However, after the commissioning of theproject the better environmental conditions may provide a better habitat to theavifauna of the area. There may be some indirect impact to avian fauna; however thatwill be minimized by adopting proper waste management, controlling noise pollutionand bird friendly lightening.4.3 Prescribe measures such as corridors, fish ladders etc. to mitigate adverse

impacts on fauna.

No direct or indirect impact on fauna is envisaged hence no mitigation measures areprescribed.

5. AIR ENVIRONMENT

5.1 Will the project increase atmospheric concentration of gases & result in

heat islands? (Give details of background air quality levels with predicted

values based on dispersion models taking into account the increased traffic

generation as a result of the proposed constructions).

The baseline study of the ambient air quality will be carried out after the TORapproval by SEIAA.However the nature of proposed IT/ITES project and activities; will not increase theatmospheric concentration of gases to such an extent that it may lead to the formation

Page 22: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

43

of heat islands. There will be only two emission sources i.e. through D.G sets only incase of power failure and vehicular movement.There will be the provision of acoustic enclosures & adequate stack height will bemaintained as per the CPCB guidelines to minimize the impact due to DG sets.The marginal increase in traffic due to project is not going to cause anysignificant increase in atmospheric concentration of gases and will not result inheat island formation. The nearness of surface water (Yamuna River) will have itsamelioration impact thereby reducing the probabilities of heat island formation.5.2 What are the impacts on generation of dust, smoke, odorous fumes or other

hazardous gases? Give details in relation to all the meteorological parameters.

There will be burning of fuel through D.G. sets, traffic movements, operation ofconstruction machines / equipment and domestic activities at site.Construction activities lead to dust generation, emission of NO2, SO2 and PM. Theimpacts on the ambient air quality during construction phase is temporary andreversible in nature (for short duration) and will be restricted to only a small area.During operation phase, D.G. set will be having adequate stack height, there will bedevelopment of green-area and maintenance of vehicles, all these efforts will reducethe impact.5.3 Will the proposal create shortage of parking space for vehicles? Furnish

details of the present level of transport infrastructure and measures proposed

for improvement including the traffic management at the entry & exit to the

project site.

There will be sufficient parking space for the vehicles. The provision of parking spacewill be as per the norms. The parking provision will be made at open surface &

basement. We are providing total 2432 ECS. The consolidated parking statement isshown in Table 14.

Table 14: Parking Statement

Parking Proposed ECS

Surface Parking 307

Page 23: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

44

Basement Parking (Mechanical) 2125Total Proposed Parking 2432

Transport Infrastructure:

The project site is in close proximity to Yamuna Expressway. Nearest Railway station isDankaur Railway Station approx. 13 Km, in East direction.Adequate measures have been proposed to manage the traffic within and outside thesite. There will be a proper entrances and exits for the proposed project to segregate theincoming and outgoing traffic. The vehicular traffic will move around the periphery ofthe project without disturbing the landscaped areas and organized open spaces.Internal roads of 9.0m have been provided for traffic along with this; separate entry andexits will be provided.5.4 Provide details of the movement patterns with internal roads, bicycle

tracks, pedestrian pathways, footpaths etc., with areas under each category.

In the circulation plan of the project, there will be proper entry and exit points forsystematic control of the vehicular movement within the project.Wide internal road around 9.0 m will be provided for the smooth traffic movement. Theproject has roads running on the periphery at all sides that will facilitate the movementof traffic. Internal roads, footpaths, ramps with suitable width have also been provided.Adequate lighting arrangement has been provided covering all corners.5.5 Will there be significant increase in traffic noise & vibrations? Give details

of the sources and the measures proposed for mitigation of the above.

There will be a marginal increase in the traffic noise; the sources are due to trafficmovement within the project area. The horns will be prohibited inside the project site.The traffic movement will be only in daytime during the construction phase. Inoperational phase only visitor’s vehicles will come inside the project boundary. Thepollution will be in very small quantity and it will be further minimized by plantation onthe sides and around the periphery of whole project.

Page 24: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

45

5.6 What will be the impact of D.G. sets & other equipment on noise levels &

vibration in & ambient air quality around the project site? Provide details.DG Sets will be used for back-up. So, D.G. set will be the main source of air and noisepollution. Gaseous pollutants like NO2, SO2 and PM shall be generated from activitieslike burning of fuel through D.G. sets. HSD diesel will be used with low sulphur.During operation, vehicular movement and operation of D.G. sets are the major sourcesof noise pollution. But both these activities – D.G. sets and vehicular movement will nothave any significant impact on the area. Since D.G. sets will not be operationalcontinuously and moreover it will be placed enclosed with suitable enclosures, hence noor minimal impact will be anticipated. It is envisaged that the movement of the motorvehicles will be restricted to designated roads only.Impacts on Air Quality

Impacts on ambient air quality during operation due to emissions from the stacksattached to standby D.G. sets would be very less. However suitable mitigation measureswill be adopted.Mitigation Measures for Impacts of DG Sets on Ambient Air Quality:

D.G. sets will be used only during power failure D.G. sets will comply with the applicable as per emission norms. Adequate stack height for D.G. sets will be provided as per C.P.C.B. norms. During operation stage, monitoring of emissions from D.G. sets and ambient airquality will be carried out as per norms.

6. AESTHETICS

6.1 Will the proposed constructions in any way result in the obstruction of a

view, scenic amenity or landscapes? Are these considerations taken into account

by the proponents?

The project site does not have any scenic amenity or landscaping in its surroundings sothere is no possibility of obstruction of above-mentioned conditions. Moreover theapproval of the architectural plan of the building will be taken from local developmentauthority.

Page 25: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

46

The project will not in any way result in the obstruction of a view scenic amenity orlandscapes. The present project itself is planned with provisions of landscaping andgreen area development and afforestation. This will surely enhance the aesthetic beautyof the area.6.2 Will there be any adverse impacts from new constructions on the existing

structures? What are the considerations taken into account?

There is no existing structure on the project site hence no such adverse impact on theexisting structures is ruled out. There is adequate space to provide landscaping. Thedevelopment of the project area is as per the approved Master Plan of Greater Noida2021.

6.3 Whether there are any local considerations of urban form & urban design

influencing the design criteria? They may be explicitly spelt out.

The Greater Noida is one of the best developing places in NCR along with the bestarchitecture, landscape, infrastructural amenities. The project has been designed localconsiderations of urban form & urban design. The project site falls under the area ofMaster Plan of Greater Noida 2021.The project is constructed within the designed siteas per the defined building by-laws of UP.6.4 Are there any anthropological or archaeological sites or artifacts nearby?

State if any other significant features in the vicinity of the proposed site have been

considered

There is not any anthropological or archaeological site or artifacts or any othersignificant features in the vicinity of the site, hence not considered.7. SOCIO-ECONOMIC ASPECTS

7.1 Will the proposal result in any changes to the demographic structure of

local population? Provide the details.

Page 26: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

47

Construction phase: About 250 labours will be engaged during construction phase.

Alteration to the existing demographic profile of the area is not anticipated as labourhutment will be provided to the labours within the project premises.Operation phase: The changing demography in the area is another impact that needsattention. The proposed IT/ITES Project will have offices, residential facility and shops.The project will mainly lead to spatial redistribution of local population and hence noconsiderable influx of population is envisaged owing to the project.7.2 Give details of the existing social infrastructure around the proposed

project.

The project site is located in the development area under the Master Plan of GreaterNoida 2021. The ancillary infrastructure like roads, public health, amenities andconveyance facilities will be developed in the project area. However some of the existingsocial infrastructures available in the nearby area are as follows.S. No. Name of existing social infrastructures Distance & Direction

1. Primary Health Centers Govt Dispensary and Hospital 4.8 Km SE2. Kanshi Ram Multi Specialty Hospital (Greater Noida) 5.7 Km N3. Yatharth wellness hospital 7.5 Km N4. DIET, BTC Training Center Dankaur 4.3 Km SE5. Gautambudh University 3.8 Km N6. Noida International University 2.5 Km SE7. Bhumia Baba Temple 3.8 Km N8. Formula One Racing Track 3.2 Km S

7.3 Will the project cause adverse effects on local communities, disturbance to

sacred sites or other cultural values? What are the safeguards proposed?

The proposed IT/ITES project is constructed within the designated site as per thedefined UP bye-laws. There are few sacred sites or cultural heritage site in nearbyvicinity of project mainly religious in nature. Respect to the local sacred sites or other

Page 27: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

48

cultural values will be an integral part of the operational policy of the proposed IT/ITESProject.

8. BUILDING MATERIALS

8.1 May involve the use of building materials with high-embodied energy. Are

the construction materials produced with energy efficient processes? (Give

details of energy conservation measures in the selection of building materials and

their energy efficiency).

Conventional construction material will be used. Energy efficient building materials willbe used as specified in the Energy Conservation Building Code. The major materialsused for the construction of the project will be steel, cement, bricks, metal, flooringtiles/stones, sanitary and hardware items, electrical fittings, water etc.8.2 Transport and handling of materials during construction may result in

pollution, noise & public nuisance. What measures are taken to minimize the

impacts?

During the construction phase the air quality has adverse impact. Construction activitiesespecially related to handling of loose material likely to cause generation of fugitive dustthat adversely impacts the air quality of the surrounding area of the project site. Tominimize the impact, loose material are either stacked or transported with propercovering.

During construction phase the expected noise levels lies between 70 – 85 dB (A), whichwill decreases with increase in distance. Administrative as well as engineering controlmeasures of noise will be implemented.8.3 Are recycled materials used in roads and structures? State the extent of

savings achieved?

Yes the recycled material will be used in the development of proposed IT/ITES Projectto the extent possible. The possibilities will be searched and if feasible following

recyclable material will be used in construction.1. Fly ash Bricks

Page 28: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

49

2. Clean wood3. Recycled Gypsum Wallboard, and cardboard4. Particle boards or other fiber-boards8.4 Give details of the methods of collection, segregation & disposal of the

garbage generated during the operation phases of the project.

During the operation phase, waste will comprise domestic as well as agricultural waste.The solid waste generated from the project shall be mainly domestic waste andestimated quantity of the waste shall be approx. 3642 kg per day (@0.50 kg per capitaper day for residents, @0.15 kg per capita per day for the visitor, @0.25 kg per capitaper day for the staff members and landscape wastes @ 0.2 kg/acre/day). Followingarrangements will be made at the site in accordance to Solid Wastes Management Rules,2016. Calculation and Composition of solid waste generation is given in Table 15 & 16.

Table 15: Solid Waste Calculation

S. No. CategoryPopulation/

AreaKg/ Capita/day

Waste generated

(Kg/day)

1Main DwellingUnits (1 BHK + 2BHK)

1266 0.5 633.00

2 Visitors 127 0.25 31.653 Staff 63 0.25 15.834 WTC One D 8349 0.25 2087.235 WTC One E 637 0.25 159.29

6 Gallery(Auditorium) 720 0.25 180.00

7 Cubit 2134 0.25 533.58

8 Landscape waste 22472.14 @ 0.2kg/acre/day 1.63

9 Total 3642.20(Source: For Waste Collection, Chapter 3, Table 3.6, Page no. 49, Central Public Health &Environment Engineering Organization, Ministry of Urban Development, (Governmentof India, May 2000)

Page 29: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

50

Table 16: Composition of Solid Waste

Sr. No. Type of Waste Quantity of Waste

1. Total Waste 3642

2. Bio-degradable Waste(@60 % of the domestic waste) 2185.2

3. Recyclable Waste (@30% of the domestic waste) 1092.6

4. Inert Waste & E waste 364.2

DETAILS OF SOLID WASTE DISPOSAL

Solid wastes which are likely to be generated in project will be domestic in nature.Domestic wastes will be collected from designated locations and segregated intoinorganic and organic wastes. All the municipal solid waste generated at the proposedIT/ITES Project shall be in accordance to Solid Waste Management Rules, 2016.DETAILS OF HAZARDOUS & ELECTRONIC WASTE DISPOSAL

Lead, glass, ceramics, bitumen, DG set used oil main hazardous waste and CFL, LED,Computers, Monitors etc will be the main Electronic waste generated in the proposedIT/ITES Project. All the hazardous and electronic waste will be disposed off through theCPCB authorized venders following the provisions of Hazardous and Other Wastes(Management and Transboundary Movement) Rules, 2016 and e-waste (Management)Rules, 2016.9. ENERGY CONSERVATION

9.1 Give details of the power requirements, source of supply, backup source etc.

What is the energy consumption assumed per square foot of built-up area? How

have you tried to minimize energy consumption?

The power supply shall be supplied by Noida Power Corporation Limited. The demandload for the project is 12160 KW. There is provision of 7 Number of DG sets for powerback up in the project (5 nos. X 2000) KVA & (2 Nos. X 1000) KVA. The DG sets will beequipped with acoustic enclosure to minimize noise generation and adequate stack

Page 30: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

51

height for proper dispersion. The DG sets will be equipped with acoustic enclosure tominimize noise generation and adequate stack height for proper dispersion.Energy Conservation Measures & Management Plan :

In the operational phase, appropriate energy conservation measures and managementplan will be adopted in order to minimize the consumptions of non-renewable fuel. Thefollowing measures are suggested to be adopted: LED will be used in place of incandescent lamps in auditorium, common areas andparking.

Percentage saving in energy consumption due to use of CFL will be 15 -20 %. Lighting and switching of common area shall be designed keeping in mind daylight integration. Roof insulation shall be planned to conserve energy. D.G. sets would be provided with auto cut and auto start mechanism. The water supply pumping system shall be provided with variable speed drive toconserve energy at part load. Space heating load will be minimized using passive solar structures. Building will have appropriate design to shut out excess heat and gain loss.Following measures have been proposed to reduce energy consumption for

Electrical installations:

Common area shall be provided LED based lighting predominantly; parking and inall common areas. Dynamic Balancing valves in piping reduce pump capacity & power consumptiondue reducing pipe lengths. Air handling unit shall be provided with Variable frequency drive system to caterexact loads. There shall be maximum utilization of natural light.

Page 31: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

52

9.2 What type of and capacity of, power back-up to you plan to provide?

In emergency situations, there are provisions of 7 no. of DG set (5nos. 2000 kVA+ 2 nos.1000 kVA). The DG sets will be equipped with acoustic enclosure to minimize noisegeneration and adequate stack height for proper dispersion.9.3 What are the characteristics of the glass you plan to use? Provide

specifications of its characteristics related to both short wave and long wave

radiation?

Suitable thickness of glass depending upon the panel size to keep the U value as per therequirement of ECBC.9.4 What passive solar architectural features are being used in the building?

Illustrate the applications made in the proposed project?

The orientation of the building will be done in such a way that maximum daylightis available. The orientation of the building would be done in such a manner that most ofglazed areas in north and east. Public areas will be cooled by natural ventilation as opposed to air conditioning. Lesser opening will be provided on the west facing walls. Landscape and green areas will be so spaced so as to cool the surroundingenvironment, which will reduce energy consumption.9.5 Does the layout of streets & buildings maximize the potential for solar

energy devices? Have you considered the use of street lighting, emergency

lighting and solar hot water systems for use in the building complex? Substantiate

with details.

Orientation is done in such a manner so that surface of the building cuts directradiation of critical hours and thus building will be less affected with the heat. Buildingunits will be made environment friendly with optimum use of solar radiations. Feasibility for installation of solar photovoltaic cells for street lighting will beassessed.

Page 32: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

53

There will be the provision of solar hot water system.9.6 Is shading effectively used to reduce cooling / heating loads? What

principles have been used to maximize the shading of Walls on the East and the

West and the Roof? How much energy saving has been effected?

The shading has been effective to reduce the cooling loads. The following techniqueswill be adopted: For walls on of the building, a maximum of 10% window to wall ratio will bethere to minimize solar radiation, which further helps minimizes cooling/ventilationcosts.

Living areas will be aligned to get maximum north south light and services areasare to be located on the western side. Shading will be used to increase cooling effect in the buildings. There will be less number of openings on the west side and more number ofopenings on the south side. Promoting awareness on energy conservation. Training of staff on methods of energy conservation and to be vigilant to suchopportunities.

Passive solar architectural measures will be adopted to provide shading devicesfor windows and roof, which would effectively reduce heating up of building envelope. Roofs will be painted with reflective, aluminum based paints with solarreflectance ranging from 0.3 - 0.6. This will result in less absorption of sunlight causing40% back reflection and less heating of building structures during summer seasons.9.7 Do the structures use energy-efficient space conditioning, lighting and

mechanical systems? Provide technical details. Provide details of the

transformers and motor efficiencies, lighting intensity and air-conditioning load

assumptions? Are you using CFC and HCFC free chillers? Provide specifications.

The design of the building will be such that maximum use of natural lighting canbe achieved. The walls, roofs and opening will be designed that influx of heat isminimum. The design also incorporates the optimal and judicious use of natural lighting.

Page 33: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

54

Energy Efficient Features:

Use of LED`s lamps instead of GLS lamps for Flats. Use of LED`s lamps instead of GLS lamps for Common area Lights. Use of T5 lamps instead of Normal Fluorescent lamps in Basements. Use of Solar backed LED landscape lights instead of par lamps.

9.8. What are the likely effects of the building activity in altering the micro-

climates? Provide a self- assessment on the likely impacts of the proposed

construction on creation of heat island & inversion effects?

The building will use energy efficient and environmental friendly designs that willcontrol formulation of heat island effect. There will be also green cover at the site toreduce formation of heat island. Passive design concepts have been used to minimizeenergy consumption and maximize the energy efficiency. Heat emission from the project and associated operations can be from the followingsources:

Heat absorbed and radiated from the paved and concrete structures, heat generatedfrom equipments/appliances and due to increased population for a particular stretch ofland. However, the heat generated will not be significant and will be dissipated with thelush green provided within the project. Hence, it can be concluded that the heat islandeffect shall not be a concern for the project and will have an overall positive effect onthe microclimate of the area. Due to the project there would be emission of air pollutants by vehicular movementsand occasional use of D.G/ sets. However, no heat island effect is envisaged. To reduce the heat load reflective insulated glass shall be used in fenestrations to cuton heat loads and subsequently capital & operating cost of air conditioning. Overall all glazing will be maintained.9.9 What are the thermal characteristics of the building envelope? (a) roof; (b)

external walls; and (c) fenestration? Give details of the material used and the U-

values or the R-values of the individual components.

Page 34: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

55

The building envelope for external walls will be made of bricks, concrete and steel.Proper roof insulation will be provided to achieve desired thermal comfort. The entirebuilding envelope, opening between conditioned and non- conditioned spaces will begasketed, provided with air curtains or sealed with sealants. Bricks, concrete & Glasswill be used as construction material.9.10 What precautions & safety measures are proposed against fire hazards?

Furnish details of emergency plans.

In case of emergency, immediate steps will be taken to raise alarm and stop fire. TheFire Protection System would be based on the regulations of National Building Code,2005 and local fire norms. Provision of Automatic water sprinklers. Provision of separate fire hydrant pipe. Provision of Overhead water storage tank. There is provision of firefighting pumps. Optical type smoke detectors shall be used in most areas. Rate of rise heat detectors shall be planned for all potentially smoky areas and in

the basements.

9.11 If you are using glass as wall material provides details and specifications

including emissivity and thermal characteristics.

Glass will not be used as a wall material.9.12 What is the rate of air infiltration into the building? Provide details of how

you are mitigating the effects of infiltration.

Reduced air infiltration combined with proper ventilation cannot only reduceenergy consumption but it can also improve the quality of indoor air. Outdoor air for which leakage account for 25 - 40% of energy will be used forheating and cooling in a typical building. For this purpose the building will be designedin a compact manner, leaving ventilation shafts in between for facilitating the escape ofhot exhaust air.

Page 35: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

56

9.13 To what extent the non-conventional energy technologies are utilized in

the overall energy consumption? Provide details of the renewable energy

technologies used.

Non- conventional energy technologies shall be used to save overall energyconsumption. Following technologies would be used in order to conserve energy: Introducing electric meters with timer. Replacement of High energy consuming incandescent lights with florescent lighting. Using solar controlled glass in windows. Renewable energy technologies will be promoted in the form solar water heating.Solar water heating system consisting of solar panels of and hot water storageinsulation tank is also proposed. After testing the viability, solar energy will also be used to meet electricityrequirements.

10. ENVIRONMENT MANAGEMENT PLAN

Introduction

The Environment Management Plan (EMP) is a site specific plan developed to ensurethat the project is implemented in an environmental sustainable manner where allcontractors and subcontractors, including consultants, understand the potentialenvironmental risks arising from the project and take appropriate actions to properlymanage that risk. EMP also ensures that the project implementation is carried out inaccordance with the design by taking appropriate mitigation actions to reduce adverseenvironmental impacts during its life cycle. The plan outlines existing and potentialproblems that may adversely impact the environment and recommends correctivemeasures where required. Also, the plan outlines roles and responsibility of the keypersonnel and contractors who will be in-charge of the responsibilities to manage theproject site. The Environment Management Plan (EMP) would consist of all mitigationmeasures for each component of the environment due to the activities increased duringthe construction, operation and the entire life cycle to minimize adverse environmentalimpacts resulting from the activities of the project. It would also delineate theenvironmental monitoring plan for compliance of various environmental regulations. It

Page 36: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

57

will state the steps to be taken in case of emergency such as accidents at the sitesincluding fire.Objectives

Actions/ activities required to comply with rules and requirements of theenvironmental clearance, consent to establish, consent to operate and other NOCfrom Govt. Departments.

Ensure that the Project meets all contractual, legal and other environmentalrequirements including best practices of construction and IT/ITES Industries.

To ensure that the proposed IT/ITES Project is operated in accordance with theapproved design.

Provide proposed IT/ITES project personnel with systems, procedures anddocumentation necessary to undertake the construction meeting with

environmental requirements and to minimize the impact on the natural

environment.

A system that addresses public complaints during construction and operation of thefacilities.

A plan that ensures remedial measures is implemented effectively in a planned way. Building and securing an unblemished reputation for environment managementwithin the market place.

EMP includes four major elements:

Commitment & Policy: The management will strive to provide and implement theEnvironmental Management Plan that incorporates all issues related to air, water,land and noise.

Planning: This includes identification of environmental impacts, legal requirementsand setting environmental objectives.

Implementation: This comprises of resources available to the developers,

accountability of contractors, training of operational staff associated withenvironmental control facilities and documentation of measures to be taken.

Measurement & Evaluation: This includes monitoring, counteractive actions andrecord keeping.

Page 37: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

58

Activities:

The following table is a detailed list of activities that will be carried out during eachphase of construction of the project and which phases require environmentalmanagement monitoring and reporting, Table 17.

Table 17. Activities and requirement of EMP

Phases Activities Required environmental

management monitoring

and reporting

Construction PhaseSite

Establishment

Fences & hoardings to sitecompound.

Temporary services and siteamenities.

Temporary access roads. Labour hutments

Required throughout theduration of this phase.

Foundations &

Ground works Bored piers. Detailed excavation. Lift Pit; Formwork.

Sand blinding & plastic

membrane.

Steel reinforcement. Place concrete In ground hydraulic services. In ground electrical services. In ground Fire Sprinkler

services.

Termite barriers.

Required throughout theduration of this phase.

Structure 1. Footings; Required throughout the

Page 38: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

59

Phases Activities Required environmental

management monitoring

and reporting

Formwork edgeboards. Sand blinding & plastic

membrane.

Steel reinforcement. Place concrete.

2. Slab on ground; Formwork edgeboards. Sand blinding & plastic

membrane.

Steel reinforcement. Place concrete.

3. Suspended Slabs Formwork decks & columns. Electrical conduits &

penetrations.

Hydraulic pipework &

penetrations.

Steel reinforcement. Place concrete.

4. Structural Steel framing.5. Roofing.

6. External wall cladding.

duration of this phase.

Fit Out & Finishes Masonry Walls

Steel Stud wall & ceiling

framing

Windows & glazed doorsRequired throughout theduration of this phase.

Page 39: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

60

Phases Activities Required environmental

management monitoring

and reporting

Electrical services Hydraulic services Mechanical services Fire sprinklers Plasterboard wall & ceiling

linings

Cement Rendering Carpentry & joinery fitout Tiling

Painting

Carpet

Vinyl

External Works Concrete Footpaths Formwork edgeboards. Sand blinding & plastic

membrane.

Steel reinforcement. Place concrete.

Required throughout theduration of this phase.

Transportable

Building Site

Establishment

Fences & hoardings to sitecompound.

Confirm location of servicesinstalled by others.

Required throughout theduration of this phase.

Transportable

Building

Foundations

Bored Piers Detailed excavation. Footings;

Fix Steel reinforcement. Place concrete

Required throughout theduration of this phase

Page 40: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

61

Phases Activities Required environmental

management monitoring

and reporting

Transportable

Building Delivery& Installation

Deliver to site on trucks Crane into position Connect Services to buildings.

Required throughout theduration of this phase

An Environmental Management Plan (EMP) is required to mitigate the adverseenvironmental impacts during construction and operation phase of the project andthese are discussed as follows.EMP for Air

Construction Phase

To mitigate the impacts of PM10 & PM2.5during the construction phase of the project, thefollowing measures are recommended for implementation:

The most cost-effective dust suppressant is water because water is easilyavailable on construction site and it can be applied using water trucks, handledsprayers and automatic sprinkler systems.

Incoming loads could be covered to avoid loss of material in transport, especiallyif material is transported off-site.

The whole site is covered with GI sheets in order to contain the dust withinproject site.

Construction equipment is commonly left idle while the operators are on breakor waiting for the completion of another task. Emission from idle equipmenttends to be high, since catalytic converters cools down, thus reducing theefficiency of hydrocarbon and carbon monoxide oxidation. Existing idle controltechnologies comprises of power saving mode, which automatically off theengine at preset time and reduces emissions, without intervention from theoperators.

Significant emission reductions can be achieved through regular equipmentmaintenance. Contractors will be asked to provide maintenance records for their

Page 41: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

62

fleet as part of the contract bid, and at regular intervals throughout the life of thecontract. Incentive provisions will be established to encourage contractors tocomply with regular maintenance requirements.

Rapid on-site construction would reduce the duration of traffic interference andtherefore, will reduce emissions from traffic delay.

Operation Phase

To mitigate the impacts of pollutants from DG set and vehicular traffic during theoperational phase of Proposed IT/ITES Project, following measures are recommendedfor implementation:

Adequate stack height will be maintained to disperse the air pollutantsgenerated from the operation of DG set to dilute the pollutants concentrationwithin the immediate vicinity. Hence no additional emission control measureshave been suggested.

During construction, vehicles will be properly maintained to reduce emission. Asit is an commercial, institutional, residential project, vehicles will be generallyhaving “PUC” certificate.

Adequate footpaths and pedestrian ways would be provided at the site toencourage non-polluting methods of transportation.

Increased vegetation in the form of greenbelt is one of the preferred methods tomitigate air and noise pollution. Plants serve as a sink for pollutants, act as abarrier to break the wind speed as well as allow the dust and other particulatesto settle on the leaves. It also helps to reduce the noise level at large extent.

EMP FOR NOISE

Construction Phase

To mitigate the impacts of noise from construction equipment during the constructionphase on the site, the following measures are recommended for implementation.

Noisy construction equipment would not be allowed to use at night time. Workers employed in high noise areas will be employed on shift basis. Hearing

protection such as earplugs/muffs will be provided to those working very closeto the noise generating machinery.

Page 42: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

63

Operation Phase

To mitigate the impacts of noise from diesel generator set during operational phase, thefollowing measures are recommended:

DG set will be housed in a suitable acoustic enclosure so that noise level at adistance of 1 m does not exceed 25 dB(A) as per CPCB standards or is meetingthe local standard (whichever is higher).

It would be ensured that the manufacturer provides acoustic enclosure as anintegral part along with the diesel generators set. Further, enclosure of theservices area with 4 m high wall will reduce noise levels and ensure that noise isat a permissible limit for residents and staff of the project and surroundingreceptors.

EMP FORWATER: Construction Phase

To prevent degradation and to maintain the quality of the water source, adequatecontrol measures needs to be adopted. The prime objective is to check the surface run-off as well as uncontrolled flow of water into any water body check dams with silt areas.The following management measures are suggested to protect the water source beingpolluted during the construction phase: Avoid excavation during monsoon season Care would be taken to avoid soil erosion Common toilets will be constructed on site during construction phase and the

waste water would be channelized to the septic tanks in order to prevent wastewater to enter into the water bodies

Any area with loose debris within the site shall be planted To prevent surface and ground water contamination by oil and grease, leak-proof

containers would be used for storage and transportation of oil and grease. Thefloors of oil and grease handling area would be kept effectively impervious. Anywash off from the oil and grease handling area or workshop shall be drainedthrough imperious drains

Page 43: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

64

All stacking and loading area will be provided with proper garland drains,equipped with baffles, to prevent run off from the site, to enter into any waterbody.

Operation Phase

In the operation phase of the project, water conservation and development measureswill be taken. Following measures will be adopted:

Minimizing water consumption. Promoting reuse of water after treatment and development of closed loop

systems for different water streams.Water Conservation

The water conservation is the need of the hour and consumption of fresh water will beminimized by combination of water saving devices and other domestic waterconservation measures. Further, to ensure ongoing water conservation, an awarenessprogram will be introduced for the residents and staff. The following section discussesthe specific measures, which shall be implemented:Domestic and Commercial Usage

Use of water efficient plumbing fixtures (low flow sinks, water efficientdishwashers and washing machines). Water efficient plumbing fixtures uses lesswater with no marked reduction in quality and service

Leak detection and repair techniques. Sweep with a broom and pan where possible, rather than hose down for external

areas.

Meter water usage: Implies measurement and verification methods. Monitoring of water uses is a precursor for management.Horticulture

Drip irrigation system shall be used for the lawns and other green area. Dripirrigation can save 15-40% of the water, compared with other wateringtechniques.

Plants with similar water requirements shall be grouped on common zones tomatch precipitation heads and emitters.

Use of low-angle sprinklers for lawn areas.

Page 44: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

65

Select controllers with adjustable watering schedules and moisture sensors toaccount for seasonal variations and calibrate them during commissioning.

Place 3 to 5 inches of mulch on planting beds to minimize evaporation.Storm Water Management

Most of the storm water produced on site will be harvested reuse by storing in aunderground water tank of suitable size. Thus proper management of water resource isa must to ensure that it is free from contamination.Contamination of Storm Water is possible from the following sources: Diesel and oil spills in the diesel power generator and fuel storage area Waste spills in the solid / hazardous waste storage area Oil spills and leaks in vehicle parking lots Silts from soil erosion in gardens Spillage of sludge from sludge drying area of sewage treatment plantStorm water management plan will incorporate best management practices which willinclude following: Regular inspection and cleaning of storm drains Clarifiers or oil/separators will be installed in all the parking areas. Oil / greaseseparators installed around parking areas and garages will be sized according to peakflow guidelines. Both clarifiers and oil/water separators will be periodically pumped inorder to keep discharges within limits Covered waste storage areas Avoid application of pesticides and herbicides before wet season Secondary containment and dykes in fuel/oil storage facilities Conducting routine inspection to ensure cleanliness Provision of slit traps in storm water drainsEMP FORWASTE: Construction Phase

The waste generated from construction activity includes construction debris, biomassfrom land clearing activities, waste from the temporary make shift labour hutments andhazardous waste. Following section discuss the management of each type of waste.

Page 45: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

66

Besides waste generation, management of the topsoil is an important area for whichmanagement measures are required.Construction Debris

Construction debris is bulky and heavy and re-utilization and recycling is an importantstrategy for management of such waste. As concrete and masonry constitute themajority of waste generated, recycling of this waste by conversion to aggregate can offerbenefits of reduced landfill space and reduced extraction of raw material for newconstruction activity. This is particularly applicable to the project site as theconstruction is to be completed in a phased manner.Metal scrap from structural steel, piping, concrete reinforcement and sheet metal workshall be removed from the site by construction contractors. A significant portion ofwood scrap will be reused on site. Recyclable wastes such as plastics, glass fiberinsulation, roofing etc shall be sold to recyclers.Hazardous waste

Construction sites are sources of many toxic substances such as paints, solvents woodpreservatives, pesticides, adhesives and sealants. Hazardous waste generated duringconstruction phase shall be stored in sealed containers and disposed off as per theHazardous and Other Wastes (Management and Transboundary Movement) Rules,2016.

Some management practices to be developed are: Herbicides and pesticide will not be over applied (small-scale applications) and

not applied prior to rain. Paintbrushes and equipment for water and oil based paints shall be cleaned

within a contained area and will not be allowed to contaminate site soils, watercourses or drainage systems.

Provision of adequate hazardous waste storage facilities. Hazardous wastecollection containers will be located as per safety norms and designatedhazardous waste storage areas will be away from storm drains or watercourses.

Segregation of potentially hazardous waste from non-hazardous constructionsite debris.

Page 46: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

67

Well labeled all hazardous waste containers with the waste being stored and thedate of generation.

Instruct employees and subcontractors in identification of hazardous and solidwaste.

Even with careful management, some of these substances are released into air,soil and water and many are hazardous to workers. With these reasons, the bestchoice is to avoid their use as much as possible by using low-toxicity substitutesand low VOC (Volatile Organic Compound) materials.

Waste from Labour Hutments

Wastes generated from temporary make shift labor hutments will mainly comprise ofhousehold domestic waste, which will be managed by the contractor of the site. Thewastewater generated will be channelized to the septic tank.Top Soil Management

To minimize disruption of soil and for conservation of top soil, the contractor shall keepthe top soil cover separately and stockpile it. After the construction activity is over, topsoil will be utilized for landscaping activity. Other measures, which would be followedto prevent soil erosion and contamination include: Maximize use of organic fertilizer for landscaping and green belt development. To prevent soil contamination by oil/grease, leak proof containers would beused for storage and transportation of oil/grease and wash off from the oil/greasehandling area shall be drained through impervious drains and treated appropriatelybefore disposal. Removal of as little vegetation as possible during the development and re-vegetation of bare areas after the project. Working in a small area at a point of time (phase wise construction). Construction of erosion prevention troughs/berms.Operational Phase

The philosophy of solid waste management at the proposed IT/ITES Project will be toencouraging the four R’s of waste i.e. Reduction, Reuse, Recycling and Recovery

(materials & energy). Regular public awareness meetings will be conducted to involvethe residents /staff in the proper segregation and storage techniques. The

Page 47: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

68

Environmental Management Plan for the solid waste focuses on three majorcomponents during the life cycle of the waste management system i.e., collection andtransportation, treatment or disposal and closure and post-closure care of

treatment/disposal facility.Collection and Transportation

Collection and Segregation of waste

1. A door to door collection system will be provided for collection of domestic waste incolored bins from household units.2. All household units shall segregate their wastes into dry, wet and hazardous wastes.Horticulture shall be handed over separately on call.3. The residents shall be made aware of E-waste and Biomedical wastes disposalsystems.

4. The residential society/ RWA shall tie up with an authorised Bio-medical wastecollection/ management center.5. The local vendors will be hired to provide separate colored bins for recyclables andBio-Degradable waste.6. For waste collection, adequate number of colored bins (Green and Blue & dark greybins– separate for Bio-degradable and Non Bio-degradable) are proposed to beprovided at the strategic locations of the area.7. Litter bin will also be provided in open areas.Treatment of waste

Bio-Degradable wastes1. Bio-degradable wastes will be composted and the compost will be used as manure.Organic Waste Composter will be installed for the purpose.2. STP sludge is proposed to be used for horticultural purposes as manure.3. Horticultural Waste is proposed to be composted and will be used for gardeningpurposes.

Recyclable wastesi. The cropped grass will be spread on the green area. It will act as manure afterdecomposition.

ii. Recyclable wastes like paper, plastic, metals, glass etc. will be sold off to recyclables.

Page 48: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

69

Figure 4: Waste Management Flow Diagram

Disposal

Recyclable and non-recyclable wastes will be disposed through Govt. approvedagency. Hence, the Municipal Solid Waste Management will be managed as per SolidWaste Management Rules, 2016. A Solid waste management Scheme is depicted inthe following figure for the project.EMP FOR ECOLOGY & BIODIVERSITY

Construction activity changes the natural environment. But the IT/ITES project alsocreates a built environment for its inhabitants. The project requires the implementationof following choices exclusively or in combination.

Construction Stage

Restriction of construction activities to defined project areas, which are ecologicallysensitive

Restrictions on location of temporary labor hutments and offices for project staffnear the project area to avoid human induced secondary additional impacts on the floraand fauna species

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

69

Figure 4: Waste Management Flow Diagram

Disposal

Recyclable and non-recyclable wastes will be disposed through Govt. approvedagency. Hence, the Municipal Solid Waste Management will be managed as per SolidWaste Management Rules, 2016. A Solid waste management Scheme is depicted inthe following figure for the project.EMP FOR ECOLOGY & BIODIVERSITY

Construction activity changes the natural environment. But the IT/ITES project alsocreates a built environment for its inhabitants. The project requires the implementationof following choices exclusively or in combination.

Construction Stage

Restriction of construction activities to defined project areas, which are ecologicallysensitive

Restrictions on location of temporary labor hutments and offices for project staffnear the project area to avoid human induced secondary additional impacts on the floraand fauna species

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

69

Figure 4: Waste Management Flow Diagram

Disposal

Recyclable and non-recyclable wastes will be disposed through Govt. approvedagency. Hence, the Municipal Solid Waste Management will be managed as per SolidWaste Management Rules, 2016. A Solid waste management Scheme is depicted inthe following figure for the project.EMP FOR ECOLOGY & BIODIVERSITY

Construction activity changes the natural environment. But the IT/ITES project alsocreates a built environment for its inhabitants. The project requires the implementationof following choices exclusively or in combination.

Construction Stage

Restriction of construction activities to defined project areas, which are ecologicallysensitive

Restrictions on location of temporary labor hutments and offices for project staffnear the project area to avoid human induced secondary additional impacts on the floraand fauna species

Page 49: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

70

Cutting, uprooting, coppicing of trees or small trees if present in and around theproject site for cooking, burning or heating purposes by the labors will be prohibitedand suitable alternatives for this purpose will be made Along with the construction work, the peripheral green belt would be developedwith suggested native plant species, as they will grow to a full-fledged covered at thetime of completion.Operation Stage

Improvement of the current ecology of the project site will entail the followingmeasures:

Plantation and Landscaping Green Belt Development Avenue PlantationThe section below summarizes the techniques to be applied to achieve the aboveobjectives:

Plantation and landscaping

Selection of the plant species would be done on the basis of their adaptability to theexisting geographical conditions and the vegetation composition of the forest type of theregion earlier found or currently observed. A total 800 nos. of trees will be plantedwithin project site.Green Belt Development Plan

The green belt will be developed as per the guidelines for developing green belt byCPCB, 2007. The plantation matrix adopted for the green belt development includes pitof 0.3 m × 0.3 m size with a spacing of 2 m x 2 m. In addition, earth filling and manuremay also be required for the proper nutritional balance and nourishment of the sapling.It is also recommended that the plantation has to be taken up randomly and thelandscaping aspects could be taken into consideration.Plantation comprising of medium height trees (7 m to 10 m) and shrubs (5 m height)are proposed for the green belt. In addition creepers will be planted along the boundarywall to enhance its insulation capacity.

Page 50: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

71

Plant Species for Green Belt Development

The selection of plant species for the development depends on various factors such asclimate, elevation and soil. The plants would exhibit the following desirablecharacteristics in order to be selected for plantation1. The species should be fast growing and providing optimum penetrability.2. The species should be wind-firm and deep rooted.3. The species should form a dense canopy.4. As far as possible, the species should be indigenous and locally available.5. Species tolerance to air pollutants like SO2 and NO2 should be preferred.6. The species should be permeable to help create air turbulence and mixing within

the belt.7. There should be no large gaps for the air to spill through.8. Trees with high foliage density, leaves with larger leaf area and hairy on both the

surfaces.

9. Ability to withstand conditions like inundation and drought.10. Soil improving plants (Nitrogen fixing rapidly decomposable leaf litter).11. Attractive appearance with good flowering and fruit bearing.12. Bird and insect attracting tree species.13. Sustainable green cover with minimal maintenance.Avenue Plantation

Gardens maintained for recreational and ornamental purposes will not onlyimprove the quality of existing ecology at the project site but also will improvethe aesthetic value.

Avenue Plantation Trees with colonial canopy with attractive flowering. Trees with branching at 7 feet and above. Trees with medium spreading branches to avoid obstruction to the traffic. Fruit trees to be avoided because children may obstruct traffic and general

movement of public.

Page 51: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

72

EMP for Socio-Economic conditions

The social management plan has been designed to take proactive steps and adopt bestpractices, which are sensitive to the socio-cultural setting of the area. The SocialManagement Plan for proposed IT/ITES project focuses on the following components:Income Generation Opportunity during Construction and Operation Phase

The Proposed IT/ITES project would provide employment opportunity duringconstruction and operation phase. There would also be a wide economic impact interms of generating opportunities for secondary occupation within and around theproposed IT/ITES Project. The main principles considered for employment and incomegeneration opportunities are out lined below: Employment strategy will provide for preferential employment of local people Conditions of employment would address issues like minimum wages and medicalcare for the workers. Contractors would be required to abide to employment prioritytowards locals and abide by the labor laws regarding standards on employee terms andconditions.

Improved Working Environment for Employees

The Proposed IT/ITES project would provide safe and improved working conditions forthe workers employed at the facility during construction and operation phase. With theproposed ambience and facilities provided, the proposed IT/ITES project will provide anew experience in living, work environment, seem less data transfer, edge cuttingtechnologies etc. Following measures would be taken to improve the workingenvironment of the area: Less use of chemicals and biological agents with hazard potential Developing a proper interface between the work and the human resource through a

system of skill improvement Provision of facilities for nature care and recreation e.g. indoor games facilities Measures to reduce the incidence of work related injuries, fatalities and diseases Maintenance and beautifications of the complex and the surrounding roads.Apart from this the company will organize a need based corporate social responsibilityprogramme fulfilling its obligation of companies act 2013.

Page 52: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

73

EMP FOR ENERGY CONSERVATION

Energy conservation program will be implemented through measures taken both onenergy demand and supply.

Figure 5: Energy Conservation measures

Energy conservation will be one of the main focuses during the proposed IT/ITES

project planning and operation stages. The conservation efforts would consist of thefollowing:

Architectural design

Maximum utilization of solar light will be done. Provision of 100% solar lightingalong the road side, stair cases, common places. Approx 15% - 20% of the totalpower requirement will be met by solar power.

Maximize the use of natural lighting through design. The orientation of the buildings will be done in such a way that maximum daylight is

available.

The green areas will be spaced, so that a significant reduction in the temperaturecan take place.

Energy Saving Practices

Energy efficient lamps will be provided within the proposed IT/ITES project. Constant monitoring of energy consumption and defining targets for energy

conservation.

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

73

EMP FOR ENERGY CONSERVATION

Energy conservation program will be implemented through measures taken both onenergy demand and supply.

Figure 5: Energy Conservation measures

Energy conservation will be one of the main focuses during the proposed IT/ITES

project planning and operation stages. The conservation efforts would consist of thefollowing:

Architectural design

Maximum utilization of solar light will be done. Provision of 100% solar lightingalong the road side, stair cases, common places. Approx 15% - 20% of the totalpower requirement will be met by solar power.

Maximize the use of natural lighting through design. The orientation of the buildings will be done in such a way that maximum daylight is

available.

The green areas will be spaced, so that a significant reduction in the temperaturecan take place.

Energy Saving Practices

Energy efficient lamps will be provided within the proposed IT/ITES project. Constant monitoring of energy consumption and defining targets for energy

conservation.

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

73

EMP FOR ENERGY CONSERVATION

Energy conservation program will be implemented through measures taken both onenergy demand and supply.

Figure 5: Energy Conservation measures

Energy conservation will be one of the main focuses during the proposed IT/ITES

project planning and operation stages. The conservation efforts would consist of thefollowing:

Architectural design

Maximum utilization of solar light will be done. Provision of 100% solar lightingalong the road side, stair cases, common places. Approx 15% - 20% of the totalpower requirement will be met by solar power.

Maximize the use of natural lighting through design. The orientation of the buildings will be done in such a way that maximum daylight is

available.

The green areas will be spaced, so that a significant reduction in the temperaturecan take place.

Energy Saving Practices

Energy efficient lamps will be provided within the proposed IT/ITES project. Constant monitoring of energy consumption and defining targets for energy

conservation.

Page 53: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

74

Adjusting the settings and illumination levels to ensure minimum energy used fordesired comfort levels.

Behavioral Change on Consumption

Promoting resident, staff, and neighbor’s awareness on energy conservation Training staff on methods of energy conservation and to be vigilant to such

opportunities.

The summary of management measures and responsibility is given at Table 18.ENVIRONMENTAL MANAGEMENT SYSTEM AND MONITORING PLAN

For the effective and consistent functioning of the complex, an Environmental

Management system (EMS) would be established at the site. The EMS would include thefollowing:

Environmental management cell. Environmental Monitoring. Personnel Training. Regular Environmental audits and Correction measures. Documentation – standards operation procedures Environmental Management Plan

and other records.ENVIRONMENTAL MANAGEMENT CELL

Apart from having an Environmental Management Plan, it is also proposed to have apermanent organizational set up charged with the task of ensuring its effectiveimplementation of mitigation measures and to conduct environmental monitoring. Themajor duties and responsibilities of Environmental Management Cell shall be as givenbelow:

To implement the environmental management plan. To assure regulatory compliance with all relevant rules and regulations. To ensure regular operation and maintenance of pollution control devices. To minimize environmental impact of operations as by strict adherence to the EMP. To initiate environmental monitoring as per approved schedule.

Page 54: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

75

Review and interpretation of monitored results and corrective measures in casemonitored results are above the specified limit.

Maintain documentation of good environmental practices and applicable

environmental laws for a ready reference. Maintain environmental related records. Coordination with regulatory agencies, external consultants, monitoring

laboratories.

Maintenance of log of public complaints and the action taken.Structure of Environmental Management Cell

Normal activities of the EMP cell would be supervised by a dedicated person who willreport to the site manager/coordinator of the proposed IT/ITES Project. Thehierarchical structure of suggested Environmental Management Cell is given infollowing Figure 7.

Figure 6: Environnent Management Cell Structure

SiteManager

CorporateEnvironmental

Division

Rep fromCorporate

Planning group

SiteEnvironmental

Coordinator

Landscape Dev.Incharge

Sewage & effluentTreatment Plant

Operator

Page 55: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

76

Table 18: SUMMARY OF MANAGEMENT MEASURES AND RESPONSIBILITY

S. No. Environmental

Issues

Potential Impacts

(Direct/ Indirect)

Potential

Source of

Impact

Management

Measures

Responsibility

Execution/ Civil Work Supervision

1. Ground Water

Quality

Ground Water

Contamination

Construction

Phase

Waste water

generated

from

temporary

labor

hutments.

No surface

accumulation will

be allowed.Contractor Project Proponent

(SHE division)

Operation Phase Discharge

from the

project

The sewage will bedischarged to themunicipal sewerafter priorpermission

RWA Project Proponent

(SHE division)

2. Ground Water Ground Water Construction Not Applicable None Not applicable

Page 56: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

77

Quantity Depletion Phase

Ground

water will

not use

during

construction

phase.

Operation Phase The source

of water

during

operation

phase is

Municipal

Supply and

ground

water

recharge is

Black and Greywater treatment

and reuse. Rainwater willbe used to storageand reuse. Awareness

Campaign to

reduce the waterconsumption.

RWA Project Proponent

(SHE division)

Page 57: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

78

not

proposed.

3. Surface Water

Quality

Surface water

contamination

Construction

Phase

Surface runofffrom site

during

construction

activity.

Silt traps andother measures

such as additionalonsite diversion

ditches will be

constructed to

control surface

run-off during sitedevelopment

Contractor Project Proponent

(SHE division)

Operation Phase Discharge of

domestic

wastewater

STP of

capacity 800

KLD

Domestic waterwill be treated intoSTP of capacity 800KLD

RWA Project Proponent

(SHE division)

Page 58: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

79

4. Air Quality Dust Emissions Construction

Phase

All heavy

construction

activities

Regular

sprinkling

Covered

transportation of

construction

material

Covered storage

of loose materialArrangement of

wheel washCovering of

project site with GIsheets

Contractor Project Proponent

(SHE division)

Emissions of PM,SO2, NO2 and CO Construction

Phase

Rapid on-site

construction and

Contractor Project Proponent

(SHE division)

Page 59: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

80

Operation ofconstruction

equipment

and vehiclesduring site

development.

Running D.G.

set (back up)

improved

maintenance of

equipment.

Operation Phase Power

generation byDG Set duringpower failure

Emission

from

vehicular

traffic in use

Use of low

sulphur diesel ifavailable

Providing

Footpath and

pedestrian ways

within the site forthe residents andstaff.

Green belt will be

RWA Project Proponent

(SHE division)

Page 60: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

81

developed with

specific species tohelp to reduce

pollution levelUse of equipmentfitted with

silencers

Proper

maintenance of

equipment.

5. Noise

Environment

Operation

Phase

Noise from

vehicular

movement

Green Belt

Development

Development of

silence zones to

check the traffic

movement

RWA Project Proponent

(SHE division)

Page 61: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

82

Noise from

DG set

operation

Provision of

noise shields

near the heavy

construction

operations and

acoustic

enclosures for DGset.

Construction

activity is limitedto day time hoursonly

DG set

room will be

equipped with

acoustic

enclosures

6. Land Soil Construction Construction Contractor Project Proponent

Page 62: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

83

Environment contamination Phase

Disposal of

construction

debris

debris will becollected and

suitably used

on site as perthe solid wastemanagement

plan for

construction

phase.

(SHE division)

Operation

Phase

Generation

of municipalsolid waste

Used oil

generated

from D.G.

set

It is proposed

that the solid

waste generated

will be managed asper Solid Waste

Management

Rules, 2016. Collection,

segregation,

RWA Project Proponent

(SHE division)

Page 63: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

84

transportation anddisposal will be

done as per SolidWaste

Management

Rules, 2016 by theauthorized agency

and Bio Medical

Waste

Management

Rules, 2016.

Used oil

generated will besold to authorizedrecyclers

7. Biological

Environment

(Flora and

Displacement of

Flora and Faunaon site

Construction

Phase

Site

Important

species of trees, ifany, will be

Contractor Project Proponent

(SHE division)

Page 64: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

85

Fauna) Development during

construction

identified and

marked and will

be merged with

landscape plan.Operation

Phase

Increase in

green

covered area

Suitable green

belts will be

developed as perlandscaping planin and around thesite using local

flora

RWA Project Proponent

(SHE division)

8. Socio-

Economic

Environment

Population

displacement andloss of income

Construction

Phase

Construction

activities

leading to

relocation

It is as perMaster Plan, of

Greater Noida

Development

Authority 2021.

Contractor Project Proponent

(SHE division)

Page 65: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

86

Operation

Phase

Site

operation

Project

Proponent will

provide

employment

opportunities to

the local people interms of labor

during

construction and

service personnel

(guards, securities,gardeners etc)

during operations Providing

quality-Integrated

infrastructure.

RWA Project Proponent

(SHE division)

9. Traffic Pattern Increase of

vehicular traffic Construction

Phase

Heavy Vehicular

movement will be Contractor Project Proponent

(SHE division)

Page 66: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES Project

8(b)Project Proponent Balaji IT Parks Pvt. Ltd.

Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

87

Heavy

Vehicular

movement

during

construction

restricted to

daytime only andadequate parking

facility will be

provided.

Operation

Phase

Traffic due

to residentsand staff

once the

project is

operational

Vehicular

movement will beregulated inside

the project with

adequate roads

and parking lots inthe project.

RWA Project Proponent

(SHE division)

Page 67: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES project “WTC NoidaCampus”

8(b)Project Proponent M/s Balaji IT Parks Pvt. Ltd.Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

88

ENVIRONMENTAL MONITORING

The purpose of environmental monitoring is to evaluate the effectiveness of implementationof Environmental Management Plan (EMP) by periodic monitoring. The importantenvironmental parameters within the impact area are selected so that any adverse effectsare detected and time action can be taken. The project proponent will monitor ambient airQuality, Ground Water Quality and Quantity, and Soil Quality in accordance with anapproved monitoring schedule.

Table 19: Environmental Monitoring Plan – Construction Phase

Source Monitoring Location Parameters to be

Monitored

Frequency

Ambient AirQuality

At 1 location atboundary of the projectsite.

PM2.5, PM10, SO2,NO2,CO

Once in a season April toSeptember and once inthe season October toMarch.

Ambient

Noise

At 1 location atboundary of the projectsite.

Day and nightequivalent noise level

Once in a season April toSeptember and once inthe season October toMarch.

Ground water At 1 location nearest tothe project site. As per standards Once in a season April to

September and once inthe season October toMarch.

SoilAt 1 location outside theproject site. As per standards Once in a season April to

September and once inthe season October toMarch.

Page 68: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES project “WTC NoidaCampus”

8(b)Project Proponent M/s Balaji IT Parks Pvt. Ltd.Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

89

Table 20: Environmental Monitoring Plan – Operation Phase

Source Monitoring Location Parameters to be

Monitored

Frequency

DG setemissions

DG stacks PM, SO2, NO2 Twice in a year or as perrequirement of SPCB

DG set noise At 0.5 m distance fromenclosure

Noise level Twice in a year or as perrequirement of SPCB

STP/ ETP Inlet and Outlet pH, BOD, SuspendedSolid, Oil & Grease Twice in a year or as per

requirement of SPCBAmbient AirQuality

At 3 locations PM2.5, PM10, SO2,NO2,CO

Once in each non-monsoon season or as perrequirement of SPCB

Ambient

NoiseAt 3 locations Day and night

equivalent noise level Once in a season or as perrequirement of SPCB

Ground water At 1 location nearest tothe project site. As per standards Once in a season or as per

requirement of SPCBAwareness and Training

Training and human resource development is an important link to achieve sustainableoperation of the facility and environment management. For successful functioning of theproject, relevant EMP would be communicated to:Staff/Residents and Contractors

Staff/residents must be made aware of the importance of waste segregation and disposal,water and energy conservation. The awareness can be provided by periodic IntegratedSociety meetings. They would be informed of their duties.

Page 69: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES project “WTC NoidaCampus”

8(b)Project Proponent M/s Balaji IT Parks Pvt. Ltd.Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

90

Environmental Audits and Corrective Action Plans

To assess whether the implemented EMP is adequate, periodic environmental audits will beconducted by the project proponent’s Environmental division. These audits will be followedby Correction Action Plan (CAP) to correct various issues identified during the audits.Fire & Safety Management

Fire Fighting Designed: As per National Building Code (NBC) 2005. As per the NBC / Local norms the present risk is falling under “LIGHT HAZARD”. Provision of Automatic water sprinklers. Provision of separate fire hydrant pipe. Provision of Overhead water storage tank. There is provision of firefighting pumps. Optical type smoke detectors shall be used in most areas. Rate of rise heat detectors shall be planned for all potentially smoky areas and in the

basements.

DETAILS OF ENERGY CONSERVATION MEASURES

Passive Solar designs refer to the use of Sun’s energy for the heating and cooling ofliving spaces.

The orientation of the building will be done in such a way that maximum daylight isavailable.

The orientation of the building would be done in such a manner that most of glazedareas in north and east.

Landscape and green areas will be so spaced so as to cool the surroundingenvironment, which will reduce energy consumption.

Public areas will be cooled by natural ventilation as opposed to air conditioning. Lesser opening will be provided on the west facing walls. Green area at the site will be maintained by the project proponents, which would

have an overall cooling effect on the surroundings. Feasibility for installation of solar photovoltaic cells for street lighting will be assessed.

Page 70: Project Name Environment Clearance for IT-ITES Project 8(b)environmentclearance.nic.in/writereaddata/Online/... · 2017-06-05 · Project Name Environment Clearance for IT-ITES Project

Project Name Environment Clearance for IT-ITES project “WTC NoidaCampus”

8(b)Project Proponent M/s Balaji IT Parks Pvt. Ltd.Project Address Plot no. 13-B, Techzone, Greater Noida, Uttar Pradesh

EnvironmentConsultant

Aplinka Solutions & Technologies Pvt. Ltd, Noida UttarPradesh

91

Use of LED`s & CFL lamps instead of GLS lamps for Flats. Use of LED`s & CFL lamps instead of GLS lamps for Common area Lights. Use of T5 lamps instead of Normal Fluorescent lamps in Basements. Use of Solar backed LED landscape lights instead of par lamps. Using electronic ballast for Discharge Lamps. Energy Saving due to use of High Grade CRGO Core transformer.