project execution plan for high rise building
TRANSCRIPT
Project Execution Plan for High Rise Building Details how the construction will be executed, monitored and controlled.
YouTube Link https://youtu.be/_gikBOisPH8
David
H M
olo
ne
y
17
th J
uly
20
16
Brief Description
The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct a high-rise building.
This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Induction Training and as a way to capture and share knowledge. Can be use to demonstrate entitlement for delays and additional payment.
Project Execution Plan (PEP) details how a project will be executed, monitored and controlled. High in Educational Value and easily understood. Recommended for Continuing Professional Development (CPD)
This Presentation is innovative and has many beneficial uses.
Table of Contents
Floor Construction
Observation Deck on Floor 124
Floor Construction Cycle Time
Floor Construction Cycle timeG
en
era
l It
em
s
Formwork Quantities
Column formwork = ½ set (50%)
Core wall formwork = 1 set (100%)
Slab formwork = 2 sets (200%) Table forms
Formwork types
Columns - Crane handled units
Core Walls - self climbing floor to floor
Slabs Formwork & Falsework – Table forms Crane handled
Cycle Time
7 working days cycle per floor
Programme
Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7
Columns Rebar, Shutter
& Pour 50%
Rebar, Shutter &
Pour 50%
Strip shutters
Walls Pour walls Climb up Fix Rebar Fix shutters
Floor Strike & Move
Forms
Slab
Formwork
Rebar MEP
Slab
Formwork
Rebar MEP
Slab
Formwork
Rebar MEP
Slab
Formwork
Rebar MEP
Pour slab
100%
Floor Construction Overview
ⓒ David H Moloney
Ge
ne
ral It
em
s
Floor Construction Formwork Types
Shuttering to ColumnsG
en
era
l It
em
s
Brief Description
Column formwork can be moved with only one crane lift complete with push-pull props and concreting platform with guard rails and ladder – alternatively moved by hand using transportation wheels. QUATTRO system by Peri
Shuttering – Columns
ⓒ David H Moloney
Ge
ne
ral It
em
s
Shuttering to Core ( Lifts & Stairs)G
en
era
l It
em
s
Brief Description
Automatic climbing formwork system
lifts itself upwards on rails bolted to
the walls using hydraulic jacks
Doka Xclimb 60
ⓒ David H Moloney
Ge
ne
ral It
em
s
Shuttering to Core ( Lifts & Stairs)
Shuttering Self Climbing for CoreC
on
cre
te
Cycle Time 4 Days
Shuttering to Floor Slabs – Table formsG
en
era
l It
em
s
Brief Description
Table forms are preassembled formwork and false units and are moved horizontally on wheels or a trolley and vertically from floor to floor by crane or by a lift fixed to the outside of the building
Shuttering to Floor Slabs – Table formsG
en
era
l It
em
s
Leapfrog table forms
Shuttering – Floor Slabs
ⓒ David H Moloney
Ge
ne
ral It
em
s
Shuttering – StairsG
en
era
l It
em
s
Shuttering – Stairs
ⓒ David H Moloney
Ge
ne
ral It
em
s
Dubai High Rise Buildings
ⓒ David H Moloney
Main Equipment
Climbing Tower Cranes
Brief Description
A climbing tower crane lifts itself up using a climbing
attachment with hydraulic jacks that surrounds the mast.
The climbing attachment lifts itself up off the erected mast
and inserts a new mast section.
Ge
ne
ral It
em
s
Climbing Tower CranesM
isce
llan
eo
us
Climbing Tower Cranes – Tie-in AssemblyM
isce
llan
eo
us
Concrete Pump – Self ClimbingG
en
era
l It
em
s
Brief Description
The concrete is pumped by a diesel powered, static concrete pump, through a fixed 125 mm pipeline, to the folding placing boom. The boom is mounted on a steel column of up to 20 metres high. The column is supported by a cross base or a system of floor frames set into the concrete floors.With floor frames , the whole column / boom assembly can climb with the building as the work progresses. For placing concrete pumping is faster than using a crane and skip and is less likely to be adversely affected by high winds.
Concrete PumpM
isce
llan
eo
us
Protection Screen - Self climbingG
en
era
l It
em
s
Brief Description
Protection screens enclose the top floors of a high rise enabling construction work to be carry out in great safety, and protected from the weather.
The screen will contain any debris and tools that would otherwise fall to the surface.
The Protection screen can be moved upwards hydraulically or using a tower crane.
Ensuring VerticalityG
en
era
l It
em
s
Brief Description
Leave 3 holes in the floor, forming a right angle. Use a laser plumb bob and a transparent sheet on the floors above. "Jump" the laser every 5 or 6 floors.
Platforms, Chutes & LiftsG
en
era
l It
em
s
ⓒ David H Moloney
Ge
ne
ral It
em
s
Platforms, Chutes & Lifts
General Items
Contractor’s Temporary Site Facilities
ⓒ David H Moloney
Ge
ne
ral It
em
s
Brief Description
Contractors Site facilities comprise:Offices, Canteens, Toilets, Drying Rooms, Stores, Plant Yard, generators and Workshops.
Dewatering
ⓒ David H Moloney
Ge
ne
ral It
em
s
Brief Description
Construction dewatering is the removal or drainage of
groundwater and or surface / rain water usually by
pumping to keep the works dry.
Dewatering
ⓒ David H Moloney
Ge
ne
ral It
em
s
Brief Description
Construction dewatering is the removal or
drainage of groundwater and or surface /
rain water usually by pumping to keep the
works dry.
Dewatering
ⓒ David H Moloney
Ge
ne
ral It
em
s
Site Hoarding examples
ⓒ David H Moloney
Ge
ne
ral It
em
s
Temporary Electricity Supply & Tower Lights
ⓒ David H Moloney
Ge
ne
ral It
em
s
Welfare Facilities
ⓒ David H Moloney
Ge
ne
ral It
em
s
Toilets – Washing
Canteen, Drying Room, Toilet & Generator
Safety & Environmental
Emergency Phone Numbers & Response H
ealth,
Safe
ty &
Envir
onm
ent
HSE Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of
current HSE statistics and historical trends
Health,
Safe
ty &
Envir
onm
ent
Safety PrecautionsH
ealth,
Safe
ty &
Envir
onm
ent
Signs Examples H
ealth,
Safe
ty &
Envir
onm
ent
Hazardous Substances Symbols H
ealth,
Safe
ty &
Envir
onm
ent
COSHH stands for the Control of Substances Hazardous to Health
Shown are the new hazard symbols
Environmentally Friendly Site Air, Noise, Water & Soil PollutionH
ealth,
Safe
ty &
Envir
onm
ent
Segregation of Waste H
ealth,
Safe
ty &
Envir
onm
ent
Segregation of waste for proper disposal and recycling. Less waste goes to landfill and hazardous waste is treated to make it safe.
Colour Code for Skips & Bins
Water Pollution PreventionH
ealth,
Safe
ty &
Envir
onm
ent
Existing Underground Utilities
ⓒ David H Moloney
Brief Description
Before digging establish the
location and route of
underground utilities.
Locator to find Utilities
Spray Paint to mark pavement
Health,
Safe
ty &
Envir
onm
ent
Existing Underground Utilities & Overhead Cables - Safety Measures
ⓒ David H Moloney
Health,
Safe
ty &
Envir
onm
ent
Trench - Safety Measures H
ealth,
Safe
ty &
Envir
onm
ent
Trench - Safety Measures
ⓒ David H Moloney
Health,
Safe
ty &
Envir
onm
ent
Earthworks
Excavate & Load, Cart, Tip & Return
Brief Description
Cycle Time for 7km haulage distance using an Excavator 45 tonne weight and Dumper with a 40 tonne capacity, the cycle time is 34 minutes
Ea
rth
wo
rks
7 minutes
14 minutes
3 minutes
14 minutes 7 km
7 km
Excavation for Trench with Stepped FacesE
art
hw
ork
s
Excavation for Trench with Battered FacesE
art
hw
ork
s
Concrete
Concrete Full Scale Trial Castings of Pier
ⓒ David H Moloney
Brief Description
The full-scale trial casting(s) shall
demonstrate/document that all
requirements to the concrete and the
execution of the work are fulfilled
simultaneously using the actual
methods and performed by personnel as
for the future production.
Co
ncre
te
BIM 3D Model Shutter Fibreglass
Concrete Batching Plant David H Moloney
ⓒ David H Moloney
Brief Description
Concrete batching plant comprises -
concrete mixer, control cabin, silos for
cement and fly ash, aggregate bins and
conveyor belt system to feed the mixer.
Also aggregate storage bays and water
storage tanks.
Co
ncre
te
Concrete Batching Plant
ⓒ David H Moloney
Co
ncre
te
Concrete Batching Plant 3Nr.
ⓒ David H Moloney
Co
ncre
te
Concrete Batching Plant - Liebherr Betomix AnimationC
on
cre
te
Concrete Batching Plant David H Moloney
ⓒ David H Moloney
Brief Description
.
The mixing is computer controlled
and has a dynamic screen display,
showing the process. The material
storage capacity is, to match two
days concrete production.
Co
ncre
te
Concrete Batching Plant – Computer Controlled
ⓒ David H Moloney
Co
ncre
te
Concrete Mix Proportions per Cu M
Brief Description
.
Details of Mix for C40
1. Concrete Grade C40
2. Cement Type = OPC
3. Slump =125mm
4. Max size aggregate = 20mm5. Max water / Cementitious ration =0.42
Co
ncre
te
Materials Qty Units
Cement 310 Kgs
Fly ash 100 Kgs
Micro-silica 12 Kgs
Washed Sand 670 Kgs
Fine Sand 106 Kgs
10mm Crushed aggregate 400 Kgs
20mm Crushed aggregates 725 Kgs
Water 145 Ltr.
Additive Rheobuild 7.5 Ltr.
Early age strength concrete is required for quick floor cycle time
Reinforcement Cutting & Bending Yard
ⓒ David H Moloney
Co
ncre
te
Brief Description
Reinforcement in 12 m lengths. Delivery in 3 ton Bundles
Reinforcement Cutting & Bending
ⓒ David H Moloney
Co
ncre
te
Reinforcement Cutting & Bending
ⓒ David H Moloney
Co
ncre
te
Reinforcement Cutting & Bending Yard David H Moloney
ⓒ David H Moloney
Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine
Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site
Co
ncre
te
Reinforced Wall Construction Sequence
ⓒ David H Moloney
Co
ncre
te
Brief Description
The sequence to construct a reinforced concrete wall is as
follows:
Tie the reinforcement.
Erect stop-ends and the wall shutters.
Pour and vibrate the concrete mix.
Remove the shutters after the concrete has hardened.
.
Cycle Time Pour per Day
Reinforced Wall Construction Sequence
ⓒ David H Moloney
Co
ncre
te
Vibrating Concrete
ⓒ David H Moloney
Co
ncre
te
Piling
Piling Construction - Plant & Methods
Brief Description
Piling Plant, Equipment and Material;
Crawler Crane, Piling Hammer, Temporary Casing,
Piling Rig, Concrete Pump, Concrete Mixer Trucks,
Tremie Pipe and Reinforcement Cage
Pili
ng
Piling Construction - Plant, Methods & SequenceP
ilin
g
Piling Construction - Plant & MethodsP
ilin
g
Piling Construction - Vertical PilesP
ilin
g
Pile Load Test
ⓒ David H Moloney
Pili
ng
Brief Description
A jack is used to load the pile in steps and
gauges measure any settlement.
Pile Load Test
ⓒ David H Moloney
Pili
ng
Progress Monitoring & Administration
Progress Monthly, Monitoring & Reporting - DashboardDashboard is a single page, graphical representation of current
progress and historical trends
Histogram Charts for Resources & Outputs
Manpower per Discipline
Concrete per Location
Man-hours for each month of the Project
Quantity for each month of the Project
ⓒ David H Moloney
Brief Description
Histograms shows resources etc. for each month of a project.
Plant & Equipment List & Worker’s Job Titles
ⓒ David H Moloney
Daily Work Record
Brief Description
Daily Work Records showing the
allocation of resources, materials and
work activities carried out daily.
Organogram
Brief Description
Shown are the line and
lateral relationships
between the various team
members and their relative
position in the site
organisation.
Staff Directory
Brief Description
List of staff and their
contact details
Quality Assurance
Quality Assurance DashboardDashboard is a single page, graphical representation of current
statistics and historical trends
Production by David H Moloney
My YouTube Channel link: https://www.youtube.com/channel/UCeJR9J7svhBd-C0ZoAH2fhQ