progress report #1 for the heyburn, idaho municipal water ... · the project site is in heyburn,...

28
Progress Report #1 for the Heyburn, Idaho Municipal Water Supply Expansion Reporting Period: January 26 – February 28, 200- Submitted by ADAGE ENGINEERING Jim Smith Bill Jones Mary Reed Justin Blue Neal Oldhome Wallace Lake to Civil Engineering Faculty Boise State University 28 Feb 200-

Upload: others

Post on 16-Mar-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

Progress Report #1 for the Heyburn, Idaho Municipal Water Supply Expansion

Reporting Period: January 26 – February 28, 200-

Submitted by

ADAGE ENGINEERING

Jim Smith Bill Jones

Mary Reed Justin Blue

Neal Oldhome Wallace Lake

to Civil Engineering Faculty

Boise State University 28 Feb 200-

Page 2: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

2

Table of Contents Page

A. Executive Summary...............................................................................................3

B. Introduction.............................................................................................................5

C. Progress of Work....................................................................................................8

1. Geotechnical Analysis......................................................................................8

2. System Component Design............................................................................10

a. Storage Tank Design..................................................................................10

b. Disinfection System Design........................................................................12

c. Pump Selection...........................................................................................13

d. Pump House Design...................................................................................13

e. Drainage Pond Design................................................................................13

3. Site Development.............................................................................................14

a. General Site Layout.....................................................................................14

b. Access Road and Parking Lot Design.........................................................15

D. Overall Assessment of the Project........................................................................15

E. Acknowledgements..............................................................................................16

F. References...........................................................................................................17

Appendix A: Memo: DEQ Guidelines and Checklists...................................................18

Appendix B: Boring 1 Liquefaction Analysis.................................................................21

Appendix C: Boring 2 Liquefaction Analysis.................................................................25

Page 3: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

3

A. Executive Summary

Adage Engineers is designing an expansion of the Heyburn, Idaho municipal water

supply system. This includes design of a water tank, pump station and necessary

support components on a 1.17 acre lot adjacent to Lincoln Boulevard in Heyburn that is

approximately 500 feet from the Snake River. We have added a drainage pond to the

design that was not included in the original proposal. This report presents the progress

made from January 26 to February 28, 200-. No problems have been encountered, and

the project is on schedule.

The design for the water storage tank is based on a maximum daily average flow of 750

gallons per min (gpm), a maximum peak hour flow of 1,500 gpm, and a two-hour fire

flow of 1,500 gpm. The nominal size of the tank based on the first of these flows is one

million gallons (1MG). Consideration of the other flows required additional storage.

Water will be supplied by a ground water well on the property that yields 1,000 gpm.

Tasks and progress to date include the following:

A. Tank Design - We have determined that the total volume needed for the storage

tank is 1.4MG. We are in the process of selecting the tank materials and design.

B. Geotechnical Analysis – Based on data from two borings and a test pit, we have

calculated a bearing capacity of 3,500 pounds per square foot (psf) and we have

determined that the potential for liquefaction of subsurface soils is very low. We

are proceeding with tank foundation and access road designs.

Page 4: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

4

C. System Component Design – We will be specifying the number and type of

pumps required, the disinfection system, and designing the three-room pump

house in the coming weeks.

D. Site Development – A preliminary site plan was developed in which the tank is

located near the center of the lot where the land is fairly level, the pump house

and parking lot are together near the high end of the property close to Lincoln

Boulevard, and the drainage pond is at the low end of the property.

The tasks we intend to complete before the next progress report include:

• Identification of all necessary permits (Appendix A)

• Finalization of site plan

• Tank design and materials

• Disinfection system design

• Pumping system design and selection of pumps

• Standby generator selection

All the design work will meet applicable local, state, and federal requirements.

Page 5: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

5

B. Introduction

This report details the progress made from January 26 to February 28, 200-, on the

project to expand the municipal water supply system for the city of Heyburn, Idaho. The

municipal water demand in Heyburn is growing and cannot be met by the existing

supply. The new water supply tank provided by the present design is expected to

satisfactorily augment the existing water system through 2025. The water will be

supplied by an existing well which has been shown to yield a constant flow of at least

1000 gpm (cite reference here).

The project scope is to develop necessary plans, profiles, and designs to:

• Construct a water supply tank with an operating capacity of 1.4 MG,

• Construct a building to house pumps, a standby generator, and chlorination

equipment

• Provide connection to the existing water system

• Provide roadways for access and fencing for access control and safety

The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th

Street in Heyburn (Figure 1b). The site is a rectangular plot measuring 210 ft by 243 ft (

1.17 acres). Water supply requirements, as specified by the city, are to meet an average

daily demand of 750 gpm, a maximum peak hour demand of 1,500 gpm, and a two-hour

fire flow of 1,500 gpm.

Page 6: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

6

Figure 1. a) Project location, and b) Aerial photograph of site (cite references)

The project work includes the following tasks:

1. Permitting

2. Geotechnical Analysis

3. System Component Design

a. Storage Tank

b. Disinfection System

a) b)

Page 7: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

7

c. Pumping System and Connection to Existing Distribution System

d. Pump House and Standby Power Generator

e. Drainage Pond

4. Site Development

a. General Site Layout

b. Access Road and Parking Lot Design

We are using IDAPA 58.01.08 (DEQ,2000a) and “Checklists for Plan and Specification

Review for Engineers and Developers” (DEQ, 2000b) as guides for the design.

As of Feb. x, 200x, we have determined the required water tank storage volume,

completed the geotechnical analysis necessary for design of the tank foundation and the

roadways, and developed a preliminary site layout. We anticipate completing water tank

design, pump sizing, connection piping design, generator selection, and chlorination

system design by March 18 and building, road, and drainage pond plans by April 22.

Work on the project is due to be completed and a final report submitted by May 1, 200-.

C. Progress to date

1. Geotechnical Analysis Figure 2 shows the location of the two boreholes and a test pit that provided the

geotechnical data for the site. These data were used to estimate the bearing capacity

and liquefaction potential of the soil. The bearing capacity was calculated using

Terzaghi’s bearing capacity equations for a square footing (Das, 2006):

Page 8: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

8

qu = 1.3c’N’c + qN’q + 0.4γBN’γ (1)

and

qall = qu / FS (2)

where qu = the ultimate bearing capacity in pounds per square foot (psf),

qall = the gross allowable bearing capacity in psf,

c’ = cohesion coefficient [assumed = 0 for sands (Das, 2006)],

ɸ’ = angle of friction for loose sand [assumed = 30 degrees (Das, 2006)],

N’c , N’q , and N’γ = modified bearing capacity factors from Das (2006) for loose sand with ɸ’ = 30 degrees, gave values, respectively, 37.16, 22.46, and 19.13,

B = length of footing in ft [assumed = 3 ft],

γ = unit weight of soil in pounds per cubic foot (pcf) [assumed = 120 pcf],

q = surcharge in psf [Bγ = 360], and

FS = factor of safety, [assumed = 3].

Eq. 1 and 2 yielded a bearing capacity of 3613 psf, which was used to design the

tank foundation.

Page 9: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

9

Figure 2. Boring and Test Pit Locations (Google, 2008).

Liquefaction potential of the site was investigated. Boring 1 showed a layer of elastic silt

from 21 feet to 27 feet below ground surface (bgs) and Boring 2 showed a layer of fat

clay from 20.5 feet to 26 feet bgs. These layers have the potential to cause liquefaction

where the fat clay/elastic silt layer comes in contact with an overlying sand layer so we

performed a liquefaction analysis with a software program called LiqIT (GeoLogismiki,

Page 10: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

10

2006).The program used soil data and other factors to calculate the Owasaki

Liquefaction Potential Index (LPI) for the soils from the two borings at the site. The LPI

values obtained at both sites were zero, indicating that the probability of liquefaction and

resulting settling due to liquefaction is very low. The results of the analysis are shown

in Appendices B and C.

2. System Component Design

a. Storage Tank Design

The first step in the storage tank design was to calculate the actual volume of the tank.

The nominal operating volume provided as a design requirement was 1MG, but other

factors that must be considered added volume to the requirement. We used IDAPA

58.01.08 Section 003.12 and Section 501.03 (DEQ, 2000a) as a guide in calculating

these additional volumes according to flow quantities specified by the city of Heyburn for

the design (e.g., 750 gpm for the maximum daily average, 1,500 gpm for the maximum

peak hour, and 1,500 gpm for two hours of fire flow).

Each component of total required volume for the tank is indicated and estimated below.

• Operational: One day of maximum daily average flow [750 gpm x 24 hrs = 1.08

MG].

• Equalization: Make-up storage between flows at maximum peak hourly rate and

well supply rate during estimated time of maximum peak hourly flow [(1,500 –

1,000) gpm for 2 hours = 0.06 MG]. This is exclusive of fire flow.

• Fire Suppression: Storage for fire flow [1,500 gpm for 2 hours = 0.18 MG].

Page 11: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

11

• Dead Volume - Water that, for whatever reason, may not be usable. For

example, this would be water located in the tank below an outflow pipe. We

intend to design the tank with no dead volume, so we used a value of zero

gallons for dead volume.

• Standby: Storage usually recommended to round the tank volume up to the

nearest 100,000 gal. [1.08 + 0.06 + 0.18 = 1.32 MG; Standby = 0.08 MG]

The total volume of the tank according to these estimates was calculated to be 1.4 MG.

The turnover time of 31 hours for the tank was calculated by dividing the volume of the

tank by the maximum daily average flow rate. This is a criterion used in design to make

sure the tank is not oversized. If the turnover time is too long, one risks stagnation

problems in the water; if it is too short, one risks running out of water quickly if supply is

interrupted. The value of 31 hours is within the range recommended by DEQ (2000a).

The next step in the tank design is to select the shape, either cylindrical or rectangular

and material of construction, reinforced concrete or steel. Our research so far favors

constructing a rectangular tank of reinforced concrete construction. We intend to have

our choice made and the design completed by the date of the next progress report.

b. Disinfection System Design

The ground water used to supply the storage tank will likely need no treatment beyond

what is required by typical disinfection with chlorine. Additional water treatment to meet

public water supply requirements, if needed, is beyond the scope of this project.

We are considering the following aspects in the design of the disinfection system:

Page 12: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

12

• Type of disinfectant to be used

• Source of the disinfectant

• Public safety

• Means to introduce the disinfectant into the water supply

• Mixing and detention time

• Residual concentration

Our preference at this time is to use chlorination with chlorine gas generated on site.

This is a common system used in many other locations to provide residual disinfection

throughout distribution systems (cite reference). This approach minimizes safety

problems associated with locating large tanks of chlorine gas on site. With on-site

generation, the chlorine gas is injected into the supply line coming from well and is

mixed by the turbulence in the pipe. The large volume of the storage tank provides the

required detention time after mixing before the water is pumped out to the distribution

lines. Baffling or other means needed to prevent short circuiting and guarantee

adequate detention times will be addressed in our design of the tank. Since the water

from the new tank will tie into the existing water supply system, we must design to match

the chlorine residual concentration at the tie-in point. The design will follow IDAPA

58.01.08 section 541.04 (DEQ, 2000a).

c. Pump Selection

The city of Heyburn requires an average pressure of 40 pounds per square inch (psi),

and a maximum of 70 psi in the water distribution system. We will provide a design of

multiple pumps that meet these pressures while pumping up to 750 gpm for normal flow,

1,500 gpm for maximum flow, and 3,000 gpm for maximum flow plus fire flow. We

Page 13: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

13

believe that three identical variable frequency drive water booster pumps of adequate

capacity would provide the benefits of economical operation, maintenance, and

replacement.

d. Pump House Design

The pump house will consist of three rooms: pump room, generator room, and

chlorination room. Selection of materials for the pump house will be based on cost and

availability. Alternative materials for walls include concrete masonry units (CMUs),

precast concrete, wood, or poured in place concrete. We are considering wood or steel

trusses for the roof. A window and an access door will be included between the main

pump room and the chlorination room for monitoring purposes. We will follow IDAPA

58.01.08 section 541.01 (DEQ, 2000a) to guide our design.

e. Drainage Pond Design

Our initial proposed design did not include a drainage pond. Such a pond is necessary

to provide catchment for tank overflow and for storage when the tank must be drained.

The pond must be there to contain water from the site and prevent any contamination of

the ground water or the nearby Snake River. We will design the pond to provide fail-

safe control.

a. General Site Layout

Figure 3 shows our preliminary site layout. The lot is 210 ft by 243 ft and slopes

Page 14: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

14

Figure 3. Initial Site Layout [Topo map from Sunrise (2000)]

approximately ten feet from the northeast corner to the southwest corner. The middle of

the lot is relatively flat.

We propose to locate the water tank in the center where there will be a minimal grading

required. The pump house is near an easy access point and is on relatively flat ground.

The pond is on the lowest area of the property. The slope of the lot would allow for

gravity flow from the tank to the pond. .

Page 15: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

15

b. Access Road and Parking Lot Design

An access road will connect the site to adjoining Lincoln Boulevard and a 3,200 ft2

parking lot will be provided (Figure 3). The design of the access road will follow the

Idaho Transportations Department (ITD) standards (ITD, 2005). Our plan is for a 16-ft

wide access gate and for the property to be protected on all sides with a 6-ft high chain

link fence topped by barbed wire. Gravel will be used for the parking lot and for a 15 ft

wide access road around the perimeter of the water tank in accordance with applicable

standards.

D. Summary

The project is on schedule. The water tank volume has been finalized and design of the

tank is underway. We have analyzed the geotechnical data and determined the bearing

capacity of the soil and evaluated the potential of liquefaction at the site. We are

proceeding with design of the tank foundation. We have done preliminary work on the

pump house design, pump selection, and the disinfection system. We have added a

pond for tank overflow and/or drainage and we will design it. A preliminary site plan has

been drawn with placement of the tank, the pump house, a parking area, access roads,

an access gate, and fencing. We have encountered no major problems in meeting our

schedule.

E. Acknowledgements

We would like to thank Sunrise Engineers and Strata, Inc. for providing us maps and

needed data concerning the project. Thanks to Keller Associates for giving input on

Page 16: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

16

storage tank design and to Materials Testing & Inspection for allowing us to use

software and resources for the geotechnical analysis.

Page 17: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

17

F. References Das, B.M (2006). Principals of Geotechnical Engineering, Sixth Edition, Thomson,

Toronto, Canada, 686 pgs.

Google (2008). “Google Maps,” Internet: http://maps.google.com/. Accessed 2/27/08.

Idaho Department of Environmental Quality (DEQ) (2000a). “Checklists for Plan and

Specification Review for Engineers and Developers,” Internet:

http://www.deq.idaho.gov/water/assist_business/engineers/checklists.cfm.

Accessed 2/20/08.

Idaho Department of Environmental Quality (DEQ) (2000b). “IDAPA 58.01.08 – Idaho

Rules for Public Drinking Water Systems,” Boise, ID, 114 pgs.

Idaho Transportation Department (ITD). (2005) “Road Design Policy Manual”. Boise,

ID, 643 pgs.

Sunrise Engineering, 2008, Water Tank Topo.dwg.

Page 18: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

18

Appendix A: Memo: DEQ Guidelines and Checklists

INTEROFFICE MEMORANDUM

TO: LE Planner and Designers

FROM: Wes Rood

SUBJECT: Propose a Change in Scope of Work for City of Heyburn

DATE: 2/14/2009

CC: Municipal Group

Hey Guys,

I met with Dr. Miller last Friday 2/15/08 at 2:30 pm to discuss the permits needed for

our project. When discussing with her I soon discovered we are not using the proper

design guidelines needed for our project. I started to see the purpose of the CE480

senior design class. The purpose of the class is to teach us how to put a project together

using state and federal rules and regulations. If we do not follow these rules our project

will never get hypothetically funded or built. Yes, it is true there is a hundred different

ways to design anything and make it work but, there is only one way to get our project

approved by the state and federal agencies. We need to use the design check lists

supplied by our state and federal agencies.

The CE480 class does not require us to have a complete set of drawings for our

municipal water project, though the class does require that we follow the correct

procedure for designing a project. I believe if we followed these rules and regulations we

will be able to perform any job or know were to start a job when we enter the work force,

Page 19: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

19

actually we will be ahead of the game because so many engineers never follow these

guidelines and end up fighting the system.

The following links will show you the guidelines that we need to follow:

http://adm.idaho.gov/adminrules/rules/idapa58/0108.pdf

Page 35 in this document is very critical we need to explain that we covered all these

requirements in our progress reports. In the final report say we need have a qualified

operator to run the new municipal system.

http://www.deq.idaho.gov/water/assist_business/engineers/checklists.cfm

This site has the engineer’s permits and check lists. Twin falls Idaho DEQ is the

regulating agency which is monitoring the City of Heyburn not the DEQ in Boise.

When we submit our final report we need to include the following: In the future before

we would start designing, we would have preliminary design drawings that we would use

to show the state and federal agencies and ask them what they will require in order for

the project to pass state and federal rules and regulations (i.e. codes). We will also need

to include these rules in our appendix (checklists and permits). We will also need to

include a TFM report this is a report explaining how the new system will effect or modify

the existing water system.

Dr. Miller has offered to sit down with us and go over the proper method of

submitting a project to state and federal agencies. She will be available on Thursday the

2/21/08 or Friday 2/22/08 we just need to set up a meeting with her. I would recommend

Page 20: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

20

this because I learned a lot from the meeting I had with her on Friday the 2/15/08. I

know this will set us back in our design but I do believe that this is very important.

Note: She said we are not allowed to move test bore pits around to suit our water

system site because this would be falsifying information. Though we can use the worst

case on the site and assume the characteristics across the site.

Bill: The correct size of the booster pump building is 30’x36’ sorry I did not get this to

you sooner. I think the site looks good we just need to check it against the codes.

Mo: I left a message on Dr. Millers white board explaining that I would be there at her

office at 10:40am because I for got I had class until 10:30am. Sorry!

Let me know your opinion. I think we need to have a meeting tomorrow 2/19/08 to

discuss this issue.

Page 21: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

21

Appendix B: Boring 1 Liquefaction Analysis

Page 22: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

22

Page 23: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

23

Page 24: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

24

Page 25: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

25

Appendix C: Boring 2 Liquefaction Analysis

Page 26: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

26

Page 27: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

27

Page 28: Progress Report #1 for the Heyburn, Idaho Municipal Water ... · The project site is in Heyburn, shown on the state map in Figure 1a, and is near 7th Street in Heyburn (Figure 1b)

28