productivity improvement of a manual assembly...

88
PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINE A Thesis by PRANAVI YERASI Submitted to the Office of Graduate Studies of Texas A&M University in partial fulfillment of the requirements for the degree of MASTER OF SCIENCE August 2011 Major Subject: Industrial Engineering

Upload: buicong

Post on 08-Feb-2018

215 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY

LINE

A Thesis

by

PRANAVI YERASI

Submitted to the Office of Graduate Studies of Texas A&M University

in partial fulfillment of the requirements for the degree of

MASTER OF SCIENCE

August 2011

Major Subject: Industrial Engineering

Page 2: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY

LINE

A Thesis

by

PRANAVI YERASI

Submitted to the Office of Graduate Studies of

Texas A&M University in partial fulfillment of the requirements for the degree of

MASTER OF SCIENCE

Approved by:

Chair of Committee, Jorge V. Leon Committee Members, Guy L. Curry David E. Claridge Head of Department, Brett A. Peters

August 2011

Major Subject: Industrial Engineering

Page 3: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

iii

ABSTRACT

Productivity Improvement of a Manual Assembly Line.

(August 2011)

Pranavi Yerasi, B.En., Sri Krishnadevaraya University

Chair of Advisory Committee: Dr. V. Jorge Leon

The current project addresses the productivity improvement of a manual

assembly line by making use of operations analysis in the framework of Lean

production. A methodology is proposed that helps to improve the productivity of any

production process. The methodology consists of selecting a product or product family

to be studied followed by current process study. Once the existing process is

documented, all the assembly tasks involved must be timed using time study techniques.

Operations analysis enables the reduction of non-productive tasks and results in a set of

standardized work elements along with the set of standard procedures for performing the

operations.

Assembly line balancing along with the associated operations analysis assists in

constructing or re-configuring an assembly system, which is the key step in improving

the overall performance of an assembly line. Following this approach, two manual

assembly line configurations (single stage parallel line and five-stage serial line) are

constructed for a case study. The results show that by changing over to the single stage

assembly line configuration the operator productivity is doubled when compared to the

existing assembly method.

Page 4: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

iv

DEDICATION

To My Family

Page 5: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

v

ACKNOWLEDGEMENTS

I would like to thank Dr. Jorge Leon for his time and advice during the course of

this project. I would also like to thank Dr. Guy Curry and Dr. David Claridge for

agreeing to be on the thesis committee and providing their input. I would also like to

thank Judy Meeks and Laura Reinisch for their patience and support throughout the

process. I would like to thank my parents and family for providing me with the best of

opportunities and having faith in my abilities. Finally, I wish to thank all my friends who

have made my stay away from home a joyous experience.

Page 6: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

vi

TABLE OF CONTENTS

Page

ABSTRACT ..................................................................................................................... iii

DEDICATION .................................................................................................................. iv

ACKNOWLEDGEMENTS ............................................................................................... v

TABLE OF CONTENTS .................................................................................................. vi

LIST OF TABLES ......................................................................................................... viii

LIST OF FIGURES ........................................................................................................... ix

1 INTRODUCTION ........................................................................................................... 1

1.1 Objectives ......................................................................................................... 2

2 LITERATURE REVIEW ................................................................................................ 3

2.1 Lean Manufacturing ......................................................................................... 3 2.2 Assembly Line Balancing ................................................................................ 5

3 ASSEMBLY LINE PRODUCTIVITY IMPROVEMENT METHODOLOGY .......... 12

3.1 Product Selection for Study ............................................................................ 12 3.1.1 A-B-C Classification Method .......................................................... 13 3.1.2 Part-Process Matrix Method ............................................................ 15

3.2 Time Study ..................................................................................................... 17 3.2.1 What and How to Time? ................................................................. 18 3.2.2 Time the Work Elements ................................................................. 20

3.3 Operations Analysis ....................................................................................... 21 3.3.1 Process Chart ................................................................................... 22 3.3.2 Purpose of the Operation ................................................................. 24 3.3.3 Material ........................................................................................... 25 3.3.4 Setup and Tools ............................................................................... 26 3.3.5 Working Conditions ........................................................................ 27 3.3.6 Material Handling ........................................................................... 27 3.3.7 Line Layout ..................................................................................... 29 3.3.8 Principles of Motion Economy ....................................................... 31

3.4 Assembly Line Balancing Problem ................................................................ 32

4 CASE STUDY .............................................................................................................. 39

4.1 Current Assembly Method ............................................................................. 40

Page 7: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

vii

4.2 As-Is Study ..................................................................................................... 41 4.3 Analysis and To-Be System ........................................................................... 42

4.3.1 Single Stage Parallel Line Configuration ........................................ 45 4.3.2 Five-Stage Serial Line Configuration ............................................. 47

4.4 System Evaluation .......................................................................................... 50 4.4.1 Objectives of the Simulation Analysis ............................................ 50 4.4.2 Material Handling System - Proposed Operation ........................... 51

4.5 Simulation Results .......................................................................................... 55 4.5.1 Material Handling Cart Capacity .................................................... 55 4.5.2 Material Handlers Required – Supply Side ..................................... 56 4.5.3 Input Buffer Size ............................................................................. 56 4.5.4 Output Buffer Size .......................................................................... 56 4.5.5 Material Handlers Required – Bar Coding Side .............................. 57 4.5.6 Analysis of Results .......................................................................... 58

5 SUMMARY AND RECOMMENDATIONS ............................................................... 61

5.1 Summary ........................................................................................................ 61

REFERENCES ................................................................................................................. 63

APPENDIX A .................................................................................................................. 66

APPENDIX B .................................................................................................................. 72

VITA ................................................................................................................................ 78

Page

Page 8: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

viii

LIST OF TABLES Page

Table 1 An Example Part-Process Matrix ........................................................................ 15

Table 2 Part-Process Matrix with Process Steps Filled .................................................... 16

Table 3 Part-Process Matrix Showing Product Families ................................................ 16

Table 4 Consolidated Results ........................................................................................... 58

Table 5 5 Stage Assembly Line Balancing Showing the Imbalance Associated With Each Stage .................................................................................. 60

Table A. 1 Work Element Sheet with Time Data ............................................................ 66

Table A. 2 Time Study Data Sheet with Work Elements ................................................ 69

Table A. 3 Time Study Data Sheet with Station Times ................................................... 70

Page 9: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

ix

LIST OF FIGURES Page

Figure 1 Two Assembly Configurations and Comparisons (Moberly and Wyman, 1973) ............................................................................... 6

Figure 2 Re-Balancing an Assembly Line (Rachamadugu and Talbot, 1991) ................. 10

Figure 3 Productivity Improvement Methodology ........................................................... 12

Figure 4 Showing the „Why?‟ Analysis ........................................................................... 23

Figure 5 Showing Examples of Different Assembly Layouts (Source: R. W. Hall, Attaining Manufacturing Excellence Homewood, IL: Dow Jones-Irwin, 1987, p. 125) .............................................. 30

Figure 6 Showing Operator Work Reach Area (International Labor Organization Guidelines) ................................................................................... 31

Figure 7 Figure Showing Master Box and Individual Packages ...................................... 39

Figure 8 Original Precedence Network Diagram ............................................................. 42

Figure 9 Modified Precedence Network Diagram ........................................................... 43

Figure 10 Proposed Assembly Line Configurations ........................................................ 45

Figure 11 Single Stage Workstation Design .................................................................... 46

Figure 12 Single Stage Parallel Line Design ................................................................... 47

Figure 13 Precedence Diagram Showing Five Assembly Stages..................................... 48

Figure 14 Five-Stage Workstation Design ....................................................................... 49

Figure 15 Five-Stage Serial Line Design ......................................................................... 49

Figure 16 Simulation Model for Single Stage Parallel Line Configuration Showing Pick-up Point ............................................................. 53

Figure 17 Simulation Model for Five Stage Serial Line Configuration Showing Pick-up Point ............................................................ 54

Figure 18 Cart Capacities for Both Configurations ......................................................... 55

Figure 19 Buffer Sizes for Both Configurations .............................................................. 56

Figure 20 No. of Material Handlers Required .................................................................. 57

Page 10: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

x

Figure 21 Results Comparing Two Configurations ......................................................... 58

Figure 22 Operator Utilization ......................................................................................... 59

Figure 23 Production Rate for Improved Assembly Line ................................................ 61

Figure A. 1 Station Time Distribution ............................................................................. 70

Figure A. 2 Loading and Unloading Time Distribution ................................................... 71

Figure B. 1 Assembly Layout With Dimensions ............................................................. 72

Figure B. 2 Material Handling Cart Routing Logic ......................................................... 73

Figure B. 3 Improved Assembly Layout ......................................................................... 74

Figure B. 4 Material Handling – Supply Side .................................................................. 75

Figure B. 5 From Assembly to Bar-Coding ..................................................................... 76

Page

Page 11: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

1

1 INTRODUCTION

Assembly lines are one of the most widely used production systems. Productivity

of a manufacturing system can be defined as the amount of work that can be

accomplished per unit time using the available resources. Pritchard (1995) defines

assembly line productivity as how well a production system uses its resources to achieve

production goals at optimal costs. The conventional productivity metrics, namely

throughput and utilization rate gives a substantial measure of the performance of an

assembly line.

These two metrics alone are not adequate to completely represent the behavior of

a production system Huang et al (2003). A set of other measures such as assembly line

capacity, production lead time, number of value added (VA) and non-value added

(NVA) activities, work-in-process, material handling, operator motion distances, line

configuration and others, along with the throughput and utilization rate, completely

characterize the performance of a production system. An assembly line yields optimal

performance by an optimal setting of all these factors.

Flexibility and agility are the key factors in developing efficient and competitive

production systems. For products involving light manufacturing and assembly, this level

of flexibility can be easily achieved through the use of manual assembly systems.

Manual assembly lines are most common and conventional and still provide an attractive

and sufficient means production for products that require fewer production steps and

___________ This thesis follows the style of International Journal of Lean Six Sigma (IJLSS).

Page 12: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

2

simple assembly processes. Global competition is forcing firms to lower production

costs and at the same time improve quality with lower production lead times.

With the introduction of Lean Manufacturing, this systematically and

continuously identifies and eliminates waste at all levels of a production system, many

improvement opportunities which substantially increase the assembly line productivity

can be successfully implemented.

1.1 Objectives

The objectives of this project are:

To optimize the productivity of a manual assembly line by applying

operations analysis in the realm of Lean production principles.

To establish the material handling system for the manual assembly line.

To compare and analyze the impact of two line configurations.

Page 13: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

3

2 LITERATURE REVIEW

2.1 Lean Manufacturing

Lean Manufacturing or simply Lean is a production philosophy that targets the

identification and elimination of any waste in the production processes; especially

reduce waste in human effort, inventory, time to produce and production space etc. The

concept of Lean was originally developed by Toyota (TPS) for their automobile

manufacturing replacing mass production Womack and Jones (1990). According to

Womack, the primary focus of Lean is to maintain the value of the product with less

work. Lean drives a self-directed work-force and is driven by output-based goals aligned

with customer satisfaction criteria Elizabeth and Cassandra (2010).

Waste is generally caused due to unnecessary delays, processes, costs and errors.

The seven types of wastes associated with Lean are overproduction, transportation,

processing, inventory (work-in-process and finished goods), waiting, motion and defects.

These wastes are also associated with support functions involved in a production system.

The main focus of Lean is to address the value-added and non-value added activities. A

non-value added activity (NVA) is most commonly defined as any activity for which the

customer is not willing to pay. Lean necessitates the reduction of these NVA‟s by

making the system perform better while consuming lesser resources Czarnecki and Loyd

(2001). Some of the widely recognized benefits of Lean manufacturing include:

Productivity Improvement.

Reduced production lead times.

Reduced inventory (Work-in-process and finished goods).

Page 14: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

4

Quality Improvement.

Better utilization.

Organized work flow and

Safer operations.

The most commonly used Lean manufacturing improvement methodologies are

Value Stream Mapping (VSM), 5-S (housekeeping), Visual Management, Standard

Work and Mistake Proofing (Poka-Yoke).

Since its introduction to manufacturing, the concept of Lean with its fascinating

principles has become a dominant strategy in managing the production systems

(Womack and Jones, 1990). Shah and Ward (2003) explore the concept of Lean

manufacturing and summarize that most of the modern manufacturing practices

commonly associated with Lean production show strong operational performance.

Implementing each of the Lean practices such as Continuous Improvement (Kaizen),

Cycle time reduction, Pull System (Kanban), bottle neck removal, JIT, etc. contribute

largely to the operating performance of a production system.

Felhann and Junker (2003) discuss about the developments of software tools that

assist managers in planning human resources to meet with the variability in product

demand and their changing volumes. The paper proposes a tradeoff between manual

assembly systems and highly automated assembly lines. Manual assembly lines are more

versatile and manual operators are more adaptable to changes in product demand and

production structure. The author highlights the importance of ergonomic considerations

while operating manual assembly systems.

Page 15: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

5

Today‟s market environment demands for high quality products with low costs

with a greater variety in products and at faster response times. The manufacturer faces

the challenge to meet these demands while maintaining a profit. Implementing Lean is

an ongoing and long term goal. Proper defining of the goals suitable to a production

process and setting baselines is the key to productivity improvement.

2.2 Assembly Line Balancing

Moberly and Wyman (1973) propose the approach of using simulation two

compare two assembly line configurations. According to Moberly, the study of

production line configurations along the length of the line is called „assembly-line‟

balancing. The set of work stations along the line that results from this balancing is the

generated line configuration. They demonstrate splitting the assembly line width wise

rather than length wise i.e., one workstation is replaced by two identical parallel stations

and they named it as dual production line. A comparison of two assembly line can be

seen in Figure 1.

Page 16: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

6

Figure 1 Two Assembly Configurations and Comparisons (Moberly and Wyman, 1973)

The author presents the concept of „expedited dual production line‟, the feature

which doubles the service rate of a non-failed work station. If one of the two parallel

workstations is failed, the operator from the failed station moves to assist the operator at

non-failed station and hence doubling the service rate. This is the main difference

between single independent line and dual assembly line configurations. The objectives

of this paper are to decide the best configuration to choose at the same given cost, two

single independent lines or one dual line. Also, the configurations are compared based

Page 17: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

7

on the output rate. The model constraints are on the workstation failure rate and service

rate for finding the output rate. Simscript II was used to simulate the model.

This paper presents close resemblance to the topic under consideration, the only

difference being the assembly line configurations and the model constraints. The thesis

model proposed considers the configurations along the length of the assembly line. Apart

from the output rate, the operator or workstation utilization and the material handling

requirements are also considered.

Bartholdi (1993) designs a computer program to balance a two-sided assembly

line. The paper mainly focuses on the case study of a small utility vehicle manufacturing

line. The important point to be noted about two-sided assembly lines is that the operators

at each pair of work stations (mated-station) work on different tasks but on the same

individual component. Hence, Bartholdi puts forward that two-sided assembly lines are

more practical for large products like vehicles and heavy machinery than small products.

In contrast to Kim et al ‟s (2009) proposition Bartholdi‟s model tries to minimize

the number of work stations for a given cycle time, by restricting the positions where

tasks can be placed. The standard ALB problem considers assigning tasks only based on

the processing times. This paper poses constraints on certain tasks that they should be

always kept together. By doing so, the operator can learn more quickly and perform a

particular set of tasks efficiently. This is good as long as the model yields sufficient

results. The author mainly focuses on balancing two sided assembly lines where the

operators at each station share the work elements assigned to that station and work on

Page 18: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

8

the same component simultaneously. This does not discuss about station imbalances and

their impact on assembly utilization.

Becker and Scholl (2006) survey the simple assembly line balancing problem and

several mathematical techniques that can be applied to solve this problem. They give an

Integer Programming and Dynamic Programming approach to solve an assembly line

balancing problem. Scholl and Becker (2006) define an assembly line balancing problem

as optimally distributing the assembly work among the m workstations with respect to

some objective. Given the number of work stations, m and assembly cycle time, c,

several assembly line balancing problems arise by varying the objective function. A few

examples are to minimize m given a c; minimize c given m, maximize the line

efficiency, E, by considering the interrelationship between c and m.

Kim, Song and Kim (2009) propose a genetic algorithm approach to solve a two

sided assembly line known as two-ALB. They present a mathematical formulation of the

two sided assembly line balancing problem with the objective of minimizing the cycle

time for a given number of paired workstations. They call these parallel paired stations

which perform similar tasks as mated-station. The advantages of the two-sided assembly

line over one-sided assembly are shorter line length, lesser material handling, reduced

tools and fixtures cost and better throughput. The performance of the GA is compared

with the heuristic approach and found to be better.

Rachamadugu and Talbot (1991) propose a heuristic procedure based on mixed

integer programming formulation of an assembly line balancing problem. They present a

procedure that rebalances an already balanced line such that the workload on all

Page 19: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

9

assembly stations is uniformly distributed. The authors review the importance of

workload smoothing in manual assembly lines and develop the methods to measure the

smoothness.

The sum of absolute deviations of workload from the cycle time, also known as

Mean Absolute Deviation (MAD) is given as,

MAD = ∑ Total workload at station i- Total Work Content

m m

i , where m is the theoretical

number of workstations, and the mean work load W, is defined as W = (Total Work

Content/ m).

The authors suggest an iterative procedure to reduce this MAD by transferring

elemental work tasks from a station with higher than mean work load (W) content to a

station with lower than mean workload content. It must be made sure that this

transferring is between precedence tasks only. If there is no precedence restriction on

any task it can be assigned to any station so that MAD is reduced. The flowchart

showing the workload variation minimization procedure is given in Figure 2.

Although this method proves to smoothen the workload on the assembly

workstations, the model does not take into account the initial constraints or grouping of

tasks to be performed at a single workstation. This model cannot be applied successfully

under such circumstances.

Page 20: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

10

Figure 2 Re-Balancing an Assembly Line (Rachamadugu and Talbot, 1991)

Merengo et al (1999) analyses some of the most common issues associated with

manual mixed-model assembly lines. This paper focuses on reducing the number of

incomplete jobs at each assembly workstation. The problem formulation similar to

Rachamadugu and Talbot (1991), but the objective is to minimize the mean number of

incomplete jobs and even out the variation at each station to improve productivity of a

mixed-model assembly line.

Boysen, Fliedner and Scholl (2007), put together the variety of assembly line

balancing problems. The authors discuss about parallelization of assembly work i.e.

increasing operator productivity by partitioning the total work content among different

Page 21: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

11

production units. This also includes division of work across several stations within the

same serial line by making sure that the average station time does not exceed the cycle

time. They survey a series of assembly line balancing problems faced and issues

associated with assembly line design problem.

Page 22: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

12

3 ASSEMBLY LINE PRODUCTIVITY IMPROVEMENT

METHODOLOGY

The common methodology as listed below in Figure 3 is followed to improve

the operational performance of the production system.

Figure 3 Productivity Improvement Methodology

3.1 Product Selection for Study

Product selection is critical as it provides focus to the project and produce

tangible improvements in a timely manner. Trying to solve all problems at the same

time creates confusion, inefficient use of resources and delays. Product selection refers

to the process of identifying a “product” or “family” of similar products to be the target

of an improvement project or study.

• Product or Product Family Selection • Current Process Study • Time Study

As-Is Study

• Operations Analysis • Assembly line Balancing • Material Handling Analysis

Analysis and To-Be System

• Performance Evaluation System Evaluation

Page 23: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

13

The selection should be based on the following criteria:

Customer importance and importance of the product to customer.

Potential to improve overall operations.

Potential to impact other products.

Different product family classification methods are available, the most dominant

in usage being the following methods

3.1.1 A-B-C Classification Method

The A-B-C classification process is a method that helps to identify products

families based on three “importance” ratings namely A-Outstandingly important, B-

Moderately important and C-Least important. This classification makes use of “Pareto‟s

Principle” which can be generally told as 20% of the products account for 80% of the

total dollar usage.

This method mainly focuses on:

Classifying product families based on Demand volume and Sales turnover.

Identifying product families that describe the majority of inventory, which in

turn helps with better inventory management.

With the demand and sales data in hand the classification procedure is as follows:

1. List the products along with the respective demand and sales values. This is

normally represented in terms of annual demand or for any relevant time

period.

2. Calculate the product of demand, D, and value, v, i.e., Dv for each product.

Page 24: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

14

3. Arrange the products in descending order, starting with the product with

largest Dv value.

4. Then calculate the corresponding cumulative dollar usage and cumulative

percentage of total usage for all the products.

5. Then the products are classified into A, B or C classes according to the dollar

usage (Dv) values obtained. Initially products can be classified using the

following guidelines:

a. Class A: The first 5 to 10% of the products, as ranked by total dollar

usage, fall under this “most important” category. They generally

represent the 20% of the total inventory. Generally the account for

50% or more of the total dollar usage.

b. Class B: The products accounting for more than 50% of the remaining

dollar usage fall under this “not so important” class. Generally they

represent the 30% of the total products.

c. Class C: A majority of the remaining products fall in this “least

important” category and they represent only a minor part of the total

dollar usage.

Once an initial classification is obtained using the rules above, the decision

maker can modify it to take into consideration other important business criteria; i.e., a

product that has particularly long lead times, new critical products, products associated

with new products, but has a low Dv can be moved into Class A.

Page 25: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

15

3.1.2 Part-Process Matrix Method

A simple yet efficient and general method to identify product families is to

generate a part-process matrix. This mainly focuses on identifying similarities in process

steps. An example of a part-process matrix is shown in Table 1. It contains the list of

products across the rows and processing steps in the columns.

Table 1 An Example Part-Process Matrix

The examples of processing steps might be face grinding, drilling, threading,

mechanical assembly etc. and each step must be clearly defined as it is carried out. Also

repeat any processing step as many times as it occurs to show the actual product flow.

For product list, give only the base model number because different models of the same

product might have different packaging, manual language differences etc., but no

process wise differences. Once the products have been listed down and process sequence

for each product is identified, mark this process against the corresponding product. This

Product No Product NameDemand

(Units/time)

Actual Sales

($/Unit) Step 1 Step 2 Step 3 Step 4 Step 5 Step 6 Step 7 Step 8

1 Product 1

2 Product 2

3 Product 3

4 Product 4

5 Product 5

6 Product 6

7 Product 7

8 Product 8

9 Product 9

10 Product 10

Product Process Sequence

Page 26: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

16

should be done for all the products. The Table 2 shows part-process matrix with process

steps marked against each product.

Table 2 Part-Process Matrix with Process Steps Filled

The next step is to sort the parts based the processing steps. This sorting brings

together all the products with almost similar processing steps. The example in table 3

shows this sorting and grouping of products.

Table 3 Part-Process Matrix Showing Product Families

Product No Product NameDemand

(Units/time)

Actual Sales

($/Unit) Step 1 Step 2 Step 3 Step 4 Step 5 Step 6 Step 7 Step 8

1 Product 1 x x x x x

2 Product 2 x x x x x x x x

3 Product 3 x x x x

4 Product 4 x x x x x x x x

5 Product 5 x x x x x

6 Product 6 x x x x x

7 Product 7 x x x x x x x x

8 Product 8 x x x x x x x x

9 Product 9 x x x x x

10 Product 10 x x x x

Product Process Sequence

Product NameDemand

(Units/time)

Actual Sales

($/Unit) Step 1 Step 2 Step 3 Step 4 Step 5 Step 6 Step 7 Step 8

Product 2 x x x x x x x x

Product 4 x x x x x x x x

Product 7 x x x x x x x x

Product 1 x x x x x

Product 5 x x x x x

Product 6 x x x x x

Product 9 x x x x x

Product 8 x x x x x x

Product 3 x x x x

Product 10 x x x x

Process Sequence

Page 27: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

17

After identifying the desired product groups, they can be labeled for easy

identification. For the above example part-process matrix four product families can be

defined and they are labeled for easy identification as:

P: Products 2, 4 and 7

Q: Products 1, 5, 6 and 9

R: Product 8

S: Products 3 and 10

Out of these product families, the one that is expected to yield maximum output

(based on sales data) is selected. Also, under some special circumstances, a product from

a different family can be dropped in the product family considered for study if the total

work content for those families lies above 30%. For example, the product 8 can be

grouped with family P, if it is a critical component. The wastes or improvement

opportunities identified by following a single product family are likely to be translated in

equal proportions in every other product or family of products.

3.2 Time Study

Time study is a technique used to establish a time standard to perform a given

assembly operation. It is based on the measuring the work content of the selected

assembly, including any personal allowances and unavoidable delays.

It is the primary step required to determine the opportunities that improve

assembly operations and set production standards. The key objectives of a time study

are:

Page 28: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

18

To increase productivity.

To balance the work force with available resources.

To determine the production capacities.

To determine standard costs of a product.

Effective production planning and control.

Efficient plant layout.

3.2.1 What and How to Time?

The amount of work that can be performed by a qualified and well-trained

employee at a normal pace, by effectively utilizing the time and resources, needs to be

measured. For this purpose, the assembly operation is broken down into elemental work

events and the standard time taken to perform these work elements is measured. This is

because the operations are either too short (ex: inspection) or too long, but in elemental

form, the times can be easily recorded by taking beginning and ending points of the

work element Niebel (1982).

Work measurement techniques, such as stop watch time study, measure standard

time data and give more accurate results. Work measurement using a stop watch

requires,

A reliable stopwatch to perform time study.

A data collection sheet to record work elements and corresponding times

(Appendix A).

The following points are observed before starting the actual Time Study,

Page 29: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

19

The obvious problems are taken care of first. There is no reason to spend

time describing and timing work elements that are obviously unnecessary or

redundant.

The time study analyst should familiarize with the assembly operations

before documenting the elemental times. Also there should be plenty of

communication between assembly operator and the time study analyst. The

operator participation must be encouraged and their ideas must be captured.

Start the study capturing all work elements first (VA and NVA) – once all

work elements have been captured, and then proceed to time them one by one.

Trying to do both simultaneously can be overwhelming and confusing.

The first step is documenting all the assembly tasks in their work elements before timing

them by observing the following points Ortiz (2006):

All other work conditions should be in their current standard settings.

Each work element should be listed in the sequence it is performed. One part

of assembly might have many work elements associated with it. Any

repeating steps should be listed down as many times they occur throughout

the process.

The „level of detail‟ of the work element is such that it allow you to capture

enough detail to provide useful insight about the process, but not too much to

overwhelm you with unnecessary information.

Work elements should be defined in a way that they can be reliably timed. If

the level of detail is such that the work element is very short in duration, then

Page 30: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

20

it will be impractical because this may be difficult or impossible to measure.

In practice, an experienced time study analyst can measure reliably elements

as short as 2.5 seconds. This can be reduced in half if the short work element

is between two relatively long work elements.

Once the work elements are listed, classify the work elements as follows:

The work elements are basically categorized as set up tasks, actual processing

tasks and system or administrative tasks. Also, any movements associated

with performing these work elements (ex: moving the subassemblies, looking

for parts and tools etc.,) should be clearly noted. It is convenient to separate

the study of setups, processing and system processes.

The work elements are further marked as value added and non-value added

activities. Value added work is the actual work that is valuable and is

reflected in the final product. Examples of non-value added activities include

searching for tools, moving the sub-assembly to a different location for next

process, unnecessary moving of parts etc.

3.2.2 Time the Work Elements

Once all the work elements are identified, they are timed using a stopwatch and

the same time units must be used throughout the study to keep the data consistent. The

times taken for performing each element can be recorded in two ways. In “continuous”

method, the stop watch is pressed on during the starting point of process, time is

recorded at the end of each work element, and the stop watch is only stopped at the end

of process. A stop watch with capabilities to measure “splits” is recommended for this

Page 31: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

21

situation. In “snapback” timing method, the watch is set back to zero at the end of each

work element and the time for next work element is recorded.

It is recommended to take several time measurements for each work element

(e.g. At least 12 time samples for each work element). Recording multiple samples

allows us to better estimate the average time and also capture the variability associated

with a given work element. Work elements can be timed two different ways: as they

occur sequentially during the assembly process, or element-by-element. The Time Study

Data Sheet can be used to record the times during the time study. If abnormal events

occur while taking a sample, the sample must be discarded or annotated.

Calculations:

Calculate the average and standard deviation.

Calculate standard error = standard deviation/√(n); A significant standard

error indicates that the number of samples used was insufficient for the

corresponding work element.

Remove outliers (those outside ±3s) and recomputed until there are no

outliers. It is important to document and explain the reason why an outlier

occurred. Explaining outliers provides useful insight and knowledge about

the assembly processes Ortiz (2006).

3.3 Operations Analysis

The operation analysis is a method used to identify and analyze the productive

and non-productive activities described above by deployment of Lean elements and is

concerned with developing techniques to improve productivity and reduce unit costs.

Page 32: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

22

Any operation improvement is a continuing process and with sufficient study of all the

operations, they can be practically improved. Some of the elements of Lean operations

analysis are as follows.

3.3.1 Process Chart

A process chart is a graphical representation of any manufacturing process or an

assembly operation. It contains the sequence of all operations in the order in which they

are performed and includes inspections, time allowances and materials used in any

business process – from the arrival of raw material to the final product.

There can be a variety of process charts depending upon the specific application

such as the operation process chart, the man and machine process chart, the flow process

chart, the operator process chart etc. It is essential to document all the work elements

performed involved in an assembly process. The procedure that follows process charts

analyzes all the work elements and the non-value added activities are given special

attention with the goal of process improvement. During the operation analysis special

consideration must be given to

Material Handling

Plant Layout

Delay Times

Storage

The questioning attitude – Improvements come from first examining what is

happening actually with an open mind and then inquiring into what might be the other

alternatives. While investigating the work elements nothing should be taken for granted

Page 33: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

23

and everything should be questioned. Answers should be given based on facts and actual

available data. The most important question that one should ask while analyzing an

operation is “why?”, this immediately leads to other questions related to the process that

take the form as shown below in Figure 4.

Figure 4 Showing the ‘Why?’ Analysis

Answering these questions may generate ideas that will lead to the process

improvement. Questions should not be asked at random, but it should proceed

systematically, in the order in which they should be acted upon. For example, it is

unwise to question upon the tools and setup times is not recommended before defining

the purpose of the operation. When this systematic questioning approach is followed,

possibilities for improvements will be uncovered. The above discussed questioning

approach should be carried out along with the following operation analysis approaches

to analyze each operation and recognize improvements Maynard (2007).

Page 34: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

24

3.3.2 Purpose of the Operation

To begin with the analysis of any assembly operation, the very first point is to

define the purpose of the operation i.e. the process boundaries are defined and the entry

points of the process inputs and the exit points of the process outputs are marked. The

process is to be studied and any opportunities to eliminate or combine an operation must

be considered before improving it. Many times unnecessary operations arise due to

improper planning when the process was initially set up. So, an initial estimate should be

made of things like volume or quantity, labor content, facilities used to perform the

operation, transportation facilities, inspection facilities, storage facilities etc. so that

there would be no interruption or delay while developing an improvement method.

Sometimes unnecessary operations may arise because of the improper

performance of the previous operation. A second touch-up operation may be necessary

to make the job acceptable. At times, this secondary operation may also be necessary to

facilitate another operation that follows. Also, sometimes an unnecessary operation may

develop because it would give the final product a decorative appeal. Some unnecessary

operations are deliberately added to prevent any reworks that might arise during testing

of the final product.

In this scenario the questioning attitude would provide better solution

opportunities. But just asking the question “what is the purpose of the operation?” does

not necessarily provide better understanding of the process. For example, further

answers should be obtained for questions like:

Is the required result accomplished by the operation?

Page 35: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

25

What makes this operation necessary?

Was the operation established based on the requirements for subsequent

assemblies?

Is the operation added to improve the appearance of final product? Is this cost

justified?

Can the purpose of this operation be justified in a different method?

Can any feasible changes be requested from the supplier to avoid any

unnecessary operations?

Efforts should be made to obtain true answers to the questions. The result of the

analysis would eliminate any obvious unnecessary operations and provides a base to

subsequent operation analysis approaches.

3.3.3 Material

The following points should be considered related to direct and indirect materials

utilized in the process:

A less expensive alternative material can be studied and analyzed to

minimize overall material costs.

Standard operating procedures must be developed for the assembly process

and followed to prevent any reworks and material wastage can be avoided.

Available material and tools must be used conservatively and economically.

Materials and tools can be standardized if possible to reduce the number of

inventory and lesser storage space. This standardization is a continuous

improvement process.

Page 36: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

26

3.3.4 Setup and Tools

Before any work is done, certain preparatory or “make-ready” operations are

performed. Setup time is the time required to prepare the equipment to perform an

operation on the required number of units. This involves procuring tools and materials,

receiving instructions, preparing the workstation, cleaning up the work station and

returning the tools to the tool crib. It is often difficult to control the setup times and this

can be improved through better production control. Suppose if the production operation

involves a batch of units the setup time can be reduced per unit by increasing the batch

size.

By making arrangements to provide the tools using palettes at work stations,

dispatching instructions and materials at the work table at correct times and return them

respectively, the need for operator to leave the workstation can be eliminated. Also by

standardizing the tools and mechanizing the manual operations, the setup times and

number of tools used can also be reduced. If required special purpose quick acting tools

may be used to reduce the setup times.

For example, typical questions which lead to improvements in this area can be

How is the job assigned to the operator?

How are instructions given to the operator?

How are materials and tools supplied?

What are the possibilities of delays in procuring tools and materials?

Could a supply boy be used to get tools, materials and instructions?

How far is the operator responsible for maintaining the workstation?

Page 37: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

27

3.3.5 Working Conditions

It is very important to provide good, safe, and comfortable working conditions.

Studies have proven that providing good working conditions has positive impact on the

overall productivity Drucker (1999). Some common considerations for improving the

working conditions are as follows:

Improve lighting conditions of work area. Eliminate shadows in work station

areas as well as provide correct level of illumination as per the standards.

Improve the temperature and comfort conditions of the work area. This

reduces heat fatigue and cramps to the operator. Uncomfortable working

conditions sometimes cause operator stress and reduce the productivity.

Provide adequate ventilation.

Promote orderliness, cleanliness and good housekeeping (5S). These reduce

accidents; improve floor space usage and employee morale.

Provide personal protective equipment.

Provide guards at points of power transmission (if required).

Provide well-formulated first-aid program.

3.3.6 Material Handling

Material handling involves motion, storage and quantity of materials throughout the

process and it mainly focuses on the following points.

The required material (raw material, in-process material, finished goods)

must be supplied periodically from one location to another location.

Page 38: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

28

The production process should not be interrupted or the customer demand

should not be lost due to early or late material arrivals.

The delivery of materials must be assured at correct place in proper quantity

and at correct time.

Sufficient storage space should be assigned, both temporary and permanent.

Material handling improvements go hand in hand with other improvements like

plant layout and working conditions. The major benefits of improving the material

handling facilities are

Reduced handling costs: The labor costs, material costs and overhead costs

can be reduced due to effective material handling.

Increased capacity: Improved material handling system along with improved

facility layout increases material storage capacity.

Improved working conditions: Better material handling system increases

safety and less fatigue to operators and better availability of product at the

required time and place.

Following are the few points that help analyze and improve the material handling

system

Time spent in picking up the material must be studied. Loose piling of

material on the floor must be avoided. Material can be stored on pallets or trays

that can be picked up directly and moved to desired location. Advanced material

handling equipment like conveyers, portable elevators may be installed if

necessary.

Page 39: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

29

Existing material handling equipment must be analyzed and equipment

utilization should be studied. Appropriate measures should be taken to efficiently

utilize the existing equipment. Repairs and preventive maintenance should be

planned accordingly to prevent any material losses.

3.3.7 Line Layout

The primary objective of an efficient layout is to establish a production system

that allows producing the desired quantity of products with desired quality at minimum

cost. An effective layout should incorporate inventory control, material handling,

scheduling, routing and dispatching. A layout that works best in a given set of operating

conditions can be poor in a different set of working conditions. Since the working

conditions can be continuously improved, there arise several opportunities to improve

the layout over the time.

A variety of assembly line layouts, as shown in Figure 5 are feasible for any

given assembly process (Straight line layout, U shaped layout). An ideal layout is

considered to be the one that provides adequate output at each work station without

causing bottlenecks and interruptions to the production flow Silver et al (1998). A

careful study of the proposed layout should be carried out before changing to a different

layout. A good analysis method is to construct a process flow chart for the proposed

layout so that the expected improvements are highlighted such as reduced material travel

distances, material storage, delays and overall costs etc., This will bring out any defects

in the proposed method and thus can further be improved to achieve best results.

Page 40: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

30

Figure 5 Showing Examples of Different Assembly Layouts (Source: R. W. Hall, Attaining

Manufacturing Excellence Homewood, IL: Dow Jones-Irwin, 1987, p. 125)

Page 41: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

31

3.3.8 Principles of Motion Economy

One of the most important operation analysis approaches is to simplify the

operator body motion i.e. analyzing the operator‟s physical activity and reduce the work

content. This approach helps to eliminate wasted motion, make operator tasks easy and

reduce operator fatigue. This goes alongside principles of Ergonomics and provides a

productive and safe work area.

The major focus of these principles is given below:

The both hands should begin and end work at the same time. Work station

design should be improved so that operator can work with both hands at same

time. The work reach area is shown in Figure 6.

Each hand should go through as few motions as possible.

Hand movements should be limited to smaller areas and long reaches should

be avoided. This can be enabled by placing the frequently used objects close

to the operator and by installing efficient material and tool storage units.

Figure 6 Showing Operator Work Reach Area (International Labor Organization

Guidelines)

Page 42: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

32

Operator unnecessary movements can be identified and eliminated for process

improvement by answering the questions such as

How can a sub-operation be made easier?

Can this operator movement be eliminated?

Can this movement be made easier?

By following the above approaches and by getting accustomed to the questioning

attitude any business operation can be continuously improved.

3.4 Assembly Line Balancing Problem

Applying Lean thinking, the first step in increasing the assembly line

productivity is to analyze the production tasks and its integral motions. The next step is

to record each motion, the physical effort it takes, and the time it takes, also known as

time and motion study. Then motions that are not needed can be eliminated also known

as non-value added activities and any process improvement opportunity exists must be

identified. Then, all the standardized tasks required to finish the product must be

established in a logical sequence and the tools must be redesigned. If required, multiple

stations can be designed and the line must be balanced accordingly. The distribution of

work on each of these stations must be uniform. The productivity can be improved by

incorporating a dedicated material handling system. This allows assembly operators to

concentrate on the essential tasks.

Some of the most critical components of an assembly line are given as follows

Chow (1990). The members of the list are mainly application dependent and can be

altered according to the assembly requirements.

Page 43: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

33

Process design or standardization

Line balance

Material handling

Parts procurement and feeding

Work-in-process management

Man power

Line size

Line configuration

All these factors are closely related with one another and have a considerable

impact on the assembly line performance as well as production cost. Various line

configurations would demand different material handling strategies and multiple levels

of line re-balancing so that the desired performance level can be achieved. Assembly

line design involves step-by-step approach by varying and analyzing each of these

factors and arriving at a best feasible design.

The operations analysis of a manual assembly system results in a set of

standardized production and assembly operations. The next step is to organize these

assembly tasks in an optimal manner to achieve the required targets. The important

decision problem that arises when constructing or re-configuring an assembly line is

assembly line balancing. The assembly line balancing consists of distributing the total

manufacturing work load uniformly among all the workstations present along the

assembly line. The overall performance of the production system is greatly affected by

this distribution of work.

Page 44: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

34

An assembly line balancing problem is associated with the design of a process

flow line, which, generally consist of a number of workstations that are joined together

by some type of material handling system, for example a conveyor Van Zante-de

Fokkert and de Kok (1997). For a given product, the entire assembly operation is broken

down into a number of work elements or tasks. Each work station performs some of

these assigned tasks. The product assembly is completed by sequential completion of all

the tasks.

Every product goes through the same sequence of assembly tasks in the same

order. The precedence relationship between the assembly work elements can be well

represented using a precedence network diagram. This on the other hand forms the basic

step in solving an assembly line balancing problem. Then, the strategic assignment of the

work elements to consecutive work stations in the assembly line follows with respect to

some objective. While doing so it must be ensured that the precedence constraints are

met.

Some of the terms associated with general assembly lines and their definitions

are given below Niebel (1982).

Precedence Diagram : The precedence diagram is a network showing the order of

assembly tasks in a sequence in which they are carried out and including the restrictions

on the performance of these tasks (such as position, precedence relationship etc.)

Minimum Rational Work Element: A minimum rational work element is an assembly

task that cannot be sub-divided into any further feasible tasks. The time taken by kth

work element can be denoted by Tek. Before starting the line balancing process, all the

Page 45: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

35

work elements involved in an assembly must be clearly defined and the time taken for

each work element must be estimated.

Let,

S Number of workstations, 1, 2, …, m

k Set of tasks, ,2, … , n

Total Work Content: The total work content (Twc) of an assembly is equal to the sum of

all work element (k) processing times associated with that assembly.

Twc = ∑ Teknk , for all values of k

Station Time : Station time is the total time available at each work station. It is the sum

of all the times of work elements that are being processed on a single work station (S).

Station time, Tsi ∑ , where work element k belongs to station S.

Cycle Time : Cycle time (Tc )can be defined as the rate of production. This is the time

between two successive assembled units coming out of the line. The cycle time can be

greater than or equal to the maximum of all times, taken at any particular station.

i.e. Tc ≥ max {Tsi}

If Tc = max {Tsi}, then there exist ideal times at all the stations, i.e. having station time

less than cycle time. It can be understood that the cycle time can be never less than the

station time.

Cycle time Tc = (available time or total work content time)/(Target production rate)

Line balance efficiency: This denotes the performance of the assembly line. It is given

by the ratio of total work content time to the total cycle time multiplied by number of

work stations.

Page 46: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

36

Line efficiency, E = Twc / (m Tc)

Balance delay: This is the measure of line-inefficiency. This arises due to imperfect

allocation of work elements to stations.

Balance delay, d = (mTc - Twc ) / mTc

The idle time or imbalance associated with the assembly line is | Tc - Tsi |

If the demand rate for a product is known and given as D,

The theoretical number of workstations required can be calculated as follows:

S = (Twc / Tc )

Then, the work elements will be assigned to these number of stations, one at a

time, by meeting cycle time requirements and precedence constraints.

A number of objectives based on the specific requirements can be associated

with assembly line balancing. A few examples of assembly line balancing objectives are:

To minimize the number of work stations for a given cycle time.

To minimize the cycle time for a given number of workstations.

To minimize the number of incomplete jobs.

To minimize the expected total costs.

To maximize the profit.

Van Zante-de Fokkert and de Kok (1997) mention that the assembly flow lines can

be classified into the following classes.

Single Model Lines – Dedicated to the production of a single model. The

tasks performed at each station are same for all the products.

Page 47: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

37

Mixed Model Lines – Handles the assembly of more than one product or

model. Each assembly station is designed such that various tasks needed to

produce any model that moves along the line can be performed. Most

consumer products have mixed model lines.

Batch Model Lines – Each model is assembled in batches. The assembly

workstations are equipped so that a required quantity of first model is

produced and then the stations are re-configured to produce the other model.

This model is economical to assemble products with medium demand and to

use one assembly line to produce various products in batches than construct a

separate line for each model.

A number of researchers proposed various optimization techniques to solve an

assembly line balancing problem, such as, linear programming method, (0,1) integer

programming method, network and assignment problem methods, dynamic

programming etc. Rekiek et al (2002). Ranked Positional Weight (RPW) heuristic was

one of the first proposed heuristics to solve assembly line balancing problem. The

ranked positional weight is defined as the sum of the operation time of the work element

and the operation times of all work elements that come after it in the precedence network

sequence. Two things need to be considered while an assignment is being made (1) The

precedence relationship is maintained at all times and (2) The overall station time does

not exceed cycle time. The manual assembly line problem considered in the case study is

balanced using RPW heuristic approach. The procedure followed using RPW heuristic

approach is given below:

Page 48: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

38

1. For all the work elements precedence events are identified and the network

diagram is drawn showing next to it the corresponding time taken to perform

the task.

2. The total work content time, workstation cycle time and the theoretical

number of work stations required are calculated.

3. The ranked positional weight for each node of the precedence network as

given below.

Let n i represent all the nodes in the path proceeding from node „i‟ in the

precedence diagram. Therefore, the RPW for node i is,

RPW (i) = Tei + Σ Tej, where j ϵ n (i)

= (work element time) + (sum of work element times of all tasks

following node i)

4. Arrange the work elements in the decreasing order of the RPW value.

5. Following the ranked order, start assigning the work elements to work

stations, one station at a time. While the tasks are assigned to the first station

make sure that (1) the precedence relationship is maintained and (2) the

overall station time does not exceed cycle time. If the following work

element is making the station time value go higher than the cycle time,

proceed to check with the next work element. A new station opens when

there is no possibility of continuing assigning operations to the currently open

station. Proceed with assigning tasks to the next station in a similar way.

Page 49: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

39

4 CASE STUDY

The three step productivity improvement methodology is applied to a real

problem consisting of a manual assembly line. The assembly line contains mobile phone

package assembly operations. The process involves initial disassembly, light assembly

and inspection operations. Each package comes in a master box which contains ten such

packages as shown in Figure 7. Once all the packages are ready they are placed in an

empty master box and the master box is moved to bar-coding area and then to the

shipping area.

Figure 7 Figure Showing Master Box and Individual Packages

The bill of materials (BOM) list for a single package is as follows:

Handset

Battery

USB data cable

Hands free set

Charger

Installation disc

Page 50: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

40

User friendly manual kit

Labels and pamphlets

Package box

Outer wrapper

Bar-coding stickers

4.1 Current Assembly Method

In the original assembly method, the input buffer has no pre-specified capacity.

The master boxes are piled at both input and output sides of the assembly table in stacks

using storage pallets. Each pallet holds approximately 40 to 60 master boxes. The

individual packages are then removed from the master box on to the table, all at a time,

and the assembly is carried out on each package by four different operators.

The subassemblies and the headset components are pushed from one person to

the next person on the table without an appropriate material handling arrangement. Once

the assembly is completed, the packages are arranged in an empty master box and placed

on storage pallet. These finished master boxes are then carried to bar coding area

manually by an operator. The major drawbacks of the current assembly method are

improper material handling structure, poor material storage system (including bins and

dispensers for labels, pamphlets etc.) and undefined standard operating procedures. This

causes repetition of tasks and unnecessary operator movements such as removing and

replacing the same accessories at two consecutive stages, confusion in assembly,

assembly reworks etc.

Page 51: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

41

4.2 As-Is Study

The first step in productivity improvement methodology is the as-is study. For

the current scenario, almost all the models produced have the similar processing steps.

Hence, the product selection step has less significance in this context. In the next step,

the current process is studied and all the assembly work elements are listed. Time studies

are then carried out and the data obtained is analyzed to identify bottle neck situations

and establish production standards. The list of operations with time study data for

original assembly method is given in Appendix A.

The precedence network diagram is drawn by the plant engineers for the original

assembly process as shown in Figure 8. Of notice is that this network is a simple

sequence of operations as performed, rather than a network showing all the possible

assembly sequences.

The target given for this assembly line is 35 boxes/operator/hour. Due to the

drawbacks associated with this method, the actual measured assembly output is observed

to be 29.8 boxes/operator/hour. From the process study and the network diagram, it can

be seen that the assembly line has large scope for improvement by careful analysis. The

next step explores these opportunities and develops methods to perform the assembly

better.

Page 52: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

42

Figure 8 Original Precedence Network Diagram

4.3 Analysis and To-Be System

The next step, operations analysis, helps to identify improvement opportunities

by highlighting productive and non-productive operations. This step also facilitates

effective ways of doing things by suggesting alternate methods to perform operations to

reduce operator fatigue and unnecessary movements to improve the overall performance.

The operations analysis step adapts certain principles of Lean manufacturing such as

standardization, visual management, 5-S and ergonomics, making the assembly line

Lean.

For the assembly line, the operations analysis is carried out and the assembly

operations are standardized by reducing the non-value added activities and the

corresponding standard times are established. This standardized list of operations along

Page 53: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

43

with time study data and cycle time is shown in Appendix A. The precedence network

diagram for the standardized assembly is given in Figure 9.

It can be seen from the precedence diagram that certain tasks are grouped (like

tasks 20 to 26; 15 to 19) which enables improve operator efficiency. It is preferable to

have a single operator complete a sequence of operations and pass a finished sub-

assembly to next stage. Setting such sub goals enables operators learn the tasks more

quickly and help perform them more dependably and faster. Also grouping of tasks

facilitates better material storage at each stage, supports visual management of work

space and mistake proofing (Poka-Yoke).

4.16

3.85

0.89 1.76 1.59

0.83 0.9 1.7

2.32

0.96 0.74

0.62

0.77 0.97

1.48

1.2

1.19 2.53 0.74 1.06 1.99 1.68 2.24 4.51

2.65

1.23 1.02

3.87 4.40

1

2

3

4 5

6

12

7 8 9

24

23

22

212028272625 33323129

30

11

10

15 18 19

13 14

16 17

START

FINISH

Figure 9 Modified Precedence Network Diagram

Page 54: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

44

Operations analysis step also results in selecting the most suitable assembly line

layout, which further helps in planning a good material handling system. Taking into

account the total assembly time required to produce one package (which is considerably

small), the simplicity of the assembly operations, the feasibility to modify the existing

layout without causing much effect on current production, the traditional straight line

configuration is chosen. A straight line configuration is well suitable for assemblies

involving operators perform a set of tasks continuously in a given sequence for all the

products (Aase et al, 2004).

The two proposed assembly line configurations for the current assembly method

are shown in Figure 10. The next step to improve the assembly line productivity is to

design and balance the assembly line accordingly to satisfy the cycle time and demand

requirements.

Both the configurations take into consideration Lean manufacturing principles

such as Standard Work, 5-S, Visual Controls, Kaizen (Continuous Improvement) and

knowledge sharing, to improve productivity, reduce work-in-process inventory, floor

space reduction, minimize operator unnecessary motion and reworks. A brief description

of each configuration with the workstation specifications follows.

Page 55: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

45

Figure 10 Proposed Assembly Line Configurations

4.3.1 Single Stage Parallel Line Configuration

The entire set of assembly operations required to produce one package will be

performed by single operator at one workstation. The number of operators is reduced

from four to one operator per assembly table from the original method. The completed

package will be placed in a master box and the finished master box with ten of these

packages is moved through conveyor to an output buffer. The master box is then

Page 56: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

46

transferred to bar coding area by a material handler. A schematic of the proposed

assembly station design and the entire line can be seen in Figure 11 and Figure 12

respectively.

Figure 11 Single Stage Workstation Design

The light signals at each table serve as Lean visual management tool and allow efficient

material handling.

Green light ON denotes that there is a box in the buffer at the table.

Orange light ON denotes an empty buffer at the table.

Red light ON denotes idle assembly table.

Page 57: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

47

Figure 12 Single Stage Parallel Line Design

Having the input buffer shelf helps reduce the excess inventory of master boxes

at the assembly station as compared with original method. Also, with the single stage

layout the floor space usage is reduced from 42.07 m2 to 24.22 m2.

4.3.2 Five-Stage Serial Line Configuration

The assembly table consists of five work stations and each stage is assigned with

a defined set of work elements. The work elements are assigned to each station using

Ranked Positional Weight (RPW) heuristic method (Section 3.4). The balanced line with

five assembly stages is shown in Figure 13.

Page 58: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

48

Figure 13 Precedence Diagram Showing Five Assembly Stages

After the completion of tasks at each stage, the components or sub-assemblies are

pushed on to a conveyor located along the center of work table by using a material tray.

The operator at the next stage pulls the tray from the conveyor and completes the

assembly. Once the package reaches the end of assembly table it is placed in the master

box and then the master box is moved to bar-coding area by a material handler. The light

signals and input buffers help make the assembly line Lean. Figure 14 and Figure 15

give the design of assembly workstation and assembly line for the five-stage

configuration.

3.85

0.89 1.76

4.18

1.7 1.59

2.32

0.96 0.83 0.9

0.74

0.62

0.95 1.48

0.77

1.22

1.19 2.53 0.74 1.06 1.99 1.68 2.22 4.51

2.65

1.23

1.02

3.87 4.4

1

2

3

4 5

6

12

7 8 9

24

23

22

212028272625 33323129

30

11

10

15 18 19

13 14

16 17

Start

FIN

Station 1

Station 2

Station 3 Station 4Station 5

Page 59: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

49

Figure 14 Five-Stage Workstation Design

The conveyor at each assembly stage can hold only two material trays. This

prevents excess work-in-process inventory in terms of packages. The stopper acts as

mistake proofing tool by avoiding accidental tray movement to the next stage.

Figure 15 Five-Stage Serial Line Design

Page 60: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

50

4.4 System Evaluation

Under ideal conditions, experimenting with the real assembly line would be

excellent, but is not feasible always. The costs associated with manipulating the system,

parameters, operators and workstations may be quite large. These costs can be in terms

of capital required to bring about the changes and the output lost during this process.

Simulation proves to be an exceptional tool in such scenario and efficiently provides an

estimation of all the performance parameters (Banks et al, 2000).

4.4.1 Objectives of the Simulation Analysis

Simulation was used to analyze the assembly line and the associated material

handling and distribution system for the proposed assembly layouts. The objectives of

the simulation analysis are to determine

The number of master boxes to be loaded per material delivery cart.

The input and output buffer sizes of the assembly tables.

The number of material handling carts required to deliver the master boxes

from storage area to assembly tables.

To determine number of material handlers required to deliver finished boxes

from assembly tables to bar-coding area.

WITNESS simulation software is used to model the two proposed manual

assembly line configurations. For all the experiments carried out, the simulation is run

for 40 hours of simulation time with a warm up period of 8 hours.

The basic assumptions of the simulation analysis are

No breakdowns are considered.

Page 61: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

51

Set-up times are considered to be zero.

All the time units are considered in seconds.

All the dimensions are considered in meters.

The station times are normally distributed (Appendix A).

4.4.2 Material Handling System - Proposed Operation

Manually operated push carts are used to deliver master boxes from the pallet

storage locations to the assembly tables. Input and output buffers located at each table

ensure a constant and controlled work-in-process at the lines, and also appropriately

protecting each station from possible material starvation. Labels and other

documentation to be assembled with each product do not need frequent replenishment

and will be stored at the point-of-use bins on the assembly table.

The master boxes are picked by material handling carts at the pick-up point

which is approximated as the centroid location of the main storage. Geometrically, the

centroid defines the center of a plane considered. While simulating, the centroid storage

location is assumed for master boxes, such that the material handling cart travels

uniform distance while dispatching material across various assembly lines following

specified logic (Appendix B). Then, the loaded carts move along the pre-determined

path and transfer master boxes to the input buffers located in front of assembly tables.

The empty cart then moves along the defined path to the pickup point to load master

boxes again.

If all the buffers are full, the cart waits at the specified point until any of the

buffers becomes empty. Once a buffer becomes empty, the cart proceeds to the buffer to

Page 62: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

52

fill material. The cart always moves along the specified path and in one direction only.

And also the material is always filled in the order in which the cart moves. The finished

master boxes are transported to bar-coding area in a similar fashion. See Appendix B for

detailed material handling logic followed by carts.

The parameters used by the cart and related assumptions are given below

The cart speed is determined experimentally so that it is not too fast or too

slow. Cart speed = 0.7 m/s.

The cart‟s loading and unloading times at each assembly table are Triangular-

distributed with mean 4 seconds and lower limit and upper limit as 3 seconds

and 5 seconds respectively (Appendix A).

Once this logic is set, the buffer size required at each assembly table, the cart

capacities and the quantity needs to be determined. The simulation model is tested for

two assembly line configurations with different material handler inputs. The results in

terms of average station utilization and the part output are plotted against the quantity

carried by material handling cart. The detailed description of material handling and

routing logic is given in Appendix B.

The schematics of the simulation model are shown in Figure 16 and Figure 17

respectively.

Page 63: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

53

Figure 16 Simulation Model for Single Stage Parallel Line Configuration Showing Pick-up

Point

For a Single Stage Line,

The model contains 4 assembly modules with 16 tables and operators in each

module.

The material handlers move along the path shown in grey across the tables.

The conveyor is located between the tables.

Cycle Time has Normal Distribution with mean = 538.7 seconds and std. dev.

= 10 (for one complete master box assembly) (Appendix A).

Page 64: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

54

Figure 17 Simulation Model for Five Stage Serial Line Configuration Showing Pick-up

Point

For Five-Stage Line,

The model contains 11 assembly modules with two assembly tables in each

module. Each table contains five stations and one operator working at each

stage.

Each module contains a worktable at the front of the line which pulls out

packages from master box and places sim card on each package. The

packages are then pulled by assembly workstation one at a time.

Page 65: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

55

The material supply carts move along the path shown in green and the

finished master boxes are moved to bar-coding area along the path shown in

grey. A conveyor is located between the tables.

4.5 Simulation Results

4.5.1 Material Handling Cart Capacity

For single stage line it can be seen from Figure 18 that at cart capacity as 6 boxes

maximum utilization is achieved. The idle time for material carts increase when the

capacity exceeds 6 units although utilization is 100%, which is not recommended.

Similarly for five-stage line, maximum table utilization is observed at a capacity of 6

boxes. So, for both the configurations the material handling cart loads 6 boxes per trip.

Figure 18 Cart Capacities for Both Configurations

73%

86%

96% 100%100%

50%

55%

60%

65%

70%

75%

80%

85%

90%

95%

100%

4 5 6 7 8

No of Boxes per Cart

Average Table Utilization

83.5%

82.8%

86.8% 86.8% 86.8%

80%

81%

82%

83%

84%

85%

86%

87%

88%

4 5 6 7 8

No. of Boxes per Cart

Avg. Table Utilization

Maximum Table Utilization

Single Stage Parallel Line Layout Five-Stage Serial Line Layout

Page 66: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

56

4.5.2 Material Handlers Required – Supply Side

With the cart capacity fixed as 6 units, iterations are run by varying the cart

quantities. For both the configurations, 2 carts are required to supply master boxes to

input buffers.

4.5.3 Input Buffer Size

The assembly tables yield maximum utilization when the input buffer size is 2

units. Figure 19 gives the analysis of changing buffer sizes on the average table

utilization.

Figure 19 Buffer Sizes for Both Configurations

4.5.4 Output Buffer Size

The output buffer size is determined by performing iterations by varying the

output buffer capacity for fixed input buffer sizes, cart capacity and quantity. The output

Single Stage Parallel Line Five-Stage Serial Line

82.30%

99.70%

75%

80%

85%

90%

95%

100%

Buffer Size - 1 Buffer Size - 2

Average Table Utilization

85.50%

86.90%

82%

83%

84%

85%

86%

87%

88%

89%

Buffer Size-1 Buffer Size-2

Average Table Utilization

Page 67: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

57

buffer capacity is obtained for single stage line as 5 units and for five-stage line as 2

units per table

4.5.5 Material Handlers Required – Bar Coding Side

The single stage line requires two operators to carry finished master boxes to bar

coding area. The five-stage line requires three material handlers with carts to transfer

master boxes to bar coding area. This is determined based on how the finished box

removal from output buffer affects the assembly utilization. The material handling

requirements based on the table utilization is shown in Figure 20.

Figure 20 No. of Material Handlers Required

Single Stage Parallel Line Five-Stage Serial Line

60%

96% 96%100%

80%

54%50%

55%

60%

65%

70%

75%

80%

85%

90%

95%

100%

1 2 3

No. of Operators

Avg. Table Utilization

Operator Avg. Utilization

83.5%

82.8%

86.8% 86.8% 86.8%

80%

81%

82%

83%

84%

85%

86%

87%

88%

1 2 3 4 5

No. of Material Handlers

Avg. Table Utilization

Maximum Table Utilization

Page 68: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

58

4.5.6 Analysis of Results

The Table 4 consolidates and compares the results for the two assembly

configurations tested.

Table 4 Consolidated Results

Parameter Single Stage Parallel Line Five Stage Serial Line

No. of material handlers

required – Supply side

2 Carts with operators 2 Carts with operators

No of material handlers

required – Bar coding side

2 Operators 3 Carts with operators

Cart capacity 6 Boxes 6 Boxes

Input buffer size 2 Boxes 2 Boxes

Output buffer size 5 Boxes 2 Boxes

Figure 21 Results Comparing Two Configurations

4

4.4

3

3.5

4

4.5

5

Configuration-1: Single

Stage Parallel Line

Configuration-2: Five

Stage Serial Line

Avg. No. of Tables Served per

Material Handler

59.77

58.1

55

56

57

58

59

60

61

Configuration-1: Single

Stage Parallel Line

Configuration-2: Five

Stage Serial Line

Box Output/Operator/Hour

Page 69: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

59

The consolidated results comparing the two assembly line configurations are as

follows.

Tables Served Per Material Handler: Number of tables served by each material handling

unit is higher for five stage serial line configuration. Figure 21 shows that the five stage

serial line requires less material handlers than the single stage line. The number of tables

to be served is lesser in five stage configuration compared to the single stage

configuration. But it can be observed that the difference is not highly dominating.

Productivity: The single stage configuration gives output as 59.7 boxes/operator/hour

where as five stage line gives 58 boxes/operator/hour. There is a considerable

improvement in productivity in both the assembly lines from the original method.

Operator Utilization: Figure 22 shows that the average operator utilization for single

stage line is about 99% and for five stage line is 86.9%. It can be seen that for a five-

stage line all the operators at different stages of assembly line are not uniformly utilized.

Figure 22 Operator Utilization

89.50% 88.17% 86.73%

63.51%

98.05%

0%

20%

40%

60%

80%

100%

120%

Stn. 1 Stn. 2 Stn. 3 Stn. 4 Stn. 5

Five-Stage Serial Line Operator

Utilization

99.10%

86.90%

80%

82%

84%

86%

88%

90%

92%

94%

96%

98%

100%

Configuration-1: Single

Stage Parallel Line

Configuration-2: Five

Stage Serial Line

Operator Average Utilization

Page 70: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

60

While solving an assembly line balancing problem, certain amount of imbalance

in station times is inevitable. In this case, the level of imbalance shows a great impact on

the assembly line utilization. The Table 5 shows the imbalances in station times for the

five stage line.

Table 5 5 Stage Assembly Line Balancing Showing the Imbalance Associated With Each

Stage

Hence, it is recommended to implement the single stage parallel line in order to achieve

higher productivity and better overall assembly performance.

S. No Operation Avg. Time Work Stn. Station Times Cycle Time Imbalance

5 Take individual box 0.96

6 Peel original import label 3.85

7 Breaking the seal of approval 0.83

8 Open Individual box 0.90

9 Remove pamphlets and disk from the box 1.70

10 Stick the label on the disc manual 2.32

11 Verify the internet address booklet 0.74

12 Check handset 0.77

13 Remove handset tray from box 1.23

15 Check full pamphlets 0.89

16 Paste label on charger box 3.87

17 check charger 4.40

20 Remove the Phone from bag 1.22

21 Remove the flip 0.9522 verify the sd card for handset 0.62

23 Verify the serial number and logo of NOM 2.65

24 Place lid back on the phone 1.19

25 Save phone in the bag 2.53

26 Arrange phone on tray 0.74

27 Return the tray in the box 1.06

14 Check complete accessories 1.02

18 Add user policy to the pamphlets 1.76

19 Add user guide to pamphlets 1.59

28 Returning pamphlets to the box 1.99

29 Close Individual box 1.68

30 Paste import tag 4.18

31 Place security seal 2.22

32 Place on individual box the outer wrapper 4.51

33 place individual box in master 1.48

Stage 1

stage 5

stage 2

stage 3

stage 4

11.31

10.77

11.16

10.97

8.04

12.39

-0.54

-0.39

-0.20

2.73

-1.62

Page 71: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

61

5 SUMMARY AND RECOMMENDATIONS

5.1 Summary

The objective of this project was to improve the productivity of the manual

assembly line. The three step methodology incorporating Lean principles is applied to a

case study problem and two different assembly configurations are developed and

compared, namely Single Stage Parallel Line and Five Stage Serial Line. Based on the

simulation performance results, the Single Stage Parallel Line is suggested to be

implemented. From Figure 23 it can be observed that the proposed system results in

doubled productivity. The original assembly line has a target output of 35

boxes/operator/hour, whereas the actual measured output came up to 29.8

boxes/operator/hour.

Figure 23 Production Rate for Improved Assembly Line

35 29.77

59.7

0

10

20

30

40

50

60

70

Initial Target Measured Improved Line

Box/Operator/Hour

Page 72: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

62

The improved assembly line gives an output of 59.8 boxes/operator/hour, which

is about a 100% increase in operator productivity from the original method. Also, with

this Single Stage Parallel Line, the floor space usage is reduced by half compared to

original method. The material handling requirements as well as the input and output

buffer sizes are also determined for this new assembly line. When having an assembly

line with multiple stations, the impact of having station imbalances on the individual

operator performance is also recognized.

Page 73: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

63

REFERENCES

Aase, G. R., Olson, J. R. and Schniederjans, M. J. 2004 , “U-shaped assembly line

layouts and their impact on labor productivity: An experimental study”, European

Journal of Operational Research, Vol. 156 No. 3, pp. 698-711.

Banks, J., Carson, J. S., Nelson, B. L. and Nicol, D. M. (2000), Discrete-Event System

Simulation, Prentice Hall, Upper Saddle River, NJ.

Bartholdi, J.J. (1993), “Balancing two-sided assembly lines: A case study”, International

Journal of Production Research. Vol.31 No.10, pp. 2447-2461.

Becker C. and Scholl A. (2006), “A survey on problems and methods in generalized

assembly line balancing”, European Journal of Operational Research, Vol. 168

No. 3, pp. 694-715.

Boysen, N., Fliedner, M., and Scholl, A. 2007 , “A classification of assembly line

balancing problems”, European Journal of Operational Research, Vol. 183, pp.

674-693.

Chow, We-Min. (1990), Assembly Line Design: Methodology and Applications, Marcel

Dekker Inc., New York, NY.

Cudney. E. and Elrod. C. (2010 , “Incorporating lean concepts into supply chain

management”, International Journal of Six Sigma and Competitive Advantage,

Vol. 6 Nos. 1-2, pp. 12-30.

Czarnecki, H. and Loyd, N. 200 , “Simulation of lean assembly line for high volume

manufacturing”, Proceedings of the Huntsville Simulation Conference, Available

online at: http://www.scs.org/confernc/hsc/hsc02/hsc/papers/hsc037.pdf.

Page 74: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

64

Drucker, P.F. (1999 , “Knowledge-worker productivity: The biggest challenge”,

California Management Review XLI, Vol. 2, pp. 79-94.

Felhann, K. and Junker, S. 2003 , “Development of new concepts and software tools for

the optimization of manual assembly systems”, Cooperative Institutional Research

Program (CIRP) Annals-Manufacturing Technology, Vol. 52 No. 1, pp. 1-4.

Huang, S.H., Dismukes, J.P., Shi, J., Su, Q., Razzak, M.A., Bodhale, R. and Robinson,

D.E. (2003), “Manufacturing productivity improvement using effectiveness

metrics and simulation analysis”, International Journal of Production Research,

Vol. 41 Issue 3, pp. 513-527.

Kim, Y.K., Song, W.S. and Kim, J.H. 2009 , “A mathematical model and a genetic

algorithm for two-sided assembly line balancing”, Computers & Operations

Research, Vol. 36, pp. 853 – 865.

Maynard, H.B. (2007), Operations Analysis, First Edition, Mc Graw-Hill Book

Company Inc, New York, NY.

Merengo, C., Nava, F. and Pozzetti, A. 999 , “Balancing and sequencing manual

mixed-model assembly lines”, International Journal of Production Research, Vol.

37 No. 12, pp. 2835-2860.

Moberly, L.E. and Wyman, P.F. (1973), “An application of simulation to the comparison

of assembly configurations”, Decision Sciences, Vol. 4 No. 4, pp. 505-516.

Niebel, B. W. (1982), Motion and Time Study, Seventh Edition, Irwin Professional

Publishing, Homewood, IL.

Page 75: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

65

Ortiz, C.A. (2006), Kaizen Assembly: Designing, Constructing, and Managing a Lean

Assembly Line, Taylor and Francis Group, Boca Raton, FL.

Pritchard, R.D. (1995), Productivity Measurement and Improvement: Organizational

Case Studies, Praeger Publishers, New York, NY.

Rachamadugu, R. and Talbot, B. 99 , “Improving the equality of workload

assignments in assembly lines”, International Journal of Production Research,

Vol. 29 No. 3, pp. 619 – 633.

Rekiek, B., Dolgui, A., Delchambre, A. and Bratcu, A. (2002), “State of art optimization

methods for assembly line design”, Annual Reviews in Control, Vol. 26, pp. 163-

174.

Scholl, A. and Becker, C. (2006), “State-of-the-art exact and heuristic solution

procedures for simple assembly line balancing”, European Journal of Operational

Research, Vol. 168 No. 3, pp. 666-693.

Shah, R. and Ward, P.T. (2003), “Lean manufacturing: context, practice bundles, and

performance”, Journal of Operations Management, Vol. 21, pp. 129–149.

Silver, E.A., Pyke, D.F. and Peterson, R. (1998), Inventory Management and Production

Planning and Scheduling, Third Edition, John Wiley & Sons, New York, NY.

Van Zante-de Fokkert, J.I., De Kok, T. G., (1997), “The mixed and multi model line

balancing problem: A comparison”, European Journal of Operational Research,

Vol. 100, pp. 399-412.

Womack, J.P., Jones, D.T. and Roos, D. (1990), The Machine That Changed The World,

Free Press, Simon & Schuster, Inc., New York, NY.

Page 76: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

66

APPENDIX A

Table A. 1 Work Element Sheet with Time Data

Company : ABC Date :

Product code:

Work

Element

Sequence

No.

Work Element

Type of Activity Time

S P A VA NVA Avg. SD

1 Take Master Box

2 Open Master Box

3 Pull packages out from master

box

4 Moves master box aside

5 Take individual package 0.82 0.21

6 Break the seal of approval 3.10 1.91

7 Check the handset model

2.80 1.06

8 Peel original import label 7.82 1.89

9 Open individual package 1.42 0.61

10 Check complete guidebooks

1.91 0.50

11 Take out the user manual with

disk

1.93 0.74

12 Paste label on disk 3.89 1.55

13 Remove the charger from box 3.56 1.88

14 Verify complete accessories 1.87 0.55

15 Take user friendly guide and user 2.44 0.82

Page 77: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

67

policy

16 Place user policy and guide 1.05 0.50

17 Place charger on the package 0.80 0.32

18 Pass to person 2 0.57 0.16

19 Remove the charger 0.69 0.24

20 Remove the user manuals 2.36 1.05

21 Take the handset tray 1.78 0.65

22 Take out the charger box

0.76 0.34

23 Paste the charger label 5.49 2.53

24 Check user policy guide 1.43 0.75

25 Check user friendly kit 1.00 0.82

26 Check the user guide labels 1.29 0.69

27 Take the charger with box and

place at the bottom of package

2.01 0.51

28 Place accessories 1.69 0.45

29 Remove handset from tray and

bag

14.53 44.56

30 Remove handset lid 1.70 0.69

31 Place sim card 2.21 1.52

32 Pass to person 3 0.71 0.39

33 Check the SD card in handset 1.40 0.66

34 Check handset NOM

0.76 0.30

35 Check user manuals and

pamphlets

2.12 0.98

36 Place handset lid back 2.96 1.54

37 Secure handset in its bag 1.87 0.86

Page 78: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

68

38 Place handset on its tray 0.98 0.59

39 Place tray in the package 2.41 0.73

40 close the package 3.10 1.32

41 Paste import label 7.09 1.53

42 Pass to person 4

0.77 0.40

43 Check the import label 0.78 0.21

44 Paste security seal 4.02 1.88

45 Place outer wrapper 6.72 3.44

46 Place the package in master box 1.36 0.43

47 Tape master box

48 Move to storage

Total

Time 107.99 Seconds

Note: Operation description and time data slightly modified from the original data.

Key:

S – Set-up Tasks P – Actual Processing Tasks A – Administrative or System Tasks VA – Value Added Activities NVA – Non-Value Added Activities

Page 79: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

69

Table A. 2 Time Study Data Sheet with Work Elements

1 2 3 4 5 6 7 8 9 10 11 12

1 Take the master box

2 Open master box

3 Pull package out from the master box

4 Move the master box aside

5 Take package 1.33 1.18 0.68 0.87 1.00 0.87 0.87 0.85 0.89 1.01 0.83 1.17 0.96 0.18 0.05

6 Peel original import label 4.24 3.30 3.10 2.68 5.90 2.72 4.62 4.58 4.09 3.97 4.31 2.71 3.85 0.94 0.27

7 Break the seal of approval 1.13 0.65 0.52 0.63 0.86 0.72 0.62 0.61 0.92 1.30 1.22 0.75 0.83 0.25 0.07

8 Open package 1.22 0.67 1.15 0.52 0.74 0.72 0.72 0.94 1.12 1.50 0.69 0.81 0.90 0.28 0.08

9 Remove pamphlets and disc from the box 3.78 1.66 1.83 1.68 1.42 1.26 1.36 1.64 1.74 1.25 1.71 1.08 1.70 0.67 0.19

10 Stick the disc label 2.49 3.31 1.64 1.59 2.40 2.45 2.26 2.40 2.36 1.12 3.73 2.12 2.32 0.68 0.20

11 Verify the manuals 0.95 0.68 0.41 0.70 0.33 1.77 1.38 0.57 0.56 0.56 0.39 0.63 0.74 0.41 0.12

12 Check handset 1.00 0.91 0.59 0.57 1.13 0.68 1.63 0.31 0.43 0.70 0.66 0.64 0.77 0.34 0.10

13 Remove handset tray from package 1.12 1.16 1.14 2.09 0.93 0.79 1.43 1.28 1.13 1.24 1.16 1.30 1.23 0.3 0.09

14 Check complete accessories 1.08 0.68 1.07 1.09 1.30 1.07 0.76 0.90 1.37 1.02 0.88 0.97 1.02 0.19 0.05

15 Check pamphlets 1.70 1.30 0.73 1.17 0.30 0.86 0.76 0.82 0.80 0.74 0.73 0.74 0.89 0.34 0.10

16 Paste label on charger box 3.54 3.62 3.88 6.89 2.92 4.19 3.21 3.43 3.47 3.87 3.69 3.72 3.87 0.96 0.28

17 Check charger 3.91 7.51 4.53 5.14 4.06 5.39 4.11 3.20 5.10 3.27 3.02 3.57 4.40 1.21 0.35

18 Add user policy to the pamphlets 2.27 1.37 1.43 1.45 2.26 1.53 1.80 1.63 1.72 1.54 1.97 2.16 1.76 0.32 0.09

19 Add user guide to pamphlets 0.84 1.48 1.19 2.12 3.23 1.14 1.60 1.56 1.92 1.07 1.17 1.76 1.59 0.61 0.18

20 Remove the Phone from bag 1.91 1.83 1.16 1.23 0.98 1.02 1.24 1.14 0.97 0.85 0.91 1.43 1.22 0.33 0.09

21 Remove the flip 1.04 0.57 0.83 0.94 1.11 1.06 1.12 1.18 0.89 0.90 0.85 0.96 0.95 0.16 0.05

22 Verify the sd card for handset 0.61 0.65 0.30 0.73 0.80 0.59 0.44 0.64 0.76 0.56 0.65 0.74 0.62 0.14 0.04

23 Verify the serial number and logo 2.42 2.11 1.94 1.98 2.89 3.51 2.96 3.11 3.01 2.62 3.00 2.30 2.65 0.48 0.14

24 Place lid back on the phone 1.08 1.27 0.94 1.08 0.70 0.88 1.56 1.91 1.09 1.06 1.80 0.89 1.19 0.36 0.10

25 Save phone in the bag 3.51 2.21 2.06 2.48 2.36 2.89 1.39 3.01 2.01 3.11 2.00 3.32 2.53 0.61 0.18

26 Arrange phone on its tray 0.88 0.59 0.72 0.50 0.66 0.62 0.79 0.81 0.67 0.87 1.00 0.73 0.74 0.13 0.04

27 Return the tray in the box 2.38 1.81 0.71 0.81 0.80 0.87 0.68 0.81 1.13 0.65 1.18 0.91 1.06 0.5 0.14

28 Returning pamphlets to the box 2.63 1.78 2.50 1.52 1.55 1.66 2.28 2.69 1.89 0.88 2.34 2.16 1.99 0.52 0.15

29 Close Individual box 1.90 1.99 1.47 1.28 1.64 1.56 1.81 1.56 1.86 1.37 2.24 1.50 1.68 0.27 0.08

30 Paste import tag 4.92 4.42 5.12 4.42 2.46 3.64 5.95 4.37 3.20 4.07 3.82 3.74 4.18 0.88 0.25

31 Place security seal 1.56 2.00 2.56 1.06 1.67 1.75 2.10 2.75 4.70 2.13 2.21 2.16 2.22 0.86 0.25

32 Place the outer wrapper 5.25 4.32 4.50 4.14 3.90 6.86 4.62 4.08 4.19 3.19 4.31 4.78 4.51 0.85 0.25

33 Place the package in master box 1.56 1.18 1.39 1.62 1.62 1.36 1.41 2.35 1.18 1.23 1.31 1.56 1.48 0.3 0.09

34 Tape the box

35 Move to storage

Total Time (Per one individual apckage) 53.87 seconds

Remarks

Company Name : ABC Date :

Product code:

Work

Element

Sequence

No.

Work Element

Time Samples

Avg

. Tim

e

Std.

Dev

.

Stan

dard

Err

or

Allo

wan

ces

Page 80: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

70

The mean station times follow a Normal Distribution and the loading and unloading

times are estimated to have Triangular Distribution. The distribution is found from the

available data for station times.

Table A. 3 Time Study Data Sheet with Station Times

Figure A. 1 Station Time Distribution

43210-1

12

10

8

6

4

2

0

Fre

qu

en

cy

Avg. time at each workstation (in sec.)Normal

Cycle Time in

Seconds

Avg. Station

Time in

Seconds

Std. Dev.

Stn 1

10.77

11.31 1.52

Stn 2 11.16 1.72

Stn 3 10.97 1.12

Stn 4 8.04 0.96

Stn 5 12.39 1.6

Page 81: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

71

The actual data is not available for loading and unloading times. Hence, it estimated that

these times lie between 3 seconds and 5 seconds. MINITAB Statistical Tool is used to

draw both the distributions.

Figure A. 2 Loading and Unloading Time Distribution

5.04.54.03.53.0

1.0

0.8

0.6

0.4

0.2

0.0

Loading and Unloading Time

De

nsit

y

Distribution PlotTriangular, Lower=3, Mode=4, Upper=5

Page 82: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

72

APPENDIX B

Material Handling Logic

Single Stage Parallel Line Configuration

The dimensions and the layout used for simulation of Single Stage Parallel Line

configuration is given below.

Figure B. 1 Assembly Layout With Dimensions

Page 83: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

73

Figure B. 2 Material Handling Cart Routing Logic

Cart movement logic

Both the carts 1 & 2 pick-up boxes at the pick-up point and go to A.

At A,

• Cart 1 checks for the total number of boxes across buffers in line 1 and

line 4. It then proceeds to the fill the line with less number of boxes .

• Cart 2 directly proceeds to point B.

At B,

• Cart 2 checks for the total number of boxes across buffers in line 5 and

line 8. It then proceeds to the fill the line with less number of boxes.

Page 84: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

74

At C,

• Cart 1 proceeds to fill lines 2 and 3. If empty, goes to the pickup point.

• If cart 2 is empty, it proceeds along line 3 to the pickup point, else goes

to fill lines 6 and 7.

At D,

• If cart 2 is empty it directly goes to pick up point to load boxes, else

goes to fill line 8.

Then, the finished master boxes are moved to bar-coding manually by operators.

Figure B. 3 Improved Assembly Layout

2.90m

0.7+0.8+0.5

4.80 m

12.75 m

14.25 m

1.50 m

2 m

1.40 m

0.5+

0.8

3 m

4.80 m

0.50 m 0.75 m 1.50 m

Material Movement from Tables to Bar Coding

≈7 m ≈ 7 m≈ 4 m≈ 4 m

Line output buffer, 5

master boxes max.

PALLETS

Bar-Coding area

Page 85: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

75

Five-Stage Serial Line Configuration

The material handling for five stage assembly line is broken down into two parts based

on master box supply and finished master box transport to bar-coding area.

Figure B. 4 Material Handling – Supply Side

Carts 1&2 load master boxes at the pickup point and proceed to point A

At point A, cart 1 goes to fill tables numbered from 1 to 6. Cart 2 goes to fill

tables numbered from 7 to 11

Page 86: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

76

After unloading at each table, if the empty carts go to the pickup point to load

master boxes through the path shown in red. Else proceeds to the next table

At point B, if the cart 2 has enough master boxes goes to fill tables 6 to 1, else

goes to the pickup point though the path shown in red

If all the buffers are full, the carts wait at point A

Cart 1 is dedicated to tables numbered 1 to 6 and Cart 2 to tables 6 to 11

Figure B. 5 From Assembly to Bar-Coding

The carts wait until at least one master box is ready at each of the buffers

Page 87: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

77

Cart serves tables , 2 and 3

Cart 2 serves tables 4, 5 and 6

Cart 3 serves tables 7,8,9, 0 and

Cart unloads at bar-coding stations BC , BC2 and in that order. Once

empty goes back along the same path to load boxes at tables ,2 and 3

Cart 2 unloads at bar-coding stations BC4, BC3 and in that order. Once

empty goes back along the same path to load boxes at tables 4,5 and 6

Cart 3 starts at table and proceeds to table 7. If full unloads at the

corresponding bar-coding station. If it has free space, goes to load at next

table and so on.

It is assumed that the empty master box is available at the end of table

Page 88: PRODUCTIVITY IMPROVEMENT OF A MANUAL ASSEMBLY LINEoaktrust.library.tamu.edu/bitstream/handle/1969.1/ETD-TAMU-2011-08... · Assembly line balancing along with the associated operations

78

VITA

Name: Pranavi Yerasi

Address: 87-794 (U/S), Lecturers‟ Colony

Madhavi Nagar, Nandyal Road

Kurnool, Andhra Pradesh 518002

Email Address: [email protected]

Education: M.S. Industrial and Systems Engineering

Texas A&M University, August 2011

B. En. in Mechanical Engineering,

Sri Krishna Devaraya University, June 2006