71 Project Management & General Services Project Management & General Services Project Management Report Development Expenditure Performance The year 2012 was the second year where the implementation of the 10 th Malaysia Plan Development Projects were carried out over two-year cycles, called the two-year rolling plan (2012 – 2013). Project performance under this system is reviewed every year. With a two-year rolling plan, a mid-term review becomes unnecessary. In 2012, the total budget allocation for both the Federal and State funded development projects was RM30.12 million. The actual expenditure for the year 2012 was RM29.5 million, which was 98.20% of the budget allocation. Table 13.1: Summary of Development Expenditure 2012 Source of Funding Allocation Received Expenditure Percentage (%) State 23,328,820 22,791,510.96 97.70 Federal 6,795,000 6,790,894.16 99.94 Total 30,123,820 29,582,405.12 98.20 Federal Funding Five projects with a total budget ceiling of RM12.64 million were approved under the Tenth Malaysia Plan (RMKe10), Second Rolling Plan (RP2, 2012 - 2013). Out of this total, a sum of RM6.79 million was allocated in the year 2012 to implement the 5 approved projects as in Table 13.2. Table 13.2: Summary of Federal Funded Development Projects in 2012 (RP1). Project Code Project Title Project Cost Project Ceiling Allocation Expenditure (Percentage) P23 10200 003 0001 Development of Heritage Forest Park at Sepilok Rainforest Discovery Centre to Stimulate Tourism Based Economy 1,000,000 700,000 700,000 699,914.59 99.99% (Completed P2 10801 009 0002 Establishment of Seed Orchard of Sabah Indigeneous Tree Species 2,100,000 1,800,000 850,000 847,772.37 99.74% (On Schedule ) P23 10802 007 0001 Community Forestry Management Project at Mangkawagu Forest Reserve , Tongod Sandakan Sabah 1,000,000 700,000 289,780 289,779.74 100% (Completed) P23 10803 001 0001 Implementation of Trus Madi Forest Reserve Conservation Plan (FMU10) 1,000,000 700,000 445,480 443,696.10 99.60% (Completed) P23 10804 001 0001 Sabah Heart of Borneo Project 19,160,000 8,748,000 4,509,740 4,509,731.36 100% (On Schedule) Grand Total 24,260,000 12,648,000 6,795,000 6,790,894.16 99.94 With RM6.79 million or 99.94% spent out of RM6.79 million allocated to the Department in 2012, the Sabah Forestry Department was ranked no.4 out of 18 agencies under the Ministry of Environment & Natural Resource. Three projects were completed and two projects ‘on-schedule’ and carried forward to the year 2013. State Funding Compared to the number of projects and the total allocation approved under RP2, the Forestry Department received a much higher allocation from the State Government of Sabah than from the Federal Government. A total of 19 projects with a budget ceiling of RM53.007 million were approved under the RP2 (2012 – 2013), RMKe-10. For the year 2012, a total of RM23.32 million was allocated to the Department. Out of this total, a sum of RM22.79 million or 97.70% were spent. Four (4) projects out of 19 projects implemented were completed. One (1) project was categorised as completed activity, 13 projects are on schedule and 1 project not yet taken off. Status of projects under RP2 funded by the State Government are summarized in Table 13.3. Table 13.3: Summary of State Government Funded Development Projects in 2012 (RP1). Project Code Project Title Project Cost Project Ceiling Allocation Expenditure Expenditure (%) (Status) D11 0200 0011 [C] Sustainable Forest Management at Deramakot Forest Reserve 32,930,000 8,000,000 5,700,000 5,515,598 96.76 On Schedule D11 0200 0015 [C] Sustainable Development and Management Planning of Supu Kinabatangan Forest Reserve 3,086,520 1,000,000 500,000 359,349.33 71.87 On Schedule D11 0200 0016 [C] Sustainable Development and Management Planning of Tangkulap Pinangah Forest Reserve 19,825,600 3,700,000 2,700,000 2,699,396 99.98 On Shedule D11 0200 0019 [C] Research and Development at the Sabah Forest Research Centre in the Identification and Formulation of Potential Commercial Herbal Products form the Forest Resource in Sabah 7,890,000 3,900,000 1,300,000 1,299,981 100 On Schedule (Phase 2) ... continued on next page

Upload: trantu

Post on 02-Feb-2017

221 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Project Management & General Services

71Project Management & General Services

Project Management & General Services

Project Management Report

Development Expenditure PerformanceThe year 2012 was the second year where the implementation of the 10th Malaysia Plan Development Projects were carried out over two-year cycles, called the two-year rolling plan (2012 – 2013). Project performance under this system is reviewed every year. With a two-year rolling plan, a mid-term review becomes unnecessary. In 2012, the total budget allocation for both the Federal and State funded development projects was RM30.12 million. The actual expenditure for the year 2012 was RM29.5 million, which was 98.20% of the budget allocation.

Table 13.1: Summary of Development Expenditure 2012

Source of Funding

Allocation Received

Expenditure Percentage (%)

State 23,328,820 22,791,510.96 97.70

Federal 6,795,000 6,790,894.16 99.94

Total 30,123,820 29,582,405.12 98.20

Federal FundingFive projects with a total budget ceiling of RM12.64 million were approved under the Tenth Malaysia Plan (RMKe10), Second Rolling Plan (RP2, 2012 - 2013). Out of this total, a sum of RM6.79 million was allocated in the year 2012 to implement the 5 approved projects as in Table 13.2.

Table 13.2: Summary of Federal Funded Development Projects in 2012 (RP1).

Project Code Project TitleProject

CostProject Ceiling

AllocationExpenditure (Percentage)

P23 10200 003 0001 Development of Heritage Forest Park at Sepilok Rainforest Discovery Centre to Stimulate Tourism Based Economy

1,000,000 700,000 700,000 699,914.5999.99% (Completed

P2 10801 009 0002 Establishment of Seed Orchard of Sabah Indigeneous Tree Species

2,100,000 1,800,000 850,000 847,772.3799.74% (On Schedule )

P23 10802 007 0001 Community Forestry Management Project at Mangkawagu Forest Reserve , Tongod Sandakan Sabah

1,000,000 700,000 289,780 289,779.74100% (Completed)

P23 10803 001 0001 Implementation of Trus Madi Forest Reserve Conservation Plan (FMU10)

1,000,000 700,000 445,480 443,696.1099.60% (Completed)

P23 10804 001 0001 Sabah Heart of Borneo Project 19,160,000 8,748,000 4,509,740 4,509,731.36100% (On Schedule)

Grand Total 24,260,000 12,648,000 6,795,000 6,790,894.1699.94

With RM6.79 million or 99.94% spent out of RM6.79 million allocated to the Department in 2012, the Sabah Forestry Department was ranked no.4 out of 18 agencies under the Ministry of Environment & Natural Resource. Three projects were completed and two projects ‘on-schedule’ and carried forward to the year 2013.

State FundingCompared to the number of projects and the total allocation approved under RP2, the Forestry Department received a much higher allocation from the State Government of Sabah than from the Federal Government. A total of 19 projects with a budget ceiling of RM53.007 million were approved under the RP2 (2012 – 2013), RMKe-10. For the year 2012, a total of RM23.32 million was allocated to the Department. Out of this total, a sum of RM22.79 million or 97.70% were spent. Four (4) projects out of 19 projects implemented were completed. One (1) project was categorised as completed activity, 13 projects are on schedule and 1 project not yet taken off. Status of projects under RP2 funded by the State Government are summarized in Table 13.3.

Table 13.3: Summary of State Government Funded Development Projects in 2012 (RP1).

Project Code Project TitleProject

CostProject Ceiling

Allocation Expenditure

Expenditure (%)(Status)

D11 0200 0011 [C] Sustainable Forest Management at Deramakot Forest Reserve 32,930,000 8,000,000 5,700,0005,515,598

96.76On Schedule

D11 0200 0015 [C] Sustainable Development and Management Planning of Supu Kinabatangan Forest Reserve

3,086,520 1,000,000 500,000 359,349.33

71.87 On Schedule

D11 0200 0016 [C] Sustainable Development and Management Planning of Tangkulap Pinangah Forest Reserve

19,825,600 3,700,000 2,700,000 2,699,396

99.98 On Shedule

D11 0200 0019 [C] Research and Development at the Sabah Forest Research Centre in the Identification and Formulation of Potential Commercial Herbal Products form the Forest Resource in Sabah

7,890,000 3,900,000 1,300,000 1,299,981

100 On Schedule

(Phase 2)

... continued on next page

Page 2: Project Management & General Services

Sabah Forestry Department

Annual Report 201272

Project Code Project TitleProject

CostProject Ceiling

Allocation Expenditure

Expenditure (%)(Status)

D11 0200 0022 [C] Investigation and Application of Molecular Markers in Forestry 844,000 337,600 168,800 168,145.53

99.61 On Schedule

D11 0200 0024 [C] Sustainable Forest Management at Ulu Segama Malua Forest Reserve

31,103,200 4,500,000 3,200,000 3,196,083

99.88 On Schedule

D11 0200 0025 [C] Sustainable Forest Management at Ulu Kalumpang-Wullersdorf Forest Reserve

14,499,700 4,170,000 2,570,000 2,536,937

98.71 On Schedule

D11 0200 0028 [C] Rehabilitation Program of Burnt Areas at Trus Madi Forest Reserve, Tambunan

16,500,000 4,010,000 1,000,000 998,951

99.90 On Schedule

D11 0200 0029 [C] Development of Mt.Silam Interpretative Centre And Viewing Platform (Phase 2), Lahad Datu

6,970,000 1,900,000 1,351,068 1,354,060

100 On Schedule

D11 0200 0030 [C] Development of Housing Complex for Forestry Staff, Tawau District

450,000 10 10 - - 100% Completed

D11 0200 0031 [C] Development of Jungle Trail for Recreation And Eco-Tourism at Sepilok Laut Forest Reserve

2,000,000 2,000,000 1,200,000 1,179,603

98.30 100% Completed

D11 0200 0032 [C] The Proposed Establishment of Recreation Centre at Membalua Forest Reserve

3,000,000 1,200,000 257,000 256,848

99.94 Reschedule

D11 0200 0033 [C] The Proposed Infrastructural Development of VJR Rafflesia Forest Reserve

5,000,000 2,250,000 750,000 739,071

98.54 On Schedule

D11 0200 0034 [C] Maintenance of Forest Road in Identified Area in the Forest Reserve in Sabah

20,572,500 10,000,000 645,932 645,816

99.98 On Schedule

D11 0200 0035 [C] Development and Upgrading of Marine Infrastructure Facilities for Sabah Forestry Department

5,630,000 1,000,000 1,000,000 999,985

100 100% Completed

D11 0200 0036 [C] The Proposed Additional Infrastructure for Nabawan District Forestry Office

750,000 425,000 425,000 424,934

99.98 100% Completed

D11 0200 0004 [B]Construction of Staff Quarters at Sabah Forestry Institute (IPS) Telupid Sabah

2,900,000 2,900,000500,000 375,920

75.18 On Schedule

D11 0200 0037 [B]Clean Water Supply For Kalabakan Regional Forestry Complex

1,515,000 1,515,000 58,000 48,82670.39

On Schedule

D11 0200 0038 [B] Consolidation of Forestry Fire Prevention System Project 3,850,000 1,000,01010

-- Will only take off

in 2013

Grand Total 179,366,520 53,007,62023,328,820 22,791,510

97.70

... continued from previous page (Table 13.3)

Notes: [C] - Continuation Project From The Ninth Malaysia Plan and the First Rolling Plan Project (RP1 – RMKe10) [B] - New Project in the Second Rolling Plan (2012 – 2013) under the Tenth Malaysia Plan (2011 – 2015)

Looking at the 2012 financial performance of project implementation, expenditure of budget allocation was very impressive. Except for one new project which is categorized as ‘not taken off’, all other projects are on schedule as planned. The project that is not taken off (Forest Fire project) is because the ceiling can only be RM800,000.00 spent in the year 2013. However, the planning was done and the project will take off in early 2013.

Project Title: Development and Upgrading of Infrastructure at VJR Rafflesia, Tambunan (26 September 2012). Contractor Jadiria handing over to Mr. Rosli Siki (DFO Tambunan).

Site Meeting with the consultant regarding the tender upgrading of the road at Ulu Segama Malua (25 May 2012)

Page 3: Project Management & General Services

Website: www.forest .sabah.gov.my

73Project Management & General Services

(L-R) Handing Over Project at Institut Perhutanan Telupid to the Kontraktor Tekun Maju (15 October 2012); Site Inspection on the tender of upgrading gravelled road at SLRC (02 November 2012); and Site Inspection on the tender of upgrading gravel road at SLRC (22 November 2012)

RMKe10 - 3rd Rolling Plan (2013-2014)Preparation for the 3rd Rolling Plan of RMKe10 started in the early month of February 2012. A series of discussions and meetings were held to review the department’s project proposals to ensure only meaningful and high-impact projects are submitted. A total of 31 projects costing about RM230.20 million and budget ceiling request of RM104.32 million were submitted to the State Government for approval. Of these, only 21 projects, including 15 continuation projects and 6 new projects with a total project cost of RM116.63 million and an allocated ceiling of RM49.73 million was approved .

On the other hand, a total of 5 continuation projects and 9 new projects with a combined cost of RM58.28 million and RM39.04 million ceiling allocation was submitted to the Federal Government through the Ministry of Natural Resources and Environment (NRE) for consideration. Unfortunately, no new projects were approved. A total of RM5.84 million was approved for the year 2013 only with 2 continuation projects, the Heart of Borneo and Seed Orchard projects. Details as shown in Table 13.4 & Table 13.5.

Table 13.4: Summary of Approved Projects by the Federal Government under RP3, RMKe10 (2013).

Project Title Project CostRP3

CeilingNotes

Establishment of Seed Orchard of Sabah Indigeneous Tree Species 2,100,000 940,000 [C]Sabah Heart of Borneo Project 19,160,000 4,900,000 [C]

Grand Total 21,260,000 5,840,000

Notes: [C] - continuation project from RP1 and RP2

Table 13.5: Summary of Approved Projects by the State Government under RP3, RMKe10 (2013-2014).

Project TitleProject Cost(Approved)

RP3Ceiling

Notes

Summary Of Existing Projects And To Be Continued Under RP3

Sustainable Forest Management at Deramakot Forest Reserve 21,499,800 8,000,000 [C]

Sustainable Forest Management at Ulu Segama Malua Forest Reserve 12,399,980 4,000,000 [C]

Sustainable Forest Management at Ulu Kalumpang-Wullersdorf Forest Reserve 10,958,031 4,100,000 [C]

Sustainable Development and Management Planning of Tangkulap Pinangah Forest Reserve 10,696,478 4,000,000 [C]

Rehabilitation Program of Burnt Areas At Trus Madi Forest Reserve, Tambunan 11,319,327 4,950,000 [C]

Sustainable Development and Management Planning of Supu Kinabatangan Forest Reserve 1,936,291 1,000,000 [C]

Development of Mt.Silam Interpretative Centre And Viewing Platform (Phase 3), Lahad Datu 4,107,344 1,200,000 [C]

Maintenance of Forest Road in Identified Area in the Forest Reserve in Sabah 17,842,507 7,835,875 [C]

The Proposed Infrastructural Development of VJR Rafflesia Forest Reserve 2,491,848 1,500,000 [C]

Research and Development at the Sabah Forest Research Centre in the Identification and Formulation of Potential Commercial Herbal Products form the Forest Resource in Sabah

5,028,225 600,000 [C]

Investigation and Application of Molecular Markers in Forestry 842,852 337,600 [C]

Construction of Staff Quarters at Sabah Forestry Institute (IPS) Telupid Sabah 2,900,000 2,400,000 [C]

Clean Water Supply for Kalabakan District Forestry Office 1,515,000 1,325,000 [C]

Enhancement of Forest Fire Prevention System 2,870,000 2,670,000 [C]

The Proposed Establishment of Recreation Centre at Membalua Forest Reserve 901,998 257,000 [C]

Sub Total 107,309,681 44,175,475 [C]

... continued on next page

Page 4: Project Management & General Services

Sabah Forestry Department

Annual Report 201274

Project TitleProject Cost(Approved)

RP3Ceiling

Notes

Summary Of New Projects Approved Under RP3

Sustainable Forest Management at Northern Mt. Rara, Kalabakan 6,000,000 3,000,000 [B]

Projek Pemeliharaan dan Pemuliharaan Hutan Simpan Destinasi Pelancongan Produk Hutan Bukan Kayu 1,219,000 1,219,000 [B]

Kajian Potensi Spesis Tumbuhan Tempatan Dalam Perhutanan Bandar 527,000 221,000 [B]

Penyelidikan Pembaikbiakan Pokok dan Penubuhan Kebun Klon ke Atas Spesis Ladang Utama iaitu Laran, Binuang, Batai dan Acacia Spp.

580,000 285,000 [B]

Kajian Penilaian Stok Karbon di Ladang Hutan, Sabah 650,000 650,000 [B]

Kajian Serangga Perosak & Penyakit Ke Atas Spesis-spesis Berpotensi Yang kurang Diketahui (Lesser Known Species)

352,000 186,000 [B]

Sub Total 9,328,000 5,561,000

Grand Total 116,637,681 49,736,475

... continued from previous page (Table 13.5)

Notes: [C] - continuation project from RP1 and RP2 [B] - New Project in the 3rd Rolling Plan (2013 – 2014) under the Tenth Malaysia Plan (2011 – 2015)

Project Activities For The Year 2012• Ministerial Level MeetingsThroughout the year, the PPA Division actively attended monthly and quarterly meetings called by the respective Federal & State agencies such as Ministry of Natural Resources and Environment (NRE), Economic Planning Unit, Putrajaya (EPU), Implementation Coordination Unit (ICU), Ministry of Finance (MOF), State Economic Planning Unit (UPEN), Chief Minister’s Department (JKM) and Ministry of Tourism (MOT). The agencies and relevant committees meet regularly to monitor the implementation of development projects by the department. The Department is a member of the following committees:- Ministerial Development Action Committee (JTPK);- Financial & Account Management Committee for

Development Project under the Chief Minister’s Department (JPKA);

- Project Monitoring System Committee (SPP II);

These meetings are necessary to ensure the close monitoring of project implementation, to report on progress and provide feedback at the strategic planning level. Monthly progress reports are prepared to document progress, overcome problems and facilitate the successful completion of projects.

• Departmental Level Meetings, Project Site Inspection/Meeting, Project Workshop- As the coordinator of the Forestry Department’s development projects, a series of meetings were arranged amongst the project managers, project consultants and contractors to

ensure the smooth implementation of their respective projects in terms of financial and physical performance. Not less than 134 meetings, site visits and special project inspections were conducted throughout the year. Amongst others, site meetings and special project inspection were carried to Mt. Silam Lahad Datu, Nabawan, Rumbia Information Centre Kuala Penyu, Trus Madi, Ulu Kukut, Deramakot, Kinabatangan, Tambunan etc.

Meeting/Briefing/Workshop• Meeting On Co-ordination in Preparation Programme and Project for the Third Rolling Plan – RMKe10 under Ministry of Natural Resources and Environment (03 February 2012)This was held in early February at Wisma Sumber Asli, Putrajaya, Kuala Lumpur and was attended by Mr. Kinus Mais and Ms Easter Jubilee.

• Key In Data Project for the Application Allocation on Third Rolling Plan (RP3 – RMKe10) Through SPP II Session at (23 February 2012)This session was coordinated by the NRE at ICU, Prime Minister Department, Putrajaya and was attended by Ms. Easter Jubilee.

• Workshop on Coordination and Final Submission Project Application On The Third Rolling Plan (RP3 – RMKe10) at Klana Resort, Seremban, Negeri Sembilan ( 28 February 2013)This workshop was coordinated by the NRE as a preparation for the final submission project application for RP3, RMKe-10, and was attended by Mr. Kinus Mais, Mr Indra P. Sunjoto, Mr. Ricky Alisky Martin, Mdm Maria Ajik and Ms Easter Jubilee.

Implementation & Monitoring Commitee Meeting (JPPP Bil 2/2012). Chaired by Mr Fidelis Edwin Bajau. The officer from JKM (Pn. Dayang Selha) and MoF (Mr. Beter Manjilang) also attended this meeting on 26 April 2012.

Page 5: Project Management & General Services

Website: www.forest .sabah.gov.my

75Project Management & General Services

• Learning Trip To Lembaga Pembangunan dan Lindungan Tanah (PELITA) at Mukah, Kuching Sarawak (14 April 2013)This learning trip about rumbia management was attended by Mr Kinus Mais, Mr. Idris Md Jair, Mr George Hubert Petol, Mr. George Anggampun, Ms Beatrice Johnlee Kulik and Mdm Noraidilroyani Juslin.

• Workshop On E-Procurement, Quotation Module, Tender, Direct Purchase and Contract Management ( 29 – 30 Jun 2012)This was held in 29 – 30 Jun 2012 at the Promenade Hotel Kota Kinabalu for two (2) consecutive days. It was coordinated by the Management and Budget Division, NRE and was attended by Ms Easter Jubilee, Mr. Hildi Poili, Ms Michelle Yap Sue Sem and Mdm Sitiana Kunching.

• Updating Data of New Project Application (2014) at EPU, Putrajaya (26 Jun 2012)This session was coordinated by Development Divission, NRE and held at EPU at Putrajaya and was attended by Mr Kinus Mais and Ms Easter Jubilee.

• Workshop on Purification Development Project RMKe10 Profile (8 – 9 July 2012)This was held at the Promenade Hotel Tawau for two days and conducted by the Development Division, NRE. The objectives of the workshop was to compile all profile projects under NRE and the selected project was presented. This workshop was attended by Ms Michelle Yap and Ms Easter Jubilee and the profile project of Sabah Heart Of Borneo was presented by Ms Michelle Yap.

• Budget Screening for RP3, RMKe10 at Wisma Sedia, UPEN, Kota Kinabalu (27 August 2012)Attended by 22 Sabah forestry officers headed by Deputy Director (Development), Mr. Fidelis E Bajau. Submission from the department comprised 19 existing projects amounting to RM82.21 million and 12 new projects amounting of RM22.10 million.

• Group Trip by Officers from NRE to three islands at Kota Kinabalu ( 11 – 15 October 2012)The three islands were Sapi Island, Manukan Island and Mamutik Island. The PPA Division coordinated the transportation (boat, bus, FWD) and guided the trip.

Page 6: Project Management & General Services

Sabah Forestry Department

Annual Report 201276

• Discussion and sorting out of financial balance of Federal Funded Projects at Jabatan Akauntan Negara, Putrajaya (24 October 2012)Headed by Mr. Kinus Mais and other officers as Ms. Easter Jubilee, Mdm Bilma Ismail and Mdm. Hajah Mislee also attended this discussion. These discussions were successful where, the officer from JAN (Ms. Nurul Sharain Binti Kamarudin) helped Sabah Forestry Department to sort out problems on Trust Fund Account.

• Presentation of Outcome Evaluation Report on Development Project (OERDP) under the NRE (24th – 27th November 2012)The Sabah Forestry Department was honoured to host a workshop on the Preparation and Presentation of Outcome Evaluation Report on Development Project under the Ministry of Natural Resource and Environment held in Promenade Hotel in November 2012. Out of twenty nine (29) OERDP papers presented in the three-day workshop, three (3) OERDP papers were from the Sabah Forestry Department (refer Table 13.6).

Table 13.6: List of Outcome Evaluation Report on Development Project (OERDP) Papers Presented in 3 Days OERDP Workshop in Promenade Hotel, 24th – 27th November 2012.

1 Sabah Heart Of Borneo Project Ms. Michell Yap Sue SemAssistant Forestry Officer

2 Community Forestry Management Project at Mangkawagu Forest Reserve, Tongod Sandakan, Sabah

Mr. Edmund WilliamAssistant District Forestry Officer

3 Human Resource Development Ms. Norfaizah Amir

Special Report on RMKe10’s Project Directly undertaken by PPA Division

Table 13.7: List of RMKe-10 Development Projects directly undertaken by PPA Division

No. Name of Project Descriptions of the Projects

1 Proposed Development and Upgrading Works in Rumbia Information Centre Kuala Penyu

Project commencement: 8th September 2011Project termination: 7th March 2012Contract Period: Six (6) MonthsContract Cost (RM): RM1,799,511.64Contractor: Sri Mutiara Indah EnterpriseHanding Over: 30th March 2012

The project was approved and funded by the Ministry of Tourism Malaysia under RP1, RMKe10. Total budget approved is RM2 million. The value of the contract for this project is RM1,799,511.64 and completed on the 7th March 2012. The scope of works for the project includes the construction of a new access road, car park, decorative security fencing, guard house, public toilet, upgrading of the existing exhibition hall, the construction of 500 feet Belian boardwalk, soft & hard landscape, maintenance & restoration of 5 acres Rumbia reserve and replanting of 3.5 acres of rumbia tree. Handing over project were done on 30th March 2012. The symbol key handing over projek from contractor Sri Mutiara Indah Enterprise were give to the Director of Sabah Forestry, Datuk Sam Mannan. These handing over project also attended by other agencies. Mr Zaffwan Ab Ghafar (Motour Ministry), Mdm Hajah Mariam Omar (KPKAS), Mr. John Angelo (KPKAS), Mr. Suraini Nurudin (Motour Sabah), Mdm Halimah Hji Hassan (Sabah Tourism Board) and Mr Edmund Peo (Kuala Penyu District Officer).

2 Development and Upgrading Works of Marine Infrastructures for Sabah Forestry Department

Implementation of project components were started as early as March 2011 through an open quotation and continue to the year 2012. As project locations varied, it is not workable to do it as a one package. Therefore, quotation were called for each locations.

Development and upgrading works of marine infrastructures had been carried out mainly in Sandakan, Lahad Datu, Tawau and Pitas. This involed the construction of concrete slipway (3 locations), Belian Jetty (3 locations) and covered docked yard (3 locations).

Page 7: Project Management & General Services

Website: www.forest .sabah.gov.my

77Project Management & General Services

Handing over project was conducted on 30th March 2012 at RIC Kuala Penyu.

Site Inspection at Sabah Forestry Complex Marine at Tanjung Mowtas after upgrading.

Page 8: Project Management & General Services

Sabah Forestry Department

Annual Report 201278

General Services Report

Report on General Services will cover maintenance activities for buildings and vehicles, procurement of new vehicles, boats engines, fuel consumption, Nursery Unit and others activities carried out by the PPA Division in 2012.

Building MaintenanceA total of RM622,862.10 [under Vote S16 120 150801 020500 00000000 28000] was spent for maintenance works in HQ, RIC and our Complexes Marine at Batu Sapi in 2012. Apart from this, about RM30,000 had been used for the new Office building of PPD Kota Belud. The spending is less than 16% from the total amount of RM738,224.90 being used in 2011. For Headquarters, the distribution of work covered the maintenance of electrical appliances (from Generator, lamps and air conditioner), the rectification of windows, gutter, downpipe, broken ceiling and floor and also the installation of new carpet of our Office (PPA). Expenditure also covered the procurement of supplies for toilets and offices.

Vehicle and Boat MaintenanceThroughout the year, a total of RM1,014,591.00 had been spent to repair and maintain all vehicles in Headquarters, Sabah Forestry Institute and other Forestry Districts. The amount increased by 19% compared to the RM854,144.70 spent in the previous year. The increment maybe due to the increase of service charges and vehicle part prices in the current market. For boats, we spent a total of RM386,017.10 for maintenance. The spending increased by 2.3% compared to the expenditure of the previous year of RM377,482.90.

Procurement of Vehicles and EnginesIn 2012, the Department purchased 17 units of vehicles at the cost of RM1.34 Million. These include 13 units of Toyota

Table 13.8: List of new vehicles purchased by the Sabah Forestry Department.

No Reg. No Location Types Of Vehicles

1 SB6529B TP(FSP) Fortunar

2 SB6531B TP(FSP) Fortunar

3 SB5758B USM Toyota Single Cab

4 SB5759B USM Toyota Single Cab

5 SAB9961K PPP SEPILOK Toyota Double Cab

6 SB6275B FRM Toyota Double Cab

7 SB6275B SPP Toyota Double Cab

8 SB6289B PPA Toyota Double Cab

9 SB6280B OPS SADANG Toyota Double Cab

10 SB6281B SPP Toyota Double Cab

11 SB6283B KUNAK Toyota Double Cab

12 SB6284B MCEE SANDAKAN

Toyota Double Cab

13 SB6285B BELURAN Toyota Double Cab

14 SB6273B KALABAKAN Toyota Double Cab

15 SB6287B SERUDONG Toyota Double Cab

16 SB6308B FMU 10 Toyota Double Cab

17 SB6309B FMU 10 Toyota Double Cab

No. Boats No./Boats Name

Engines Power

Location

1 2 Units Yamaha Engines

200 HP JP48 Maliau (PPD Tawau

2 7 Units Yamaha Engines

15 HP Kompleks Marin, Batu Sapi

3 1 Unit Yamaha Engines

30HP Kompleks Marin, Batu Sapi

4 1 Unit Yamaha Engine

5 HP MCEE Kudat

New Toyota Double Cab

New Toyota Double Cab New Toyota Fortunar for Deputy Director (Forest Sector Planning).

Other than this, there was an expenditure of RM227,540.00 for the purchase of outboard engines. The list of Outboard Engines is shown in Table 13.9.

Table 13.9: List of new outboard Engines purchased by the Sabah Forestry Department.

Fuel Usage for 2012A special program was initiated and developed to monitor the use of fuel by the perspective forestry offices. However, the accuracy of information on fuel usage captured by the PPA Division was very much dependent on the submission by the respective forestry offices. A preliminary trend analysis showed that total volume fuel consumption irrespective of fuels type is on an increasing trend in general. The total fuel consumption for diesel, oil two stroke and engine oil in 2012 was higher compared to 2011 (refer Table 13.10).

Double Cab, 2 units of Toyota Single Cab and 2 units of Toyota Fortuner. Distribution of vehicles is shown in Table 13.8.

Page 9: Project Management & General Services

Website: www.forest .sabah.gov.my

79Project Management & General Services

Table 13.10: Trend of Fuel Usage by Regional Forestry Offices, 2010 - 2012

Region / Division

Diesel Petrol Oil Two Stroke Oil Engine

(Litre) (Litre) (Litre) (Litre)

2010 2011 2012 2010 2011 2012 2010 2011 2012 2010 2011 2012Tawau 207,469 303,568 482,196 112,799 96,720 166,172 1,028 696 2,533 70 130 303Sandakan 110,851 183,705 141,418 103,992 201,259 139,929 2,406 1,767 2,860 72 1,012 50Kudat 53,570 42,321 35,960 20,240 31,149 13,587 485 683 154 15 40 2Kota Kinabalu 76,975 59,063 57,432 5,476 5,391 7,613 - - 33 65 20 4Keningau 130,950 104,584 112,955 2,899 2,212 1,537 - 25 - 5 14 70Forest Research Centre 65,284 48,115 70,986 7,483 7,509 200 64 20 - 214 - 5Forestry Headquarters 157,943 128,382 91,050 10,585 4,887 836 5 - - 51 70 -SFD Marine Complex 32,745 40,688 35,339 59,210 49,600 52,411 874 853 781 4 4 281

TOTAL 835,787 930,355 1,027,336 322,684 398,923 382,285 4,862 4,044 6,361 496 1,290 1,306Source: Data captured are based on the submission of fuel report from the respective forestry offices.

Nursery UnitIn 2012, our Nursery Unit gave more emphasize on planting activities at our new garden at Taman Warisan, Headquarters. Species planted included Agathis spp, Diospyros diepenhorstii (Kayu Malam), Intsia palembanica (Merbau), Gonystylus bancarus (Ramin), Shorea spp. (Kawang), Terminalia catappa (Ketapang), Podocarpus rumphii (Kayu Cina), Azardirachta excels (Sentang) and other Dipterocarp species. Apart from this, they also carried out pruning activities in Taman Sandakan and tree planting at the Rainforest Discovery Centre and Rumbia Information Centre, Kuala Penyu. Major outside events included the preparation of landscapes and decoration in RDC during the Sultan of Brunei’s visit and also during the opening ceremony of “Tower of Heaven” at Mount Silam in Lahad Datu. Such vast experience had put our Nursery team among the best technicians for landscape and stage decoration.

Trees being planted by our nursery staff.

Application of fertilizer on planted trees and the ongoing grass cutting activities.

Page 10: Project Management & General Services

Sabah Forestry Department

Annual Report 201280

Other ActivitiesUpgrading work of HQ Fences[July 2012]The 2nd Phase of fence upgrading in HQ had been completed on July 2012. It involved the parameter fences along side the Sandakan Golf Club and its stretches along the highway from the main entrance gate. This upgrading work was confined to the stretch up to 1,063 feet (324 meters) of concrete fences. The expenditure was covered under Forest Development Vote [S16 120 150801 050800 00000000 28000].

Preparation of concrete wall for the fence and new fence built along the Sandakan Golf Club.