Page 1: PROJECT COMPLETION PLAN

PROJECT COMPLETION PLANNBS ARCHITECTURE

BRENDAN BOYLE

LAURA FEATHERSTONESHAY MCMAHON

JULIAN MINASHANNON STUBBS

Page 2: PROJECT COMPLETION PLAN

ROLES BRENDAN BOYLE (project manager/ architect) GROUND FLOOR REMODELLER JULIAN MINA (architect)

GRANNY FLAT REDESIGNER LAURA FEATHERSTONE (architect)

EXTERIOR RENOVATIONS SHANNON STUBBS (architect)

BASEMENT REMODELLER SCOTT (architect / web site administrator)

FIRST FLOOR EXTENSION

Page 3: PROJECT COMPLETION PLAN

PROJECT SELECTION SUSTAINABLE HOUSE – THE TERRACE

NEWCASTLE NSW BY JULIAN MINA

Page 4: PROJECT COMPLETION PLAN

SUSTAINABLE HOUSE

Page 5: PROJECT COMPLETION PLAN

SUSTAINABLE HOUSE

Page 6: PROJECT COMPLETION PLAN

SUSTAINABLE HOUSE

Page 7: PROJECT COMPLETION PLAN

GROUP WORK As part of our roles we are to come together as a

collaborative group and work on 2D drawings, renders and flythrough. This is kept consistent through using the same presents and Artlanis files to create the multimedia presentations to a consistent standard.

Modelling of the project is kept consistent through using similar library products, textures and materials throughout to give consistency.

Furthermore with the recent leaving of a group member from our group we have all collaborated to construct the mesh and landscape that was previously assigned to this member to a less detailed standard to ensure the project completion.

Page 8: PROJECT COMPLETION PLAN

INDIVIDUAL OUTCOMES

Page 9: PROJECT COMPLETION PLAN

GRANNY FLAT REDESIGN1. CUTTING THE MESH OUT TO ALLOW FOR

ENLARGEMENT OF THE ‘BATHHOUSE’ INTO A GRANNY FLAT.

2. INCREASING THE FLOOR AREA OF THE BATHOUSE TO ALLOW FOR AN EXPANSION INTO A GRANNY FLAT.

3. ADDING A BEDROOM TO THE BATHHOUSE.4. ADDING A KITCHENETTE TO THE BATHHOUSE.5. INCREASING THE SIZE OF WINDOWS TO

MAXIMISE VIEWS.6. CHANGING THE ROOF TO A FLAT ROOF TO

ALLOW FOR THE DECK TO EXTEND OVER THE TOP OF THE BATHHOUSE AS A LOOKOUT POINT.

7. ADDING CUSTOMISED TEXTURES TO THE WALLS AND FLOORS INSIDE THE BATHOUSE.

8. ADDING STAIRWELL ACCESS FROM THE GRANNYFLAT TO THE LOOKOUT POINT.

9. ADDING FURNITURE TO THE GRANNY FLAT.10. ADDING LIGHTS AND OBJECTS INTO THE

GRANNY FLAT.

Page 10: PROJECT COMPLETION PLAN

TIMETABLE

Page 11: PROJECT COMPLETION PLAN

GROUND FLOOR REMODELLING

1. FIX UP EXTERIOR WALL PLACEMENT WITH LF 2. CHANGE WINDOW CONFIGURATION AND

PLACEMENT CORRECTNESS WITH LF 3. CHANGE OBJECTS AND FURNIATURE AND

MODIFY THE EXISTING TO SUIT DEISGN 4. INCLUDE NEW TEXTURES TO WALLS, FLOORS

AND OBJECTS 5. CHANGE INTERIOR LAYOUT OF WALLS AND

DOORS 6. MODEL SHADE SCREENING DEVICES TO

INTERIOR WINDOWS (COMPLEX PROFILE) 7. FIX UP STAIRS AND CHANGE PROFILE

SETTINGS 8. FIX BALISTRATE AND CHANGE TO SUITABLE

APPEARANCE 9. WORK WITH LF TO INCLUDE

INDOOR/OUTDOOR PATIO AT FRONT 10. WORK IN COLLABORATION WITH GROUP FOR

FINAL 2D PRESENTATION AND FLYTHROUGH 11. COMPILE INDIVIDUAL SUBMISSION 12. CREATE 2X RENDERS OF INTERIOR DESIGNED

VIEWS INCLUDING PEOPLE

Project Manager Role • Conduct weekly meetings in

tutorial times • Post regular blog updates and

Facebook updates • Keep group members up to date

with tasks and roles and enforce completion dates

• Provide assistance for group members with research and ideas for modelling

• Ensure weekly objectives are met so that we can submit the finalised project on time and on date.

• Mark role for attendance

Page 12: PROJECT COMPLETION PLAN

TIMETABLEOBJECTIVE

WEEK 7 WEEK 8 WEEK 9 HOLIDAYS A

HOLIDAYS B

WEEK 10 WEEK 11 WEEK 12 WEEK 13

123456789101112

Page 13: PROJECT COMPLETION PLAN

BASEMENT REMODELLING ADJUSTMENT AND CORRECTION OF ALL WALLS,

WALL JUNCTIONS AND THE SLAB. REMODELLING THE EXISTING LAYOUT OF THE

EXTERNAL WALLS AND THE INTERNAL WALLS AND DOORS; TO INCLUDE A MASTER BEDROOM WITH A FEATURE WALL AND A DOUBLE BEDROOM.

ADJUSTING WINDOWS; SIZES, PLACEMENT, MATERIALS.

REMOVING/CHANGING THE EXISTING OBJECTS AND FURNITURE AS TO COMPLIMENT THE DESIGN

APPLY NEW TEXTURES TO THE OBJECTS, FLOORS, WALLS, DOORS, WINDOWS ETC, AS TO COMPLIMENT THE DESIGN.

ADJUSTING AND MAKING CHANGES OF PROFILE TO THE STAIRCASE.

INCLUDE ACCESS TO THE SMALL GARDEN WORKING IN COLLABORATION WITH THE GROUP

FOR: DESIGN DECISIONS AND IMPLIMENTATION; THE FINAL 2D PRESENTATIONS AND FLY-THROUGH.

CREATING 2X INTERNAL RENDERS OF THE REMODELLED BASEMENT DESIGN; THE VIEWS TO INCLUDE PEOPLE

COMPILING MY INDIVIDUAL SUBMISSION

Page 14: PROJECT COMPLETION PLAN

TIMETABLEOBJECTIVE

WEEK 7 WEEK 8 WEEK 9 HOLIDAYS A

HOLIDAYS B

WEEK 10 WEEK 11 WEEK 12 WEEK 13

123456789101112

Page 15: PROJECT COMPLETION PLAN

FIRST FLOOR EXTENSION1. Draft extension2. Discuss extension with group3. Collaborate with group

members whose areas are affected

4. Construct extension in archiCAD

5. Collaborate with others to choose textures

6. Design furniture layout7. Final touches8. Put design in Artlantis9. Enhance textures and render

and photoshop10. Website Creation11. Website construction

(Groups, Post Collation)12. Continued Website updates

• As sole designer of the first floor extension I will need to work independently as well as collaboratively with the designers of the ground, first and second floors.

• Teamwork will be required as I will be changing existing designs, requiring communication between myself and the previous designer in order to create a fluid and efficient floor plan.

• I will discuss with the group any changes to the existing before, during and after making any amendments.

• I will listen to each architects perspective on my plans and consider any feedback, positive or negative, given.

• I will endeavour to work to the best of my abilities, whilst maintaining connection with the guidelines and goals of my group.

• As website administrator I will enable group communication to flow efficiently through accurate grouping of topics and themes, and enable locations for information to be posted and read quickly.

• The website should reflect the image, style of the group.

Page 16: PROJECT COMPLETION PLAN

TIMETABLEOBJECTIVE

WEEK 7 WEEK 8 WEEK 9 HOLIDAYS A

HOLIDAYS B

WEEK 10 WEEK 11 WEEK 12 WEEK 13

123456789101112

Page 17: PROJECT COMPLETION PLAN

EXTERIOR RENOVATIONS 1. WORK WITH BB ON EXTERIOR WALL

PLACEMENT2. WORK WITH BB ON EXTERIOR WINDOW

PLACEMENT3. MODIFY EXTERIOR TEXTURES4. CREATE ROOFTOP AREA ON MAIN HOUSE5. CREATE ACCESS TO ROOFTOP AREA6. CREATE ROOFTOP AREA ABOVE GRANNY

FLAT7. JOIN ROOFTOP AREAS8. FURNISH ROOFTOP AREAS9. CREATE WATER SYSTEM

(GUTTERS/DOWNPIPES/WATER TANKS)10. CREATE 2 RENDERS OF ROOFTOP AREAS11. WORK WITH CROUP ON FINAL

PRESENTATION12. WORK ON INDIVIDUAL SUBMISSION

Page 18: PROJECT COMPLETION PLAN

TIMETABLE OF COMPLETIONOBJECTIVE

WEEK 7 WEEK 8 WEEK 9 HOLIDAYS A

HOLIDAYS B

WEEK 10 WEEK 11 WEEK 12 WEEK 13

123456789101112

Page 19: PROJECT COMPLETION PLAN

PROBLEMS WITH COLLABORATION WHEN AN OBJECT IS RESERVED OTHERS CANNOT

MODIFY THAT PARTICULAR ELEMENT COMMUNICATION BETWEEN USERS OVERLAPPING OF RESPONSIBILITIES DIFFERENCES OF OPINIONS SPREADING THE WORK LOAD EQUALLY AMONG

THE COLLABORATORS DIFFERENCES IN WORKLOAD AND WORK OUTPUT THE PROJECT TO PRESENTATION STAGE CANNOT

BE COMPLETED UNTIL THE LAST MEMBER HAS FINISHED THEIR SECTION

Page 20: PROJECT COMPLETION PLAN

CONCERNS AND QUERIES GETTING EVERYTHNG FINISHED ON

TIME AND IN CORRECT FORMAT COMPATIBILITY ISSUES CORRECT ARCHICAD UPDATES LOADING AND RENDERING TIME ISSUES PROBLEMS WITH BIMSERVER NOT

WORKING FLYTHROUGH MOVIE AT CORRECT SIZE

AND DEFINITION