project appraisal document +pad+ +disclosable version+ - p130014

63
Document of The World Bank Report No: 79517 VN INTERNATIONAL DEVELOPMENT ASSOCIATION PROJECT APPRAISAL DOCUMENT FOR A CREDIT IN THE AMOUNT OF US$ 180 MILLION EQUIVALENT TO THE SOCIALIST REPUBLIC OF VIETNAM FOR AN IRRIGATED AGRICULTURE IMPROVEMENT PROJECT October 7, 2013 This document has a restricted distribution and may be used by recipients only in the performance of their official duties. Its contents may not otherwise be disclosed without World Bank authorization.

Upload: nhan-tran

Post on 21-Jul-2016

24 views

Category:

Documents


0 download

DESCRIPTION

This is the project appraisal document

TRANSCRIPT

Page 1: Project Appraisal Document +PAD+ +disclosable version+ - P130014

Document of

The World Bank

Report No: 79517 VN

INTERNATIONAL DEVELOPMENT ASSOCIATION

PROJECT APPRAISAL DOCUMENT

FOR A CREDIT

IN THE AMOUNT OF US$ 180 MILLION EQUIVALENT

TO THE

SOCIALIST REPUBLIC OF VIETNAM

FOR AN

IRRIGATED AGRICULTURE IMPROVEMENT PROJECT

October 7, 2013

This document has a restricted distribution and may be used by recipients only in the

performance of their official duties. Its contents may not otherwise be disclosed without World

Bank authorization.

Page 2: Project Appraisal Document +PAD+ +disclosable version+ - P130014

CURRENCY EQUIVALENTS (Exchange Rate Effective)

Currency Unit

VND21,000

= VND Vietnamese Dong

= 1US$

FISCAL YEAR January – December 31

ABBREVIATIONS AND ACRONYMSAAA Analytical and Advisory Assistance

CPMU Central Project Management Unit (under

CPO)

CPO Central Project Office

CPS Country Partnership Strategy

CSA Climate Smart Agriculture

DARD (Provincial) Department of Agriculture

and Rural Development

DSU Dam Safety Unit

DWR Department of Water Resources

EAP Environnemental Action Plan

EIA

ECOP

Environment Impact Assessment

Environmental Code of Practice

EMDP Ethnic Minority Development Plan

FM Financial Management

GAP Gender Action Plan

GHG Green- House Gases

GOV Government of Vietnam

ha Hectare

IAIP Irrigated Agriculture Improvement

Project

ICB International Competitive Bidding

IDA International Development Agency

IDMC Irrigation and Drainage Management

Company

IMT Irrigation Management Transfer

IPF Investment Project Financing

ISF Irrigation Service Fee

MARD Ministry of Agriculture and Rural

Development

MIS Management Information System

MIS Management Information System

MOF Ministry of Finance

MOF Ministry of Finance

MONRE Ministry of Natural Resources and

Environment

MPI Ministry of Planning and Investment

NCB National Competitive Bidding

NGO Non-Government Organization

O&M Operation and Maintenance

OP/BP Operational Policy/Bank Procedure

ORAF Operational Risk Assessment Framework

PAP Project Affected People

PIM Participatory Irrigation Management

PISC Project Implementation Steering

Committee

POE Panel of Experts

PPC Provincial Peoples Committee

PPMU Provincial Project Management Unit

QCBS Quality and Cost Based Consultant

Selection

RAP Resettlement Action Plan

RPF Resettlement Policy Framework

SBV State Bank of Vietnam

SCADA Supervisory Control and Data

Acquisition

SOE Statement of Expenses

SRI System of Rice Intensification

TA Technical Assistance

VAWR Vietnam Academy of Water Resources

VND Vietnam Dong

VWRAP Vietnam Water Resources Assistance

Project

WUA Water User Association

WUO Water User Organization

Regional Vice President: Axel Van Trotsenberg

Country Director: Victoria Kwakwa

Sector Director: John Roome

Sector Manager: Jennifer Sara

Task Team Leader: Abdulhamid Azad

Cuong Hung Pham

Page 3: Project Appraisal Document +PAD+ +disclosable version+ - P130014

VIETNAM

Vietnam Irrigated Agriculture Improvement Project

TABLE OF CONTENTS

Page

I. STRATEGIC CONTEXT .................................................................................................1

A. Country Context ............................................................................................................ 1

B. Institutional Context...................................................................................................... 2

C. Higher Level Objectives to which the Project Contributes .......................................... 2

II. PROJECT DEVELOPMENT OBJECTIVES ................................................................3

A. PDO............................................................................................................................... 3

B. Beneficiaries ................................................................................................................. 3

C. PDO-Level Results Indicators ...................................................................................... 3

III. PROJECT DESCRIPTION ..............................................................................................4

A. Project Components ...................................................................................................... 4

B. Project Financing .......................................................................................................... 5

C. Lessons Learned and Reflected in the Project Design .................................................. 5

IV. IMPLEMENTATION .......................................................................................................7

A. Institutional and Implementation Arrangements. ......................................................... 7

B. Results Monitoring and Evaluation (M&E) .................................................................. 8

C. Sustainability................................................................................................................. 8

V. KEY RISKS AND MITIGATION MEASURES ............................................................9

A. Risk Ratings Summary Table ....................................................................................... 9

B. Overall Risk Rating Explanation .................................................................................. 9

VI. APPRAISAL SUMMARY ..............................................................................................10

A. Economic and Financial Analyses .............................................................................. 10

B. Technical ..................................................................................................................... 11

C. Financial Management .............................................................................................. 12

D. Procurement ................................................................................................................ 12

E. Social (including Safeguards) ..................................................................................... 13

F. Environment (including Safeguards) .......................................................................... 14

Page 4: Project Appraisal Document +PAD+ +disclosable version+ - P130014

i

.

PAD DATA SHEET

Vietnam

Irrigated Agriculture Improvement Project (P130014)

PROJECT APPRAISAL DOCUMENT .

EAST ASIA AND PACIFIC

EASVS

Report No.: 79517 VN .

Basic Information

Project ID Lending Instrument EA Category Team Leader

P130014 Investment Project

Financing

B - Partial Assessment Abdulhamid Azad

Cuong Hung Pham

Project Implementation Start Date Project Implementation End Date

1 April 2014 31 March 2020

Expected Effectiveness Date Expected Closing Date

1 April 2014 30 September 2020

Joint IFC: No

Sector Manager Sector Director Country Director Regional Vice President

Jennifer J. Sara John A. Roome Victoria Kwakwa Axel van Trotsenburg .

Borrower:

Responsible Agency: Ministry of Agriculture and Rural Development

Contact: Tran Kim Long Title: Deputy Director-General, ICD

Telephone: Email:

Responsible Agency: Central Project Office, MARD

Contact: Vu Dinh Hung Title: CPO Deputy Director General

Telephone: 84-945095908 Email: [email protected]

.

Project Financing Data(US$M)

[ ] Loan [ ] Grant [ ] Other

[ X ] Credit [ ] Guarantee

Page 5: Project Appraisal Document +PAD+ +disclosable version+ - P130014

ii

For Loans/Credits/Others

Total Project Cost (US$M): 210

Total Bank Financing

(US$M):

180

.

Financing Source Amount(US$M)

BORROWER/RECIPIENT 30

International Development Association (IDA) 180

Total 210 .

Expected Disbursements (in US$ Million)

Fiscal Year 2014 2015 2016 2017 2018 2019 2020

Annual 10 20 25 35 35 35 20

Cumulative 10 30 55 90 125 160 180 .

Project Development Objective(s)

The Project Development Objective (PDO) is to improve the sustainability of irrigated agricultural

production systems in selected provinces in the Central Coastal and Northern Mountainous Regions of

Vietnam.

.

Components

Component Name Cost (US$ Millions)

Component 1: Improved Irrigation Water Management 10

Component 2: Irrigation and Drainage Scheme Level Improvements 170

Component 3: Support Services for Climate-Smart Agricultural Practices 23

Component 4: Project Management, and Monitoring and Evaluation, 7 .

Compliance

Policy

Does the project depart from the CAS in content or in other significant

respects?

Yes [ ] No [ X ]

.

Does the project require any waivers of Bank policies? Yes [ ] No [ X ]

Have these been approved by Bank management? Yes [ ] No [ ]

Is approval for any policy waiver sought from the Board? Yes [ ] No [ X ]

Does the project meet the Regional criteria for readiness for implementation? Yes [ X ] No [ ] .

Safeguard Policies Triggered by the Project Yes No

Environmental Assessment OP/BP 4.01 X

Natural Habitats OP/BP 4.04 X

Page 6: Project Appraisal Document +PAD+ +disclosable version+ - P130014

iii

Forests OP/BP 4.36 X

Pest Management OP 4.09 X

Physical Cultural Resources OP/BP 4.11 X

Indigenous Peoples OP/BP 4.10 X

Involuntary Resettlement OP/BP 4.12 X

Safety of Dams OP/BP 4.37 X

Projects on International Waterways OP/BP 7.50 X

Projects in Disputed Areas OP/BP 7.60 X .

Legal Covenants

Name Recurrent Due Date Frequency

Section I of Schedule 2 NO N/A

Description of Covenant:

The recipient shall maintain the implementation arrangements as described in Section I of Schedule 2 to

the Financing Agreement. .

Conditions

Name Type

Description of Condition

Team Composition

Abdulhamid Azad Task Team Leader/Sr.

Irrigation Engineer

Irrigation and Drainage MNSWA

Cuong Hung Pham Co- Task Team Leader/ Sr.

Water Resources Specialist

Water Resources EASVS

Steven M. Jaffee Lead Rural Development

Specialist

Agricultural Development/

Diversification

EASER

Christopher Paul Jackson Lead Rural Development

Specialist

Agricultural Development/

Diversification

EASVS

Masood Ahmad Lead Water Resources

Specialist

Peer Reviewer SASDA

Jacob Burke Lead Irrigation Specialist Peer Reviewer TWAIWA

Yuling Zhou Lead Procurement

Specialist

Procurement EASR2

Toru Konishi Sr. Economist Water Resources EASVS

Mei Xie Sr. Water Resources Peer Reviewer WBICC

Page 7: Project Appraisal Document +PAD+ +disclosable version+ - P130014

iv

Specialist

Nagara Rao Harshadeep Sr. Environmental

Specialist

Peer Reviewer AFTN1

Nina Masako Eejima Sr. Counsel Legal LEGEN

Kishor Uprety Sr. Counsel Legal LEGES

Son Duy Nguyen Sr. Operations Officer Portfolio EACVF

Khang Van Pham ET Consultant Environment EASVS

Miguel-Santiago

Oliveira

Senior Finance Officer Disbursements CTRLN

Mai Thi Phuong Tran Financial Management

Specialist

Financial Management EASFM

Tuan Anh Le Social Development

Specialist

Social and Gender EASVS

Huong Thi Mai Nong Associate Counsel Legal EACVF

Thang Toan Le Procurement Specialist Procurement EASR2

Thu Thi Le Nguyen Operations Analyst Climate Smart Agriculture EASVS

Tam Thi Do Team Assistant Team Assistant EACVF

Vansa Chatikavanij ET Consultant Water Resources SASDI

Non Bank Staff

Name Title Office Phone City

Chris Davey Sr. Irrigation and Drainage

Engineer, Consultant

King’s Lynn, United

Kingdom

Douglas Vermillion Institutional and Water

Management Specialist, FAO

Consultant

Spokane, Washington,

USA

Ravichandran Kannan Agronomist and Climate-

Smart Agriculture Specialist,

FAO Consultant

Chennai, India

Altaf Iqbal Sr. Agricultural Economist,

FAO Consultant

Lahore, Pakistan

John Weatherhogg Sr. Agriculture Economist

Consultant

Rome, Italy

.

Locations

Country Province Location - District Planned Actual Comments

Vietnam 1- Thanh Hoa

2- Ha Tinh

3- Quang Tri

4- Quang Nam

5- Ha Giang

6- Phu Tho

Page 8: Project Appraisal Document +PAD+ +disclosable version+ - P130014

v

7- Hoa Binh

Institutional Data

Sector Board

Agriculture and Rural Development

.

Sectors / Climate Change

Sector (Maximum 5 and total % must equal 100)

Major Sector Sector % Adaptation

Co-benefits %

Mitigation

Co-benefits %

Agriculture (20%); Climate

change (20%); Irrigation and

Drainage (60%).

96% 13%

Total

I certify that there is no Adaptation and Mitigation Climate Change Co-benefits information

applicable to this project.

Themes

Theme (Maximum 5 and total % must equal 100)

Major theme Theme %

Environment and natural resources

management

Water resource management 80

Rural development Rural services and infrastructure 20

Total 100

Page 9: Project Appraisal Document +PAD+ +disclosable version+ - P130014

1

I. STRATEGIC CONTEXT

A. Country Context

1. Over recent decades Vietnam’s agriculture has made major gains, playing an

important role in the achievement of national objectives related to economic growth, food

security, poverty reduction, social stability, and trade. Despite broader structural and

demographic changes, the sector still accounts for 22% of Vietnam’s GDP, 30% of exports and

60% of total employment. Area expansion, productivity improvements, and diversification into

higher value crops and animal products have each contributed to Vietnam’s impressive

agricultural growth story. Thanks to this widely acknowledged success, the challenges for food

security in Vietnam are no longer about total production of rice, but about addressing nutrition,

affordability, and pockets of vulnerability.1

2. Irrigation and drainage investments have had a strong impact on agriculture

intensification, productivity and diversification. Some 9.6 million hectares or 29% of

Vietnam’s total land area is cultivated. Around 4.5 million ha or 46% are irrigated and about

2.5million ha or 26% have drainage. Long-term gains have been achieved in paddy productivity

and cropping intensity. In 2012 milled rice export exceeded 8 million tons, making Vietnam the

second largest rice exporter in the world. Irrigation has also contributed significantly to

expansion of coffee, horticulture and aquaculture production.

3. However, the sustainability of these gains is at risk. Over half of the irrigation and

drainage systems are deteriorating and/or operating below their potential capacity. Rates of water

productivity are well below international standards and this poses a threat given climate change

impacts and increased competition for water resources. The financial sustainability of many

irrigation systems is uncertain. Irrigation service providers need to improve their performance to

meet the increasingly complex demands of farmers.

4. The Central Coast Region, dominated by large schemes for rice cultivation, faces

increasing challenges for water management. Inadequate drainage and flood management

infrastructure often leads to damage to lower end distribution systems, especially earth-lined

channels. Water demand for hydropower, aquaculture, municipal and industrial needs is

increasing, but institutional arrangements for water sharing are lacking. As a result of increased

water storage, withdrawals and climate change, saline intrusion is increasing. Although rice

continues to dominate, diversification into crops such as high value horticulture and sugarcane

is growing as a result of local government initiatives and nascent market forces.

5. The Northern Mountain Region has an underdeveloped potential for agricultural

commercialization. Its farming population is generally very poor. In this region there are

some pockets of successful sugarcane, livestock, and horticultural crop production. Irrigation

schemes tend to be small and often include pump stations. As in the Central Coast Region,

schemes are prone to flooding and drainage problems. Water storage - for multiple purposes - is

especially important in the mountainous terrain where catchments are narrow and steep.

1 “From Rice Bowl to Rural Development: Challenges and Opportunities Facing Vietnam’s Mekong Delta Region”, Jaffee et al.

(2012).

Page 10: Project Appraisal Document +PAD+ +disclosable version+ - P130014

2

B. Institutional Context

6. Investments in irrigation, flood control, and to a lesser extent drainage have

dominated public expenditures in agriculture. The Department of Water Resources (DWR) at

the Ministry of Agriculture and Rural Development (MARD) is responsible for development and

management of the irrigation sub-sector. The Provincial Departments of Agriculture and Rural

Development (DARDs) are responsible for planning, operation and maintenance (O&M),

monitoring and regulation of irrigation at the provincial level under the guidance of the

Provincial People’s Committee (PPCs). O&M is financed through state and provincial budgets

and carried out by Irrigation and Drainage Management Companies (IDMCs). Farmers are

responsible for tertiary and on-farm level O&M. An increasing share of the IDMCs’ budgets is

allocated to staff salaries, while less priority is given to maintenance.

7. While irrigated agriculture has been highly successful, modernization of the

irrigation and drainage sector is needed in response to various drivers of change which

include evolving markets, competition for resources (public finance, land and water), and climate

change. Increased rice production has been achieved but consumption trends are shifting rapidly,

requiring cropping changes and more flexible irrigation systems. Systematic changes are needed

beyond infrastructure, including institutional changes, and a more equitable, precise, and flexible

service delivery. Irrigation and drainage improvement also needs to be accompanied by strong

agricultural support services for farmers to maximize investment returns and promote

sustainability. At present the participation of women in irrigation management and water users’

association decision-making processes remains limited.

8. Agricultural sector restructuring, a new Water Law, and a forthcoming Law on

Hydraulic Works present opportunities for irrigation modernization. MARD’s plan for

restructuring the agricultural sector, approved by the Prime Minister in June 2013, calls for

performance monitoring of returns on resources invested, and the added value to the economy.

The new Law on Water Resources stipulates that water must be allocated in an economically

efficient manner in anticipation of growing pressures on water resources from increased

urbanization, industrialization and climate change. Both these reforms require a more strategic,

efficient, and market-oriented approach. The new Law on Hydraulic Works (expected in 2015)

will provide an opportunity to promote new concepts of modernization for the sector, especially

with respect to institutions.

C. Higher Level Objectives to which the Project Contributes

9. This project is consistent with the World Bank Vietnam Country Partnership

Strategy (CPS) for 2012 to 2016 with respect to: (i) strengthening competitiveness through

increased productivity and land-use efficiency; (ii) enhancing sustainability through improved

water productivity; and (iii) broadening access to social and economic opportunity through

improved access to water services. It also supports CPS themes by: (i) strengthening governance

through enhanced accountability of irrigation service providers; (ii) increasing resilience to

economic and climate-related shocks through promotion of climate-smart agriculture activities;

and (iii) priority to gender issues and active participation of men and women in the project.

Page 11: Project Appraisal Document +PAD+ +disclosable version+ - P130014

3

10. The Government of Vietnam has requested World Bank support to the irrigation

and drainage sub-sector. In support of MARD’s initiative of agricultural restructuring, the

Government has requested the Bank to fund selected investments and institutional strengthening

measures associated with irrigated agriculture in selected provinces located in the Central

Coastal and the Northern Mountainous Regions.

11. This project is closely linked to the World Bank portfolio in Vietnam, including

investment projects and analytical work. The World Bank currently has several active

irrigation projects in Vietnam. Small-scale investments in irrigation are also included in the

Second Northern Mountains Poverty Reduction Project. The Bank also supports policy and

institutional development in the irrigation sector in the ongoing Climate Change Development

Policy Operation Series.

12. The long-term vision is to support the Government in developing programmatic, results-

based approaches. This is predicated on the continued progression of institutional reforms, such

as irrigation management transfer to water users associations, and improvement of the

performance of the IDMCs, as well as necessary improvements in the legal, financial and

monitoring/reporting systems. Once these improvements are in place, Vietnam, like many other

countries, would benefit from launching a large-scale irrigation and drainage modernization

programme in which public-private partnerships could also play a role.

II. PROJECT DEVELOPMENT OBJECTIVES

A. PDO

13. The Project Development Objective (PDO) is to improve the sustainability of irrigated

agricultural production systems in selected provinces in the Central Coastal and Northern Mountainous

Regions of Vietnam.

B. Beneficiaries

14. The key beneficiaries of this project include farmers and other rural households,

irrigation and drainage entities, and water users organizations/associations in the project areas.

Through direct irrigation and drainage service investments (covering an area of 83,400 ha) and

on-farm water management focused in these areas, it is estimated that 243,000 farm families will

benefit from the project.

C. PDO-Level Results Indicators

15. The key PDO-level results indicators are (see Annex 1 for more details):

i) Area provided with improved irrigation and drainage services.

ii) Female and male water users provided with improved irrigation and drainage

services.

iii) Number of farmers adopting improved agricultural practices.

Page 12: Project Appraisal Document +PAD+ +disclosable version+ - P130014

4

iv) Operational WUAs created and/or strengthened.

III. PROJECT DESCRIPTION

A. Project Components

16. Geographic Focus: The proposed project will focus on two regions of Vietnam: the

Central Coast Region (Thanh Hoa, Ha Tinh, Quang Tri, and Quang Nam provinces) and the

Northern Mountainous Region (Ha Giang, Phu Tho, and Hoa Binh provinces). The provinces

and their irrigation and drainage systems are representative of their respective regions and

therefore lessons learned under this project can be used elsewhere in the regions.

17. Project Components: The project will have four components. (Detailed descriptions are

provided in Annex 2.)

18. Component 1: Improved Irrigation Water Management (US$10 million). This

component will improve institutional capacity for modern, efficient, and accountable irrigation

and drainage service delivery. The establishment of a financially self-reliant and transparent

water services sector will enable reduction in recurring government expenditure on O&M of

irrigation systems in all project provinces and at Ministry level. The component will include: i)

formation or strengthening of water user organizations and associations and the application of

the concept of Irrigation Management Transfer (IMT); ii) enhancing irrigation and drainage asset

management and investment planning at provincial and scheme levels; iii) updating and applying

efficiency and performance standards for water user organizations and associations as well as

irrigation and drainage management companies; and (v) application of remote sensing imagery

for monitoring of crop performance.

19. Component 2: Irrigation and Drainage Scheme Level Improvements

(US$170 million). The poor condition of irrigation and drainage infrastructure in the project area

is a major factor in poor water service delivery and low efficiency. This component represents

the bulk of infrastructure investments in the project areas (83,400 ha). It will improve bulk water

delivery to irrigation systems, service delivery, and management in the selected irrigation and

drainage schemes through: (i) physical improvement of selected existing large, medium and

small-scale irrigation and drainage infrastructure such as canals, pumps, weirs, pipes, and control

structures; (ii) improvement of protection works for existing dams; (iii) rehabilitation or

construction of small multi-purpose village ponds; and (iv) construction of measuring devices

and installation of control and data acquisition systems for improved water management, with

associated logistical support.

20. Component 3: Support Services for Climate-Smart Agricultural Practices

(US$23 million). This component will build on the improved irrigation infrastructure and water

delivery activities realized under Component 2 to improve the productivity and quality of

agriculture, increase farmers’ incomes, and reduce their vulnerability to adverse climatic events.

It will involve: i) enhancing on-farm systems for crop intensification and diversification; ii)

provision of laser land-leveling services; iii) advisory services to facilitate shifts towards feed

and horticultural crop production; iv) identification and implementation of measures to reduce

the water and environmental footprints of cropping systems; v) promoting community-led

Page 13: Project Appraisal Document +PAD+ +disclosable version+ - P130014

5

initiatives to increase ownership and accountability at the local level; and vi) stimulating

modernization by promoting the use of sprinkler and drip irrigation systems. Through Farmer

Field Schools (FFS) and other methods information will be disseminated and field

demonstrations will be organized. Each province will undertake research projects on technical

and policy-related issues to resolve specific problems which occur with regard to water

management and agricultural production as a result of climate change. This research will be

carried out during the first two years so that results can be applied during the last four years of

project implementation.

21. Component 4: Project Management, Monitoring and Evaluation (US$7 million). This component supports the operating costs of the implementing agencies including MARD and

the selected provinces. It will finance: (a) incremental operating costs; (b) equipment and

vehicles purchase; (c) monitoring and evaluation, including third-party monitoring; (d) staff

training; (e) internal and external audits; and (f) various consultancies for the design,

construction supervision, quality control support, a gender action plan, and safeguards

compliance.

B. Project Financing

22. The lending instrument is Investment Project Financing (IPF). The total project cost over

a six-year implementation period is estimated at US$210 million, of which the World Bank will

provide US$180 million. The Government of Vietnam will provide the remaining US$30

million.

Table 1: Project Cost and Financing Plan

(US$ Million)

Project

Project Cost and Component Cost

US$ million

Component 1: Improved Irrigation Water Management 10

Component 2: Irrigation and Drainage Scheme Level Improvements 170

Component 3: Support Services for Climate Smart Agricultural Practices 23

Component 4: Project Management, Monitoring and Evaluation 7

Total project cost (including physical and price contingencies) 210

Government of Vietnam (14%) 30

World Bank (86%) 180

C. Lessons Learned and Reflected in the Project Design

23. The project builds on international irrigation, drainage and agricultural sector experience,

gained notably from the recently completed Vietnam Water Resources Assistance Project

(VWRAP), and from the findings of the recent technical assistance (TA) on the Irrigated

Page 14: Project Appraisal Document +PAD+ +disclosable version+ - P130014

6

Agriculture and Irrigation Systems Management Reform. The project design also recognizes

Vietnam’s irrigated agriculture sector’s vulnerability to climate change.

24. Irrigation and drainage improvement also needs strong agricultural support

services to maximize investment returns and promote sustainability. To maintain

productivity in the face of climate change impacts, and to diversify production systems in line

with changing economic conditions and demands, farmers need to acquire and apply knowledge

about improved agronomic and risk management practices.

25. Irrigation management and infrastructure improvements must go hand in hand. Extensive international experience has demonstrated that irrigation modernization is not merely a

matter of adding measurement and control structures, but also requires a mindset change:

irrigation services for farmers, and existing institutional arrangements and policies must be

systematically analyzed and redefined. Therefore, project design is based on a combination of

infrastructure improvement and management solutions (e.g. improvements in monitoring,

planning, institution strengthening, and operation).

26. Transparency and accountability are core elements of performance management

and service delivery. There is a need to strengthen accountability and governance on the side

of the providers (IDMCs) as well as the recipients (farmers) of the service. To overcome

chronic problems of poor maintenance and inadequate service delivery in irrigation schemes,

the aforementioned TA emphasized the importance of having a clear agreement between

IDMCs, WUAs and farmers about respective roles and responsibilities, proper financing

arrangements2, and transparency and accountability in monitoring the agreement

3.

27. IDMC business plans can be an effective tool to improve water delivery. The IDMC

business plans can clarify performance indicators, and specify methods and targets for

improving service delivery, human resources, asset management, cooperation with WUAs, and

financial accountability.

28. The Government’s decentralization of project planning and supervising has

improved irrigation performance. The project will further strengthen this decentralized

approach both at scheme level and at field level by supporting the formation of WUAs.

29. Scaling up local knowledge and initiatives on sustainable farming practices is

essential. A close linkage between farmers and researchers has been fostered under many

previous initiatives and has led to an increased capacity, nationally and locally, to design and

guide the implementation of climate-smart agriculture. This project will engage with local

research institutes and universities to support the (continued) application by water users

associations/organizations of sustainable farming practices and techniques in project areas.

2 A Government Decree 115/2008/ND-CP in 2008 exempted most farmers from paying fees for services provided

by the IDMCs. 3 The deficiencies of the current irrigation monitoring system have been acknowledge in MARD’s strategy

Restructuring the Agriculture Sector towards Greater Added value and Sustainable Development (August 2012).

Page 15: Project Appraisal Document +PAD+ +disclosable version+ - P130014

7

IV. IMPLEMENTATION

A. Institutional and Implementation Arrangements.

30. The Ministry of Agriculture and Rural Development (MARD) will be the executing

agency for the project. Through previous projects, MARD has built substantial capacity and

knowledge about Bank procedures at the sectoral and project levels. MARD will establish a

Project Implementation Steering Committee (PISC) to be led by the Vice-Minister for Irrigation,

with the support of the Vice-Minister for Agriculture.

31. At ministry level the Vice-Minister for Irrigation will oversee project implementation,

provide policy and strategy related guidance, and chair the PISC. Within MARD, the Vice-

Minister for Irrigation is supported by the Department of Construction Management and the

Directorate of Water Resources (DWR) which are mandated to provide policy, planning, and

management oversight of irrigation schemes. The Department of Crop Production and of Plant

Protection will be responsible for overseeing the implementation of Component 3. To ensure

smooth implementation a clear division of responsibilities amongst the various implementation

departments within MARD has been defined and is presented in the Project Operational Manual

(POM).

32. The project owner would be MARD’s Central Project Office (CPO) which manages all

ODA-financed water resources sector projects. CPO staff, which include managers, engineers,

safeguards specialists, procurement specialists, and financial management specialists, are

familiar with both Governmental and Bank requirements. A Central Project Management Unit

(CPMU) has been established within CPO to provide day-to-day project management and

coordination support between the implementation agencies, the Bank, provincial authorities and

other relevant departments of MARD. This arrangement is in line with Government Decree 38

on management and utilization of ODA projects/programs.

33. The key principles of project management are as follows:

Full decentralization and empowerment will be granted from MARD and the provincial

authorities to the appropriate project implementing agencies at both the project and sub-

project levels.

MARD and CPO will provide supervision, monitoring and technical assistance support to

the project at all levels involved. They will also participate in the Bank’s regular

implementation support missions throughout project implementation.

34. Implementation of the subprojects will take place at the provincial level though the

existing Provincial Project Management Units (PPMU). The PPMUs will be composed primarily

of staff from the provincial Departments of Agriculture and Rural Development (DARD) and the

Irrigation and Drainage Management Companies (IDMCs), under the authority of the Provincial

Page 16: Project Appraisal Document +PAD+ +disclosable version+ - P130014

8

People’s Committees (PPCs)4. Operating under the overall MARD project management

framework, the PPMUs will be responsible for launching the calls for proposals, conducting

proposal screening and short-listing, managing procurement for the subproject, supervising

construction activities, and making payments to contractors. MARD’s CPMU will oversee

management of the project designated account, the procurement of ICB and QCBS contracts, and

will ensure safeguards compliance. The CPMU will report to IDA and MARD as appropriate.

B. Results Monitoring and Evaluation (M&E)

35. The project’s M&E system will focus on tracking and assessing project implementation

progress, outputs, outcomes and impacts across the four components.

36. The CPMU will be responsible for monitoring implementation progress (see Annex 1

project results and monitoring framework). During implementation, the CPMU will recruit

dedicated staff to monitor project progress and update the monitoring indicators. Reports on

progress, financial and procurement information, as well as updated indicators will be provided

to the Bank on a semi-annual basis.

37. An external third-party agency, such as a university or research institute, will be

responsible for evaluating the project’s impact on beneficiaries. For this purpose, funding is

included to undertake baseline and final year surveys, including a provision for any thematic

studies that the Government and the Bank jointly regard as relevant, justified and supportive of

Components 1, 2 and 3. As an important part of M&E the project will utilize remote sensing

studies on an experimental basis to assess irrigated areas, water volume consumed by crops

(actual evapotranspiration) and agricultural production (yields).

38. Prior to the mid-term review, the CPMU will provide the Bank with a summary project

progress report, updated results indicators (as in Annex 1), updated project cost estimates, and

plans for completion. The CPMU will also prepare environmental and social safeguards

implementation reports,

C. Sustainability

39. Sustainability is a core project principle and has been factored into the project design

through the following features:

40. Commitment to institutional reform (related to Component 1): Long-term

sustainability of the project’s benefits depends primarily on the introduction of institutional

reforms supported by the provincial authorities under MARD oversight. The Government and

MARD recognize the need to develop appropriate legal codes and guides to improve public and

private sector governance, management and financing of irrigation and drainage systems.

Specifically, following the enactment of the Water Resources Law in January 2013, MARD is

drafting the Law on Hydraulic Works. The provisions of the current draft include the collection

of baseline surveys, planning, financing, management and institutional reform. The

4 Except for Ha Tinh province where implementation responsibility rests with the South-Ha Tinh Irrigation and

Drainage Management Company acting through its PPMU

Page 17: Project Appraisal Document +PAD+ +disclosable version+ - P130014

9

Government’s commitment to institutional reform is evident through the project’s PIM programs

which will be established in each of the project provinces to help provide a forum for increased

farmer interaction with the IDMCs.

41. Irrigated agriculture investments (related to Component 2 and 3): Close engagement of

WUOs, WUAs and farmers as well as the Government is necessary to ensure adequate human

and financial resources for operation and maintenance of the investments, which is vital for

future sustainability. All activities, including the major infrastructure works and agriculture

packages are designed to involve stakeholder participation. For instance, the designs for the

rehabilitation of the infrastructure works will involve extensive community consultations,

involving both the Women’s Union and Farmer’s Union. This approach is considered critical to

ensuring that the investment impacts are long-lasting.

42. Service-delivery and physical asset sustainability. The project creates incentives and

provides support for good asset maintenance and management, including assets procured through

the project. With regard to institutional capacity, the PDO reflects the overall project focus of

building viable irrigation and drainage schemes and improved capacity for service delivery.

43. Borrower’s commitment and ownership: The Government’s commitment to the project

is evident through the resources it has allocated to the project such as: i) sufficient budget and

staff have been provided to various divisions under MARD to undertake preparatory work and to

ensure a smooth transition into project implementation; and ii) the GOV’s agreement to finance

14% of the total project cost.

V. KEY RISKS AND MITIGATION MEASURES

A. Risk Ratings Summary Table

Stakeholder Risk M

Implementing Agency Risk

- Capacity M

- Governance S

Project Risk

- Design M

- Social and Environmental M

- Program and Donor NA

- Delivery Monitoring and Sustainability M

Overall Implementation Risk M

B. Overall Risk Rating Explanation

44. The overall risk rating for this project is moderate given the high level of ownership

displayed at the Government, WUOs, and farmer’s level, as well as the experience of the

Page 18: Project Appraisal Document +PAD+ +disclosable version+ - P130014

10

Government in implementing Bank-funded projects. Various consultations with a number of

Governmental departments and stakeholders have been conducted since the concept stage to

build ownership of the project at all levels. These consultations will continue during

implementation. MARD will continue to oversee and guide the implementation and monitoring

of all project activities in order to ensure synergy and coordination amongst activities and

relevant agencies. The risks identified and mitigation measures proposed are detailed in Annex 4,

the Operational Risk Assessment Framework (ORAF).

VI. APPRAISAL SUMMARY

A. Economic and Financial Analyses

45. Project Benefits: The project will improve the water services in each sub-project

command area, resulting in a more reliable, flexible, equitable, and responsive water delivery to

users, including farmers. The irrigation modernization component is expected to increase the

land area under full gravity-serviced irrigation, while reducing the non-irrigated and/or

unreliably irrigated land area. Improved water supply and irrigation will also provide farmers

with the opportunity to intensify and/or diversify their present cropping patterns. For example, an

increased diversification into higher-value crops such as peanuts and soy beans is expected to not

only provide farm families with increased income but also improve soil fertility, and reduce pest

and disease incidence by breaking the cycle of grain cropping.

46. The main benefits will be to agricultural production in the command area, and most of the

benefits will accrue as increases in crop production arising from the conversion from rain-fed to

irrigated agriculture, or from improvements in output of existing irrigated areas resulting from

more reliable and timely available water supply.

47. Economic Rate of Return: The analysis indicates that irrigation rehabilitation is

economically viable in all the regions, with internal rates of returns (ERRs) ranging from 14 to

24% as detailed in Annex 6. The overall ERR is calculated at 18% with a net present value at a

10% discount rate of US$66.0 million (VDN 1,386 billion). These results are robust across a

range of sensitivity tests relating to changes in project cost and benefit assumptions.

48. Financial Analysis. The farm-level analysis indicates that annual net margins for a

typical 0.34 ha full gravity-irrigated farm increases by around VND 1.84 million or US$88

annually at full project development. For the partially irrigated and pumped 0.34 ha farm the

increase is VND 2.2 million or US$ 107 annually. Overall, about 243,000 families will benefit

directly from improved irrigation and drainage. The irrigation improvement works would give

the greatest benefit to farms at the lower end of canal systems which presently suffer from

inadequate irrigation or flooding, and to farms currently only rain-fed. These areas are home to

the poorest families in the schemes and the project is therefore inherently poverty-targeted.

49. Fiscal Impact. The project is expected to have a positive impact in reducing the

Government’s O&M costs in several ways, including: (i) conversion of schemes from

(expensive) pumped to (cheaper) gravity irrigation; (ii) support to formation and strengthening of

WUOs and WUAs to enable them to take over an increased share of the O&M burden currently

resting on the IDMCs; (iii) reduction in O&M costs as a result of canal lining and other

Page 19: Project Appraisal Document +PAD+ +disclosable version+ - P130014

11

improvements as well as expansion of the scheme command areas; and (iv) improvement in

overall management efficiency of MARD and the IDMCs. In addition to these cost reduction

benefits there would be an increase in tax revenue as a result of the increased agricultural

production.

50. The project will reduce the pump- irrigated area from 17,524 ha to only 2,159 ha in the

project areas. Associated pumping costs currently being paid by the farmers would be reduced by

88%. In monetary terms, this is equivalent to a reduction from VND 7.010 billion (US$ 0.334

million) to VND 0.864 billion (US$ 0.041 million) per annum. Savings in the pumping costs

would reduce the burden on the Government of subsidies being offered to the farmers.

51. The above cost savings and increased tax revenue from most schemes would likely be

sufficient to cover debt servicing at the provincial level, assuming continued government

subsidies to the IDMCs. Therefore, the overall fiscal impact of the project is expected to be

generally neutral.

B. Technical

52. The project will introduce innovations in the selected project provinces. These will

include (i) using the global best practice of climate-smart agriculture to ensure that agricultural

and water productivity are maximized; (ii) (continued) support to the state and provincial

agricultural and water agencies to enhance agricultural modernization plans; (iii) using the

project framework to help facilitate coordination across various programs and departments; and

(iv) introducing better water governance through improving information, water user

participation, and accountability for the irrigation and drainage service delivery.

53. Improvement of irrigation and drainage schemes will focus on structural and non-

structural measures. There is a need to improve both the physical systems, as well as institutional

arrangements for system operation. The physical works will be implemented by reputable

contractors under adequate day-to-day supervision by consultants appointed by DARD. Similar

irrigation projects have been carried out successfully, which gives support to the expectation that

the project works can be implemented without major difficulties.

54. The project will develop climate-smart agriculture which implies an effective and

efficient use of the irrigation and drainage systems. The effective adoption of climate-smart

practices will require intensive awareness building and training through farmer-field schools, and

learning-by-doing approaches.

55. The project proposes improvements in modern agricultural practices for improving both

technical and service delivery. It includes supporting farmers in adopting systems of rice

intensification (SRI) and crop diversification, introducing and promoting drip and sprinkler

irrigation systems, integrated pest management, improved fertilizer use based on soil tests and

the utilization of crop residues to reduce emission.

56. The project includes the conversion of irrigated areas from pumped irrigation to gravity.

One of the large-scale irrigation and drainage schemes will be converted to gravity by the supply

Page 20: Project Appraisal Document +PAD+ +disclosable version+ - P130014

12

of water from a recently completed reservoir. Appropriate modern technologies (such as turbine

pumps and low-cost drip irrigation) will be introduced in some areas within the schemes.

C. Financial Management

57. The CPMU will be responsible for financial management (FM) at a central level. Key

financial management personnel will have experience in managing Bank projects. The financial

management function in the provinces will be performed by existing provincial PPMUs except in

the two new provinces Ha Giang and Hoa Binh where new PPMUs will be established. These

arrangements meet the Bank’s minimum financial management requirements at both central and

provincial level.

58. Fund flow will be channeled through the Designated Account and provincial project

accounts opened at commercial banks. There will be one segregated Designated Account (DA)

denominated in US$ dollars maintained by CPMU for the whole project. Each of the provinces

will maintain a provincial project account in VND at a commercial bank in the province to

receive funds from the Designated Account for the activities to be implemented by the provinces.

59. There will be a single auditor, hired by CPMU. CPMU will consolidate all provincial

financial statements to provide one overall project financial statement, to be audited and

submitted to the Bank annually within 6 months after the year-end. Interim Financial Reporting

(IFR) will be done on a semester basis to be submitted to the Bank within 45 days after the end

of each semester.

D. Procurement

60. The CPMU will lead and coordinate the procurement activities for the whole project,

provide guidance to the PPMUs on all procurement-related aspects, and monitor the procurement

activities to be carried out by the PPMUs, while PPMUs will be responsible for procurement

within their respective provinces. The capacity assessment of the CPMU and PPMUs has been

conducted by reviewing the project organization structure and functions, past experience of

implementing agencies, staff skills, quality and adequacy of supporting and control systems, and

the legal and regulatory aspects. The CPMU and several PPMUs are familiar with the Bank’s

procurement procedures. However, there is a risk that procurement delays occur at all stages of

the procurement cycle including planning, preparation of procurement documents, bid

evaluation, approval of bid evaluation report and award recommendation and contract

management.

61. Procurement plan and readiness for implementation. The procurement plan for

activities to be taken up during the first 18 months of project implementation has been agreed

and is available in the project files. The procurement of major civil works, goods and

consultancies has been identified. Detailed engineering designs and bidding documents for over

35,000 ha, or more than 42% of the project area have been completed. More details on the

procurement arrangements are provided in Annex 3.

Page 21: Project Appraisal Document +PAD+ +disclosable version+ - P130014

13

E. Social (including Safeguards)

62. The project promotes transparency and informed participation of the target beneficiaries,

encouraging farmer participation and supporting the realization of the project’s expected broad

range of positive social impacts including reduced time and efforts needed to irrigate fields and

to maintain irrigation canals; reduced conflicts as a result of better on-farm water management

practices and more reliable irrigation services; improved access to water at tail-ends of the

canals; increased participation of women in water users organizations and associations and on-

farm irrigation, resulting from less physically-demanding operations at the farm outlet.

Agricultural productivity and resilience to climate variability and extreme weather events are

expected to increase with the improvement of irrigation and drainage infrastructure, the

promotion of enhanced climate-smart practices, and the building of stakeholders’ capacity.

63. A Social Assessment (SA) was carried out during project preparation to: (a) explore

potential positive and negative impacts of the project to inform the project design and impact

mitigation measures; and (b) to consult with ethnic minority peoples present in the project area in

accordance with OP 4.10. The SA confirmed that the overall social impact of the project is

positive, given its aim to strengthen national, provincial, and local capacities for better irrigation

management. However, some negative impacts, primarily related to acquisition of land to allow

for rehabilitation of existing infrastructure, is unavoidable. In some sub-project areas, land

acquisition is expected to affect ethnic minority households. The results of the SA are set out in

Annex 7 and summarized as follows:

64. Loss of land would affect some 4,500 households, but 95% of these would lose only

a small strip beside the canal. Affected households number 220, of which 13 may require

relocation. Some 97 ha would need to be permanently acquired and 105 ha temporarily

during construction. 65. Adverse impact on ethnic minority peoples is primarily due to land acquisition to

allow rehabilitation of the existing infrastructure. However, for them, too, the project will

lead to improved water availability. The project design has furthermore kept the number of

affected households to a minimum, project preparation included full consultation and the

ethnic minority peoples have indicated community support for the project and will be fully

involved in Participatory Irrigation Management (PIM).

66. Involuntary Resettlement (OP 4.12) was triggered due to the need for land acquisition

and a Resettlement Policy Framework (RPF) was prepared to guide Resettlement Action Plans

(RAP).

67. Indigenous Peoples (OP 4.10) was triggered and an Ethnic Minority Policy Framework

(EMPF) prepared. As detailed in Annex 7, the EMPF was developed to ensure ethnic minorities

have an opportunity to receive socioeconomic benefits from the project in a way that is culturally

appropriate to them, and to provide guidance on preparation of Ethnic Minority Development

Plans (EMDP) for sub-projects to be identified during project implementation.

Page 22: Project Appraisal Document +PAD+ +disclosable version+ - P130014

14

68. Social safeguards implementation: The implementation of the RAPs and EMDPs will

be the responsibility of the respective PPMUs. Land acquisition will be financed by the

Government whereas the budget for EMDP will be funded by the Bank.

69. Gender mainstreaming: Females in the project area are generally at a disadvantage.

Although equality laws have been passed, men still dominate most aspects affecting agricultural

development, including implementing processes for improving productivity. Men dominate at

meetings where landowners meet, including extension training. Men also dominate in water

management since they are considered more able to resolve disputes and technical problems. In

community organizations about 30% of the members are women, but they mostly hold the lower

clerical-type positions. The GAP has been developed during project preparation, and it has

included consultation with relevant governmental mass organizations at the central level (Central

Women’s Unions and Farmers’ Associations). The GAP aims to change the ideas, attitudes and

behaviors of the community with regard to full participation of women in project activities,

which will benefit the position and power of women in the project areas. The GAP will be

implemented and monitored as part of Component 4.

70. Public Consultations and Information Disclosure: A series of public consultations

have been conducted in accordance with Bank policy requirements and national laws. Before

conducting public consultations, the relevant project documents have been disseminated to

project-affected groups and local NGOs. The Vietnamese and English versions of these

documents were disclosed at the Bank’s InfoShop and in Vietnam during the period from June

19 to July 16, 2013.

F. Environment (including Safeguards)

71. The overall environmental impacts of the project are expected to be positive. The

improvement and upgrading of irrigation and drainage infrastructure and on-farm irrigation and

drainage will lead to more efficient and productive use of irrigation water and increased crop

yields. The dissemination of irrigation technology and the strengthening of water users

associations and local farmer organizations will further improve overall water and land

management at the local level. For purposes of O.P. 4.01 on Environmental Assessment, the

project has been classified as Category B, given that no significant, irreversible or long-term

adverse environmental impacts are anticipated and that any identified adverse impacts can be

effectively addressed through appropriate preventative or mitigating measures. The project could

result in intensifying crop production in terms of vertical expansion, which could increase the

residual pesticide/ fertilizer load per hectare in some project areas. These and other

environmental issues were examined closely during the Environmental Impact Assessment (EIA)

and are addressed in the Environmental Management Plan (EMP). The CPMU will be

responsible for implementation of the EMP, whereas the day-to-day management of the

prevention/ mitigation activities will be undertaken by PPMUs. The EMP addresses the

environmental impacts identified by the EIA through a combination of preventative actions and

mitigation measures, including environmental monitoring/benchmarking and institutional

capacity building.

72. Further details are provided in Annex 7. The project triggers five environmental safeguard

policies, namely:

Page 23: Project Appraisal Document +PAD+ +disclosable version+ - P130014

15

OP/BP 4.01(Environmental Assessment): The project has civil works for irrigation and

drainage schemes. An Environmental and Social Management Framework (ESMF) has been

prepared for the project and Environmental Management Plans (EMP) and Environmental

Codes of Practices (ECoP) have also been prepared for sub-projects in accordance with Bank

safeguards policies.

OP/BP 4.11 (Physical Cultural Resources): Relocation of 12 graves in Thanh Hoa sub-

project triggered OP/BP 4.11. Mitigation measures have been included in the EMP for this

sub-project. Also, a “chance find procedures” will be included in EMP and ECOP in case any

unexpected cultural resources are found during construction.

OP/BP 4.09 (Pest Management): The project will not finance the purchase of pesticides but

with the increase in irrigated land area to 83,400 ha the amount of agricultural chemicals

including fertilizers and pesticides will increase. An Integrated Pest Management Plan

(IPMP) has been prepared by MARD as part of the ESMF.

OP/BP 4.37(Safety of Dams): A Dam Safety Framework has been prepared to comply with

the requirements on dam safety.

OP/BP 7.50 (International Waterways): The sub-project to improve the South Ma scheme

will draw water from the Cua Dat Reservoir, located on the trans-boundary Chu River. This

project falls within the exception provided for in paragraph 7(a) of OP 7.50.

Page 24: Project Appraisal Document +PAD+ +disclosable version+ - P130014

16

Annex 1: Results Framework and Monitoring

Irrigated Agriculture Improvement Project

.

Project Development Objectives

The Project Development Objective is to improve the sustainability of irrigated agricultural production systems in selected provinces in the Central Coastal

and Northern Mountainous Regions of Vietnam.

.

Project Development Objective Indicators

Cumulative Target Values

Frequency Data Source/

Methodology

Responsibility

for Data

Collection Description

(Indicator

Definition)

Indicator Name Core Unit of

Measure Baseline

Y

R1 YR2 YR3

YR4

YR5 YR6

Direct project

beneficiaries HHs 0 0 0 100,200 165,300 210,800 243,000 Yearly

Project

reporting PMU

Area provided

with irrigation

and drainage

services -

Improved

Hectare

0 0 5,450 31,760 57,520 75,370 83,400 Yearly

IDMC records,

Third party

supervision

consultancy

records

Not including

area for

aquaculture

Water users

provided with

improved

irrigation and

drainage

services

Number 0 0 0 252,900 450,800 633,900 674,800 Yearly

Water users

provided with

improved

irrigation and

Number

(Female) 0 0 0 125,900 224,600 316,000 336,700 Yearly

Page 25: Project Appraisal Document +PAD+ +disclosable version+ - P130014

17

drainage

services

Water users

provided with

improved

irrigation and

drainage

services

Number

(Male)

0 0 0 127,000 226,200 317,900 338,100 Yearly

Farmers in

scheme area

adopting

improved

production

techniques

HHs Number 0 0 1,000 3,950 7,650 11,950 15,700 Seasonal Project report PPMU

Techniques

promoted for

adoption in each

location need to

fir the local

conditions.

Operational

water users

association

created and/or

strengthened

Number 0

0

2

5

10

20

20

Baseline,

mid-term,

yearly, and

final

WUA records,

IDMC

records, WUA

support

consultancy

records, impact

evaluation

surveys

Intermediate Results Indicators

Indicator Name Core Unit of

Measure Baseline

Cumulative Target Values

Data Source/

Methodology

Responsibility

for

Data

Collection

Description

(indicator

definition) YR1 YR2 YR3 YR4 YR5 YR6 Frequency

Component 1: Improved irrigation water management

Each province

develops and

implements a

five year and

Provincial

plans

Existing

plans not

comprehen

sive,

3 3 7 7 7 7

Page 26: Project Appraisal Document +PAD+ +disclosable version+ - P130014

18

annual

modernized

irrigated

agriculture plans

partially

implement

ed

Improved

performance of

IDMC Score cards

To be

determined Yearly

IDMC annual

reports

DARD or

Consultant

The score card

will be based on

few easily

measured

indicators,

weighted to

provide an

overall score

WUAs -PIM

agreements

established and

implemented

Number of

service

contracts

0

0

2

5

10

20

20 Yearly

IDMC annual

reports

DARD or

Consultant

Percentage

increase in

WUAs

assessing

service delivery

by IDMC as

satisfactory

% of WUAs 0 0 0 30 40 50 90 Seasonal

Seasonal

interviews

with WUO

officer

DARD or

Consultant

Component 2: Irrigation and drainage scheme level improvement

Area provided

with irrigation

and drainage

services -

Improved

Hectare 0 0 5,451 31,763 57,515 75,368 83,425

Increase in crop

yields in project

areas

- Paddy

(winter-

spring)

0

- - 0.19 0.34 0.47 0.54

Remote

sensing data,

ground truth

data

Paddy 0 - - 0.18 0.35 0.49 0.57

Page 27: Project Appraisal Document +PAD+ +disclosable version+ - P130014

19

(summer-

autumn)

collection,

impact

evaluation

surveys Maize 0 - - 0.11 0.19 0.26 0.29

Increase in

irrigation

intensity % 0 100 107 136 151 175 205

Component 3: Support services for climate smart agriculture practices

Seasonal

Farmers Field

School

establishes

Number 0 35 105 245 385 525 670 Seasonal Project report PPMU

Area under ICM

cultivation5 Hectare 0 0 800 1,500 5,000 12,000 20,000 Seasonal Project report PPMU ICM

6

Area under drip

irrigation Hectare 0 0 50 110 260 500 698 Seasonal Project report PPMU

New cropping

system with

technologies Number 0 0 28 28 28 28 28 Yearly Project report PPMU

Systems will

have better

profits and

reduced negative

impacts on the

environment due

to adoptions of

ICM.

5 Area under ICM cultivation in scheme commands including: appropriate varieties; good quality seed/seedlings; appropriate plant density; proper management of plants

(fertilization, irrigation, weeding); integrated pest management (IPM); appropriate harvest and post-harvest technique; and proper management of waste. 6 ICM is the complete technique package covering all the production steps from preparation to harvest and post-harvest. Depending on the local conditions, ICM can be

adopted completely or only partly. However, in any case IPM and appropriate balanced fertilizer regimes will need to be followed.

Page 28: Project Appraisal Document +PAD+ +disclosable version+ - P130014

20

Annex 2: Detailed Project Description

VIETNAM: Irrigated Agriculture Improvement Project

Project Components

1. The project will have four components with a total investment of US$210 million.

Project

Project Cost and Component Cost

US$ million

Component 1: Improved Irrigation Water Management 10

1.1. Operationalizing the government regulations and guides

1.2. Strengthening irrigation and drainage management companies

1.3. Strengthening the knowledge base for service contracts, performance assessment

and introduction of innovative technology and management tools

1.4. Strengthening Water Users Organizations and Associations

Component 2: Irrigation and Drainage Scheme Level Improvements 170

1. Thanh Hoa province: South Ma irrigation and drainage scheme

2. Ha Tinh province: Ke Go and Rac river irrigation and drainage schemes

3. Quang Nam province: Phu Ninh and Khe Tan irrigation and drainage schemes

4. Hoa Binh province: Medium and Small scale irrigation and drainage schemes

5. Phu Tho province: Tam Nong and Thanh Thuy irrigation and drainage schemes

6. Quang Tri province: Medium scale irrigation and drainage schemes

7. Ha Giang province: Small scale irrigation and village ponds Component 3: Support Services for Climate-Smart Agricultural Practices 23

Component 4: Project Management, Monitoring and Evaluation 7

Total project cost (including physical and price contingencies) 210

Government of Vietnam (14%) 30

World Bank (84%) 180

Component 1: Improved Irrigation Water Management (Estimated Cost: US$10 million,

including contingencies).

2. The main objectives of the VIAIP are to improve the performance of irrigation

management services in terms of productivity, equity and sustainability. The project aims to

improve agricultural productivity, adapt agriculture to climate change, protect the environment

and enhance people’s standards of living. Component 1 focuses on a number of the immediate

interventions designed to promote institutional strengthening and develop good governance,

management and financing of irrigation and drainage systems. Strengthened capacity of

governmental institutions will allow for the development of effective irrigation and water

services policies, thus contributing to the project’s long-term objectives.

Page 29: Project Appraisal Document +PAD+ +disclosable version+ - P130014

21

3. Government Regulations and Guides. A number of draft regulations (circulars or

decisions) and guides will be supported. This will include assessments, M&E, studies,

stakeholder consultations, and workshops for the preparation and finalization of these regulations

and guides.

4. Irrigation and Drainage Management Companies (IDMCs) and Public-Private

Partnerships (PPPs). This activity focuses on strengthening IDMCs’ capacity to improve

irrigation and drainage services; to manage demand; to develop business plans aimed to

strengthen professionalism and autonomy; to conduct research on the application of PPPs in the

irrigation sector; and to prepare the annual, mid-term and final reports for the sub-component.

5. Technical and Economic Norms, Service Contracts, Performance Assessment and

Introduction of Innovative Technology and Management Tools. This activity will support:

the review and update the technical and economic performance standards of the IDMCs and

WUOs for irrigation O&M and management at the provincial level; the development of criteria

to systematically assess the efficiency and operational performance of service contracts; prepare

a guide for adoption of technical and economic norms for I&D systems; implement I&D service

contracts between the IDMCs and WUAs; develop and implement Geographic Information

System (GIS) database with information on irrigation and drainage structures to aid the

development and implementation of service contracts; provide support for the installation of

SCADA systems at key regulating sites on some schemes, including transmitters and data control

centres; provide regulators and gauging structures at the interface between WUAs and IDMC

zones; develop irrigation scheme maps that include performance data used to support

decentralization of management; develop and implement databases for asset management and

service contract performance; and prepare the annual, mid-term and final reports on the

activities.

6. Development of WUAs and Irrigation Management Transfer (IMT). This activity

aims to support the establishment of new WUAs. The focus will be on selecting WUOs that can

be federated to form WUAs at secondary canal levels. The activities have been designed to link

with sub-components 1, 2 and 3 through reconfiguration of the institutional arrangements in

large and medium size schemes. The activities will include: (i) collect an inventory of the

existing types of WUOs in the project provinces and identify the locations where new WUAs can

be formed; (ii) identify locations where technical/managerial improvements are needed; (iii)

explore incentives and systems to increase the rate of water user payments of the Irrigation

Service Fee (ISF); (iv) prepare action plans for WUOs federation to form WUAs and IMT for the

selected WUAs; (v) introduce performance-based monitoring by the WUAs; and (vi) preparation

of annual, mid-term and final reports on this sub-component.

Since the Irrigation and Drainage Management Companies (IDMCs) have the responsibility

for operation and maintenance of the headworks and main canals and are responsible for the

supply of water to the WUAs, irrigation service agreements will be prepared, implemented

and monitored during implementation. In provinces where an IDMC is not appointed, the

irrigation service agreement will be between the Provincial Peoples Committee (PPC) and

the WUA.

Page 30: Project Appraisal Document +PAD+ +disclosable version+ - P130014

22

More than 20 Water User Associations will be established or strengthened during project

implementation.

7. Funds are provided for training proposed for the WUAs on all aspects including

technical, management and operation processes, all aimed to improve the capacity of the WUAs

in overall efficiency of the management of the available water resources.

Component 2: Irrigation and Drainage Scheme Level Improvements (Estimated Cost:

US$170 million, including contingencies).

8. This component will support infrastructure improvement investments for a total

command area of 83,400 ha, including the upgrading and modernization of selected existing

irrigation and drainage projects in the project area as well as making provision for some small

multi-purpose village ponds (to serve livestock, irrigation and drinking water supply) in one of

the seven provinces. Increasing the numbers of water control structures will improve the capacity

for effective and efficient management of the water resources. On all schemes the existing

infrastructure including canals, pumps, weirs, and surface drains will be upgraded and/ or

modernized. Indicators showing the present situation on some of the projects are shown in the

following table.

Indicators Phu Ninh South Ma Ke Go Rac River Khe Tan

Designed Command Area, ha 19,427 11,525 21,538 8,532 3,500

Actual Area Irrigated (5 years average), ha 11,287 6,586 14,735 4,182 2,105

% of design area irrigated 0.6 0.6 0.7 0.5 0.6

Annual irrigation water supply (m3/ha)

26,113 18,106 22,116 35,530 21,344

Actual Water Delivery Service by the

Main Canals to the Second-level Canals Average Average Average Average Average

Actual Water Delivery Service to farms Poor Poor Poor Poor Poor

% of I&D Infrastructure in good

conditions 50% 60%

50% 50% 50%

% of command area with functioning

drainage 35% 40% 35% 35% 35%

9. Works include: remodelling canal systems to be hydraulically more efficient, replacing

primary, secondary or tertiary sluice gates with more effective and efficient options; constructing

small bridges; strengthening canal banks; upgrading and modernizing energy-efficient turbine-

pumps and associated weirs with appurtenant water delivery pipelines; refurbishing existing

infrastructure; and modernizing and increasing the efficiency of major drainage pumping plants.

10. With all the project schemes reliant on dams, improving dam safety and ensuring

appropriate monitoring systems are in place is an essential activity. Funds will be allocated for

each province to adequately upgrade existing dams and appurtenant works to the standards now

Page 31: Project Appraisal Document +PAD+ +disclosable version+ - P130014

23

established by the Dam Safety Unit, including appointment of a POE to review all requirements

specified in the Dam Safety Framework completed for the project.

11. If a mid-term review concludes that works are significantly lagging and/or institutional

reforms such as irrigation management transfer are not progressing at an adequate pace, funds

could be reallocated to a better-performing province.

12. Detailed descriptions of the schemes are summarized below:

13. Phu Ninh Irrigation and Drainage scheme: The area under irrigation on this large scheme

will be increased from the present 11,287 ha to its original designed area of 19,427 ha by

upgrading the main and other canals and related works, ensuring water supplies to the tail end of

the system. The extension of one secondary canal across the Ba Ren River will increase the

command area by about 1,800 ha, providing gravity water supplies for that area, and allowing the

decommissioning of eight pump stations. This area had declining productivity due to intrusion of

saline water, in the river water as a result of climate change.

14. Southern Ma River scheme: This entire scheme will be converted by the project from a

pumped scheme, drawing water from the Ma River to a fully gravity fed irrigation scheme,

making it particularly energy efficient. This scheme will use water from the recently completed

Cha Dat Reservoir. About 80 pump stations will be decommissioned, including the Southern Ma

Pumping Station, and the conversion will save more than 6 million kWh per year.

15. Improvement of small irrigation and drainage schemes in Hoa Binh: The project will

improve small irrigation and drainage schemes covering about 4,270 ha scattered in the province.

Some schemes include upgrading the pump-turbines that raise water from rivers level to the

project areas. On other schemes project works will resolve problems such as inadequate spillway

capacity, poor construction quality control and inappropriate structural design, so as to ensure

stability and longevity of the structure.

16. Ke Go Irrigation and Drainage scheme in Ha Tinh Province: This scheme will be

improved by further upgrading of the canal system, including selective canal lining, introduction

of additional canal measurement structures, and SCADA system. All these actions will provide

the WUAs with tools to improve overall water management on the scheme and ensure that the

irrigated area increases from 11,900 ha to the original designed area of 21,563ha.

17. Rac River Irrigation and Drainage Scheme in Ha Tinh Province: The project will upgrade

the capacity of the canal system and the regulating structures for the full original design area of

8,523 ha, an increase of more than 3,600ha, including canal lining, and the introduction of flow

measurement structures. Installation of a SCADA system will assist the WUA in improving

management of the system.

18. Khe Tan Irrigation and Drainage scheme in Quang Nam Province: Only about 2,000 ha

of the original design area of 3,500 ha functions at present. The project will upgrade the main

and secondary canals, providing canal lining, regulators and other protection works to bring the

original full command area under gravity irrigation.

Page 32: Project Appraisal Document +PAD+ +disclosable version+ - P130014

24

19. Truc Kinh Irrigation and Drainage schemes in Quang Tri Province: A major part of the

works on this scheme concerns essential works to ensure the safety of the dam. The project will

upgrade the main dam section and strengthen the spillways to pass the maximum design flood. In

addition, the intake electrical valve operators would be replaced, and the overall power system

for gate and headworks operation would be repaired. In addition the canal network which covers

an area of 2,350 ha would be upgraded, including selective canal lining works, rehabilitation of

surface drainage, upgrading regulators and off-takes and providing additional gauging structures,

and SCADA system.

20. La Nga Irrigation and Drainage scheme in Quang Tri Province: The project will upgrade

the main dam section and strengthen the spillways to pass the maximum design flood. In addition

monitoring equipment for seepage and subsidence will be installed. The electrical system

including intake electrical valve operators and the overall power system for gate and headworks

operation would be upgraded. The scheme covers an area of 2,000 ha. The improvement works

will include selective canal lining, and provision of regulators and measuring weirs control

structures and a SCADA system to allow efficient and effective management of available water

resources. Existing main drains will be reinstated, including upgrading gates and salinity

prevention sluices.

21. Ha Thuong Irrigation and Drainage scheme in Quang Tri Province: The upgrading of this

1.050 ha scheme includes stabilizing canal banks by selective lining, and provision of

measuring weirs, control structures and rehabilitation of surface drainage to allow efficient and

effective management of available water resources.

22. Tam Nong irrigation and drainage scheme in Phu Tho Province: Drainage infrastructure

will be provided under this scheme to benefit an area of 3,840 ha, including both agricultural

(partly irrigated) and urban areas. The drainage pumps will remove the excess rainwaters and

flood flows, and improving the irrigation and drainage canals and water control structures

serving the irrigated area.

23. Than Thuy irrigation and drainage scheme in Phu Tho Province: Drainage infrastructure

will be provided to service an area of 2,122 ha. The drainage pumps will remove the excess

rainwaters and flood flows. The pumping stations will remove up to 20m3/sec with a maximum

head of 7.2 m.

24. Small-Scale Irrigation in Ha Giang Province including village ponds: Multi-purpose

village ponds will be constructed. These rectangular tanks have a capacity generally between

3,000 to 5,000 m3

with a maximum depth of 3m. Village ponds are constructed for the following

purposes: (i) to provide safe drinking water for rural communities in areas which have droughts

and hence face substantial difficulties in getting daily water requirements; (ii) to provide water

for livestock and poultry which provide these rural communities with a major part of their

incomes; and (iii) to provide water for irrigation between 3 – 14 ha, these cultivated areas would

provide a major post in reducing poverty. A total of about 80 ha irrigated area would be

developed. To purify the drinking water the water is passed through a standard simple sand filter,

and then delivered by pipe to the closest downstream village. The water for livestock is released

Page 33: Project Appraisal Document +PAD+ +disclosable version+ - P130014

25

untreated and is similarly delivered to the downstream village. The irrigated areas would be

partly provided with family drip irrigation systems (component 3), using the water under

pressure from the pond to cultivate vegetables and fruit trees (oranges).

Component 3: Support Services for Climate-Smart Agricultural Practices (Estimated Cost:

US$25 million, including contingencies)

25. This component will build on the improved irrigation and drainage infrastructure and

water delivery activities in Component 2 to improve the productivity of agriculture, increase

farmers’ incomes, and reduce their vulnerability to adverse climatic events.

26. The Farmer-Field-School (FFS) approach is proven to be an effective mechanism to

improve agronomic and water management practices, and also to augment institutional capacity

of WUAs for water management, operation and maintenance. The FFS will consist of 20-30

farmers serving about 15-20 ha. Some of the types of activities may include: i) season-long

farmer field studies on a range of agronomic approaches e.g. ridge and furrow irrigation, border

irrigation, raised and sunken bed; ii) crop-water budgeting sessions; iii) community interactions

and consultations; iv) sustainable intensification of crop production (e.g. soil testing for

integrated plant nutrient management) and ecosystem-based and ecologically-sound crop

protection practices (e.g. IPM); and v) FFS Field Days for sharing results with other WUOs and

WUAs farmers. With all these activities, the project aims to encourage at least 20,000 farmers in

scheme areas to adopt improved production techniques during the project period.

27. All provinces will implement demonstration areas and extension of new integrated

agricultural technology packages on farmer’s fields that will increase their resilience to climate

change. Such integrated packages will comprise relevant technologies that have been proven to

be successful in climate change adaptation, but are not widely known in project areas to date.

Packages may include improved seeding technologies, crop rotations, saline/ drought/ pest

resistant varieties depending on the local conditions, systems and techniques of rice

intensification, supplemental irrigation. In particular the project will promote the use of drip and

sprinkler irrigation on 700 ha in the seven provinces, with beneficiaries contributing part of the

cost. In areas most affected by poverty the cost of installation of these more modern technologies

would be covered substantially under the project.

28. The project will finance awareness building and communication on climate smart

agriculture to the wider range of stakeholders. This will include real-time information delivery

including weather-related risks and related responses through ICT, and information awareness

campaigns through professionally produced multi-media, including radio, television, websites,

technical training materials, brochures, and other promotional and extension materials.

29. In order to capitalize on a large potential of greenhouse gas (GHG) reductions in the rice

cultivation and help Vietnam reduce GHG emissions while enhancing economic growth and

reducing poverty, the project would provide platforms to integrate GHG assessment, develop

standardized baseline on GHG emissions from rice production and to monetize the benefits of

the GHG reductions.

Page 34: Project Appraisal Document +PAD+ +disclosable version+ - P130014

26

30. Soil sampling and soil fertility testing will be undertaken so that chemical fertilizer is

applied according to fertilizer recommendations. This will result in more efficient application of

chemical fertilizers. Soil health cards and soil maps will be produced for WUOs and WUAs. Use

of organic fertilizers will be promoted. All provinces will undertake regular monitoring of

selected soil fertility properties at standard sites to evaluate the impact of soil and land

management practices on soil fertility status.

31. Finally, various types of crop residue management will be applied in all provinces to

improve soil organic matter content, soil moisture and nutrient retention. Crop residue

management will include mulching, spreading of crop residues on the soil surface to reduce

evaporation, mechanical crushing and chopping of crop residues and incorporating them into the

soil through tillage, and application of a biological agent prior to soil incorporation to speed up

crop residue decomposition.

Component 4: Project Management, Monitoring and Evaluation (Estimated Cost: US$7

million, including contingencies)

32. This component supports the operational costs and capacity development for the

implementing agencies within MARD to manage the project. The main content of this

component is: (a) project management and M&E consultation, technical consultation and

assistance for project management, consultation on implementation, monitoring, and auditing;

(b) support CPMU and PPMUs to implement the project management and implementation

activities; (c) capacity building, transfer technology, strengthen the project management and

implementation capacity of Management Units, especially the local sub-project management

units; and (d) support for implementation of the project Gender Action Plan (GAP).

33. The GAP will focus on efforts to promote participation of the whole community to

motivate them to develop the communities’ resources to achieve greater benefits, and create

favourable conditions d beneficiaries to participate in decisions affecting the project. The project

will provide more opportunities for women to become involved in the economic process,

including managing the WUAs. Empowerment of women aims to resolve the gender inequality.

The action plan will focus on (i) raising awareness at all levels of project management on gender

issues; (ii) encouraging local authorities to support gender development, and (iii) piloting

agricultural development models (including family drip systems) and strengthen WUAs with the

involvement of women.

Page 35: Project Appraisal Document +PAD+ +disclosable version+ - P130014

27

Annex 3: Implementation Arrangements

Project Institutional and Implementation Arrangements

1. The Ministry of Agriculture and Rural Development (MARD) will be the executing

agency for the project. Through previous project engagements, MARD has built substantial

capacity and knowledge about the World Bank procedures at the sector and project levels. To

support the implementation of the project MARD will establish a Project Implementation

Steering Committee (PISC) to be led by the Vice-Minister in charge of irrigation with close

coordination with the Vice-Minister in charge of agriculture.

2. The Vice-Minister has the overall responsibility to oversee project implementation as

well as to provide policy and strategy related guidance. The Vice-Minister would be supported

by the Department of Construction Management on technical aspects and the Department of

Water Resources (DWR) on institutional aspects. These two departments are mandated to

provide policy, planning, and management oversight of irrigation schemes in Vietnam. The

Departments, according to the Ministry’s authority, are also responsible for verification, review

and to make recommendation for MARD concerning approval of the proposals prepared and

submitted by CPMU and the Project Provinces.

3. The existing Central Project Office (CPO) of MARD is assigned as the project owner and

is responsible for the management of the project following the Government Decree 38-ND-CP

on managing ODA-funded projects plus the coordination and monitoring of the project

implementation at different levels. CPO will act through its Central Project Management Unit

(CPMU) which will be established by MARD and located within the CPO.

4. The CPMU, established by MARD and dedicated to implement this project, has the

following responsibilities: i) liaising with the Bank and all concerned departments and provincial

authorities; ii) serve as the secretariat of the PISC; iii) review the draft annual work plan to

determine consistency with the project objective and with the overall implementation schedule;

iv) prepare consolidated annual work plans submitted by PPMUs and submit them to the Bank;

v) coordinate and monitor project activities based on the M&E and the environment management

plans; vi) review the semi-annual progress reports based on technical inputs from the PPMUs

and submit them to the Bank; vii) review the request letters and disbursement document of the

PPMUs to transfer funds from the Designated Account (DA) to provincial project accounts; viii)

consolidate the financial management report of the DA; ix) prepare withdrawal applications; x)

arrange special studies to fulfill the project development objective; xi) prepare procurement

guidelines, standards and specifications for equipment, vehicles and spare parts; xii) carry out

internal procurement review to PPMUs; xiii) support the preparation of the Mid-Term review

report and the implementation completion report; xiv) consolidate the financial management

reports; xv) perform TA support to project provinces in all aspects; xvi) ensure the processing

quality of prior review contracts, and then submitting them to the Bank for review and clearance;

xvii) prepare and implement training for staff involved in project implementation; and xviii)

address other policy matters, including as climate change.

Implementation Structure

Page 36: Project Appraisal Document +PAD+ +disclosable version+ - P130014

28

5. Implementation of the subprojects will take place at the provincial level though the

Provincial Project Management Units (PPMUs) established by the respective Provincial People’s

Committee (PPC). The PPMUs will be composed primarily of staff from the provincial

Departments of Agriculture and Rural Development (DARD) and the Irrigation and Drainage

Management Companies (IDMCs), under the authority of the Provincial People’s Committee

(PPC). The PPMUs will carry out their duties and functions as guided by the CPMU,

Directorates and Departments of MARD as well as through the Provincial departments according

to current construction investment regulations and management. The PPMUs will receive

guidance and supervision from CPMU on the issues directly related to project implementation.

6. Operating under the general MARD project management framework, the PPMUs will

also be responsible for launching the calls for proposals, conduct proposal screening and

shortlisting, and handling procurement and supervise construction activities. MARD CPMU will

be responsible for the management of the project designated account, procurement of ICB and

QCBS contracts given the complexity of these procurement methods and their advantage in

foreign languages, payments of contractors, and ensure safeguard compliance. The CPMU will

report to IDA, MARD, and the GOV as appropriate.

7. A Project Operation Manual (POM) has been prepared which provides further detailed

implementation arrangements

8. The PPMUs will be authorized to manage the implementation of project within the

administrative boundary of provinces. These responsibilities include: i) prepare annual

procurement plans. The plans will be adjusted and updated annually by the PPMUs on the basis

of actual implementation progress. The plans will be reviewed by the CPMU and approved by

the provinces; ii) carry out the approved procurement plans and manage contracts in accordance

with the POM; iii) prepare annual funding plans (disbursement plans) for the provincial level and

submit it to the PPCs for approval; iv) prepare and submit resettlement and compensation plans

for approval; implementing compensation, land acquisition activities for construction; v)

supervise construction including environmental and social impacts supervision; vi) manage the

secondary project account at the provincial level; vii) procurement handling and payment for

contractors; viii) prepare transfer request letter and disbursement documentations for submission

to CPMU in accordance with the POM; ix) undertake liquidation and audit of subproject; and x)

conduct subproject handover in accordance with current regulations.

Page 37: Project Appraisal Document +PAD+ +disclosable version+ - P130014

29

Description D

u

r

aComponent 1: Improved Water ManagementCPMU

TA consultant: assist MARD’s CPMU, Provincial PMUs, IMCs, in all technical

aspects in project implementation .

7

2

TA consultant: PIM and IMT, and other international consultants 7

2

GOODS: Quang Nam / Thanh Hoa / Quang Tri / Hoa Binh / Ha Tinh / Ha

Giang / Phu Tho

Supply office equipment, communication, computers etc 3

Develop & use a GIS-based database for asset management and irrigation

management system for IMC6

Install equipment to assist in management for WUAs 3

0

Component 2: Irrigation and Drainage Scheme

ImprovementsProject Supervision Consultant assist Provincial PMUs, IMCs in project

implementation

Quang Nam

Thanh Hoa

Hoa Binh

Ha Tinh

Quang Tri

Phu Tho

Ha Giang

Component 3: Agriculture support serviceConsultants in all aspects to support introduction and development

of CSA systems

Design and develop pilot CSA systems 7

2

Support to up-scaling of adoption of CSA practices and replication of the CSA

systems

3

6

Baseline surveys in each province to assess the outputs and results of the

activities

7

2

Assess the impacts of the CSA systems (economic benefits, emission

benefits, efficiency of water use...

Final evaluation and final workshop for lessons drawing and

recommendations

1

2

Component 4: Project management, monitoring &

evaluation

Technical assistance (TA) consultants7

0

Independent Supervision Consultants for Environment and Resettlement 4

8

Support for capacity building and training

2018 2019

Project Schedule

2014 2015 2016 2017

Page 38: Project Appraisal Document +PAD+ +disclosable version+ - P130014

30

Financial Management, Disbursements and Procurement

9. The disbursement categories are as follows:

Category

Amount of

the

Financing

Allocated

(expressed

in US$

million)

Percentage of

Expenditures to be

Financed

(inclusive of Taxes)

Works, goods, services, training

including workshops and incremental

operating cost

180

100%

(Note: This amount will be stated in equivalent SDR in the Financing Agreement)

10. An assessment of the financial management (FM) arrangements for the proposed project

has been conducted based on the guidelines issued by the FM Sector Board with the conclusion

that the project meets the minimum Bank FM requirements, as stipulated in OP/BP 10.0.

11. The financial management manual will be updated by the CPO in accordance to the

agreed project implementation arrangement. The draft Financial Management Manual will be

submitted to the World Bank for review and concurrence prior to negotiation.

12. CPMU will be responsible for consolidating financial statements from provinces and

appointing an external auditor. The audit fee for the first three years of the project will be

included in the procurement plan prior to negotiation.

13. Account management and payments of provincial level component activities will be

conducted by each of the provinces, as to promote decentralization of project implementation.

Confirmation on the activities and level of payments will be confirmed with the Bank. The

description of fund flow and management of provincial project accounts will be included in the

financial management manual.

14. The CPO and provinces will identify (with high accuracy) the expected amount of

counterpart funding required each year. For the provincial sub-projects that require high

counterpart funds, the provincial authorities will provide the official commitment to the World

Bank prior to the approval of the sub-project.

15. In order to strengthen the financial management arrangements for the project and to

help further reduce the risk of fraud and corruption, particular attention will be paid to the

following areas: (a) clear FM responsibilities with avoidance of gaps and overlaps of duties has

been included in the FM Manual; (b) enhanced disclosure and transparency of financial

information by publishing project and entity financial statements; (c) internal audit and

inspection by MARD and Provincial People’s Committees for components implemented in

their local areas (country system); and (d) authorization of Expenditures Verification Agencies

(Provincial State Treasuries) will be obtained before any payment is made.

Page 39: Project Appraisal Document +PAD+ +disclosable version+ - P130014

31

Disbursement

16. Disbursement will be made primarily via Advances. A segregated Designated Account

(DA) at a commercial bank acceptable to the World Bank will be maintained by the CPMU.

The DA will be denominated in United States Dollars (US$). The ceiling of DA will be fixed at

US$ 25,000,000. Supporting documentation required for documenting eligible expenditures

paid from the DA (and for Reimbursements) will be the Statement of Expenditure (SOE) and a

list of payment against the contracts that are subject to the Bank’s prior review, together with

Records. The frequency for documenting expenditures paid from the DA will be quarterly. The

Reimbursement, Special Commitment, and Direct Payments disbursement methods can also be

used. Direct Payments will be documented by Records. The Minimum Application Size for

Reimbursements, Special Commitments and Direct Payments will be US$ 2,000,000

equivalent.

17. The Project will have a Disbursement Deadline Date (final date on which World Bank

will accept applications for withdrawal from the Recipient or documentation on the use of

Credit proceeds already advanced by the World Bank) four months after the Closing Date.

This "Grace Period" is granted in order to permit the orderly project completion and closure of

the Credit account via the submission of applications and supporting documentation for

expenditures incurred on or before the Closing Date. Expenditures incurred between the

Closing Date and the Disbursement Deadline Date are not eligible for disbursement, except as

otherwise agreed with the World Bank.

Procurement

18. Procurement financed by the Bank under the proposed project will be carried out in

accordance with the Bank’s “Guidelines: Procurement of Goods, Works, and Non-Consulting

Services under IBRD Loans and IDA Credits & Grants by World Bank Borrowers” dated

January 2011; and “Guidelines: Selection and Employment of Consultants under IBRD Loans

and IDA Credits & Grants by World Bank Borrowers” dated January 2011; as well as the

relevant provisions under the Financing Agreement.

19. Procurement Capacity and Risk Assessment (PCRA) of the CPMU under MARD, and

PPMUs at provincial level was carried out during project preparation. The CPMU and several

PPMUs have been involved in the Bank financed projects and are familiar with the Bank’s

procurement procedures. However, the following risks are also identified: (a) possible

procurement delays could occur at all stages of the procurement cycle including planning,

preparation of procurement documents, bid evaluation, approval of bid evaluation report and

award recommendation and contract management and (b) possible non-compliance with Bank

procedures (including governance and corruption issues) may occur at the different levels.

Therefore the procurement risk for the project is rated “Substantial”. To mitigate the risks and

build up capacity, the Bank team has discussed and agreed with the CPMU that the following

key measures shall be taken:

CPMU shall appoint at least two qualified procurement specialists with adequate

experience on the Bank procurement procedures prior to the project effectiveness.

Page 40: Project Appraisal Document +PAD+ +disclosable version+ - P130014

32

CPMU shall adopt a Project Operational Manual, including an adequate procurement

manual (covering clear rules, procedures and division of responsibilities, sample

documents and evaluation report for small procurements), prior to the project

effectiveness.

Each PPMU shall appoint at least two qualified procurement specialists by the project

effectiveness.

Staff of CPMU and PPMUs who are involved in procurement implementation should

receive intensive training on the Bank procurement procedures prior to the start-up of

the project and throughout the project implementation. CPMU and PPMUs will take

procurement actions according to the agreed procurement plans, including advance

procurement activities.

The Bank shall conduct regular procurement post reviews and provide feedback for

timely corrective actions as needed.

20. Procurement Plan: The CPMU has developed an acceptable procurement plan for the

initial 18 months of project implementation. The procurement plan includes contracts that are

to be awarded under advance procurement; all such contracts, irrespective of value, are subject

to prior review. The various items under different expenditure categories are described below in

Table 3.1. The procurement plan will be updated annually or as required to reflect the project

implementation needs. The procurement plan and its updates will be published on the Bank’s

external website in accordance with the Guidelines.

Table 3.1: Summary of Initial 18 months Procurement Plan

Ref.

No

Description Estimated

Cost US$

(million)

No. of

Packages

Review by

the Bank

(Prior/Post)

Comments

(Prior

Review

Contract)

1 Summary of the NCB (Works)

packages

95.74 82 Prior/Post prior-review

the first 2 or 1

contract(s)

depending on

the PPMU’s

capacity

2 Summary of the ICB (Goods)

packages

11.10 2 Prior

3 Summary of the NCB (Goods)

packages

1.75 14 Prior/Post prior-review

the first 2 or 1

contract(s)

depending on

the PPMU’s

capacity

4 Summary of the Shopping

contracts (Non-consulting services)

0.60 8 Post

5 Summary of number of contract

≥USD0.2m that will be let under

QCBS/QBS

6.18 5 Prior

6 Summary of number of contracts

<USD0.2m that will be let under CQS

1.73 11 Prior/Post prior-review

the first 2 or 1

contract(s)

depending on

the PPMU’s

Page 41: Project Appraisal Document +PAD+ +disclosable version+ - P130014

33

capacity

7 Summary of Individual Consultant

Contracts

0.35 Multi-

contract

Post

Total 117.45

Table 3.2: Procurement Plan for Advance Procurement Activities

Contract No. Description

Estimated

Cost (US$

million)

Procurement

Method

Review by

Bank

Expected

Bid

Opening

CS5/TA/CPO/

2014

TA consultant for overall project

implementation 2.5 QCBS Prior Dec.-13

CS6/ISC/CPO/

2014

Independent Monitoring Consultant

(Third party) 0.75 QCBS Prior Feb-14

CS7/M&E/CP

O/2014 M&E Consultant 0.58 QCBS Prior Dec.-13

CS8/AUD/CP

O/2014 Financial Audit for the first 3 years 0.07 CQS Prior Jan-14

21. Prior Review by the Bank: Thresholds for the Bank’s prior review and thresholds for

procurement/selection methods, currently applicable for this project, are shown in the Table 3.3

below. Contracts with cost estimates below the thresholds of Prior review shall be subject the

Bank’s Post review, which will be conducted annually and cover 20% of the total post-

reviewed contracts.

Table 3.3: Procurement Method and Prior Review Thresholds

Category

Procurement Method Thresholds Prior Review Thresholds

Applicable

thresholds

(in USD

million)

Remarks Applicable thresholds (in

USD million) Remarks

Works

ICB ≥ $10 m All ICB contracts

NCB < $10 m First maximum 2 NCB

contracts for each CPMU /

PPMU

Shopping < $0.2 m None

Goods

ICB ≥$1 m All contracts

NCB < $1 m Where goods are not

normally available from

within Vietnam, the method

of procurement will be ICB

even if the contract value is

less than $1 m.

First maximum 2 NCB

contracts for each CPMU /

PPMU

Shopping < $0.1 m None

Consultant Services

CQS < $ 0.3 m Para 3.7 of Consultant

Guidelines.

Other methods (QCBS,

QBS, LCS) may also be

applied for contracts below

$0.3 m.

Firms: ≥$0.3 m (for

competitive selection) plus

the first contract for each

method (QCBS, QBS, LCS,

CQS) regardless of value.

SSS: All SSS contracts.

Essential individual

assignments will be

defined in the

Procurement Plan

Page 42: Project Appraisal Document +PAD+ +disclosable version+ - P130014

34

All Audit contracts

Individuals: for essential

assignments (procurement

consultant, accountant…).

22. For achieving the project development’s objective the services of certain government-

owned universities and research centers and institutions will be critical for project

implementation. These agencies will provide services for capacity building, training and

institutional strengthening. These include: (a) Vietnam Academy of Agricultural Sciences and

Hanoi University of Agriculture provide services under Climate Change Agriculture practice

support (Component 3); (b) Vietnam Academy of Water Resources provides services under

water management improvement including Participation Irrigation Management (PIM)

program, Irrigation Management Transfer (IMT) program and national policies development

(Component 1&3&4); and (c) Hanoi University of Irrigation provides services under Irrigation

modernization capacity building and training (Component 4). These agencies are leading

national centres and are in a unique position to provide such services and have staff with strong

expertise and experience. The services would be procured in accordance with requirements

stipulated in paragraph 1.13(c) of the Bank’s Consultant Guidelines.

Page 43: Project Appraisal Document +PAD+ +disclosable version+ - P130014

35

Annex 4 Operational Risk Assessment Framework (ORAF)

Vietnam: Irrigated Agriculture Improvement Project (P130014)

.

Project Stakeholder Risks

Stakeholder Risk Rating Low

Description: There is a strong

commitment and ownership from all

project stakeholders as evidenced by

consultations during project

identifications and preparation. MARD

has a good record of engaging various

stakeholders and getting them involved

in project preparation and

implementation. The stakeholder

assessment and consultation was

carried out with direct project

beneficiaries, farmers, ethnic

minorities, women’s union, WUOs,

farmers’ association, and NGOs during

project preparation. As the overall

expected impact of the project is

positive, stakeholders all provided their

support for the project objective.

Risk Management: Consultation of project affect people, beneficiaries, and other stakeholders will

continue through project implementation.

Resp: Stage: Recurrent:

Due Date: Frequency: Status:

Page 44: Project Appraisal Document +PAD+ +disclosable version+ - P130014

36

Implementing Agency (IA) Risks (including Fiduciary Risks)

Capacity Rating Moderate

Description: Project lead implementing

agency MARD is familiar with Bank

procedures and policies including

fiduciary, safeguards, and monitoring and

evaluation. Some of the provinces have

ongoing Bank supported projects. The

capacity risks would be related to the new

provincial staff and their limited

knowledge and experience in applying the

Bank’s guidelines.

Risk Management: Project management offices will be fully staffed with appropriate skills sets

particularly on monitoring and evaluation. Whenever possible, staff with prior World Bank experience

will be used for this project. The Bank will continue to make sure low capacity issues will be

addressed. Newly hired staff will receive consultant support as well as training to meet procurement

requirements.

Resp: Stage: Recurrent:

Due Date: Frequency

:

Status:

Description: The projected is expected to

receive US$ 30 million of counterparts

funding. The CPMU and PPMUs will

identify (with high accuracy) the expected

amount of counterpart funding required

each year. For the provincial sub-projects

that require high counterpart funds, the

provincial authorities will provide the

official commitment to the World Bank

prior to the approval of the sub-project.

Risk Management: Counterpart fund from central and provincial has gone through assessment and does

not present an issue.

Resp: Stage: Recurrent: Due Date: Frequency: Status:

Governance Rating Moderate

Description: Coordination between

agencies and within MARD at the central

and provincial levels may be weak.

Governance structure includes a steering

committee at the central and provincial

level.

Risk Management: During implementation the Bank will continue to monitor the level of coordination

effectiveness between agencies. Project implementation arrangements will be clearly defined and

outlined in the project implementation plan to improve coordination between the various implementing

agencies.

Resp: Stage: Recurrent:

Due Date: Frequency

:

Status:

Project Risks

Page 45: Project Appraisal Document +PAD+ +disclosable version+ - P130014

37

Design Rating Moderate

Description: Economic sustainability of

investments could be weak if technical

designs are not optimized in accordance

with demand. Detailed demand analysis

will be used to help customize the technical

designs. Through project preparation,

extensive consultation was carried out to

get the stakeholders’ view on the proposed

investment. Walk through survey at the

sites was conducted to identify the current

stage, readiness and needs of each project

site. Close consultation with stakeholders

was also conducted to ensure congruence

between agriculture support services and

infrastructure improvement needs.

Risk Management: Consultation with stakeholders will continue through preparation to ensure the

demand, needs and readiness is being met.

Resp: Stage: Recurrent:

Due Date: Frequency

:

Status:

Description: The large number of project

activities across seven provinces requires

coordination between agricultural support

services and infrastructure improvement is

also a risk.

Risk Management: The detailed descriptions of the project schemes have been formulated.

The designs and quality of construction will reviewed by project implementation consultants

and third party consultants to ensure quality.

Resp: Stage: Recurrent:

Due Date: Frequency: Status:

Description: Possible low adoption rates/

unsuccessful demonstration of new climate

change adaptation measures at selected

sites and failure of mainstreaming

adaptation into overall MARD program.

Risk Management: Use of appropriate extension and dissemination of information and project status

updates will be employed. Activities to strengthen expand and integrate agricultural extension services

and technical support systems have been included in the project design. Adaptation methods were

selected based on good scientific practice, and farmers’ and local officials’ participation in decision

making. Information dissemination will continue through project implementation. Pilot activities will

be closely monitored and supported.

Resp: Stage: Recurrent:

Due Date: Frequency: Status:

Social and Environmental Rating Moderate

Page 46: Project Appraisal Document +PAD+ +disclosable version+ - P130014

38

Description: Construction activities and

climate smart agriculture are expected to be

simple in nature. There is not a lot of land

acquisition involved. ESMF and SAP have

been developed, and in the past the

implementation agencies have

demonstrated the ability to carry this out.

Risk Management: MARD is experienced with Bank's requirements and procedures on safeguard

policies through previous projects. All ESMF and SAP have been approved by the provinces. MARD

will provide training to the PPMUs social and environmental staff on a annually basis. The Bank and

third party consultant will undergo close monitoring.

Resp: Stage: Recurrent:

Due Date: Frequency: Status:

Description: Land acquisition, both

temporary and permanent, would be a

potential risk during project

implementation. In some sub-project areas,

land acquisition is expected to affect ethnic

minority households.

Risk Management: An SA carried out in early 2013 confirmed that the overall social impact of the

project is positive, given the project aims to strengthen national, provincial, and local capacities for

better irrigation management. However, some negative impacts, primarily related to acquisition of land

to allow for rehabilitation of existing infrastructure, is unavoidable. On the basis of the SA, MARD will

prepare an Indigenous Peoples Plan (IPP) for the sites that have ethnic minorities; an Indigenous

Peoples Policy Framework (IPPF) for areas where ethnic minority people are identified during project

preparation. While the project does not anticipate any major land acquisition or resettlement of project

affected person (PAPs), MARD will also prepare Resettlement Action Plans (RAPs) for all sub-

projects that are identified by appraisal and also a Resettlement Policy framework (RPF) for those sub-

projects that will be identified and prepared during project implementation. MARD is experienced with

Bank's requirements and procedures on safeguard policies through previous projects.

Resp: Stage: Recurrent: Due Date: Frequency: Status:

Program and Donor Rating Moderate

Description: NA Risk Management:

Resp: Stage: Recurrent: Due Date: Frequency: Status:

Delivery Monitoring and Sustainability Rating Moderate

Page 47: Project Appraisal Document +PAD+ +disclosable version+ - P130014

39

Description: Delays in project

implementation particularly civil works

may take place due to engineering or

climatic related factors. The M&E system

will be used and supported by a MIS

system to closely monitor contract

management and other implementation

aspects. A robust baseline survey would

also be established for every monitoring

indicator across the seven participating

provinces to establish parameter

benchmarks against which project progress

will be measured.

Risk Management: Construction will be planned and scheduled carefully for optimal alignment

between design and implementation process. Timing will also be laid out as such to make the best use

of dry season construction periods. During preparation, operational plans and detailed water balance

studies have been prepared. Third party monitoring and remote sensing for monitoring project progress

and delivery will continue through implementation.

Resp: Stage: Recurrent:

Due Date: Frequency

:

Status:

Description: Close engagement with

IDMCs and WUA/WUOs is vital to ensure

participation in system operations. Firm

commitment by the borrower is equally as

important.

Risk Management: Continuing policy discussion between World Bank and government on its

subsidy for irrigation service fees to ensure income of IDMCs and WUAs/WUOs adequately

covers sustainable irrigation O&M costs. The focus on building up the institutional capacity

and developing a policy framework for climate-smart activities ensures that the project goes

beyond one-off investments in the irrigation sector.

Resp: Stage: Recurrent: Due Date: Frequency: Status:

Other (Optional) Rating

Description: NA Risk Management:

Resp: Stage: Recurrent: Due Date: Frequency: Status:

Other (Optional) Rating

Description: NA Risk Management:

Resp: Stage: Recurrent:

Due Date: Frequency: Status:

Overall Risk

Preparation Risk Rating: Moderate Implementation Risk Rating: Moderate

Page 48: Project Appraisal Document +PAD+ +disclosable version+ - P130014

40

Description: The overall preparation risk is rated as Moderate. This

rating is acceptable as the project will be introducing innovative

components that will require the task team to work closely with MARD.

Description: The overall risk rating for this project is Moderate.

Non-disclosable Information for Management Attention (Optional)

Comments:

Note for information: this section is not disclosed at Negotiation and Board presentation stages

Note : Include on average no more than 3 Risk Management Measures per Risk Category

Page 49: Project Appraisal Document +PAD+ +disclosable version+ - P130014

41

Annex 5 Implementation Support Plan

VIETNAM: Irrigated Agriculture Improvement Project

Strategy and Approach for Implementation Support

1. The strategy for Bank implementation support has been developed based on the nature of

the project and its risk profile. The ORAF rates the overall implementation risk to be moderate

and all individual risk categories are rated either low or moderate. Bank supervision will

therefore focus significantly on compliance on Bank procurement, FM and safeguards

requirements.

2. During the first 18 months of the project implementation, Bank implementation support

missions will be fielded every three to four months, including short follow up missions, in order

to proactively provide the implementation agencies with technical guidance both at the central

and provincial levels to facilitate project implementation. Implementation support missions will

also focus on selected technical issues such as dam safety, climate smart agriculture,

development of a baseline for GHG emissions and irrigation modernization.

3. In parallel, a series of refresher training courses will be carried out for all implementing

agency staff covering procurement, financial management and safeguards aspects to enable them

to fully understand the updated guidelines (particularly procurement) and operational policies.

The Bank will also review and confirm that adequate qualified staff and consultants are in place

for project management, detailed engineering, design and construction supervision, and on

environmental and social safeguards. The Bank will maintain regular contact with MARD

management to inform them on the findings of implementation support missions and give

remedial measures, as necessary. This will be particularly important for the sub-projects carried

out at the provincial level.

4. In order to provide timely implementation support through missions and on demand

guidance, the majority of the Bank Task Team (technical, procurement, financial management,

environmental and social safeguards specialists) will continue to be based in the Bank’s Hanoi

Office. The table below indicates the level of effort that will be needed from the Bank to provide

implementation support for the project.

Table: Annual Skills Mix Required

Skills Needed Number of Staff

Weeks per annum Number of Trips

per annum Comments

TTL – co-TTL Irrigation 16 4 Bank staff

Institutional specialist 6 2 International and national

consultants

Agriculture 6 2 International and Country-office

based Bank staff

Water Users Associations

Specialist

6 2 International and national

consultants

Bank Safeguards 2 2 each Country-office based Bank staff

Bank FM 1 2 Country-office based Bank staff

Page 50: Project Appraisal Document +PAD+ +disclosable version+ - P130014

42

Skills Needed Number of Staff

Weeks per annum Number of Trips

per annum Comments

Bank Procurement 2 2 Country-office based Bank staff

M&E specialist 4 2 International

Irrigation Engineer with

modernization experience

6 2 International and national

Dam safety 4 2 International

Page 51: Project Appraisal Document +PAD+ +disclosable version+ - P130014

43

Annex 6: Economic and Financial Analysis

A. Introduction

1. The financial and economic analyses are confined to assessing costs and benefits of

Component 2, Irrigation and Drainage Scheme Level Improvements which accounts for more

than 70% of the total project costs. The analyses examined the impact of the project investments

in the following areas:

Increased agricultural production and revenues from increases in irrigated area and

yields;

Lower production costs due to reduction in private pumping and labor to bring water to

the fields;

Non-quantified benefits: reduced risk of dam and main canal failure; greater reliability

for municipal and industrial water users;

Benefits, not-quantified which are expected from proposed installation of drip technology

for existing and new orchards of citrus, various vegetables and peanuts.

2. The expected diversification into higher value and higher return crops is expected due to

availability of timely and reliable water with a resultant increase in cropping of maize and

vegetables. High returns and diversification to high value crops is also expected due to proposed

drip irrigation for orchards and peanuts in some provinces. The benefits from this technology

have not been quantified for financial and economic analysis at this stage.

3. Both the financial and economic analyses rely on the information available with and

collected by the project study team and consultants at DARD and VAWR offices responsible for

preparing the report on engineering aspects as well as for the feasibility study report. The

information was supplemented during the pilot visits in the field and conducting scoping sessions

with the farmers and staff of the provincial agriculture departments by the project appraisal team.

B. Approach and Methodology

4. Cultivated Area by Crops and by Sub-Projects. For estimating the benefits for each

sub-project/scheme, the average of last five years of the cropped area has been used as the basis

for estimating the cropped area under gravity irrigation, pumped irrigation as well as for

estimating the non-irrigated land. In fact, a large part of the non-irrigated land is being cultivated

as rain-fed, which has also been considered as productive area in the without project situation.

5. Crop Budgets for Estimating Quantifiable Benefits. Although the nine sub-projects

are widely scattered and therefore differ in climatic conditions and soil type, all nine sub-projects

are in predominantly rice growing areas with generally limited areas of non-paddy crops.

Separate crop budgets have been developed under with and without project scenarios for winter

and summer crops of rice, maize, peanuts and sweet potatoes for each sub-project under full

gravity or partial irrigation as well as for rain fed cultivated areas. Data on average yields and

Page 52: Project Appraisal Document +PAD+ +disclosable version+ - P130014

44

inputs have been estimated based on information collected from the field, available reports and

from MARD.

6. Based on the above crop budgets, a one ha farm model has been prepared to show typical

costs and returns for each sub-project of: (a) a full gravity irrigated farm, (b) a partially irrigated

or pumped farm; and (c) non-irrigated farm. These farm models has been utilized for estimating

the quantifiable agriculture benefits at scheme/ subproject level first and then aggregated at

overall project level.

7. Cropping Pattern and Intensities. The cropping pattern for the partial and fully pumped

irrigation farm budget for the areas of non-paddy crops (maize, peanuts, sweet potatoes,

vegetable and other crops) have been established based on the published agricultural statistics for

the last five years by provinces.

8. Incremental Agricultural Benefits. Computation of incremental agricultural benefits is

based on the crop and farm budgets developed for the financial and economic analysis with

prices adjusted to reflect at the farm-gate level. The prices to be used for commodities produced,

production inputs, the main commodities – rice, maize, peanuts – and for fertilizers have been

derived from June 2013 World Bank Commodity Price Forecasts. For all other commodities

produced and inputs used, it is assumed that farm-gate prices adequately reflect economic values

and no conversion factor has been used for converting the financial prices of these commodities

into the economic values.

9. Input Cost for Pumping water. Data on cost of pumping water has been considered as

about VND 200,000 per crop based on discussion on the information provided by the project

staff and supplemented from the discussions with the WUAs in the field.

10. Benefited area; Following Table summarizes the area under with and without project

scenarios, benefits of the project have been estimated in financial as well as in economic terms

based upon the area as below;

Table 1: Area under Each Scheme (ha)

Rain-fed Pumped Gravity Rain-fed Pumped Gravity

Large scale schemes

Ha Tinh Ke Go 6,803 0 14,735 - - 21,538

Quang Nam Phu Ninh 4,899 1,760 10,968 - 1,760 19,427

Thanh Hoa South Ma - 11,525 - - - 11,525

Medum scale schemes

Ha Tinh Rac River 4,341 0 4,182 - - 8,523

Quang Nam Khe Tan 1,395 - 2,105 - - 3,500

Phu Tho Tam Nong - 3,840 - - - 3,840

Pho Tho Thanh Thuy - - 2,122 - - 2,122

Quang Tri 3-Schemes Combined 1,352 399 3,680 - 399 5,400

Sub Total 18,790 17,524 37,792 - 2,159 75,875

Small scale schemes 7,550 7,550

Total 26,340 17,524 37,792 - 2,159 83,425

Without Project Condition With Project ConditionProvince Name of Scheme

Page 53: Project Appraisal Document +PAD+ +disclosable version+ - P130014

45

Financial Analysis

11. Based on the above crop budgets, one ha farm budgets have been prepared to show

typical costs and returns for each sub-project of: (a) a full gravity irrigated farm, and (b) a

partially irrigated or pumped farm.

12. For evaluating impact of the project over beneficiaries, typical farm budgets have been

developed at scheme level. The size of an average typical farm has been computed at each

scheme by dividing the area provided with irrigation and drainage services - improved with the

number of direct beneficiaries households, it ranges between 0.24 ha (Than Hao) and 0.49 ha (Ha

Thinh) with an simple average of 0.34 ha. The Table below shows the average returns at typical

farm of 0.34 ha.

13. It is evident from the above table that net returns per labor day increase by 3.4 times for

the farms irrigating by pumping and by 1.8 times on farms with full gravity irrigation. The high

returns per day to labor on farms with partial irrigation are due to the savings in cost of pumping.

14. The comparison shows that net margins after conversion of the rainfed areas to full

gravity or partial and pumped irrigation would be much higher in the with-project situation.

Average returns in rainfed areas have been estimated as VND 2.1 million (US$100) per ha,

which may increase up to VND 6.8 million (US$324) per annum after conversion to gravity

irrigation. Thus many farmers at the bottom end of the canal system might not be in a very

different situation from the rainfed farmers. The fact that the project through improving water

transfer tends to benefit canal tail-end farmers more than those at the head-end, implies that the

project is to a significant extent self- targeted on poverty.

Table 2: Net Margin at Farm Level

Description

Partial and pumped

irrigation

Full gravity

irrigation Partial

and pumped

VND 000 US$ VND

000

US$

Without-project annual net Margin 947 45 2,193 104

With-project annual net margin 3,202 152 4,033 192

Increase per year 2,255 107 1,841 88

Increase % 238% 84%

Results of the financial analysis

15. Financial Internal Rate of Return: The financial internal rates of return for each sub-

project and for the project as a whole has been estimated considering the approach and

methodology described above. Following is Table showing summary of results:

Page 54: Project Appraisal Document +PAD+ +disclosable version+ - P130014

46

Table 3: Summary of Results of the Financial Analysis

Costs

Increases

by 20%

Benefits

Decreases

by 20%

Costs

Increases

& Benefit

decreases

by 20%

Large scale schemes

Ha Tinh Ke Go 15.7% 1.43 176,410 13.3% 12.0% 10.0%

Quang Nam Phu Ninh 21.1% 1.84 389,121 18.0% 16.6% 14.0%

Thanh Hoa South Ma 10.9% 1.06 38,183 9.0% 7.7% 6.1%

Medum scale schemes

Ha Tinh Rac River 19.5% 1.76 124,302 16.7% 15.4% 13.1%

Quang Nam Khe Tan 14.0% 1.29 23,817 11.7% 10.4% 8.5%

Phu Tho Tam Nong 12.9% 1.18 45,782 10.5% 9.1% 7.2%

Pho Tho Thanh Thuy 12.8% 1.18 24,239 10.4% 9.0% 7.1%

Quang Tri 3-Schemes Combined 13.9% 1.21 104,106 11.0% 9.4% 7.1%

Overall 15.15% 1.36 925,961 12.62% 11.29% 9.18%

SensitivityAnlaysis (IRR %)

Province Name of Scheme

FIRR %

(Base

Case)

BC RatioNPV (VND

000 Million)

Economic Analysis

16. In the economic analysis, the financial prices were converted into economic values by

removing taxes and subsidies from input and output prices and calculating import and export

parity prices of major inputs and outputs (rice and fertilizers). Considering the market

competitive and in equilibrium status, it is considered that no price distortion in price structure is

prevailed in Vietnam economy, hence no conversion factor has been applied to local prices of

agricultural commodities for estimating the project costs and benefits in economic terms.

17. The economic analysis is carried out in a similar manner and using the same

methodology adopted in the financial analysis except using the economic values in place of

financial prices.

18. Data for investment costs by project component has been taken from engineering

estimates, project costs and benefits are estimated at constant prices over a period of 31 years,

including the six-year project implementation period.

19. Prices: For the economic analysis, prices of inputs and outputs have been expressed in

June 2013 constant prices. Data on open market prices was collected through various sources for

determining the farm-gate financial prices. Economic evaluation has been carried out using

economic prices. Parity prices have been derived for rice and fertilizers using commodity price

data issued by World Bank in June 2013.

Page 55: Project Appraisal Document +PAD+ +disclosable version+ - P130014

47

O&M Costs

20. A conservative approach has been adopted and the possible reduction7 in O&M cost after

rehabilitation/modernization has not been credited as a benefit. Considering the requirement for

smooth operation and for maintaining equitable distribution of water through gravity canals, a

provision for O&M has been included equivalent to 4% of the investment costs.

Main Assumptions

Following are the main assumptions used in the analysis:

a. The life of project civil works is 31 years including the six-year investment period;

b. Total project cost, net of taxes is estimated at US$ 152.492 million.

c. No allowance has been made for any possible reduction in operation and maintenance

as a result of project improvements to irrigation infrastructure.

21. Estimation of incremental agricultural benefits. The economic analysis is based on

the crop and farm budgets developed for the financial analysis with prices adjusted to reflect

economic values. The prices used for commodities produced, production inputs, the main

commodities – rice, maize, soybeans – and for fertilizers are derived from June 2013 World

Bank Commodity Price Forecasts. For all other commodities produced and inputs used, it is

assumed that farm-gate prices adequately reflect economic value.

Results of Economic Analysis and Sensitivity Analysis

22. Economic Rate of Return by Sub-Projects: The analysis indicates that irrigation

rehabilitation is economically viable in all the regions, with internal rates of returns (ERRs)

ranging from 13.7-23.9% as summarized in the following table. The overall ERR is calculated at

18.2%.

7 During field visits, mission collected data from farmers and on operation and maintenance costs. It is clear

that the farmers spend considerable resources (time, labor and money) to keep the system functional even at

the low efficiency, before rehabilitation. After rehabilitation, the O&M cost will reduce substantially.

However, the benefit of reduction savings in O&M cost has not been accounted for in the analysis.

Page 56: Project Appraisal Document +PAD+ +disclosable version+ - P130014

48

Table-4: Summary of Results – Economic Analysis

Costs

Increases

by 20%

Benefits

Decrease

s by 20%

Costs

Increases

& Benefit

decreases

by 20%Large scale schemes

Ha Tinh Ke Go 17.4% 1.60 228,501 14.9% 13.7% 11.6%

Quang Nam Phu Ninh 23.9% 2.05 450,056 20.4% 18.9% 16.0%

Thanh Hoa South Ma 13.7% 1.27 148,288 11.5% 10.3% 8.4%

Medum scale schemes

Ha Tinh Rac River 23.3% 2.12 164,141 20.1% 18.8% 16.0%

Quang Nam Khe Tan 17.5% 1.57 42,311 14.8% 13.5% 11.3%

Phu Tho Tam Nong 15.1% 1.33 74,803 12.5% 11.1% 8.9%

Pho Tho Thanh Thuy 14.7% 1.30 37,692 12.1% 10.7% 8.6%

Quang Tri 3-Schemes Combined 19.6% 1.53 241,040 15.8% 14.1% 11.2%

Overall 18.16% 1.58 1,386,833 15.31% 13.92% 11.57%

SensitivityAnlaysis (IRR %)

Province Name of Scheme

EIRR %

(Base

Case)

BC RatioNPV (VND

000 Million)

Sensitivity Analysis A sensitivity analysis was made to determine the impact of a 20% increase

in costs and a 20% decrease in benefits. The results of the analysis, summarized in the above

table demonstrates that even with increased costs and decreased benefits overall EIRR would fall

to around 11.6%, indicating that the project is relatively robust.

Page 57: Project Appraisal Document +PAD+ +disclosable version+ - P130014

49

Annex 7: Environment and Social Safeguards

The safeguard Context

1. Environmental impacts may arise due to certain planned activities, like disposal of silt

during the rehabilitation of irrigation infrastructure, construction and installation of irrigation

control structures and increased used of agro-chemicals for increased crop productivity. To deal

with these impacts, an Environmental Management Plans (EMP) and an Environmental and

Social Management Framework (ESMF) have been prepared, which provide appropriate

mitigation measures to reduce, contain and reverse some of these potential impacts. The system

rehabilitation and modernization is expected to involve a small amount of land acquisition and

resettlement, including resettlement of indigenous people. For this exceptional circumstance, the

Bank OP/BP 4.10 on Indigenous Peoples and OP/BP 4.12 on Involuntary Resettlement shall be

invoked as a precautionary measure. Indigenous Peoples Plan (IPP), Indigenous Peoples Policy

Framework (IPPF), Resettlement Action Plans (RAPs) and Resettlement Policy framework

(RPF) will be prepared. The safeguards policies trigger by the project are Environmental

Assessment (OP/BP 4.01), Physical Cultural Resources (OP/BP 4.11), Pest Management (OP/BP

4.09), Safety of Dams (OP/BP 4.37), International Waterways (OP/BP 7.50), Indigenous Peoples

(OP/BP 4.10), and Involuntary Resettlement (OP/BP 4.12).

Safeguard Instrument for Managing Impacts and Risks

2. To ensure that the planned project activities do not lead to adverse environmental and

social impacts, an elaborated Environment and Social Assessment was undertaken in all the

project areas proposed. The potential negative impacts and mitigation measures are presented for

the Project, and predicted based on the activities of proposed nine sub-projects, in which work on

three sub-projects commence in the 1st year.

3. Based on the findings from the ESA, an ESMP has been developed to provide measures

to avoid, minimize and mitigate adverse environmental and social impacts of planned

investments, as well as to include measures to enhance and replicate positive impacts. EMPs are

developed for construction related work. The final ESA/ESMF/EMP reports were publically

disclosed for inviting stakeholder comments, including a translation of the executive summary in

Vietnamese and meet the Bank’s disclosure policy requirement.

4. Measures to be taken to mitigate, minimize, reduce or offset these negative

environmental impacts, during Project preparation MARD and PPMUs of Thanh Hoa, Quang

Nam and Hoa Binh have prepared environmental safeguards instruments including project

ESMF, two EMPs for Thanh Hoa and Quang Nam Subprojects and ECOP for Hoa Binh

Subproject in accordance with the Bank safeguards policies. During Project implementation,

PPMUs will be responsible for preparing EMPs or ECOPs for identified Subprojects.

Environmental and Social Management Framework (ESMF) – this instrument sets out

principles, guidelines and procedures for environmental and social assessment. It includes

measures and plans to mitigate, minimize, and/or offset negative environmental impacts

and enhance environmental benefits, cost estimates for such measures and information of

Page 58: Project Appraisal Document +PAD+ +disclosable version+ - P130014

50

the responsible agency to address project impacts. An integrated pest management plan

has been prepared and included as part of this ESMF.

Environmental Management Plan (EMP) includes: (a) the mitigation, monitoring and

institutional measures to be taken during the implementation and operation of the project

to eliminate or offset adverse environmental and social impacts or to reduce them to

acceptable levels; (b) measures to enhance positive environmental and social impacts;

and (c) the actions needed to implement these measures.

Environmental Codes of Practice (ECOP) set outs generic mitigation measures for minor

construction impacts. ECOP will be included in bidding documents.

Regarding Dam Safety: The Dam Safety Reports (DSR) have been prepared, not included

in the ESMF, and will be reviewed by an independent Panel of Experts.

5. Monitoring and Supervision Arrangements: CPMU is responsible for environmental

safeguards implementation and will report compliance as part of semi-annual progress reports

submitted to IDA, copied to MONRE. Construction management consultants will supervise

environmental compliance by the construction contractors. An environmental consultant will be

hired to (a) provide monitoring of the overall project impacts; (b) provide guidance to

construction supervision consultants in supervising environmental mitigation measures by

contractors; (c) provide training of PPMU staff; and (d) assist PPMU in implementing the EMP

and ECOP.

Potential Long-Term Environmental and Social Impacts

6. The impacts as a result of the project, if not monitored and mitigated, have the potential

to lead to long term impacts. This is often witnessed as a long-term impact of irrigation

investments (over one or two decades) but it is unlikely, as seepage along canals would decrease

once they start carrying irrigation water per their design discharges and with effective irrigation

control structures in place. The proposed lining in selected stretches, and rehabilitation of

drainage would also improve overall drainage in the command areas and reduce chances of water

logging. The participation of WUOs and WUAs would further ensure improved maintenance of

irrigation infrastructure and thereby reduce seepage and water logging. In general, the project

will likely have very little potential indirect or long-term impacts on the environment as it is

aimed to modernize and rehabilitate existing irrigation structures.

7. Another potential long-term impact could be a result of enhanced agriculture production,

which could indirectly result in increased dependence on groundwater and possibly increased use

of agro-chemical in the future. However, the ‘climate smart’ agriculture component of the

project aims to foster the culture and knowledge of using less chemicals and increase adaptive

planting of crops, as well as improving irrigation water service delivery. If these factors are

implemented correctly, they would reduce agricultural inputs. The awareness building of the

WUAs and the farmers will be disseminated through farmer field-school and farmer-to-farmer

practices.

Page 59: Project Appraisal Document +PAD+ +disclosable version+ - P130014

51

Institutional Capacity for Addressing Safeguards

8. At PPMUs will be responsible for subprojects safeguards implementation and

management. EMP and ECOP implementation: Mitigation measures during construction will be

implemented by contractors with the cost incorporated in the bidding proposal, and be supervised

by the construction management consultants. Operation mitigation measures will be undertaken

by the facility operator. The cost of mitigation measures is included in the construction cost.

9. MARD has significant experience engaging with the World Bank and has sound

knowledge of the World Bank procedures at the sector (institutional) and project

(implementation) levels. At central level, MARD founded a safeguards unit with its qualified

environmental and social safeguards staff to assist in monitoring and evaluation of project

environmental safeguards compliance. Besides, MARD will hire qualified environmental

management consultants to assist in training, monitoring and evaluation. At provincial level,

PPMU will establish a safeguards unit with its environmental and social staff to assist in

monitoring and evaluation of subproject environmental safeguards performance. Given the low

capacity of PPMU on the Bank environmental safeguards, MARD will provide annual training

for PPMU environmental and social safeguards staff. Cost estimate for the training is

US$150,000.

Public Consultations

10. A series of consultations have been carried out during project preparation. The first

consultation was conducted in December, 2012 with government officials in all 7 provinces. The

second consultation was made in February and March, 2013 at the project areas with

participation of key stakeholders such as farmers, representatives of the women unions, affected

people as well as beneficiaries. In addition, a series of consultations with affected households,

who may be relocated, was also conducted as part of the preparation of ESMF. All comments

and suggestions have been incorporated in the ESMF, EMPs and ECOP.

Environmental and Social (including safeguards)

11. Social Assessment (SA): The SA confirmed that the overall social impact of the project is

positive, given the project aims to strengthen national, provincial, and local capacities for better

irrigation management. However, some negative impacts, primarily related to acquisition of land

to allow for rehabilitation of existing infrastructure, is unavoidable. In some sub-project areas,

land acquisition is expected to affect ethnic minority households. The summarized outcome of

the SA are as follows:

Loss of land, assets, and businesses associated to land: The project will acquire

land (both permanently and temporarily) to allow rehabilitation of the existing

infrastructure. It is estimated that 4,500 households would be affected. While the

number of affected household is substantial, the impact at the household level is

expected to be minimal. Most (95%) of the households are expected to lose a small

strip of land due to rehabilitation of existing irrigation channels. The number of

severely affected household is also expected to be low – about 220 households

Page 60: Project Appraisal Document +PAD+ +disclosable version+ - P130014

52

scattered across the nine sub-projects. Only 13 households are anticipated to require

relocation. In total, about 97 hectares of land will be permanently acquired, while 105

hectares would be temporarily affected to allow for construction operations. Most of

the permanently affected land (97.2%) is agricultural land, while the remaining is

residential land.

Impact on ethnic minority peoples: The adverse impact on ethnic minority

households is primarily due to land acquisition to allow for the rehabilitation of the

existing infrastructure. However, various technical design options have been explored

to keep the number of affected households to the minimum. As the impacts from the

project are expected to be primarily positive (e.g. improve and ensure more reliable

access to water), the ethnic minority peoples indicated broad community support for

project implementation. During implementation, the project would ensure that local

people have opportunities to contribute in Participatory Irrigation Management.

i. Involuntary Resettlement (OP 4.12): Resettlement Policy Framework (RPF) was

prepared in accordance with the World Bank’s OP 4.12 to guide how a

Resettlement Action Plan (RAP) for a sub-project (to be identified during project

preparation, including RAPs prepared for first-year subprojects) should be

prepared. The RPF specifies steps to be taken for preparation, review, and

clearance. The RPF specifies how compensation should be assessed for land,

structures, crops, and businesses affected by the sub-project, including how

graves should be relocated and compensation assessed, and how livelihood

restoration of people should be monitored and supported, when needed, to assure

a full and timely restoration of livelihoods on the part of affected households to

the pre-project level.

ii. Indigenous Peoples (OP 4.10): Because ethnic minority peoples (as defined by

the World Bank’s OP 4.10) are present in the project area, and some are affected,

an Ethnic Minority Policy Framework (EMPF) was prepared on the basis of free,

prior, and informed consultation with affected ethnic minority peoples. The

consultation was conducted (as part of the social assessment exercise) to ensure

the potentially affected ethnic minority peoples, including those who are not

adversely affected as a result of land acquisition, are informed of the project

activities and their potential impact and on the basis of that confirm if they

provide broad community support for project implementation. The consultation

indicated that affected ethnic minority households and those not affected both

support the project implementation. The EMPF was developed to ensure ethnic

minorities have an opportunity to receive socio-economic benefits from the

project in a way that is culturally appropriate to them, and to provide guidance on

how an Ethnic Minority Development Plan (EMDP) should be prepared for sub-

projects to be identified during project implementation.

iii. Social safeguards implementation. The implementation of the RAPs and

EMDPs will be the responsibilities of the respective provincial PMUs. The cost

for land acquisition will be financed by the Government whereas the budget for

EMDP implementation will be from the Bank’s fund under this Project. Social

Page 61: Project Appraisal Document +PAD+ +disclosable version+ - P130014

53

staff will be appointed at the CPMU (the central level) and at the PPMU

(provincial level) to provide support to RAP and EMDP implementation. The

CPMU will ensure social safeguards implementation and monitoring are in

accordance with the project’s RPF. An independent monitoring agency will also

be hired by the project to carry out periodic monitoring to ensure social

safeguards implementation under the project is in full compliance with the

project’s RPF. Both RPF and EMPF specify a grievance redress mechanism.

iv. Gender mainstreaming. Since the project aims to bring direct benefit to an

estimated 243,000 households who use water for irrigation, a gender analysis

was carried out. The purpose of the gender analysis (GA) was a) to analyze the

current gender-related constraints at household and community level and explore

the opportunities to promote gender mainstreaming under the project through

identifying and proposing appropriate interventions; b) to promote gender

equality in the context of water utilization across the beneficiary irrigated area;

and c) to contribute to the gender equality/mainstreaming goal as set forth in the

CPS.

v. A Gender Action Plan (GAP): was developed on the basis of the gender

analysis (with consultation at the community level), and the consultation with

relevant governmental mass organizations at the central level, in Central

Women’s Unions and Farmers’ Associations. The GAP will be part of the project

plan and will be implemented under project component 4.

Environment (including Safeguards)

vi. Environmental concerns of the project are primarily related to the activities under

Component 2 and 3. However, no potentially large scale, significant and/or

irreversible impact is envisaged as the project is designed to benefit the farming

communities through investments in rehabilitation of irrigation systems and

allied agricultural activities. For these reasons, the project is rated Category B. It

triggers five environmental safeguard policies, namely:

vii. OP/BP 4.01(Environmental Assessment): The project implementation involves

civil works to improve irrigation infrastructure such as existing irrigation canals

and reservoirs, and provides rural water supply schemes for ethnic peoples.

Given the negative environmental impacts associated with civil works this policy

is triggered to help ensure the environmental soundness and sustainability of

investment. An Environmental and Social Management Framework (ESMF) has

been prepared for the project. For subproject impacts identified during project

preparation, respective an Environmental Management Plan (EMP) and an

Environmental Codes of Practices (ECOP) have also been prepared in

accordance with the Bank safeguards policies.

viii. OP/BP 4.11 (Physical Cultural Resources): During preparation, 12 graves were

identified in Thanh Hoa sub-project. These graves will be relocated. The OP/BP

Page 62: Project Appraisal Document +PAD+ +disclosable version+ - P130014

54

4.11 is trigged to minimize and manage physical cultural resources and avoiding

their destruction or damage. Mitigation measures have been included in the EMP

for this sub-project. Also, a “chance find procedures” will be included in EMP

and ECOP in case any unexpectedly cultural resource is found during

construction.

ix. OP/BP 4.09 (Pest Management): The project will not finance the purchase of

pesticides. However, after the completion of the project, it is expected that the

irrigated land area will increase to 83,400 ha. The amount of agricultural

chemicals including fertilizers and pesticides are expected to increase. This

policy is triggered to minimize and manage the environmental and health risks

associated with the use of pesticide and to promote and support safe, effective,

and environmentally sound pest management practices. An integrated pest

management plan has been prepared as part of the ESMF.

x. OP/BP 4.37(Safety of Dams): The project will finance minor rehabilitation of

existing dams to improve dam safety aspects. This policy is triggered to ensure

the adequate safety of dams. A Panel of Experts (POE) will be assigned the task

to carry out the review of the dam safety reports. The Department of Water

Resources has recently been upgraded to a Directorate of Water Resources, and

the Dam Safety Unit has been transferred to the Infrastructure and Management

Division, forming one of the three Units in the Division.

Page 63: Project Appraisal Document +PAD+ +disclosable version+ - P130014

55