prince mohammad bin fahd university - pmu.edu.sa416c6920416c2d4d... · facilities applying saudi...

18
Prince Mohammad Bin Fahd University College of Engineering Department of Mechanical Engineering Internship Report At Saudi Aramco Company Reporting Period [14/07/2012 - 25/07/2012] Submitted by [Ali Mohammad Al-Marri] [200800905] [submission date (27/07/2012)] Mechanical Engineering Department Summer 2012 2012

Upload: dokhanh

Post on 21-Jul-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

Prin c e Moh ammad Bin Fah d Un iversity C o l l e g e o f E n g i n e e r i n g

Department of Mechanical Engineering

Internship Report

At

Saudi Aramco Company

R e p o r t i n g P e r i o d

[14/07/2012 - 25/07/2012]

S u b m i t t e d b y

[ Al i M o h a m m a d Al - M a r r i ]

[ 2 0 0 8 0 0 9 0 5 ]

[ s u b m i s s i o n d a t e ( 2 7 / 0 7 / 2 0 1 2 ) ]

Mechanical Engineering Department

Summer 2012

2012

1

Summary

I got a chance to have my internship with Saudi Aramco Company which is the national oil company

of Saudi Arabia and the largest oil company in the world. Saudi Aramco has both the largest proven

crude oil reserves, at more than 260 billion barrels and largest daily oil production. Saudi Aramco

owns the Ghawar Field, the world's largest oil field, and the Shayba Field, one of the world's largest

oil fields. Ghawar is an oil field located in AL-Hasa ,Saudi Arabia. Measuring 280 by 30 km, it is by

far the largest conventional oil field in the world. Ghawar is entirely owned and operated by Saudi

Aramco, the nationalized Saudi oil company. Relatively little technical information is publicly

available, because the company and Saudi government closely guard field performance data and per-

field production details. Historically, Ghawar has been subdivided into five production areas, from

north to south: 'Ain Dar and Shedgum, 'Uthmaniyah, Hawiyah and Haradh. The major oasis of AL-

Hasa and villages are located on Ghawar's east flank, corresponding to the 'Uthmaniyah production

area. Ghawar was discovered in 1948 and put on stream in 1951. Some sources claim Ghawar peaked

in 2005, though this is strongly contested by the field operators.

Approximately 60-65% of all Saudi oil produced between 1948 and 2000 came from Ghawar.

Cumulative production until April 2010 has exceeded 65 billion barrels . Currently, Ghawar is

estimated to produce over 5 million barrels of oil a day (6.25% of global production).

Ghawar also produces approximately 2 billion cubic feet of natural gas per day.

2

Figure 1: this figure shows all oil and gas fields handled by Saudi Aramco. As notice the largest one is the GHAWAR Field.

3

Background

I have joined one of the company’s departments which is North Ghawar Producing Department

(NGPD). It consists of five divisions; three operations divisions and two maintenance divisions. I start

working on June16, 2012 with Abqaiq Producing Division (ABPD) in Abqaiq Gas Oil Separation

Plant# 5 (ABGOSP-5) as assistant to Operations Engineer who is assigned to be my Mentor. His

name is Mohammed A, Al-Hadrami. Mohammed got his bachelor degree “Chemical Engineering”

from KFUPM and he joined Saudi Aramco in 2008. He worked with Safaniyah Offshore Producing

Department (2008-2009) as Plant Engineer. Then, he joined Northern Area Technical Support

Department (2009-2010) as a Design Engineer. After that, Mohammed moved to North Ghawar

Producing Department with Engineering Division. Now, he is handling two facilities (GOSPs) plus

Oil Field as an Operations Engineer. Moreover, he is responsible for new hired engineers’

orientations. Mohammed contact mean as follows,

Mail PO Box 45, Abqaiq 31311, Kingdom of Saudi Arabia Mobile +966 55 1158 10

Email [email protected]

As planned, the third two weeks, from July 14 until July 25, 2012, I joined North Ghawar Engineering

Division. This division is under NGPD (North Ghawar Producing Department) and has 4 engineering

units: Plant Engineering (PEU), Technical Support (TSU), Project Coordination (PCU) and Inspection

& Corrosion (ICU). I was assigned with Inspection since it is in charge of inspecting all NGPD

facilities applying Saudi Aramco standards. This unit has three groups (Mechanical, Support,

Corrosion).

In this report I will explain the three groups activities with the inspection procedure and how they are

implementing Aramco standards on their duties.

4

Progress

Mechanical Inspection:

This group is focusing on three fields; Plant equipments, welding and coating.

A) Plant equipments are the most important portion in the GOSP, so to get efficient operating

equipment you need to implement a high-quality inspection standard before using it. Following are

some of the equipments Valves, Pipes, and Drums.

In this report I will concentrate on those equipments that I have observed their inspection.

Pipes:

Figure 1: Pipes

1. Verify the piping layout as installed conforms to the drawings.

2. Verify the weld preparations conform to WPS.

3. Verify the qualifications of all welders (coaters, blasters, other as necessary) on the installation.

4. Verify pre-installation pressure testing of the equipment.

5. Verify the welding consumables ate of the proper type and properly stored.

6. Inspect the internal and external coating.

7. Check for damaged materials and equipment.

8. Verify the preheat treatment of the welds

9. Inspect piping support.

10. Inspect trenching of backfill of ditch, if applicable.

11. Verify post heat treatment of the welds.

5

Valves:

Figure 2: Valve

1. Locate the specific valve on the P&ID.

2. Identify the valve make and type.

3. Obtain a drawing of the valve.

4. Determine the pressure rating which will be on the valve body as part of the casting.

5. Measure the valve for nominal bore size and flange size.

6. Inspect the valve for corrosion/erosion.

7. Witness the body and seat hydro-test, if hydro-test is required.

Coating inspection

Figure3: Coating layers on the pipe

6

Coating is the layer that is applied to a pipe or valve to protect it from corrosion, different types of

coating are used on external and internal surfaces.

The inspector role is to check the application of coating e.g. inspect the surface preparation before

coating, verify the optimal thickness for the coating, verify the proper abrasives and checking the

coating preparation.

- Nondestructive evaluation techniques (NDE)

- Radiography

Radiography is one of the most widely used NDE techniques. Radiation is directed through the

material of interest, and a photographic image is recorded on film.

Radiography can be useful in locating failures and it presents no problems in the subsequent failure

analysis.

Through my assignment I have seen the benefit of this test, the case was that a gate valve was used in

bypass line so the valve was used as throttling valve while it should be an isolation valve, later after a

certain time the valve was found passing, after implementing the radiography test it has shown that

the disk was bend as a result of throttling flow and it can be shown in the following figure:

Figure 4: Gate Valve

- Hydro and pneumatic testing

Hydro test is also one of the commonly used tests it ensure that there is no any leak appear under a

certain pressure, the water will seep through a certain parts in the valve; seat and the whole body of

the pipe. Pneumatic test is more efficient than the hydro test but the pneumatic test has a greater risk

of catastrophic rupture so this test needs the manager approval before implementing it.

7

- Magnetic particle testing

Magnetic particle testing can be used to detect defects at or near a surface of ferromagnetic materials

and its most effective when it’s used to detect small cracks on two steps in the technique are as

follows:

1- Magnetization of the test piece by means of alternating current for surface defects or direct

current for subsurface defects.

2- Application of finely divided magnetic particles in either a dry powder or suspended in a

liquid. The magnetic particles, in forming visible indications, are attracted to the leakage flux

that is created by the magnetic field.

- Ultrasonic testing

Figure 5: Principles of Ultrasonic Testing

The ultrasonic inspection technique uses low energy and high frequency sound waves to measure wall

thickness and to detect defects in materials. Sound waves are beamed into the test material and

reflected from surfaces or discontinuities.

Based on the time for return of the echoes, metal thickness can be determined or defects located,

usually by calibration with reference standards.

Advantages Disadvantages

High Penetrating power Manual operation require careful attention by experience technicians

High sensitivity Extensive technical knowledge is required for

the development of inspection procedure.

No Effects on Equipment and materials Possible interference problems with foreign

structures resistivity

Capable of portable or highly automated

operation

Surface must be prepared by cleaning and

removing loose scale, paint, etc

Table1: Advantages and disadvantages of UT test

8

Through the assignment I have done the ultrasonic test on a pipe and it was easy to operate and it

gives you the thickness in a short time.

- Liquid penetrate testing

Liquid or dye penetrant testing is a relatively simple technique that is used to locate surface defects.

Liquid penetrant spread on the sample seeps into small cracks or defects. After the excess penetrant is

wiped or washed from the surface, a developer, which draws the penetrant to the surface to reveal

small defects, is applied.

Figure 6: General Steps for Water-Washable PT Technique

Advantages Disadvantages

High sensitivity to small surface discontinuities Only surface breaking defects can be detected

Few material limitations Only materials with a relatively nonporous surface can be inspected

Penetrant materials and associated equipment are relatively inexpensive

The inspector must have direct access to the surface being inspected

Aerosol spray cans make penetrant materials very portable

Chemical handling and proper disposal is required

Table 2: Advantages and disadvantages of Liquid penetrate test

9

Support Inspection:

The support inspection can be classified into two groups: Civil and Electric inspection.

Civil inspection:

In this part I will go through the major civil inspection jobs:

A) Excavation:

Figure 7: Excavation job

1- Verify location of excavation is correct.

2- Locate vertical and horizontal control references points(if applicable)

3- Verify excavation work meets safety guidelines: slide sloping, shoring, method of (entry, exit,

safety boundary, markets)

4- Verify work in progress: soil type, soil conditions, elevation control, water table and horizontal

control.

B) Filling:

To inspect the filling you should first verify if the preparation of the site is meeting the requirements

then check if the fill meet the requirements e.g. type, gradation, maximum dry density or relative

density test results.

10

C) Compaction:

Figure 8: Compaction equipment

Verify the grading and proof rolling prior to laying first lift and also checking the lifts if it exceeds the

requirements, in addition make sure that the moisture content and uniform are mixed and distributed,

also the compactor should be checked if its meet the requirements, besides monitoring the compaction

efforts e.g. number and direction of passes and noticeable weak spots.

D) Concrete Placement

During the concrete placement the inspector should verify five things

1- Concrete mix

2- Cleanliness of job site concrete handling equipment

3- Temperature of concrete

4- Slump of concrete

5- Use the proper consolidation method

Also the inspector is supposed to inspect the conveying of concrete and methods to prevent

segregation.

11

Electrical inspection: With the electrical inspection the inspector should stick with the inspection steps in sequence to get

the inspection done safely. In the report I will choose the procedure of the two major equipments

inspection:

A) Inspecting MV oil filled transformer

Figure 9: Transformer

1- Verify that the transformer feeder is tagged and locked out. (High voltage ; gloves and face shield

is needed)

2- Verify that spill and fire containment barriers (dikes, trenches, basins, firewalls, sprinkler system)

are installed where required.

3- Verify the nameplate data.

4- Visually inspect the integrity of the transformers enclosure.

5- Visually inspect the primary and secondary cubicles of transformer.

6- Inspect the primary and secondary cable terminations and verify the torque.

7- Inspect the primary and secondary bushings.

8- Verify the transformer turns ration test results.

9- Verify the megger test results.

10- Verify the dielectric oil test results

11- Verify that all grounds are correct and installed using approved methods.

12- Verify that all inspection reports are filled correctly.

12

B) Inspecting MV motor control center (MCC)

Figure10: Motor control center.

1- Verify that the MCC feeder is tagged and locked out. (High voltage; gloves and face shield is

needed).

2- Verify that all primary, secondary and control power is de-energized.

3- Verify that all component labels are present and correct.

4- Verify the integrity of the MCC housing.

5- Inspect all cable terminations and connections and verify the torque.

6- Inspect the primary and secondary connection points in all breaker compartments.

7- Inspect all compartments for loose parts and tools

8- Verify that the shutters are working correctly.

9- Verify that all racking devices are operating properly.

10- Inspect all bushes and insulators.

11- Inspect all bus connection points and verify the torque.

12- Verify doctor (low resistance test) of all bus joints.

13- Verify that the thermostat and heaters are working correctly.

14- Verify that all grounds are correct (size, type, color) and installed using approved methods.

15- Verify hi-pot test results.

13

Corrosion Inspection: This group can be organized into two teams Cathadoic protection (cp) and corrosion team.

- Cathadoic protection

There are two types of Cathadoic protection:

A) Galvanic protection

Figure 11: Galvanic anodes in a Vessel

Galvanic anode system is applied when the current requirement is low and it uses sacrificial anodes to

generate the required current, the galvanic system usually used in vessels (Zink), water tanks

(Aluminum), and pipes under road and camel crossings (Magnesium).

Advantages Disadvantages

External power source is not required Driving voltage is limited

Installation costs are low Current output is limited

Maintenance cost are low Effective only in low soil resistivity

Table 3: Advantages and disadvantages of Galvanic Protection

B) Impressed current system

Figure 12: Impressed current system

14

This system is required when high current is needed, it uses rectifier to produce the essential current,

and it’s used on well casing and buried pipelines.

It can be installed horizontal or vertical depending on the conductivity of the soil.

Coke grease is added to the system to increase the flow of the current.

Advantages Disadvantages

High driving voltages High equipment and installation costs

High current outputs High maintenance costs

Adjustable current output low Possible interference problems with

foreign structures resistivity

Table 4: Advantages and disadvantages of impressed current system

- Corrosion group

The main objective of this group is to evaluate the failure cases which occurred, and give

recommendation based on their evaluation. They can evaluate by analyzing the data which they

obtained from the monitoring systems and coupons. Also this group is responsible of the type of

coatings and the material selection.

Through the assignment I have learned that most of the corrosion cases were due to old piping design.

The pipes were designed based on the previous flow rates, so this proves that the velocity of the flow

is an important factor in corrosion occurrences.

That is why the new technologies are required to reduce the corrosion, since the idea of changing the

design to the current flow will cost a lot.

Following is the group techniques to reduce the corrosion:

• Chemical inhibitor

Corrosion inhibitor is injected in three locations; production header, before entering the gas fin fan

and wash water. It’s injected to be mixed with water to form a layer on the pipe to protect it from

corrosion, the corrosion engineer is responsible to calculate and give the exact dosage rate to the

operation. In the oil side the inhibitor rate is depending on the water cut while in the gas side it’s

depending on the flow rate.

15

• Squeezing wells

Corrosion and scale inhibitor are injected to the oil well by a pump and the well should shut in for 48

hours to allow the inhibitor to precipitate on the formation.

• Scraping

The Scraper is used for scales in pipelines that cannot be removed by acid or other chemicals and it’s

applied one in a year. The following figure shows the types of scrapers:

Figure13: Types of scraper

References

1. Saudi Aramco Engineering Standards

2. Engineering Encyclopedia

3. http://www.sievert.in/ndt.html

16

Plans In this report I have explained the different fields of inspection unit and their major activities.

One of the best things that I have learned in this assignment was being familiar with the Saudi

Aramco Engineering Standards and Engineering encyclopedia, and I have used them in my existing

report.

The most interesting thing in the assignment was that how they are implementing the engineering

standards on their daily activities, and if there was any issue will conflict the standards it will be

rejected even if it’s urgent, this indicates how Saudi Aramco pay attention to the safety factor.

During the assignment I have been introduced to I-plant, and I have familiarized myself with it and

used it to search for pipes drawings.

The next assignment will be with Production Engineering Division as advised by Mentor.

17