presentation of critical chain and theory of constraints

Upload: bln

Post on 29-May-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    1/30

    - A breakthrough solution in Multi-ProjectManagement

    Critical Chain Project Management

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    2/30

    Objective

    Common problems with todays Project Management environment.

    Critical Chain concepts

    The Multi Project Management the TOC concept

    Typical Benefits -

    Organisations that have benefited. Aim of TOC Project Management Solution : Complete projects on or before

    the scheduled due date.

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    3/30

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    4/30

    What is Project Management the TOC way?

    Better managing the inherent variability in Project Management.

    Combining both the project layout and accessibility of resources assigned to projecttasks to determine project lead time.

    Project scheduling that treats resource and task constraints equally - Critical Chain.

    With the focus being on project execution.

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    5/30

    Typical Project Problems / issues

    Existing project work is not complete before new projects require a shifting in priorities.

    The organization is too slow responding to important opportunities.

    Managers feel constant pressure to increase staff to handle peak project loads.

    Promised lead times are longer than desired.

    There are difficulties completing projects on time.

    There is too much rework activity.

    There are difficulties completing projects within budget.

    Project scope/content is too often compromised to meet dates and/or budget.

    Some projects are abandoned or completed without the organization gaining the promised benefit.

    Project Managers and Resource Managers have frequent conflicts about priorities and resourcecommitments.

    Problems in one project cascade into problems in other projects.

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    6/30

    Project Management has high uncertainty

    When should I planWhen should I plan

    on starting:on starting:day 15 or day 27?day 15 or day 27?

    10+/-3days

    10+/-3days

    Sources of uncertainty

    Creating something new, cannot estimate with

    precision

    Environment in constant flux: technologykeeps changing, consumer needs keepshifting, etc.

    Non-uniform skills: every knowledge worker isdifferent

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    7/30

    Project Management Environments have become more distributed

    Virtual Teams

    Some team members are sharedacross multiple programs

    Distributed decision-making

    Functionalpools

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    8/30

    The effects of conflicting resource priorities betweenprojects

    Three Tasks arrive at the same time for the same

    resource. All Projects are essential for the success ofthe program what can the resource do?

    Task A

    Project 1One Week

    Task BProject 2

    One Week

    Task CProject 3

    One Week

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    9/30

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    10/30

    Collaboration has become impossible to achieve

    Engineers

    Team leaders Project managers Resource managers Program managers Business unit managers

    Multiple decision points

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    11/30

    Current feedback after surveying more than dozen cases

    30% of projects cancelled before finished

    75% of completed projects are late

    Average cost overruns of 189% Average time overruns of 222%

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    12/30

    How these issues are addressed

    Multi - Project Management the TOC Way has five

    main components:

    1. Synchronization mechanism.

    2. Planning processes

    3. Scheduling processes

    .4. Resource Behavior

    5. Project Control & Visibility

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    13/30

    KEY CONCEPTS

    Buffers

    Critical Chain

    Critical Chain:

    Longest chain

    incorporates resourcedependencies/constraints

    Buffers: Use available slack in

    feeding chain to isolatecritical chain from delays

    Remove buffer from critical

    chain components, andinsert it in the end

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    14/30

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    15/30

    Project Planning :

    Have strategic protection times - Buffers

    5 85

    8 8

    10 Project Buffer 28

    FeedingBuffer 16

    10

    20

    16 16

    1610

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    16/30

    Change in behaviours allows aggregated buffers to be smaller than the

    individual safety.

    ie There is less Multi-tasking!!!

    5 85

    8 8

    10Project Buffer

    14

    FB 8

    5 85

    8 8

    10 Project Buffer 28FeedingBuffer 16

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    17/30

    Does it ever happen that a resource is needed in two places at

    the same time?

    A5 C 8B5

    D8 C 8

    E10Project Buffer

    14

    FB 8

    What happens if the lower path experiences uncertainty beyond its durationtimes and the top doesnt? Wont we have a need for the C Resource at the

    same time?

    Solution: The Critical Chain

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    18/30

    Identifying the Critical Chain

    B5 C8

    D8 C8

    A5

    E10

    Resource dependencies are identified once resource contention is removed.

    Finally, the longest path of dependent events - the Critical Chain - is identified.( We have already removed the safety from the task times, which was half oforiginal task estimate).

    A5 B5

    E10D8 C8 C8

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    19/30

    A feasible and immune schedule

    A5 B5

    E10D8 C8 C8

    A5 B5

    E10D8 C8 C8 Project Buffer 17

    FB5

    Buffers - Strategic protection of the Due date

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    20/30

    Buffers are used to provide focus and early warning to

    protect the critical chain and due date

    OKZone 3

    WATCH& PLAN

    Zone 2

    ACTZone 1

    RemainingProject Buffer:

    BUFFER

    MANAGEMENT

    PB

    100% 67% 67% 33% 33% 0%

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    21/30

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    22/30

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    23/30

    Typical Benefits - Globally

    Completing projects ahead of schedule

    Increasing capacity - i.e. more projects (thru-put ) with the same number of

    resources (typically 20 to 50%);

    Competitive advantage - can guarantee customers when delivery will be

    Increased revenue and profitability

    Management has clearer view of project status and resource availability

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    24/30

    Typical Benefits - Continued

    Unified approach to managing, scheduling and synchronizing projects

    Visibility and understanding of project requirements

    Resources (internal and contractors) have one system for priority

    More accurate forward planning of resources and projects

    Less stress burnout at the Program Director / Project Manger level

    Resource planning becomes logical and not emotional

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    25/30

    Project Management the TOC Way - summary

    Is both LOGISTICAL and CULTURAL.

    Multi-Project Management the TOC Way has five main components:

    1. A synchronization mechanism that allows projects to be started later, but finished sooner

    and that clarifies resource assignment priorities.

    2. Planning processes that account for the needed dependencies and completion criteria.

    3. Scheduling processes that concentrate safety where it will provide the most protection.

    4. Changes in behavior that support a world class relay team culture.

    5. Mechanisms that create Project Control & Visibility to assist in global decision

    making.

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    26/30

    Results - June 1999 - Seabridge - Israel

    Telecommunications start-up - with Multi-Service Access Platform (50 people - 35 inR&D)

    Purchased by Siemens & NewBridge in November 1997

    To deliver Release 2.0 by March 1998 - Bonus tied

    Performance - 5 months late

    CEO reads Critical Chain - decides to implement Sept 1998

    1st project on schedule; 2nd project 2 months early; 3rd on track to meetUnrealistic time constraint;

    Major review by Siemens on company turnaround

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    27/30

    Results -

    Harris Semiconductor - new $250m plant

    New technology product - first 8-inch discrete power wafer fabNew raw material, new automated technologyNew facility, doubling capacityProject scope - construction, installation, ramp-up,Focus on actual delivery of production via the Critical Chain

    Industry norm Groundbreaking to first silicon - 28-36 months

    Time to ramp production - 18 months

    Harris results with Critical Chain

    Groundbreaking to first silicon - 13 months

    Time to ramp production - 21 days

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    28/30

    Results -

    Balfour Beatty Civil Engineering (UK)

    1st Project - By pass road (A13) 80 M GBP - 2.5 yr

    Half way stage - well behind schedule

    Handover 2 weeks early -

    99% complete vs Industry norm of 80%

    2nd Project - 8km highway (A50)- 35M GBP- 2.4 yr

    Beat tender program by 9.5 weeks

    45 weeks earlier than contract completion date.

    Increased Project Profit Margin.

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    29/30

    The change is both logistical and cultural!

    Staggering the introduction of work to minimize the negative effects of badmultitasking.

    Building and scrutinizing individual project networks in a way that significantlyreduces the opportunity for missing critical dependencies.

    Constructing project schedules in a way that recognizes both resource and pathdependencies.

    Placing safety strategically to protect the project, not the individual tasks.

    Eliminating behaviors that waste safety.bad multi-tasking unreported early finishes

    unclear task completion criteria delayed task starts (StudentSyndrome)

    Managing resource assignments according to which project has the greatest need.

    (Buffer Management) Managing project progress according to buffer depletion - taking corrective actions

    when and only when required.

  • 8/9/2019 Presentation of Critical Chain and Theory of Constraints

    30/30

    Thanks You