Page 1: PRESENTATION ON WATER SERVICES BACKLOGS

PRESENTATION ON WATER SERVICES BACKLOGS

Municipal Manager4 May 2007

Page 2: PRESENTATION ON WATER SERVICES BACKLOGS

2

Outline Background Locality Map Backlog Figures Budget Requirements Bucket Eradication Projects Funding Required For Buckets Challenges

Page 3: PRESENTATION ON WATER SERVICES BACKLOGS

3

Page 4: PRESENTATION ON WATER SERVICES BACKLOGS

4

Background

– 8 municipalities in 37 294 km2 – Population = 810 214 = 12.4% of Provincial population– 3rd Largest DM in the EC– Mostly rural and youthful

Page 5: PRESENTATION ON WATER SERVICES BACKLOGS

5

Backlog FiguresLocalMunicipality:

Total Population WaterBacklog (R)

Sanitation Backlog (R)

Total

Emalahleni LM 116,945 46,383,437 55,314,923 101,698,360

Inkwanca LM 20,489 490,904 21,845,355 22,336,259

Intsika Yethu LM 196,816 87,727,856 102,191,773 189,919,629

Inxuba Yethemba LM 61,058 4,123,644 10,678,517 14,802,161

Lukhanji LM 194,144 66,569,326 50,972,858 117,542,184

Ngcobo LM 150,597 284,561,192 102,608,463 387,169,655

Sakhisizwe LM 54,665 10,288,601 13,769,867 24,058,468

Tsolwana LM 32,977 19,976,426 31,830,559 51,806,985

Chris Hani DM 810,214 R 520,121,386 R 389,212,315 909,333,701

Page 6: PRESENTATION ON WATER SERVICES BACKLOGS

6

Budget Requirements Service 2007/8 2008/9 2009/10 2010/11

Water 260,060,693 260,060,693

Sanitation 97,303,078 97,303,078 97,303,078 97,303,078

TotalMTEF (BILL)

357,363,772

207,000,419

357,363,772

161,918,181

97,303,078

189,186,000

97,303,078

Page 7: PRESENTATION ON WATER SERVICES BACKLOGS

7

Bucket Eradication Projects 6976 Buckets in total 1120 Buckets already eradicated

(06/07) 5856 Buckets still to be eradicated 11 Projects for buckets 3 projects completed 5 projects under construction 3 projects at planning stage

Page 8: PRESENTATION ON WATER SERVICES BACKLOGS

8

Bucket Eradication

Page 9: PRESENTATION ON WATER SERVICES BACKLOGS

9

Funding Required For Buckets Total required for buckets

R150m. Funds already available R77m.

[MIG (R45m), DHLGTA (R12m), Equitable Share R10m and DBSA Loan R10m]

Funds still required R73m

Page 10: PRESENTATION ON WATER SERVICES BACKLOGS

10

Challenges More funding required to meet water and sanitation backlogs Figures do not include dilapidated infrastructure and bulk for

augmentation especially Karoo towns Creating a balance between basic infrastructure and LED High costs per capita due to scattered villages Sustainability of VIPs Communities want water borne to replace buckets If R73m is ring-fenced from R207million then committed

projects would be delayed and costly Non-performing service providers Few contractors with high ratings with respect to CIDB Retention of skilled personnel (engineers) Implementation of the Supply Chain Management

Regulations

Page 11: PRESENTATION ON WATER SERVICES BACKLOGS

11

THE END