www.NetComLearning.com 1 Project Management Professionals Hot Topics & Challenges Time Management Presenter: Sohel Akhter, PMP, CCNA,ISMS PMP Instructor, NetCom Learning Adjunct Professor , MBA program, CUNY Topic: How PMI’s 7 Time Management processes make sense in real world?

Upload: vothu

Post on 03-Apr-2018

227 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Project Management Professionals Hot Topics & … Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) - sohel_akhter_pm@yahoo.com, 347-536-2811 1 Project Management Professionals Hot Topics

PMP Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) - [email protected], 347-536-2811 www.NetComLearning.com www.NetComLearning.com 1

Project Management Professionals

Hot Topics & Challenges – Time Management

Presenter: Sohel Akhter, PMP, CCNA,ISMS

PMP Instructor, NetCom Learning

Adjunct Professor , MBA program, CUNY

Topic: How PMI’s 7 Time Management processes

make sense in real world?

Page 2: Project Management Professionals Hot Topics & … Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) - sohel_akhter_pm@yahoo.com, 347-536-2811 1 Project Management Professionals Hot Topics

PMP Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) - [email protected], 347-536-2811 www.NetComLearning.com www.NetComLearning.com

Agenda

47 Process defined by PMI

Time Management Processes

Develop a project schedule in real life

Questions?

2

PMP | Time Management

Page 3: Project Management Professionals Hot Topics & … Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) - sohel_akhter_pm@yahoo.com, 347-536-2811 1 Project Management Professionals Hot Topics

PMP Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) , [email protected], 347-536-2811 www.NetComLearning.com www.NetComLearning.com 3

Process Groups

Total # of

Processes

Initiating Planning Executing Monitoring &

Controlling

Closing

Kn

ow

led

ge A

rea

s

Integration 1 1 1 2 1 6

Scope 4 2 6

Time 6 1 7

Cost 3 1 4

Quality 1 1 1 3

Human Resource 1 3 4

Communication 1 1 1 3

Risk 5 1 6

Procurement 1 1 1 1 4

Stakeholder 1 1 1 1 4

Total # of Processes 2 24 8 11 2 47

PMP | Time Management

PMI’s 47 Processes

Page 4: Project Management Professionals Hot Topics & … Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) - sohel_akhter_pm@yahoo.com, 347-536-2811 1 Project Management Professionals Hot Topics

PMP Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) , [email protected], 347-536-2811 www.NetComLearning.com www.NetComLearning.com

Plan Schedule Management - Planning

Define Activities - Planning

Sequence Activities - Planning

Estimate Activity Resources - Planning

Estimate Activity Durations - Planning

Develop Schedule - Planning

Control Schedule – Monitoring & Controlling

4

PMP | Time Management

7 Processes for Time Management

Page 5: Project Management Professionals Hot Topics & … Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) - sohel_akhter_pm@yahoo.com, 347-536-2811 1 Project Management Professionals Hot Topics

PMP Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) , [email protected], 347-536-2811 www.NetComLearning.com 5

1. Activities or tasks

2. Dependencies

3. Resources

4. Durations

5. Start Date and End Date

PMP | Time Management

Components of a project Schedule

Page 6: Project Management Professionals Hot Topics & … Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) - sohel_akhter_pm@yahoo.com, 347-536-2811 1 Project Management Professionals Hot Topics

PMP Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) , [email protected], 347-536-2811 www.NetComLearning.com www.NetComLearning.com

6

1. Fix holes on walls

2. Sand all walls

Home Construction

1.0 Exterior

1.1 Outside

Wall

1.2 Front Yard

1.3 Back Yard

2.0 Interior

2.1 Drywall

2.2 Painting

2.3 Carpeting

PMP | Time Management

How to come up with activity list?

Page 7: Project Management Professionals Hot Topics & … Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) - sohel_akhter_pm@yahoo.com, 347-536-2811 1 Project Management Professionals Hot Topics

PMP Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) , [email protected], 347-536-2811 www.NetComLearning.com www.NetComLearning.com 7

Start End

B

A

D E

C

Collect

Requirement

Setup

Server

Complete

Design

Complete

Coding

End

Start

Complete

Testing

PMP | Time Management

How to come up with activity sequence?

Page 8: Project Management Professionals Hot Topics & … Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) - sohel_akhter_pm@yahoo.com, 347-536-2811 1 Project Management Professionals Hot Topics

PMP Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) , [email protected], 347-536-2811 www.NetComLearning.com

Major Milestones Durations Resources Dependency

8

Dry wall

1.1 Fix holes on walls

1.2 Sand all walls

Res A

Res M, N

4 days

3 days 1.1

3/3 3/6

3/7 3/9

Painting

2.1

2.2

2.3

Carpeting

3.1

3.2

Baseline Baseline Actual

Start Date

Actual

End Date

1. Plan

Schedule

Management

2. Define

Activities

3. Sequence

Activities 4. Estimate

Activity

Resources

5. Estimate

Activity

Durations

6. Develop

Schedule 7. Control

Schedule

Start Date End Date

3/4 3/8

PMP | Time Management

Page 9: Project Management Professionals Hot Topics & … Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) - sohel_akhter_pm@yahoo.com, 347-536-2811 1 Project Management Professionals Hot Topics

PMP Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) , [email protected], 347-536-2811 www.NetComLearning.com 9

Time Management Process Done During Key Outputs

Plan Schedule Management Planning Phase

Schedule Management Plan

Define Activities Planning Phase Activity List

Activity Attributes

Sequence Activities Planning Phase Project Network Diagram

Estimate Activity Resources

Planning Phase Resource Requirements

RBS

Estimate Activity Durations Planning Phase Duration Estimates

Develop Schedule Planning Phase Project Schedule

Schedule Baseline

Control Schedule

Monitoring and Controlling Work Performance Information

Change Request

Time Management processes with key outputs

PMP | Time Management

Page 10: Project Management Professionals Hot Topics & … Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) - sohel_akhter_pm@yahoo.com, 347-536-2811 1 Project Management Professionals Hot Topics

PMP Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) , [email protected], 347-536-2811 www.NetComLearning.com 10

Schedule Management Plan: Defines how schedule will be planned,

developed, managed, executed, and controlled. • Scheduling methodology and tools

• Schedule baseline

• Unit of measurements

• Acceptable and unacceptable variances

• Schedule change control procedures

• Schedule reporting formats and frequency

• Guideline on schedule variance identification and controlling

• Rules of performance measures, such as schedule variance (SV), and

schedule performance index (SPI)

Key Outputs

PMP | Time Management

Page 11: Project Management Professionals Hot Topics & … Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) - sohel_akhter_pm@yahoo.com, 347-536-2811 1 Project Management Professionals Hot Topics

PMP Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) , [email protected], 347-536-2811 www.NetComLearning.com 11

Activity List: This list should have all the scheduled activities that are

required to complete the project work

Activity Attributes: Activity ID, WBS ID, name, completion date,

description, predecessor and successor, resource assigned, constraints

and assumptions, level of effort etc.

Milestone List: Milestones are considered to be major significant

events or points in the project

Key Outputs

PMP | Time Management

Page 12: Project Management Professionals Hot Topics & … Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) - sohel_akhter_pm@yahoo.com, 347-536-2811 1 Project Management Professionals Hot Topics

PMP Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) , [email protected], 347-536-2811 www.NetComLearning.com

Activity Resource Requirements: Resource requirement such as resource types, quantities etc for each activity in the work package is the key outputs.

Resource Breakdown Structure: RBS is a graphical and hierarchical structure of the identified resources

12

Project Manager

IT Team Lead

Jr Programmer1

Jr Programmer2

Sr Programmer 1

QA Team Lead

QA Tester1

QA Tester2

DB Team Lead

DBA

DB Developer

Engineering Team Lead

Engineering Team

members

Network Team Lead

Network team members

Key Outputs

PMP | Time Management

Page 13: Project Management Professionals Hot Topics & … Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) - sohel_akhter_pm@yahoo.com, 347-536-2811 1 Project Management Professionals Hot Topics

PMP Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) , [email protected], 347-536-2811 www.NetComLearning.com

Activity Duration Estimates: These are the estimates of the likely number of work periods required for each activity.

Work Performance Measurements: Schedule variance (SV), schedule performance Index (SPI) and other relevant measurements

Change Requests: Change request can be generated to the schedule baseline

13

Key Outputs

PMP | Time Management

Page 14: Project Management Professionals Hot Topics & … Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) - sohel_akhter_pm@yahoo.com, 347-536-2811 1 Project Management Professionals Hot Topics

PMP Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) , [email protected], 347-536-2811 www.NetComLearning.com

NetCom’s PMP Promotion

PMP Training for $999 (50% off limited time)

• 4 consecutive days, 36 Hours

• Book Included

• Available In-class or Live Online

• Upcoming classes: May 12th, June 2nd

What you'll get:

• Expert led lectures with Real-life examples

• Tips and tricks to conquer the exam

• 36 PMI PDUs

• Assistance with the PMI application process

http://www.netcomlearning.com/packages/441/Project-Management-Professional-PMP-Certification-

training.html

Page 15: Project Management Professionals Hot Topics & … Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) - sohel_akhter_pm@yahoo.com, 347-536-2811 1 Project Management Professionals Hot Topics

PMP Bootcamp , Sohel Akhter (PMP, ISMS, CCNA) , [email protected], 347-536-2811 www.NetComLearning.com

Questions?

15

Project Management Professionals

Hot Topics & Challenges – Time Management