presentation to the select committee on economic development update on lpg issues 02 november 2011

19
PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC DEVELOPMENT UPDATE ON LPG ISSUES 02 November 2011 1

Upload: yelena

Post on 09-Jan-2016

24 views

Category:

Documents


0 download

DESCRIPTION

PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC DEVELOPMENT UPDATE ON LPG ISSUES 02 November 2011. PRESENTATION OUTLINE. Supply / Demand Situation Retail Price Regulation; Update on the Pilot Projects; LPG Strategy; and Way Forward. DEMAND / SALES ISSUES. Monthly demand varies - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC DEVELOPMENT UPDATE ON LPG ISSUES 02 November 2011

PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC

DEVELOPMENTUPDATE ON LPG ISSUES

02 November 2011

1

Page 2: PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC DEVELOPMENT UPDATE ON LPG ISSUES 02 November 2011

PRESENTATION OUTLINE• Supply / Demand Situation

• Retail Price Regulation;

• Update on the Pilot Projects;

• LPG Strategy; and

• Way Forward

2

Page 3: PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC DEVELOPMENT UPDATE ON LPG ISSUES 02 November 2011

DEMAND / SALES ISSUES• Monthly demand varies

o Unplanned shutdowns

o Limited imports

• Demand sectors

o manufacturing

o hospitality industries (including restaurants)

o households

• Licensing

o Difficult to monitor and enforce compliance with safety standards because LPG retailers are not licensed

3

Page 4: PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC DEVELOPMENT UPDATE ON LPG ISSUES 02 November 2011

LPG SUPPLY• Six Refineries

o Sapref in Durban

o Sasol’s synfuels (CTL) facility in Secunda

o PetroSA’s synfuels (GTL) facility Mossel Bay

o Natref in Sasolburg

o Enref in Durban

o Chevref in Cape Town

• Imports

o Durban

o Port Elizabeth

o Richards Bay

4

Page 5: PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC DEVELOPMENT UPDATE ON LPG ISSUES 02 November 2011

LPG IMPORTS• Normal ship load: 2,500 tons

• Afrox may import via Richards Bayo Facility leased by Afrox from Island View Storage

o Working capacity: 3,500 tons

o About 200 tons per day throughput – investigating rail option to increase throughput

• Easigas imports via Port Elizabetho Owned by Shell

o Maximum holding capacity: 1,600 tons (2 spheres of 800 tons each)

• Imports via Durban through Sapref facilitieso Owned by SAPREF

o Maximum holding capacity: 1,000 tons (2 spheres of 500 tons each; there are other spheres in the refinery but store gases)

5

Page 6: PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC DEVELOPMENT UPDATE ON LPG ISSUES 02 November 2011

LPG IMPORTS (contd.)• East London facility now mothballedo BP-owned

• Saldanha Bay: ship-to-road operation?o Safety and operational concerns

o NERSA has already awarded a licence for an import facility in Saldanha Bay

o Alignment among players is key: particularly DoE, Transnet and NERSA

• NOTEo Inadequate import facilities

o Throughput challenges with existing infrastructure

o Seasonality – Northern hemisphere winters versus southern hemisphere summers and vice versa

o RSA summer shortages coincide with high European winter demand - cargoes destined for Europe

6

Page 7: PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC DEVELOPMENT UPDATE ON LPG ISSUES 02 November 2011

LPG SUPPLY SHORTAGES• Occur every winter due to high demand

• Planned (scheduled) and unplanned shutdownso Refinery shutdowns, currently:

o PetroSA - on an unplanned shutdown: back mid-Nov.

o ENREF - on a scheduled maintenance shutdown which was brought forward due to a fire accident on the plant.

o SAPREF - shutdown again (for 14 days) due to technical problems with the cracker unit: operating at~50% LPG production rate at best

• Frequent unplanned shutdowns – o Infrastructure integrity (old RSA refineries and demand that has outstripped

domestic supply).

o Need for investment in refining infrastructure and maintenance thereof

o Failure to bring units back on line as planned

o Accidents and equipment failures result in:o Unplanned shutdowns depending on how critical to the process the involved equipment is

o Delayed start-ups or drawn forward shutdowns

o Unusual Spring / Summer shortages

7

Page 8: PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC DEVELOPMENT UPDATE ON LPG ISSUES 02 November 2011

LPG SUPPLY SHORTAGES• Importation of LPG is the primary solution o Possible demand growth will not be met by domestic supply

o Maximum Refinery Gate Price (MRGP Review)

o Investment in additional LPG import facilities

8

Page 9: PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC DEVELOPMENT UPDATE ON LPG ISSUES 02 November 2011

LPG SUPPLY MANAGEMENT

• Submission of shutdown schedules by the oil companieso Per refinery and consolidated to get industry picture

o Updated on a monthly basis

o Contingency plans: challenge of executing according to plan

• Regular supply meetings o Chaired by DoE mainly comprising SAPIA members and Transnet

o Conditional exemption of industry by Competition Commission

o Individual company submissions and consolidation thereof

o Joint meetings between Department and industry

o Focus on product type as per need – interconnectedness of product types

o Regular LPT Meetings feeding into top level meetings

9

Page 10: PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC DEVELOPMENT UPDATE ON LPG ISSUES 02 November 2011

CHALLENGES

• Lack of sanctions to those who fail to supply other than the normal financial losses due to lost sales and associated losseso Probability of a non-supplying company negotiating hard with other for own optimal

financial situation at the expense of the overall product supply to the market.

o Contingency plans: challenge of executing them as planned

o Exploring possibility of imposing sanctions through revision of licensing conditions

• Frequent unplanned shutdowns – o Aggravates the situation when coinciding with other shutdown(s)

o Low refining margins?

o LPG not main product?

10

Page 11: PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC DEVELOPMENT UPDATE ON LPG ISSUES 02 November 2011

CHALLENGES (contd.)

• Demand / supply imbalance o Unenviable position of Government: coaxing the oil companies to do what they are

supposed to do

o Difficulty of managing imports: delays due to inclement weather; congestions / scheduling at the port – high demurrage costs and supply shortages; inadequate import facilities

o Investment in domestic refining capacity as well as additional port facilities

11

Page 12: PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC DEVELOPMENT UPDATE ON LPG ISSUES 02 November 2011

CURRENT LPG SUPPLY SITUATION• Planned (scheduled) and unplanned refinery shutdownso PetroSA - on an unplanned shutdown: back mid-Nov.

o ENREF - on a scheduled maintenance shutdown.

o SAPREF - shutdown again (for 14 days) due to technical problems with the cracker unit: operating at ~50% LPG production rate at best

• LPG Importso AFROX: Imported 7 kt, of which 3.5kt arrived last Wednesday and the balance is

due 20-30 November 2011

o EASIGAS: Imported 5 kt, of which 2.5kt arrived last Friday and the balance is expected this week

o Challenge: European winter demand & lack of adequate import facilities

• Department-led coordinated responseo Individual oil company contingency plans

o Regular LPT meetings

12

Page 13: PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC DEVELOPMENT UPDATE ON LPG ISSUES 02 November 2011

MAXIMUM REFINERY GATE PRICE (MRGP)• LPG Maximum Refinery Gate Price (MRGP) is based on 93 octane

movements within the Basic Fuels Price (BFP) mechanism whereas

the import price of LPG is based on Saudi prices

• A review of the MRGP and the Working Rules governing the retail

price of LPG in the DoE’s 2011/12 Strategic Plano Provides firm basis to progressively look at the whole LPG value chain

o Terms of reference formulated and research on international prices and pricing mechanisms done

o LPG stakeholder workshop organized for the 10-Nov-11 for gathering inputs from stakeholders: will lead to proposed review of the MRGP and the Working Rules

o Verification of allegations of losses in respect of importation (and local manufacturing) of LPG

o Revised MRGP and Working Rules will be promulgated before the end of the 2011/12 fiscal year

o Encouraging new investments in the LPG sector

o Subscription to relevant information sources and continuous monitoring

13

Page 14: PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC DEVELOPMENT UPDATE ON LPG ISSUES 02 November 2011

TRANSFORMATION OF THE LPG INDUSTRY

• Two-fold but interrelated:

o Structurally – the value chain

o Participants – broad-based economic empowerment of Blacks / HDSAs (historically disadvantaged South Africans) in the sector

14

Page 15: PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC DEVELOPMENT UPDATE ON LPG ISSUES 02 November 2011

LPG STRATEGYOBJECTIVES:

• The LPG Expansion Strategy aims to provide access to safer, cleaner, efficient, portable, environmentally benign and affordable thermal fuel for all households nationally

• Switch low income households from the use of coal, paraffin and biomass to LPG as the thermal fuel

• Contribute to demand side management by minimizing the use of electricity on cooking and space heating; investing a fraction of the cost of a power plant in LPG switching cost could lead to a delay in the investment in new power plants;

• Enhance the level and quality of energy services currently available to residential users throughout South Africa; and

• Contribute to the Government’s green economy programme aimed at reducing greenhouse gas emissions

15

Page 16: PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC DEVELOPMENT UPDATE ON LPG ISSUES 02 November 2011

STRATEGIC INTERVENTIONS• Development of supply infrastructure

o The construction of the open access import infrastructure is of paramount importance. This would have to be supported by the construction of storage facilities.

• Licensing Regime

o This would have to be used to regulate prices and the enforcement of safety

• Combating uncompetitive behaviour

o Hoarding of cylinders is uncompetitive. The Department would encourage all service providers to report such behaviour to the Competition Commission.

o Vertical integration of the LPG supply chain: Manufactures of LPG being wholesalers & retailers at the same time - total control of the supply value chain.

16

Page 17: PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC DEVELOPMENT UPDATE ON LPG ISSUES 02 November 2011

STRATEGIC INTERVENTIONS (contd.)• Local production of cylinders

o The expansion of the LPG market will in the medium to long term necessitate the investment in the local cylinder manufacturing plant(s); this will create sustainable jobs for South Africans.

17

Page 18: PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC DEVELOPMENT UPDATE ON LPG ISSUES 02 November 2011

WAY FORWARD

• Conclusion of MRGP Review

• Conclusion of the Development of the Strategy

o Contextualize and fit the pieces of puzzle together

o Policy cohesion

o Infrastructure development

• Working closely with the LPG Industry stakeholders to address supply challenges

o Including Transnet SOC Ltd (TNPA in particular for infrastructure)

o Explore possible interventions

18

Page 19: PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC DEVELOPMENT UPDATE ON LPG ISSUES 02 November 2011

Ke ya lebogaKe ya leboga Thank youThank you

Ke a lebohaKe a leboha

Ke a lebogKe a lebogNgiyabongaNgiyabonga

NdiyabulelaNdiyabulelaNgiyathokozaNgiyathokoza

InkomuInkomu

Ndi khou livhuwaNdi khou livhuwaDankieDankie

19