progress of work till date
TRANSCRIPT
A1- 5 Star Hotel A2 A3
A4
Serviced Apartments
A5
F3- Ballroom
Marine Work
Inner
Creek
Foot Bridge
Jewel Of The Creek Package # 8
On Plots No. 129-104 at Port Saeed, Dubai/UAE.
HLG Weekly Internal Report – Week # 87 (29.01.2016)
Client:
M/s. Dubai Int'l Real Estate “DIRE”
Engineer:
M/s. Kling Consult – Kieferle & Partner
Contractor:
M/s. Al Habtoor Leighton Group
Construction Progress Photographs:
Buildings A1, A2, A3, A4 and A5 – Elevation view
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A1 – Elevation view.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A1 – Elevation view.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A2 – Elevation view.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A2, 6th ,5th , 4th Floors, Exterior Aluminum and Glazing work by Al Abbar in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Jewel Of The Creek Package # 8 _ Week # 87
Building A3 – Elevation view.
Construction Progress Photographs:
Building A4 – Elevation view.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A5 – Roof Level in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A5 – Roof Level in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A1, 17th Floor, remaining portion of structural work in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A1, 14th Floor, Block work in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A1, 13th Floor, Internal wall plaster at lift lobby in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A1, 12th Floor, Internal wall plaster at lift lobby in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A1, 11th Floor, Flood screed at Lift lobby.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A1, 9th Floor, Floor tiling at Lift lobby in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A1, 7th Floor, MEP fixes at wet area in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A1, 4th Floor, Emergency lighting cable installation in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A1, 3rd Floor, MEP 1st and 2nd fixes inside units in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A2, 11 Floor, Various MEP 1st and 2nd fixes along corridor in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A2, 8th Floor, Wall tiling work at lift lobby in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A2, 6th Floor, Installation of external Aluminum and Glazing work in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A2, 5th Floor, Installation of external Aluminum and Glazing work in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A2, 4th Floor, Installation of external Aluminum and Glazing work in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A3, 14h Floor, Internal wall plaster in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A3, 12th Floor, Various MEP fixes along corridor in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A3, 10th Floor, Various MEP 1st and 2nd fixes inside units in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A3, 6th Floor, Various MEP fixes along corridor in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A3, 4th Floor, Various MEP 1st and 2nd fixes along corridor in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A4, 15th Floor, Floor tiling work at Electrical room in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A4, 10th Floor, Various MEP 1st and 2nd fixes along corridor in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A4, 8th Floor, Electrical conduit work inside units in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A4, 7th Floor, Wall tiling work in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A4, 5th Floor, Mock-up unit (two bedroom), Installation of wood cladding wall finish
and ceiling grids at bedroom.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A4, 5th Floor, Mock-up unit (two bedroom), Installation of exterior Aluminum and
Glazing work (living room area).
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A4, 5th Floor, Mock-up unit (two bedroom), Floor tiling finish and exterior Aluminum
and Glazing work (balcony area).
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A4, 5th Floor, Mock-up unit (two bedroom), Installation of ceiling grids.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A4, 5th Floor, Mock-up unit (two bedroom), Floor screed at wet area.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A4, 5th Floor, Mock-up unit (two bedroom), Exterior Aluminum and Glazing work in
progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A5, 14th Floor Block work in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A5, 13th Floor Block work in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A5, 11th Floor, Internal wall plaster preparation work in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A5, 7th Floor, Installation hangers clip for MEP fixes along corridor.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A5, 5th Floor, CHW piping work along corridor in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A5, 4th Floor, Mock-up unit (one bedroom), Installation of ceiling grids in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A5, 4th Floor, Mock-up unit (one bedroom), Various MEP fixes above ceiling and
installation of ceiling grids in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Building A5, 4th Floor, Mock-up unit (one bedroom), Various MEP fixes above ceiling and wall
(wet area) in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Basement 1, Mockup – Traffic Markings
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Basement 1, Mockup – Corridor
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Basement 1, Mockup – Corridor leading to main door
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Basement 1, Mockup – Exécutive Suite – Bedroom
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Basement 1, Mockup – Executive Suite – Bed , TV & Sofa
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Basement 1, Mockup – Executive Suite - Bathroom
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Basement 1, Mockup – Executive Suite: Marble counter top with sink
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Basement 1, Mockup - Standard room - Bedroom
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Basement 1, Mockup – Standard Room-Sofa and tables
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Basement 1, Mockup - Standard Room – Bath room
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Basement 1, Mockup – Standard Room – Counter top and sinks at Bath room
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Basement 1, Mockup – Standard Room - Vanity
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Basement 1, Mockup – Exterior Aluminum and Glazing
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Basement 1, A1 – Floor tiling work in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Basement 2, A3 – Various MEP 1st and 2nd fixes in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Basement 3, A4 – Fire Fighting piping in progress.
Jewel Of The Creek Package # 8 _ Week # 87
Construction Progress Photographs:
Basement 4, A5 – Epoxy wall
Jewel Of The Creek Package # 8 _ Week # 87
Project Commencement Date : 1st June 2014
Revised Project Completion Date : 31st August 2017
Revised Construction Period : 39 Months
(1187 Calendar Days)
Milestones
a) Commence Landscaping Works not before : 1st June 2016
b) Air Conditioning System “Partially Operational” : 29th September 2016
(i.e. Remaining period 244 Cal. Days) Time Elapsed as of 29th January 2016 : 608 Calendar Days
(i.e. 51.22%, Remaining Days = 579 Cal. Days)
Contract Value in AED : 1,450,000,000.00
Approved Variations : 3,708,267.86
Revised Contract Value : TBA
Approved Extension of Time : nil
Project Completion Date : 31st August 2017
Project Calculated / Expected Completion Date as of
29th January 2016 (Program update – Cl. 14.1 Rev. 02) : 7th October 2017
16th August 2017
Jewel Of The Creek Package # 8 _ Week # 87 (29.01.2016)
Project Information (Key Dates, Milestones, Contract Value and Time)