Progress Report 12/13/11
![Page 2: Progress Report 12/13/11. Progress Schedule December 2011 Work Completed December: Installed Concrete topping on roof Rough In M&E East side screen wall](https://reader030.vdocuments.us/reader030/viewer/2022032517/56649c9c5503460f9495b119/html5/thumbnails/2.jpg)
Progress ScheduleDecember 2011
Work Completed December:
• Installed Concrete topping on roof
• Rough In M&E • East side screen wall
foundations poured• Building Insulation• Tower Foundation Completed• Rough in of Fire Protection
System• Interior Plumbing, Roof Drains
Work Scheduled January:
• Complete Roofing• Frame Interior Walls• Rough in M & E• Erect Tower• Run Electrical Service• Run Natural Gas Service• Start Masonry Screen Walls• Complete Exterior Brick•Window Installation
![Page 3: Progress Report 12/13/11. Progress Schedule December 2011 Work Completed December: Installed Concrete topping on roof Rough In M&E East side screen wall](https://reader030.vdocuments.us/reader030/viewer/2022032517/56649c9c5503460f9495b119/html5/thumbnails/3.jpg)
Progress 12/13/11
West Mechanical Screen Wall Roof Blocking
![Page 4: Progress Report 12/13/11. Progress Schedule December 2011 Work Completed December: Installed Concrete topping on roof Rough In M&E East side screen wall](https://reader030.vdocuments.us/reader030/viewer/2022032517/56649c9c5503460f9495b119/html5/thumbnails/4.jpg)
Progress 12/13/11
Tower Foundation Call Center
![Page 5: Progress Report 12/13/11. Progress Schedule December 2011 Work Completed December: Installed Concrete topping on roof Rough In M&E East side screen wall](https://reader030.vdocuments.us/reader030/viewer/2022032517/56649c9c5503460f9495b119/html5/thumbnails/5.jpg)
Office Corridor Rough InOffice Corridor Rough In
Progress 12/13/11
![Page 6: Progress Report 12/13/11. Progress Schedule December 2011 Work Completed December: Installed Concrete topping on roof Rough In M&E East side screen wall](https://reader030.vdocuments.us/reader030/viewer/2022032517/56649c9c5503460f9495b119/html5/thumbnails/6.jpg)
Progress 12/13/11
Staff Support Rough In Call Center