SAP ERP Manufacturing - ProductionPlanning (SAP PP): Problems related to MRPcreated schedule lines
Posted by Nancy Guo 05-Jan-20151. Schedule lines are not created by MRP, instead planned orders or purchase requisitions are created
1967840 - MRP does not create schedule lines2. Schedule lines are not displayed in MD04
Check the reduced quantity in field EKET-DABMG. If it is equal or larger than the schedule line quantity,the schedule line is not displayed in MD04. If you still don't know why, you may try to debug by setting a breakpoint at form PRUEFEN_MDBS ofprogram SAPLM61X. Refresh MD04 list. The debugger will stop at the breakpoint.
3. Schedule lines are shown as firmed in MD042088322 - Schedule lines are displayed with an asterisk ( * ) in t-code MD04/MS04
4. Vendor is wrongMRP: Vendor is not selected and general problems on source determination
5. Stock transport delivery date is not correct361308 - Stock transf.releases:Scheduling via plnd dely time76301 - Scheduling stock transport order/PReq
6. Multiple / redundant schedule lines are created1745312 - MRP creates redundant proposals though there are fixed future receipts which can cover therequirements.
7. Duplicate / double schedule lines on the same date2108166 - Duplicate schedule lines are created with the same date by MRP