mrp relevance for delivery schedule type testing - sap

12
MRP Relevance for Delivery Schedule Type Testing Contents Schedule Line Categories ......................................................................................................................... 2 A – Requirements according to FDS, deliveries according to validity ........................................................ 2 B – Requirements according to validity, deliveries according to validity ................................................... 4 C – Requirements according to FDS, deliveries according to JDS .............................................................. 6 D – Requirements according to validity, deliveries according to JDS......................................................... 8 E – Not JIT Delivery Schedules ............................................................................................................... 10 There are 5 MRP schedule types provided by SAP standard. The MRP relevance for delivery schedule type can be used to control schedule line category which is relevant for planning and delivery. Here I create some testing data to explain how this field is working.

Upload: others

Post on 21-Nov-2021

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MRP Relevance for Delivery Schedule Type Testing - SAP

MRP Relevance for Delivery Schedule TypeTestingContentsSchedule Line Categories ......................................................................................................................... 2

A – Requirements according to FDS, deliveries according to validity ........................................................ 2

B – Requirements according to validity, deliveries according to validity ................................................... 4

C – Requirements according to FDS, deliveries according to JDS .............................................................. 6

D – Requirements according to validity, deliveries according to JDS ......................................................... 8

E – Not JIT Delivery Schedules ............................................................................................................... 10

There are 5 MRP schedule types provided by SAP standard. The MRP relevance for delivery scheduletype can be used to control schedule line category which is relevant for planning and delivery.

Here I create some testing data to explain how this field is working.

Page 2: MRP Relevance for Delivery Schedule Type Testing - SAP

Schedule Line CategoriesFollowing schedule line categories are generally used by normal business scenario of schedulingagreement (type LZ):

· L1: MRP + Delivery· L2: MRP – No Delivery· BN: No MRP – No Delivery· CN: No MRP + Delivery

A – Requirements according to FDS, deliveries according to validityCreate a sales scheduling agreement with type LZ. Set the MRP relevance to “A” which represents thatFDS is relevant for MRP planning, and delivery will be controlled by validity (JIT horizon). If it is withinthe JIT horizon, the JDS will be considered for delivery creation; if it is out of the JIT horizon, the FDS willbe considered for delivery creation.

Check “Forecast Delivery Schedule” tab for the schedule line category determination

Page 3: MRP Relevance for Delivery Schedule Type Testing - SAP

Within the JIT horizon (26/10/2018), the schedule lines of FDS are not relevant for delivery (L2). Afterthe JIT horizon, the FDS schedule lines are relevant for delivery (L1).

Go to tab “JIT Delivery Schedule” to check the schedule line category determination:

Page 4: MRP Relevance for Delivery Schedule Type Testing - SAP

Out of the JIT horizon, the schedule lines are not relevant for delivery (BN).

B – Requirements according to validity, deliveries according to validityCreate a sales scheduling agreement with type LZ. Set the MRP relevance to “B” which represents thatboth FDS and JDS are relevant for MRP planning and delivery according to validity period setting. If it iswithin the JIT horizon, the JDS will be considered for MRP and delivery creation; if it is out of the JIThorizon, the FDS will be considered for MRP and delivery creation.

Page 5: MRP Relevance for Delivery Schedule Type Testing - SAP

Go to tab “Forecast Delivery Schedule” to check the schedule line category determination:

Schedule line category “BN” represents non-MRP relevant and non-delivery relevant. So within JIThorizon, the whole control is in JDS side. FDS only handles MRP and delivery creation out of JIT horizon.

Go to tab “JIT Delivery Schedule” to check the schedule line category determination:

Page 6: MRP Relevance for Delivery Schedule Type Testing - SAP

Different from the settings on FDS, all schedule lines within the JIT horizon are relevant for MRP anddelivery.

C – Requirements according to FDS, deliveries according to JDSCreate a sales scheduling agreement with type LZ. Set the MRP relevance to “C” which represents thatFDS is only relevant for MRP and JDS is only relevant for delivery. If it is within the JIT horizon, the JDSwill be considered for delivery creation; if it is out of the JIT horizon, the JDS will not be considered fordelivery creation. The FDS is always used for MRP.

Page 7: MRP Relevance for Delivery Schedule Type Testing - SAP

Go to tab “Forecast Delivery Schedule” to check the schedule line category determination:

For all dates (within or without JIT horizon), the schedule lines on FDS are always not relevant fordelivery and only for MRP.

Page 8: MRP Relevance for Delivery Schedule Type Testing - SAP

Go to tab “JIT Delivery Schedule” to check the schedule line category determination on JDS:

Out of the JIT horizon, the schedule lines (BN) are neither relevant for MRP, nor relevant for delivery.

D – Requirements according to validity, deliveries according to JDSCreate a sales scheduling agreement with type LZ. Set the MRP relevance to “D” which represents thatMRP is relevant for delivery, and delivery is always relevant for JDS. If it is within the JIT horizon, the JDSwill be considered for MRP and delivery creation; if it is out of the JIT horizon, FDS is considered for MRPonly. In this setting, no delivery will be created from FDS.

Page 9: MRP Relevance for Delivery Schedule Type Testing - SAP

Go to tab “Forecast Delivery Schedule” to check the schedule line category determination:

Within the JIT horizon, the schedule lines (BN) are neither for MRP nor for delivery. Out of JIT horizon,the schedule lines (L2) of FDS are only relevant for MRP. The delivery is not possible for FDS schedulelines.

Page 10: MRP Relevance for Delivery Schedule Type Testing - SAP

Go to tab “JIT Delivery Schedule” to check the schedule line category determination:

Only within the JIT horizon, the schedule lines (L1) are relevant for MRP and delivery. After the JIThorizon date, schedule lines (BN) on JDS cannot do further things.

E – Not JIT Delivery SchedulesCreate a sales scheduling agreement with type LZ. Set the MRP relevance to “E” which disables the JIT.With this setting, the MRP and delivery is always relevant for FDS, and no JIT can be processed.

Page 11: MRP Relevance for Delivery Schedule Type Testing - SAP

Go to tab “Forecast Delivery Schedule” to check schedule line category determination:

The JIT delivery schedule cannot be maintained at all. For all entries in FDS, the schedule lines arerelevant for MRP and delivery.

Page 12: MRP Relevance for Delivery Schedule Type Testing - SAP