1  Form-I for seeking clearance for project attracting CRZ notification Basic information Name of the Project Resort project at VarachaPatta, Guhagar, Ratanagiri. Location or site alternatives under consideration S. no. 53/1,55/1 at VarachaPatta, Guhagar, Ratanagiri. Latitude 17°29'39.41"N Longitude 73°11'17.62"E Location Map is enclosed as Annexure-I Size of the project (in terms of total area) Total plot area is 4070 m 2 CRZ classification of the area CRZ-III CRZ Map is enclosed as Annexure-II Expected cost of the project Rs. 2,00,00,000 / - Contact Information Mr.Suhas M. Ponkshe/MrNitin M Ponkshe ShriArihant co-op HsgSoc, Plot no. 23, Flat no. B105, Sector 16A, VASHI – 400703 Maharashtra Near State Board building Mob:9867612678 Email: [email protected] (II) Activity 1. Construction, operation or decommissioning of the Project involving actions, which will cause Physical changes in the locality (topography, land use, changes in water bodies, and the like) Sr.no. Information/Checklist confirmation Yes/No Details thereof (withapproximate quantities /rates,wherever possible) with sourceof information data 1.1 Permanent or temporary change in land use,land cover or topography including increase inintensity of land use. No There is no permanent or temporary change in land use, land cover or topography. 1.2 Details of CRZ classification as per theapproved Coastal Zone Management Plan? CRZ-III As per the CRZ map prepared by NCSCM, Chennai, the proposed project activity comes under CRZ-III category. 1.3 Whether located in CRZ-I area? No -

Upload: others

Post on 10-Mar-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Form-I for seeking clearance for project attracting …environmentclearance.nic.in/writereaddata/online/EC/...1 Form-I for seeking clearance for project attracting CRZ notification

1  

Form-I for seeking clearance for project attracting CRZ notification

Basic information

Name of the Project Resort project at VarachaPatta, Guhagar, Ratanagiri.

Location or site alternatives under

consideration

S. no. 53/1,55/1 at VarachaPatta, Guhagar, Ratanagiri.

Latitude 17°29'39.41"N

Longitude 73°11'17.62"E

Location Map is enclosed as Annexure-I

Size of the project (in terms of total area) Total plot area is 4070 m2

CRZ classification of the area CRZ-III

CRZ Map is enclosed as Annexure-II

Expected cost of the project Rs. 2,00,00,000 / -

Contact Information

Mr.Suhas M. Ponkshe/MrNitin M Ponkshe

ShriArihant co-op HsgSoc, Plot no. 23, Flat no. B105,

Sector 16A, VASHI – 400703 Maharashtra

Near State Board building

Mob:9867612678

Email: [email protected]

(II) Activity

1. Construction, operation or decommissioning of the Project involving actions, which will cause

Physical changes in the locality (topography, land use, changes in water bodies, and the like)

Sr.no. Information/Checklist

confirmation Yes/No

Details thereof (withapproximate quantities

/rates,wherever possible) with sourceof

information data

1.1

Permanent or temporary change

in land use,land cover or

topography including increase

inintensity of land use.

No There is no permanent or temporary change in land

use, land cover or topography.

1.2

Details of CRZ classification as

per theapproved Coastal Zone

Management Plan?

CRZ-III

As per the CRZ map prepared by NCSCM,

Chennai, the proposed project activity comes

under CRZ-III category.

1.3 Whether located in CRZ-I area? No -

Page 2: Form-I for seeking clearance for project attracting …environmentclearance.nic.in/writereaddata/online/EC/...1 Form-I for seeking clearance for project attracting CRZ notification

2  

1.4 The distance from the CRZ-I

areas. No

Development activities are proposed beyond NDZ

i.e. 200 m from high tide line.

1.5

Whether located within the

hazard zone as mapped by

Ministry of Environment and

Forests/National Disaster

ManagementAuthority?

No -

1.6

Whether the area is prone to

cyclone, tsunami, tidal surge,

subduction, earthquake etc.?

No None

1.7 Whether the area is prone for

saltwateringress? No -

1.8 Clearance of existing land,

vegetation and buildings? No -

1.9 Creation of new land uses? No Open land will be developed for tourism which is

in accordance with local development rules.

1.10 Pre-construction investigations

e.g. bore hole, soil testing? Yes

Geotechnicalinvestigation will be conducted for

the proposed project site.

1.11 Construction works? Yes

S.

No

Project Component Area

in m2

1 COTTAGE 546.84

2 SUITES 149.24

3 ADMIN 39.49

4 CLUB HOUSE 40.56

Tota

l

762.50

1.12 Demolition works? No --

1.13

Temporary sites used for

construction works or housing of

construction workers?

No --

Page 3: Form-I for seeking clearance for project attracting …environmentclearance.nic.in/writereaddata/online/EC/...1 Form-I for seeking clearance for project attracting CRZ notification

3  

1.14

Above ground buildings,

structures orearthworks including

linear structures, cut and fill or

excavations

Yes

Nearly leveled ground, cutting filling nearly

balances, top-soil used for greening, excavation in

the form of rubble will be partly used for back-

filing and as sub-structure for roads.

1.15 Underground works including

mining ortunneling? No None

1.16 Reclamation works? No --

1.17

Dredging/reclamation/land

filling/disposal of dredged

material etc.?

No --

1.18 Offshore structures? No --

1.19 Production and manufacturing

processes? No --

1.20 Facilities for storage of goods or

materials? No Storage facilities are not envisaged

1.21 Facilities for treatment or disposal

of solid waste or liquid effluents? Yes

STP for treatment of sewage during the operation

phase.

Segregation of solid waste into non-biodegradable

and biodegradable waste in the construction and

the operational phase.

Biodegradable waste will be treated in an OWC

during the operational phase.

Segregation of Non-biodegradable waste into

recyclable & non-recyclable during operational

phase.

Recyclable waste: Will be handed over to the

recyclers

Non-Recyclable waste: Will be handed over to the

local authorized vendors during the operational

phase.

Dried sludge from STP: Will be used as manure

after treatment during operational phase.

1.22 Facilities for long term housing of Yes Existing staff quarters available

Page 4: Form-I for seeking clearance for project attracting …environmentclearance.nic.in/writereaddata/online/EC/...1 Form-I for seeking clearance for project attracting CRZ notification

4  

operational workers?

1.23 New road, rail or sea traffic

during construction or operation? No

During construction and operationstage the existing

facilities will be used.

1.24

New road, rail, air waterborne or

othertransport infrastructure

including new oraltered routes

and stations, ports, airports etc?

No --

1.25

Closure or diversion of existing

transportroutes or infrastructure

leading to changes intraffic

movements?

No No closure or diversion of existing transport routes

or infrastructure.

1.26 New or diverted transmission

lines orpipelines? No --

1.27

Impoundment, damming,

culverting,realignment or other

changes to the hydrologyof

watercourses or aquifers?

No --

1.28 Stream and river crossings? No --

1.29 Abstraction or transfers of water

form groundor surface waters? No Nil

1.30

Changes in water bodies or the

land surfaceaffecting drainage or

run-off?

No Nil

1.31

Transport of personnel or

materials forconstruction,

operation, decommissioning?

Yes Labours will be transported to site during

construction period only.

1.32

Long-term dismantling or

decommissioning, restoration

works?

No Nil

1.33

Ongoing activity during

decommissioningwhich could

have an impact on

theEnvironment?

No Nil

Page 5: Form-I for seeking clearance for project attracting …environmentclearance.nic.in/writereaddata/online/EC/...1 Form-I for seeking clearance for project attracting CRZ notification

5  

1.34

Influx of people to an area in

either temporarily or

permanently?

No

During Construction Phase:

Maximum 20 workers during construction.

During Operation Phase:

There will be an influx of approx. 60-80people in

the proposed project which comprises of the

visitors.

1.35 Introduction of alien species? No None.

1.36 Loss of native species or genetic

diversity? No Proposed area is not in an eco-sensitive area

1.37 Any other actions? No None

2. Use of Natural resources for construction or operation of the Project (such as land, water,materials or

energy, especially any resources which are non-renewable or in short supply):

Sr. No. Information/ checklist

confirmation

Yes/

No

Details thereof (withapproximate quantities

/rates, wherever possible) with source of

information data

2.1 Land especially undeveloped or

agriculturalland (ha)

No Proposed development is in the existing land under

development.

2.2 Water (expected source &

competing users) unit: KLD

Yes During Construction Phase:

From water tankers(for construction): 5 m3/day

For Workers :Water of potable quality from tankers:

2.25 m3/day

During operational Phase:

Source of water: Local Authority

Domestic: 5 m3/day

Flushing: 3 m3/day

Gardening(Recycled water):2 m3/day

2.3 Minerals (MT) No --

2.4 Construction material – stone,

aggregates, sand/soil (expected

source – MT)

Materials like sand, gravel, cement will be procured

from nearby licensedsources/ reputed manufacturers

as per requirement.

2.5 Forests and timber (source – MT) Yes Timber required for doors sourced from local

suppliers.

Page 6: Form-I for seeking clearance for project attracting …environmentclearance.nic.in/writereaddata/online/EC/...1 Form-I for seeking clearance for project attracting CRZ notification

6  

2.6 Energy including electricity and

fuels (source, competing users)

Unit: fuel (MT), energy (MW)

Yes Source:MSEDCL

During Operation phase-

Connected load :105KW

Maximum demand:84.48

DG Sets: 1 DG set of 100kVA

2.7 Any other natural resources (use

appropriate standard units)

No Nil

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to

human health or the environment or raise concerns about actual or perceived risks to human health.

Sr

No.

Information/checklist

confirmation

Yes/

No

Details thereof (withapproximate quantities

/rates,wherever possible) with source of

information data

3.1 Use of substances or materials,

which are hazardous (as per

MSIHC rules) to human health or

the environment (flora, fauna, and

water supplies)

Yes Minor quantities of empty paint cans andwaste oil

will be generated during construction phase.

3.2 Changes in occurrence of disease

or affect disease vectors (e.g.

insect or water borne diseases)

No None

3.3 Affect the welfare of people e.g.

by changing living conditions?

No

3.4 Vulnerable groups of people who

could be affected by the project

e.g. hospital patients, children, the

elderly etc.,

No None

3.5 Any other causes, that would

affect local communities, fisher

folk, their livelihood, dwelling

units of traditional local

communities etc

No None

Page 7: Form-I for seeking clearance for project attracting …environmentclearance.nic.in/writereaddata/online/EC/...1 Form-I for seeking clearance for project attracting CRZ notification

7  

4. Production of solid wastes during construction or operation or decommissioning (MT/month)

Sr

No.

Information/checklist

confirmation

Yes/

No

Details thereof (withapproximate quantities

/rates,wherever possible) with sourceof

information data.

4.1 Spoil, overburden or mine wastes No --

4.2 Municipal waste (domestic and or

commercial wastes)

Yes

Type Nos.

Solid Waste generation (kg/day)

Biodegra

dable

Non

DegradableTotal

Guest59 19 8 27

Staff

4.3 Hazardous wastes (as per

Hazardous Waste Management

Rules)

No Minor quantities of empty paint cans and waste oil

will be generated during construction phase, which

will be sent to authorize contactor.

4.4 Other industrial process wastes No Nil

4.5 Surplus product No Nil

4.6 Sewage sludge or other sludge

from effluent treatment

Yes Dried sludge from STP will be used as manure for

landscaping.

4.7 Construction or demolition

wastes

Yes Solid waste generation during construction phase is

mainly due to excavation in the form of rubble and

soil. Part of this soil and rubble will be used for

back filling and remaining material will be disposed

by covered trucks to the authorized sites if required.

4.8 Redundant machinery or

equipment

No Nil

4.9 Contaminated soils or other

materials

No Nil

4.10 Agricultural wastes No Nil

4.11 Other solid wastes No Nil

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)

Sr No. Information/checklist

confirmation

Yes/

No

Details thereof (withapproximate quantities

/rates,wherever possible) with source

Page 8: Form-I for seeking clearance for project attracting …environmentclearance.nic.in/writereaddata/online/EC/...1 Form-I for seeking clearance for project attracting CRZ notification

8  

of information data

5.1 Emissions from combustion of

fossil fuels from

stationary or mobile sources

Yes Operation of Diesel generators and Construction

machineries may cause emission of SO2, NOx and

CO which will be monitored periodically and to

lower the point source emissions.

5.2 Emissions from production

processes

No --

5.3 Emissions from materials

handling includingstorage or

transport Emissions from

materials handling

includingstorage or transport

No The project may cause rise in dust levels during

construction

phase.Watersprinklingwillbedoneatregularintervalst

oreducecontrolofdustgeneration.

5.4 Emissions from construction

activities includingplant and

equipment

No No major Plant and Equipment source at site.

5.5 Dust or odours from handling of

materialsincluding construction

materials, sewage and waste

No Dust generation will be controlled as described

above at serial no 5.3. Proper ventilation will be

provided around STP and solid waste management

facilities for odour control.

5.6 Emissions from incineration of

waste

No --

5.7 Emissions from burning of waste

in open air (e.g.slash materials,

construction debris)

No --

5.8 Emissions from any other sources No --

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

Sr.

No.

Information/checklist

confirmation

Yes/

No

Details thereof (withapproximate quantities

/rates,wherever possible) with sourceof

information data

Page 9: Form-I for seeking clearance for project attracting …environmentclearance.nic.in/writereaddata/online/EC/...1 Form-I for seeking clearance for project attracting CRZ notification

9  

6.1 From operation of equipment e.g.

engines,ventilation plant, crushers

Yes For control of noise following measures shall be

adopted:

Regular noise monitoring to be scheduled to

maintain the noise level within the levels

prescribed by CPCB during day and night time

Provision of ear plugs to workers

Use of good efficiency mufflers

Regular maintenance of noise generating

machinery

No noise polluting work in night shifts

6.2 From industrial or similar

processes

No --

6.3 From construction or demolition Yes Noise from the machineries shall be kept below the

threshold noise level. Personnel Protection

Equipment (PPE) will be provided to workers

during construction activities.

6.4 From blasting or piling No

6.5 From construction or operational

traffic

Yes During Construction phase:

Proper traffic management for the construction

vehicles

Regular maintenance of vehicles with suitable

enclosures and intake silencers

Planning and ensuring effective implementation of

the waste movement plan for loading and offsite

movement in non-traffic hours.

During Operation Phase :

Install traffic control measures to regulate the flow

of traffic

Assign traffic wardens to regulate flow of project

traffic during peak hours

6.6 From lighting or cooling systems No --

6.7 From any other sources No --

Page 10: Form-I for seeking clearance for project attracting …environmentclearance.nic.in/writereaddata/online/EC/...1 Form-I for seeking clearance for project attracting CRZ notification

10  

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers,

surface waters, groundwater, coastal waters or the sea:

Sr

No.

Information/checklist

confirmation

Yes/

No

Details thereof (withapproximate quantities

/rates,wherever possible) with sourceof

information data

7.1 From handling, storage, use or

spillage ofhazardous materials

No During construction stage there may be

storage/handling of hazardous materials for various

construction related activities.

Such materials shall be stored and handled as per

the provisions of the manufacturer, storage and

import of Hazardous Chemical Rules, Hazardous

Wastes (Management and Handling)

Rules and Amendments thereof.

7.2 From discharge of sewage or

other effluents towater or the land

(expected mode and place

ofdischarge)

No During Construction Phase:

Mobile sanitary toilets will be installed and toilets

will be regularly maintained by Authorized Vendor

During Operation Phase:

The treated sewage will be reused for flushing and

gardening within the premises. Excess treated

sewage will be disposed off to the existing sewer

line.

7.3 By deposition of pollutants

emitted to air into theland or into

water

No Dust will be generated during construction phase

from earthworks and movement of vehicles.

Appropriate fugitive dust control measures,

including watering, water sprinkling of exposed

areas and dust covers for trucks, will be provided

to minimize any impacts.

DG exhaust will be discharged at stipulated height

by providing adequate stack height to the DG sets

7.4 From any other sources No Nil

7.5 Is there a risk of long term build

up of pollutants in the

environment from these sources?

No Nil

Page 11: Form-I for seeking clearance for project attracting …environmentclearance.nic.in/writereaddata/online/EC/...1 Form-I for seeking clearance for project attracting CRZ notification

11  

8. Risk of accidents during construction or operation of the Project, which could affect human health or

the environment.

Sr

No.

Information/checklist

confirmation

Yes/

No

Details thereof (withapproximate quantities

/rates,wherever possible) with sourceof

information data

8.1 From explosions, spillages, fires

etc from storage,handling, use or

production of

hazardoussubstances.

No --

8.2 From any other causes

No --

8.3 Could the project be affected by

natural disasterscausing

environmental damage (e.g.,

floods, Earthquakes, landslides,

cloudburst etc)?

No The proposed construction is made to withstand the

most adverse conditions.

9. Factors which should be considered (such as consequential development) which could lead

toEnvironmental effects or the potential for cumulative impacts with other existing or planned activities in

the locality.

Sr

No.

Information/checklist

confirmation

Yes/

No

Details thereof (withapproximate quantities

/rates,wherever possible) with sourceof

information data

9.1 Lead to development of

supporting utilities, ancillary

development or development

stimulated by the project which

could have impact on the

environment e.g.:

Supporting infrastructure

(roads, power supply, waste or

waste water treatment, etc.)

No

Supporting infrastructure is already in existence.

Page 12: Form-I for seeking clearance for project attracting …environmentclearance.nic.in/writereaddata/online/EC/...1 Form-I for seeking clearance for project attracting CRZ notification

12  

housing development

extractive industries supply

industries

other housing development

extractive industries supply

industries other

9.2 Lead to after-use of the site,

which could have an impact on

the environment

No The proposed project would be a permanent

establishment.

9.3 Set a precedent for later

developments

Yes Will create job opportunity in construction phase

and operation phase for support staff like security,

maintenance, household workers, shop keepers etc.

9.4 Have cumulative effects due to

proximity to other existing or

planned projects with similar

effects

No

III. Environmental Sensitivity

Sr.no

Areas

Name/

Identity Aerial distance (within 15 km)Proposed project locationboundary

1 Areas protected under international

conventions, national or local

legislation for their ecological,

landscape, cultural or other related

value

No -

2 Areas which are important or sensitive

for ecological reasons - Wetlands,

water courses or other water bodies,

coastal zone, biospheres, mountains,

forests

Yes Guhagar beach at 0.50 km to the West

3 Areas used by protected, important or

sensitive species of flora or fauna for

breeding, nesting, foraging, resting,

No -

Page 13: Form-I for seeking clearance for project attracting …environmentclearance.nic.in/writereaddata/online/EC/...1 Form-I for seeking clearance for project attracting CRZ notification

13  

over wintering, migration

4 Inland, coastal, marine or underground

waters

Yes Arabian Sea is at 0.50km to the West

5 State, National boundaries No -

6 Routes or facilities used by the public

for access to recreation or other tourist,

pilgrim areas

No -

7 Defense installations No

8 Densely populated or built-up area No

9 Areas occupied by sensitive man-made

land uses (hospitals, schools, places of

worship, communityfacilities) Areas

occupied by sensitive man-made land

uses(hospitals, schools, places of

worship, community facilities)

No -

10 Areas containing important, high

quality or scarce resources (ground

water resources, surface resources,

forestry, agriculture, fisheries, tourism,

minerals)

No Nil

11 Areas already subjected to pollution or

Environmental damage. (those where

existing legal environmental standards

are exceeded)

No Nil

12 Areas susceptible to natural hazard

which could cause the project to

present environmental problems

(earthquakes, subsidence, landslides,

erosion, flooding or extreme or adverse

climatic conditions)

Yes The project falls under Seismic Zone III

(moderate earthquake zone) as per the

Seismotectonic Atlas of India. The project

area lies beyond the cyclone zone

andtherefore the risk of cyclones is not

significant. During the design stage, the

effects from natural disasters will be

considered and necessary precautionary

measures would be built-in / implemented.

Page 14: Form-I for seeking clearance for project attracting …environmentclearance.nic.in/writereaddata/online/EC/...1 Form-I for seeking clearance for project attracting CRZ notification

14  

Page 15: Form-I for seeking clearance for project attracting …environmentclearance.nic.in/writereaddata/online/EC/...1 Form-I for seeking clearance for project attracting CRZ notification
Page 16: Form-I for seeking clearance for project attracting …environmentclearance.nic.in/writereaddata/online/EC/...1 Form-I for seeking clearance for project attracting CRZ notification