Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez, Lead Inspector March 2, 2011

Upload: timothy-anthony

Post on 17-Jan-2016

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

Presented to:

By:

Date:

Federal AviationAdministrationConstruction Safety

Phasing Plans and Part 139

Airports Conference – Hershey, PA

Evelyn Martinez, Lead Inspector

March 2, 2011

Page 2: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

2Federal AviationAdministration

Eastern Region Airports Conference March 2, 2011

2

ObjectiveTo Ensure Compliance with 14 CFR Part 139

Page 3: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

3Federal AviationAdministration

Eastern Region Airports Conference March 2, 2011

3

FAA Review Process

Airport SponsorAirport Sponsor

Project Manager ReviewProject Manager Review

AEA-620 AEA-620 ReviewReview

(Part 139 (Part 139 Inspector)Inspector)

Line of Line of Business Business ReviewReview

Project Manager Final Project Manager Final ReviewReview

FAA Objectio

n

Complete/

Acceptable

7460 process

FAA Respons

e

Notice to

Proceed

Issued

Page 4: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

4Federal AviationAdministration

Eastern Region Airports Conference March 2, 2011

4

Why is a Construction Safety Plan required?

The Construction Safety Plan is written to meet the requirements of:

• A/C 150/5370-2E, Operational Safety on Airports during Construction.

• FAR Part 139, §139.341, Identifying, Marking, and Lighting Construction and Unserviceable Areas.

Page 5: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

5Federal AviationAdministration

Eastern Region Airports Conference March 2, 2011

5

Who needs a Construction Safety Plan?

Per AC 150/5370-2e:• Airports certificated under 14 CFR Part 139

• Airports using AIP grant funds; and

• Airport projects using Passenger Facility Charge (PFC) program

Page 6: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

6Federal AviationAdministration

Eastern Region Airports Conference March 2, 2011

6

Construction Safety Phasing Plans and Part 139

Key Point

The primary focus of the Construction

Safety Plan is Airport Operations,

not the construction itself.

Page 7: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

7Federal AviationAdministration

Eastern Region Airports Conference March 2, 2011

7

What is a Construction Safety Plan?

A Construction Safety Plan is NOT:

• An OSHA Safety Plan (29 CFR 1926)

• The Project Plans and Specifications

• Description of proposed or finished work (i.e. Sign & Marking Plan)

Page 8: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

8Federal AviationAdministration

Eastern Region Airports Conference March 2, 2011

8

Construction Safety Phasing Plans and Part 139

• Inspectors may participate in Pre-design/Pre-construction Conferences when a construction project is complex or there is significant work that might impact compliance with Part 139.

• Inspectors review submitted CSPPs during project design phase.

• Final Inspection of Completed Projects. – Upon completion of a construction project involving complex or

significant work, the Inspector, may accompany the FAA project engineer/manager to assure compliance with Part 139 requirements.

Page 9: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

9Federal AviationAdministration

Eastern Region Airports Conference March 2, 2011

9

Construction Safety Phasing Plans and Part 139

• Surveillance Inspections– announced or unannounced conducted in addition to

the periodic inspection.• monitoring airfield safety during construction activity

Page 10: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

10Federal AviationAdministration

Eastern Region Airports Conference March 2, 2011

10

Construction Safety Phasing Plans and Part 139

139.309, Safety Areas • Occasionally, FAA contract construction crews have

compromised the integrity of the runway/taxiway safety areas by creating ruts or leaving construction equipment or material there.

• Airport must notify the FAA local Technical Operations Office to repair the damage.

Page 11: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

11Federal AviationAdministration

Eastern Region Airports Conference March 2, 2011

11

Construction Safety Phasing Plans and Part 139

139.311, Marking, signs, and lighting• Ensure that temporary marking and lighting of areas

servicing air carrier aircraft meet standards required by Section 139.311.

• Reminder: Reference 150/5210-22, Airport Certification Manual – Submit signage and marking changes to Dennis O’Donnell no

later than the 90% design stage and prior to bidding of project

Page 12: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

12Federal AviationAdministration

Eastern Region Airports Conference March 2, 2011

12

Construction Safety Phasing Plans and Part 139

139.333, Protections of NAVAIDs

• Procedures must be established to prevent the construction of facilities on the airport that would derogate the operation of both electronic and visual NAVAIDs or the air traffic control facilities on the airport. Coordinate with FAA Tech Ops.

• Such procedures are intended to prevent activities associated with construction and/or maintenance from shutting down, interrupting, or altering NAVAID signals.

– CSPP should address vehicle parking location, equipment and material storage locations near NAVAIDs.

Page 13: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

13Federal AviationAdministration

Eastern Region Airports Conference March 2, 2011

13

Construction Safety Phasing Plans and Part 139

139.329 Pedestrians and ground vehicles

AC 150/5210-20, Change 1, Ground Vehicle Operations on Airports

• Page 3, para 8 states in part that the airport operator should give special consideration to training temporary operators, such as construction workers, even if escort service is being provided.

• Page 4, para 11 provides guidance for non-routine operations such as airside construction and states that planning meetings associated with such activities offer an opportunity to revise driving rules and regulation, communications and procedures, and air traffic control procedures as well as other important operations issues.

Page 14: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

14Federal AviationAdministration

Eastern Region Airports Conference March 2, 2011

14

Construction Safety Phasing Plans and Part 139

139.329 Pedestrians and ground vehicles cont’d

AC 150/5370-2E

• Page 3, para 2-2 l. includes vehicle identification to help track the number of vehicles at a construction site during any time.

• Page 5, para 2-4 includes vehicle and pedestrian access routes for airport construction projects must be controlled to prevent inadvertent or unauthorized entry of persons, vehicles, or animals onto the AOA. This includes aircraft movement and non-movement areas.

• The airport operator should develop and coordinate a construction vehicle plan with airport tenants, contractors, and the ATCT. The safety plan should include specific vehicle and pedestrian requirements.

– Ground Vehicle Operations Training Manual (approved in ACM)

Page 15: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

15Federal AviationAdministration

Eastern Region Airports Conference March 2, 2011

15

Construction Safety Phasing Plans and Part 139

139.341, Identifying, Marking, and Reporting Construction and Other Unserviceable Areas

• The certificate holder is responsible for establishing procedures, such as the review of plans, to protect utilities, cables, wires, pipelines, and other underground facilities prior to construction activities. Must follow AC 150/5370-2, Operational Safety on Airports During Construction.

• Mark and, if appropriate light in a manner authorized (AC guidance):– Each construction area and unserviceable area that is on or adjacent to any

movement area or any other area of the airport on which air carrier aircraft operate.

– Each item of construction equipment and each construction roadway that might affect the safe movement of aircraft on the airport.

– Any area adjacent to a NAVAID that, if traversed, could cause derogation of the signal or failure of the NAVAID.

– The certificate holder must have procedures in place to repair any damage that occurs to an existing utility.

Page 16: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

16Federal AviationAdministration

Eastern Region Airports Conference March 2, 2011

16

Construction Safety Phasing Plans and Part 139

139.341, Identifying, Marking, and Reporting Construction and Other Unserviceable Areas cont’d

AC 150/5370-2E• Page 1, para 1-2 b.(6) the restriction of construction vehicles to

construction areas by flagging and barricading, erecting temporary fencing, or providing escorts, as appropriate.

Page 17: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

17Federal AviationAdministration

Eastern Region Airports Conference March 2, 2011

17

Construction Safety Phasing Plans and Part 139

• 139.321 Handling and storing of hazardous substances and materials (HAZMAT)

• 139.325 Airport Emergency Plan (routes)• 139.327 Self-Inspection program (daily)• 139.337 Wildlife hazard management

(attractants)• 139.339 Airport Condition Reporting

(NOTAMs)

Page 18: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

18Federal AviationAdministration

Eastern Region Airports Conference March 2, 2011

18

Page 19: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

19Federal AviationAdministration

Eastern Region Airports Conference March 2, 2011

19

Construction Safety PlanNarrative

•Very beginning…project description.

•Each narrative section should, to the extent practical, focus on the specific subject exclusively.

•Be specific.

•Reference related sections, by section number and name, as required.

•Reference attachments as required.

•Avoid duplicate responses.

Page 20: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

20Federal AviationAdministration

Eastern Region Airports Conference March 2, 2011

20

Responsibilities

Everyone Plays a Part!

• Airport Sponsor• Contractors• Tenants• FAA

Page 21: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

21Federal AviationAdministration

Eastern Region Airports Conference March 2, 2011

21

Construction Safety PlanReference Attachments

•All material referenced in the narrative MUST be attached to the Construction Safety Plan.

•Excerpts from Advisory Circulars or other publications may be attached.

•Avoid attaching entire Advisory Circulars or other unrelated published material.

•Graphics such as diagrams, photographs, sketches, or drawings should be included.

Page 22: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

22Federal AviationAdministration

Eastern Region Airports Conference March 2, 2011

22

Construction Safety PlanReference Attachments

•Drawings specific to Operational Safety during Drawings specific to Operational Safety during construction – by phase – construction – by phase –

Page 23: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

23Federal AviationAdministration

Eastern Region Airports Conference March 2, 2011

23

Construction Safety Phasing Plans and Part 139

During Movement area Inspection FAA Inspector will confirm:

If construction activity is in progress:– Check for adherence to the CSPP – Identify any potentially hazardous condition to runway/taxiway safety posed by

excavations, trenches, or stockpiled material– Verify there is adequate marking and lighting of the construction area– Verify correct marking and lighting of temporary thresholds– Verify the placement of construction equipment away from the movement area

Observe ground vehicle operations for the following:– Limited access to movement and safety areas to only those vehicles necessary

for airport operations– Appropriate and correct procedures and communications, adherence to

pilot/controller phraseology, and driver understanding of Air Traffic Control conventions

– Properly marked vehicles

Page 24: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

24Federal AviationAdministration

Eastern Region Airports Conference March 2, 2011

24

Construction Safety PlanGuidance/Reference Material

Advisory Circulars:• 150/5370-2E Operational Safety on Airports During

Construction• 150/5200-28 NOTAMS for Airport Operators• 150/5210-20 Ground Vehicle Operations on Airports• 150/5300-13 Airport Design• 150/5340-1 Standards for Airport Markings• 150/5340-18 Standards for Airport Sign Systems• 150/5340-30 Design and Installation Details for

Airport Visual Aids

Page 25: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

25Federal AviationAdministration

Eastern Region Airports Conference March 2, 2011

http://www.faa.gov/airports/eastern/airport_safety/cert_bulletins

25

Page 26: Presented to: By: Date: Federal Aviation Administration Construction Safety Phasing Plans and Part 139 Airports Conference – Hershey, PA Evelyn Martinez,

26Federal AviationAdministration

Eastern Region Airports Conference March 2, 2011

Questions?

26