project escalation · sanral / safcec and the like, can agree baskets to suit differi ng project...
TRANSCRIPT
SOUTH AFRICAN FORUM OF CIVIL ENGINEERING CONTRACTORS | LR 2/6/3/138
PROJECT ESCALATION
NORMAN MILNE
CONTINUITY ADVISOR SAFCEC
South African Forum of Civil Engineering Contractors | LR 2/6/3/138
WHY DO WE NEED CONTRACT PRICE ADJUSTMENT (CPA)? IT IS ABOUT MANAGING RISK; WHICH PARTY IS BEST EQUIPPED TO DEAL WITH RISING COSTS?
IN THE SOUTH AFRICAN CONTEXT, THE EMPLOYER BEST SUITED TO DEAL WITH PRICE INCREASES
THUS, CONTRACTUAL MECHANISM IS IN PLACE TO “REIMBURSE” THE CONTRACTOR
METHODOLOGY – THE FORMULAE (GCC / SAICE)
2
BACKGROUND
South African Forum of Civil Engineering Contractors | LR 2/6/3/138
A BRIEF LOOK AT THE FORMULAE (GCC / SAICE) THE NON-ADJUSTABLE ELEMENT (TYPICALLY 10% OR 15%) IS: X
THE MAIN COMPONENTS OF CONSTRUCTION COST ARE: L, P, M & F BEING THE LABOUR + PLANT + MATERIALS + FUEL ELEMENTS OF CONSTRUCTION
THE COEFFICIENTS ARE REFLECTED BY: A, B, C & D BEING THE APPORTIONMENT OF EACH COMPONENT IN THE TOTAL COST(TOTAL IS TO BE 1)
THE INDICES APPLIED ARE: T AND O BEING THE BASE MONTH (O) AND THE MONTH OF PAYMENT STATEMENT (T)
3
BACKGROUND
South African Forum of Civil Engineering Contractors | LR 2/6/3/138
THE DISCUSSION TODAY, IS ABOUT THE INDICES LABOUR TAKEN FROM STATS-SA P0141 - CPI PER PROVINCE
RECENT CHANGE, AS “REGIONAL CPI INDICES” WERE DISCONTINUED
PLANT TAKEN FROM STATS-SA P0151 – TABLE 4
MATERIALS TAKEN FROM STATS-SA P0151 – TABLE 3
FUEL TAKEN FROM STATS-SA P0151 – TABLE 4
4
BACKGROUND
South African Forum of Civil Engineering Contractors | LR 2/6/3/138
TABLES 3 & 4 WILL BE DISCONTINUED (DECEMBER 2017)STATS-SA EXPLAINED THIS BY CITING QUALITY CONCERNS
NOT SATISFIED WITH THE DATA THAT IS COLLECTED
ELEMENTS OF THESE INDICES CAN NO LONGER BE SUSTAINED
HOWEVER, CONSENSUS IS THAT REPLACEMENT INDICES ARE NECESSARY
ORGANS OF STATE, EMPLOYERS AND CONTRACTORS GENERALLY WILL PREFERTHE ‘INDEX METHOD’ FOR CPA (BEING A “SCIENTIFIC BASED CALCULATION”)
CONTRACTORS (LARGE OR SMALL) WILL NOT BE ABLE TO SUSTAIN PRICING / TENDERINGPOLICIES TO ALLOW FOR THE RISK OF PRICE FLUCTUATIONS
5
THE ISSUE
South African Forum of Civil Engineering Contractors | LR 2/6/3/138
A WORKING COMMITTEE CHAIRED BY STATS-SA ESTABLISHED PARTICIPANTS INCLUDE SAFCEC, SANRAL, SEIFA, SAICE AND OTHERS
THE PURPOSE IS ESTABLISHING NEW INDICES BY YEAR END
INFORMATION AND DATA FOR NEW INDICES OBTAINED FROM TWO SOURCES,NAMELY: ORGANS OF STATE, EMPLOYERS AND CONTRACTORS GENERALLY WILL PREFER
THE “INDEX METHOD” FOR CPA (BEING A “SCIENTIFIC BASED CALCULATION”) 3-YEAR SURVEY (STATS-SA, 2014): FOR THE COMPOSITION OF THE INDICES, I.E.
THIS WAS HOW CONSTRUCTION ORGANISATIONS PURCHASED DIFFERENT MATERIAL GROUPS
6
WHAT IS BEING DONE
South African Forum of Civil Engineering Contractors | LR 2/6/3/138
LABOURFURTHER DISCUSSION REQUIRED:
WHETHER A LABOUR INDEX, BASED PART ON CPI AND THE WAGEAGREEMENT IS NECESSARY
STATS-SA’S OPINION THAT THIS IS AN INDUSTRY DISCUSSION
IT IS STATED THAT INDUSTRY PARTICIPANTS CAN FORMULATEOWN “INDEX”
7
WHAT IS BEING DONE
South African Forum of Civil Engineering Contractors | LR 2/6/3/138
FUELSTATS-SA IS NOT OBJECTING TO CONTINUE WITH CURRENT FUEL INDICES:
IT IS POSSIBLE THAT ONLY A NATIONAL INDEX, WITH NODIFFERENTIATION BETWEEN COASTAL AND INLAND
CLARIFICATION REQUIRED AS TO THE LEVIES PLACED ON FUELQUESTIONS REGARDING WHOLESALE / PUMP PRICE?
MEMBERS’ OPINIONS WILL BE SURVEYED
8
WHAT IS BEING DONE
South African Forum of Civil Engineering Contractors | LR 2/6/3/138
MATERIAL & PLANT
A DUAL APPROACH IS ENVISAGED HEADLINE INDICES (BEING A BASKET OF OTHER INDICES) PUBLISHED RESPECTIVELY
THE UNDERLAYING INDICES INCLUDED IN EACH HEADLINE INDEX WILL ALSO BE PUBLISHED
THE ADVANTAGE WILL BE THAT INDUSTRY SANRAL / SAFCEC AND THE LIKE, CAN AGREE BASKETS TO SUIT DIFFERING PROJECT TYPES
BASKETS CAN BE CHANGED MUCH QUICKER TO ALLOW FOR OTHER CIRCUMSTANCES
SEPARATE BITUMEN OR NON-BITUMEN BASED BASKETS CAN BE MAINTAINED
THE IMPLICATIONS OF A “PLANT HIRE INDEX” ARE INVESTIGATED
9
WHAT IS BEING DONE
South African Forum of Civil Engineering Contractors | LR 2/6/3/138
SPECIAL MATERIALS AND BITUMEN
AUDIENCE PARTICIPATION!
SHOULD THE “RISE AND FALL” METHOD FOR BITUMEN CONTINUE?
IS THERE A CASE FOR TREATING BITUMEN ON AN INDICE BASIS?
SHOULD THERE BE ANY OTHER SPECIAL MATERIALS IDENTIFIED?
10
WHAT IS BEING DONE
South African Forum of Civil Engineering Contractors | LR 2/6/3/138 11
MATERIAL: NEW INDEX DEVELOPMENT
CURRENT DEVELOPMENTNEW
STANDARDEXCLUDINGBITUMEN
EXCLUDINGSTEEL
ROADS & EARTHWORKS
CIVIL ENGINEERING
STEEL (STRUCT & REBAR) 27.0 34.6 0.0 17.7 39.7
CEMENT 22.3 28.0 30.8 16.8 30.8
AGGREGATES 16.3 20.4 22.4 30.2 10.9
BRICKS BLOCKS & TILES 8.5 10.6 11.7 1.4 2.6
PIPES, TUBES & FITTINGS 3.4 4.3 4.7 7.7 6.4
PAINT 1.6 2.1 2.2 - -
GEOFABRICS - - - 0.9 0.6
OTHER - - - 2.3 6.4
BITUMEN 20.9 0.0 28.0 23.0 2.6
South African Forum of Civil Engineering Contractors | LR 2/6/3/138 12
MATERIAL: NEW VS OLD
South African Forum of Civil Engineering Contractors | LR 2/6/3/138
AN IMPORTANT ASPECT HERE IS DECIDING ON A: CAPITAL COST BASED INDIEX (RELIABLE INFORMATION READILY AVAILABLE)
OR
HIRE RATE BASED COST INDEX (QUESTIONS REGARDING RELIABILITY)
ANY OPINIONS IN THE AUDIENCE?
13
PLANT: NEW INDICE DEVELOPMENT
South African Forum of Civil Engineering Contractors | LR 2/6/3/138
ALL PARTIES DESIROUS TO HAVE NEW INDICES
STATS-SA LIKELY TO CONTINUE WITH STATUS QUO, UNTIL NEW INDICES IN PLACE
FURTHER “INDEX DEVELOPMENT” REQUIRED BETWEEN SAFCEC, SANRAL AND OTHER ORGANS OF STATE (TRANSNET, ESKOM AND THE LIKE EMPLOYERS)
RATIONALISATION OF INDICES:
BITUMEN INCLUDED & EXCLUDED
14
WHAT IS BEING DONE
South African Forum of Civil Engineering Contractors | LR 2/6/3/138
THANK YOU
15