presentation on over view of indian transmission grid
TRANSCRIPT
Presentation on Over view of Indian
Transmission Grid
TOPICS
» Generation, Transmission and Distribution utilities
» Indian Power Scenario
» Long Range Transmission Plans (Development of National
Grid)
» Load Dispatch Centers
Indian Power Sector – Generation, Transmission and Distribution Utilities
• Electricity is a concurrent subject, i.e Development and Management of this sector by both Central and state Governments
• Central Sector Generating utilities- NTPC, NHPC, NLC, NEEPCO, THDC , NPCIL & NJPC
Transmission Utility – POWERGRID, wheels power of Central generating utilities and inter state Mega IPPS
• State sector • Mostly Vertically integrated. i.e Responsible for Generation, Transmission and
Distribution of power within the state
• Reform process are underway and many SEB’s have been divided into three different corporations viz., GENCO, TRANSCO and DISCO
• There are few private distribution agencies as bulk licensee namely CESC, BSES, Tata Power, AECO etc.
• Three levels for Grid management system adopted, namely, National ( to be evolved) Regional and state-
• Implementation and Operation of National and Regional LD&C and their modernization are the responsibility of the Central Transmission Utility (CTU) I.e POWERGRID
• State LD&C is under the State transmission Utility(STU)
Power Scenario – at a Glance• Indian Power System is being operated as five Electrical regions
– Northern, Southern, Western, Eastern and North=Eastern Region.
• Installed capacity - 1,08,000 MW Coal – 71%
Hydro – 25% Nuclear & others – 4%
• Peak demand
Peak power - 81,555 MW
Energy (average) - 1430 MU/day
• Availability
Peak power - 71,260 MW
Energy (average) - 1325 MU/day
• Shortage Peak power - 10,300 MW (12.6%)
Energy - 107 MU/day (7.5%)
Inter Regional Links - Existing
• All the five regions are inter connected through inter regional links.
• Inter Regional links– ER and SR: 500 MW HVDC back to back at Gazuwaka
– NR and WR : 500 MW HVDC back to back at Vindhyachal
– WR and SR : 1000 MW HVDc back to back at Chandrapur.
– ER and NR : 500 MW HVDC back to back at Sasaram( to be commissioned shortly)
– ER and WR : Rourkela – Raipur 400 kV Ac link ( to be commissioned shortly)
– ER and NER : Malda- Bongaigaon Synchronous link
• Cumulative Inter Regional Power transfer Capacity– 4850 MW
Figs. are in ckt. km
State Central Total (POWERGRID)
HVDC 1,504 1,632 3,136
800 KV 400 550 950
400 kV 13,000 32,500 45,500
220/132 kV 2,06,000 9000 2,15,000
Indian Transmission System – PresentIndian Transmission System – Present
• Incorporated in 1989 and started operation on management basis w.e.f. August, 1991
• Notified as Central Transmission Utility (CTU) in December 1998 to discharge following functions
Undertake Inter-state Transmission of energy Planning and co-ordination Exercise Supervision and Control of Inter-state Transmission
including operation of RLDCs Direction, control & supervision of the functions (construction
maintenance & operation) of Transmission Licensees
POWERGRID - THE TRANSMISSION ORGANIZATION
GROWTH PROFILE
1992-93 2001-02 Growth (%) Physical Physical ((Provisional)• No. of S/s 39 68 74• MVA capacity 13,200 34,288 160• Circuit kms 23,000 45,545 76• Inter-regional 500 4,700 840
transfer capacity(MW)• Export of Surplus 0 8,700 -
Power from ER (MUs)
Financial (Rs crs.)Financial (Rs crs.)• Net profit 236 760 222• Turnover 634 2,860 351
• Operating world’s largest transmission network and maintaining availability of more than 98%.
• About 40% of the total power generated in the country wheeled through its network
• Rated “EXCELLENT” under MOU with MOP since 1993-94 • Only PSU in the power sector to receive “The Prime Minister’s MOU
Award” for four consecutive years i.e., for the years 1997-98 to 2000-01
• Honoured with Prime Minister’s Shramvir Award
PERFORMANCE OF POWERGRID
Demand - Supply Scenario – by 2012
• Projected Peak Demand - 157,000 MW • Capacity addition envisaged –
In 10th Plan - 45,000 MW In 11th Plan - 55,000 MW
(Approx. 10000 MW Capacity Addition per Year)
• Major Resources for Capacity Addition Hydro potential in J&K, HP & NER Coal potential in Bihar, Orissa
• Major Load Center – Bulk power need to be transferred from ER/NER to other
deficit regions
Long Range Transmission Plan
• Uneven disposition of energy resources Major Hydro resources in NER & NR Coal reserves mostly in Bihar/Orissa/West Bengal
Cost of power transmission (1.11 cents/kwh) lower than cost of fuel transportation (3.33 cents/kwh).
• Some Regions are no longer Self-sufficient
Major resources in SR exhausted In NR, mainly hydro resources having long gestation period
• Unbalanced Growth of different Regions
Some regions are surplus and some are deficit.
• Optimisation of generation capacity addition Utilising time diversity Spinning reserve optimisation
Development of National Grid
Major Considerations
• Development in a phased manner – commensurate with generation/ load
growth
• Conservation of Right-of-Way - especially in areas with scarcity of ROW
---- viz. area near hydro, chicken-neck area, forest area, town etc.
• Minimisation of transmission cost - immediate as well as long-term basis.
• Flexible enough to accommodate change in load-generation pattern.
Development of National Grid – Technological options
• 400kV AC– Expertise available.
– Transfer capacity can be increased by –Application of latest technology viz FACTS --- also improves
voltage regulation Increasing maximum conductor temperature from 75°C to 95°C ---
increases thermal capacity by 1.5 times.Application of more number of conductors in a phase.
• 765kV AC – Can carry power of the order of 2500 MW -- 4 to 5 times of 400kV
– Relatively less T&D loss – Effectively less Right-of-Way required.
•Limitations:
–Less world-wide market
–Reactive power management difficult.
Development of National Grid – Technological options
• HVDC – HVDC bipole suitable for point-to-point long distance bulk power
transmission.
– So far HVDC bipole upto 3000 MW has been established.
– Provide better flexibility/ controllability in the system.
Limitations: Economical only for long distance (1000 km or more) No tapping feasible in-between (multi-terminal HVDC is a solution
--- due to high cost, justified only in specific cases)
On techno-economic reasons, Hybrid System (combination of HVDC & 765/400kV AC lines)
has been adopted for development of National Grid.
Plan for National Grid PHASE-I
• Interconnection of Regional Grids through HVDC Back-to-Back links - To take care of widely varied operational parametersUnder OperationNorth – West: 500MW Vindhyachal Back-to-Back West – South: 1000MW Chandrapur Back-to-Back East – South: 500MW Gazuwaka Back-to-Back Under Construction East – North: 500MW Sasaram Back-to-Back
• Link between ER and NR is the last link of phase-I to be completed by Oct., 2002.
• With Completion of Phase-I, Cumulative Inter regional Capacity would be 4850 MW
DEVELOPMENT OF NATIONAL GRID
NER
ER
NR
WR
SR
EXISTING
500MW
MW1000
MW500
GAZUWAKA
CHANDRAPUR
VINDHYACHAL
SASARAM
UNDERCONST.
EXISTING
400 kV
220 kV
BONGAIGAONBIRPARA
MALDA
KORBA BUDHIPADAR
KOLHAPUR
BELGAUM
U.SILERU
BALIMELA
DEHRISAHUPURI
MALANPUR
AURAIYA
PHASE-I(By 2002)
Plan for National Grid
PHASE-II (By 2007):
• High capacity “Transmission highways” envisaged along with major generation projects Highways already constructed
• Kishenpur - Moga 765 kV 2xS/c in J&K
• Kathalguri – Malda 400kV D/c in NER
• Hybrid HVAC and HVDC interconnection planned
• Implementation already commenced 2000 MW HVDC bipole between Talcher-Kolar bet. ER & SR
400kV AC link between Rourkela and Raipur bet. ER & WR
• High capacity 400 kV link from Tala to Delhi bet. ER & NR
2nd Gazuwaka HVDC back-to-back by 500MW bet ER & SR
• About 5000 ckt. km of 765 kV lines planned alongwith upcoming Mega projects in ER
• With the completion of Phase-II, the inter-regional capacity would be 23,000 MW
North-eastern
Salakati
Bongaigaon
Birpara
Malda
Dehri
Sasaram
Sahupuri
Allahabad
Eastern
Northern
Belgaum
Kolhapur
Budhipadar
Rourkela
Korba
Raipur
Auraiya
Malanpur
Western
Southern
Balimela
Upper Sileru
Chandrapur
Ramagundam
Jeypore
Gazuwaka
Singrauli
Vindhyachal
400kV
220kV
220kV
500MWWV
500MW220kV
1000MWWV
500MW
500MW
220kV
400kV
220kVWV
Existing Link
Talcher
Kolar
2000MW220kV
Legend
HVDC back-to-back link
HVDC bipole
INTER- REGIONAL LINKS
(Existing/New Approved Scheme)
Plan for National Grid
PHASE-III (By 2012) :
Strengthening of inter-regional link to have a ring of
765kV lines inter-connecting Northern, Western and
Eastern Regions
ER inter-connection with SR to be strengthened through
HVDC lines (asynchronous link)
Completion of Phase-III would lead to cumulative
capacity of inter-regional link to 30,000 MW
4850
23000
30000
0
5000
10000
15000
20000
25000
30000
35000
Plan
Cum
ulat
ive
Cap
acity
(MW
)
By 2002 By 2006-07 By 2011- 12
Growth of Cumulative capacity of Inter-regional linksGrowth of Cumulative capacity of Inter-regional links
• For efficient, secured and reliable operation of the grid and inter-regional power exchange, POWERGRID has planned for Unified Load Despatch schemes in all five Regional GridsNorthern Region : In operation
Southern Region : In operation
North-eastern Region: Under implementation - completion by June, 2003
Eastern Region: Under implementation - completion by Sept, 2003
Western Region: NIT to be issued – completion by January, 2005
• Estimated Cost of above projects : US $ 470 million (Rs. 2170 Cr).
• National Load Despatch Schemeinter-connecting all the five ULDCs has also been plannedFeasibility Report is under preparation
Expected completion schedule – by 2007
Estimated Cost : US $ 54 million (Rs. 250Cr)
Unified Load Despatch & Communication
Hierarchical setup of Regional ULDCHierarchical setup of Regional ULDC
REGIONAL LOAD DESPATCH
CENTRE
RTU RTU RTU
SUB LDC SUB LDC SUB LDC
SLDC SLDC SLDC
NRLDC WRLDC ERLDC SRLDC NERLDC
STATE LOAD DESPATCH
CENTRE
AREA LOADDESPATCH CENTRE
REMOTE TERMINALUNIT
(AT SUB-STATIONS &GENERATING STNS
NLDCNATIONAL LOAD DESPATCH
CENTRE
SLDCSLDC
SUB LDC SUB LDC
RTURTU
DEVELOPMENT OF SOUTH ASIAN GRID
South Asian Countries – Common Features
• Abundant reserves of Natural resources
• Low per capita electricity consumption
• Deficit of Power & Fast Growth in Demand
• Common frequency of operation
• Similar voltage class
South Asian Countries – Energy Resources
• India – Dominated by Coal
• Bangladesh – Dominated by natural gas
• Bhutan – High dependence on hydro
• Nepal – High dependence on hydro
• Pakistan – Largely petroleum and natural gas
• Sri Lanka – Dependence on petroleum
Exploitation of Resources - Options
• In order to capture benefits of resource sharing as experienced all over the world, Countries in South Asian Region should also move forward and explore feasibility of interconnections with each other.
• Large scale trading of coal and natural gas is limited due to constraints in its handling & transportation
• Hydel energy can be traded thru tr. network only
• Transmission of power is the only feasible solution for bulk exchange of energy
Why South Asian Grid ?
• Optimal Utilization of Natural Resources
• Opportunity of Energy Trading
• Economy of Scale
• Advantage of Peak diversity
• Minimization of Environmental Damages
Feasibility of Interconnection
• India is centrally placed sharing boundaries with
SAARC Countries.
• Vast Interconnected transmission network.
• Development of Strong National Grid on the
Anvil.
Indian Initiative towards South Asian Grid
• Current Status
Limited Energy trade based on bilateral agreements
Power exchanges under governmental control
• Ongoing Power Exchange
India and Nepal
Over 16 links at 132/33/11 kV
About 50 MW of power being exchanged
Net export to Nepal (about 10% of demand of Nepal met
through imports from India)
Supply of free power from Tanakpur (India) to Nepal –
70MU/annum
Indian Initiative towards South Asian Grid
• Ongoing Power Exchange - India and Bhutan Interconnection established with Chukha HEP (4x84 MW) in
Bhutan, built with Indian technical and financial assistance
Chukha-Birpara 220kV 3 ckts.
All surplus power from Chukha HEP (336MW) in Bhutan is exported to India. Presently, this constitutes 75% to 80% (1400 MU/year) of total power generated.
Earning to Bhutan - Rs. 140 crs. Annually
Part of this power re-imported through Bongaigaon-Geylegphug 132kV S/c line to Bhutan to meet radial loads close to Indian border.
India getting cheap hydro power
Kurichu HEP (4x15 MW) of Bhutan already connected to Indian Grid through Kurichu – Geylegphug – Salakati 132 kV line
South Asian Grid
Future Propects
South Asian Grid - India and NepalSouth Asian Grid - India and Nepal
• Nepal expected to be surplus in power by 2002
• 3 nos. 132kV lines under construction between India & Nepal Butwal(Nepal) – Anandnagar(India) Birgunj(Nepal) – Motihari(India) Dalkebar(Nepal) – Sitamarhi(India)
• Large potential projects being considered for development and export of power to India West Seti HEP 750 MW Arun HEP 685 MW Pancheshwar HEP 6,500 MW
• EHV transmission links planned for evacuation of power to India West Seti – Bareilly – Muradnagar 400 kV line Arun HEP – Muzaffarpur 400 kV line 400/765kV lines from Pancheshwar HEP to India
South Asian Grid - India and BhutanSouth Asian Grid - India and Bhutan
• Interconnection being established at 400kV level from Tala in Bhutan to Delhi in India for evacuation of power from Tala HEP(6x170MW)
• More hydro projects to come up in Bhutan Wangchu: 900MW Bunakha : 180MW Sankosh : 4060MW
• Power from these projects also to be imported by India
South Asian Gird - India and BangladeshSouth Asian Gird - India and Bangladesh
• East Zone of Bangladesh(generation dominated) shares border with the Eastern Region of IndiaBangladesh can supply power to Eastern India
• West Zone of Bangladesh(load dominated) shares border with the North-Eastern Region of India India can supply power to Western Bangladesh
• 2 nos. of 220kV links,one at each side, initially envisaged for limited exchange of about 150 MWKrishnanagar(Eastern India)-Ishurdi(Western Bangladesh)Shahjibazar(Eastern Bangladesh)-Kumarghat(N-E India)
South Asian Gird - India and BangladeshSouth Asian Gird - India and Bangladesh
• There are proposals to set up Gas projects by IPPs for selling power to India
• Scheme evolved for importing 1000 - 1500 MW power from Gas projects in Bangladesh
Establishment of a S/s at Krishna Nagar in West Bengal through LILO of Farakka-Jeerat 400 kV D/c line
Gen. station - Ishurdi (Bangladesh) 400 kV 2xD/c Ishurdi - Krishna Nagar (India) 400 kV 3 ckt. Krishna Nagar - Jamshedpur 400 kV D/c Jamshedpur - Rourkela 400 kV D/c
South Asian Grid – India and Pakistan South Asian Grid – India and Pakistan
• Pakistan has surplus power of about 1500-2000 MW
• Discussions were held for exchange of power between India and Pakistan
• To start with, 220kV interconnection was envisaged for transfer of 300MW from Pakistan to India Dinanath – Firozpur 220kV line
• In the long term, HVDC interconnections was envisaged for bulk power exchange (upto 2000MW)
South Asian Grid – India and MyanmarSouth Asian Grid – India and Myanmar
• Govt. of Myanmar had proposed to develop Tamanthi HEP (12x100MW) across the river Chindwin
• About 700 to 800 MW power from this project might be transferred to India
• Myanmar shares boundary with North-Eastern Region of India
• 400kV links proposed for evacuation of power into India
Tamanthi – Badarpur – Misa – Siliguri line
South Asian Grid – India and Sri Lanka South Asian Grid – India and Sri Lanka
• Proposal for interconnection of Sri Lanka with Southern
Regional Grid of India under discussion
• Usage of HVDC bipole or HVDC back-to-back in
conjunction with AC lines suggested
Issue to be addressed• Technical
Planning of Interconnections Firming-up the power availability ie.
o Quantum of power available for exchange
o Periodicity of availability/Allocation of firm power
Identification of Reliability criteria
Detailed system studies need to be conducted by participating countries, with following objectives Establishing the Feasibility of Interconnection Choice of Interconnection / Technology, considering –
o Right Of Way
o Cost
o Equipment Availability
o Reliability
Issue to be addressed
• Operation of Interconnection
Establishment of Operation Code by the participating countries
• Commercial arrangements Pricing of power
Payment Security Mechanism
Terms for Indemnification for disruption of Transmission service
Sharing of International Experience for Bulk Power Exchange
Issue to be addressed
• Legal arrangements
Firming up of procedures for dispute settlement and Arbitration
Applicability of Laws of Respective countries/ International Laws
• Institutional Arrangement
Identification/ Creation of Common Agency to regulate, Administer and Operationalize the Interconnection on long term basis
Establishment of Co-ordination Centres to Govern the Operational matters on Daily and Short Term basis
Issue to be addressed
• Financial arrangements
Following are possibilities of funding arrangement
Multilateral Funding
Private Investment
In either case following aspects are to be considered:Sale/ Purchase of Power on a sustained/ long term
basis
Security of Payment / Signing of Covenant
Immunity to Political Changes and changes in Law
Thank YouThank You
SAARC Grid as Envisaged