progress payment schedule...*disclaimer: please note that the progress payment schedule attached to...

1
PROGRESS PAYMENT Schedule MERIDIAN HOMES | 1300 855 138 | WWW.MERIDIANHOMES.NET.AU *Disclaimer: Please note that the progress payment schedule attached to this brochure is indictive only and should be used as a guide. Speak to one of our consultants at the display home or call 1300 855 138 if you require further clarification. Full external site costs including leveling, soil removal, structural piering, drop edge beams, retaining walls etc and BASIX requirements will be quoted following an inspection of your proposed building site and is not discussed on this brochure. Tender must be accepted within 7 days of presentation. Meridian Homes reserves the right to withdraw this offer at any time without notice or obligation. Builders Licence 240445c CONTRACT STAGE Deposit FRAME & TRUSS Supplied & Installed SLAB Slab poured on the ground BRICK & ROOF Windows, bricks & roofing substantially complete SERVICE ROUGH-IN & LINING All walls & ceilings rough-in completed & plasterboard lined TILING, PAINTING & KITCHEN Tiling, painting & Kitchen substantially complete COMPLETE All outstanding contract works substantially complete 10% 20% 20% 20% 15% 10% 5%

Upload: others

Post on 13-Jul-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PROGRESS PAYMENT Schedule...*Disclaimer: Please note that the progress payment schedule attached to this brochure is indictive only and should be used as a guide. Speak to one of our

PROGRESS PAYMENT Schedule

M E R I D I A N H O M E S | 1 3 0 0 8 5 5 1 3 8 | W W W . M E R I D I A N H O M E S . N E T . A U

*Disclaimer: Please note that the progress payment schedule attached to this brochure is indictive only and should be used as a guide. Speak to one of our consultants at the display home or call 1300 855 138 if you require further clarification. Full external site costs including leveling, soil removal, structural piering, drop edge beams, retaining walls etc

and BASIX requirements will be quoted following an inspection of your proposed building site and is not discussed on this brochure. Tender must be accepted within 7 days of presentation. Meridian Homes reserves the right to withdraw this offer at any time without notice or obligation. Builders Licence 240445c

ContraCt stageDeposit

Frame & trussSupplied & Installed

slabSlab poured on the ground

briCk & rooFWindows, bricks & roofing substantially complete

serviCe rough-in & liningAll walls & ceilings rough-in completed & plasterboard lined

tiling, painting & kitChenTiling, painting & Kitchen substantially complete

CompleteAll outstanding contract works substantially complete

10%

20%

20%

20%

15%

10%

5%