progress of work till date

65
A1- 5 Star Hotel A2 A3 A4 Serviced Apartments A5 F3- Ballroom Marine Work Inner Creek Foot Bridge Jewel Of The Creek Package # 8 On Plots No. 129-104 at Port Saeed, Dubai/UAE. HLG Weekly Internal Report Week # 87 (29.01.2016) Client: M/s. Dubai Int'l Real Estate “DIRE” Engineer: M/s. Kling Consult Kieferle & Partner Contractor: M/s. Al Habtoor Leighton Group

Upload: mohsen-almashharawi

Post on 08-Jan-2017

416 views

Category:

Documents


0 download

TRANSCRIPT

A1- 5 Star Hotel A2 A3

A4

Serviced Apartments

A5

F3- Ballroom

Marine Work

Inner

Creek

Foot Bridge

Jewel Of The Creek Package # 8

On Plots No. 129-104 at Port Saeed, Dubai/UAE.

HLG Weekly Internal Report – Week # 87 (29.01.2016)

Client:

M/s. Dubai Int'l Real Estate “DIRE”

Engineer:

M/s. Kling Consult – Kieferle & Partner

Contractor:

M/s. Al Habtoor Leighton Group

Construction Progress Photographs:

Buildings A1, A2, A3, A4 and A5 – Elevation view

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A1 – Elevation view.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A1 – Elevation view.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A2 – Elevation view.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A2, 6th ,5th , 4th Floors, Exterior Aluminum and Glazing work by Al Abbar in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Jewel Of The Creek Package # 8 _ Week # 87

Building A3 – Elevation view.

Construction Progress Photographs:

Building A4 – Elevation view.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A5 – Roof Level in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A5 – Roof Level in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A1, 17th Floor, remaining portion of structural work in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A1, 14th Floor, Block work in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A1, 13th Floor, Internal wall plaster at lift lobby in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A1, 12th Floor, Internal wall plaster at lift lobby in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A1, 11th Floor, Flood screed at Lift lobby.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A1, 9th Floor, Floor tiling at Lift lobby in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A1, 7th Floor, MEP fixes at wet area in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A1, 4th Floor, Emergency lighting cable installation in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A1, 3rd Floor, MEP 1st and 2nd fixes inside units in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A2, 11 Floor, Various MEP 1st and 2nd fixes along corridor in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A2, 8th Floor, Wall tiling work at lift lobby in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A2, 6th Floor, Installation of external Aluminum and Glazing work in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A2, 5th Floor, Installation of external Aluminum and Glazing work in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A2, 4th Floor, Installation of external Aluminum and Glazing work in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A3, 14h Floor, Internal wall plaster in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A3, 12th Floor, Various MEP fixes along corridor in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A3, 10th Floor, Various MEP 1st and 2nd fixes inside units in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A3, 6th Floor, Various MEP fixes along corridor in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A3, 4th Floor, Various MEP 1st and 2nd fixes along corridor in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A4, 15th Floor, Floor tiling work at Electrical room in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A4, 10th Floor, Various MEP 1st and 2nd fixes along corridor in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A4, 8th Floor, Electrical conduit work inside units in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A4, 7th Floor, Wall tiling work in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A4, 5th Floor, Mock-up unit (two bedroom), Installation of wood cladding wall finish

and ceiling grids at bedroom.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A4, 5th Floor, Mock-up unit (two bedroom), Installation of exterior Aluminum and

Glazing work (living room area).

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A4, 5th Floor, Mock-up unit (two bedroom), Floor tiling finish and exterior Aluminum

and Glazing work (balcony area).

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A4, 5th Floor, Mock-up unit (two bedroom), Installation of ceiling grids.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A4, 5th Floor, Mock-up unit (two bedroom), Floor screed at wet area.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A4, 5th Floor, Mock-up unit (two bedroom), Exterior Aluminum and Glazing work in

progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A5, 14th Floor Block work in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A5, 13th Floor Block work in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A5, 11th Floor, Internal wall plaster preparation work in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A5, 7th Floor, Installation hangers clip for MEP fixes along corridor.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A5, 5th Floor, CHW piping work along corridor in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A5, 4th Floor, Mock-up unit (one bedroom), Installation of ceiling grids in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A5, 4th Floor, Mock-up unit (one bedroom), Various MEP fixes above ceiling and

installation of ceiling grids in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Building A5, 4th Floor, Mock-up unit (one bedroom), Various MEP fixes above ceiling and wall

(wet area) in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Basement 1, Mockup – Traffic Markings

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Basement 1, Mockup – Corridor

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Basement 1, Mockup – Corridor leading to main door

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Basement 1, Mockup – Exécutive Suite – Bedroom

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Basement 1, Mockup – Executive Suite – Bed , TV & Sofa

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Basement 1, Mockup – Executive Suite - Bathroom

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Basement 1, Mockup – Executive Suite: Marble counter top with sink

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Basement 1, Mockup - Standard room - Bedroom

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Basement 1, Mockup – Standard Room-Sofa and tables

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Basement 1, Mockup - Standard Room – Bath room

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Basement 1, Mockup – Standard Room – Counter top and sinks at Bath room

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Basement 1, Mockup – Standard Room - Vanity

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Basement 1, Mockup – Exterior Aluminum and Glazing

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Basement 1, A1 – Floor tiling work in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Basement 2, A3 – Various MEP 1st and 2nd fixes in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Basement 3, A4 – Fire Fighting piping in progress.

Jewel Of The Creek Package # 8 _ Week # 87

Construction Progress Photographs:

Basement 4, A5 – Epoxy wall

Jewel Of The Creek Package # 8 _ Week # 87

Project Commencement Date : 1st June 2014

Revised Project Completion Date : 31st August 2017

Revised Construction Period : 39 Months

(1187 Calendar Days)

Milestones

a) Commence Landscaping Works not before : 1st June 2016

b) Air Conditioning System “Partially Operational” : 29th September 2016

(i.e. Remaining period 244 Cal. Days) Time Elapsed as of 29th January 2016 : 608 Calendar Days

(i.e. 51.22%, Remaining Days = 579 Cal. Days)

Contract Value in AED : 1,450,000,000.00

Approved Variations : 3,708,267.86

Revised Contract Value : TBA

Approved Extension of Time : nil

Project Completion Date : 31st August 2017

Project Calculated / Expected Completion Date as of

29th January 2016 (Program update – Cl. 14.1 Rev. 02) : 7th October 2017

16th August 2017

Jewel Of The Creek Package # 8 _ Week # 87 (29.01.2016)

Project Information (Key Dates, Milestones, Contract Value and Time)