presentation of critical chain and theory of constraints
TRANSCRIPT
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
1/30
- A breakthrough solution in Multi-ProjectManagement
Critical Chain Project Management
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
2/30
Objective
Common problems with todays Project Management environment.
Critical Chain concepts
The Multi Project Management the TOC concept
Typical Benefits -
Organisations that have benefited. Aim of TOC Project Management Solution : Complete projects on or before
the scheduled due date.
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
3/30
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
4/30
What is Project Management the TOC way?
Better managing the inherent variability in Project Management.
Combining both the project layout and accessibility of resources assigned to projecttasks to determine project lead time.
Project scheduling that treats resource and task constraints equally - Critical Chain.
With the focus being on project execution.
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
5/30
Typical Project Problems / issues
Existing project work is not complete before new projects require a shifting in priorities.
The organization is too slow responding to important opportunities.
Managers feel constant pressure to increase staff to handle peak project loads.
Promised lead times are longer than desired.
There are difficulties completing projects on time.
There is too much rework activity.
There are difficulties completing projects within budget.
Project scope/content is too often compromised to meet dates and/or budget.
Some projects are abandoned or completed without the organization gaining the promised benefit.
Project Managers and Resource Managers have frequent conflicts about priorities and resourcecommitments.
Problems in one project cascade into problems in other projects.
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
6/30
Project Management has high uncertainty
When should I planWhen should I plan
on starting:on starting:day 15 or day 27?day 15 or day 27?
10+/-3days
10+/-3days
Sources of uncertainty
Creating something new, cannot estimate with
precision
Environment in constant flux: technologykeeps changing, consumer needs keepshifting, etc.
Non-uniform skills: every knowledge worker isdifferent
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
7/30
Project Management Environments have become more distributed
Virtual Teams
Some team members are sharedacross multiple programs
Distributed decision-making
Functionalpools
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
8/30
The effects of conflicting resource priorities betweenprojects
Three Tasks arrive at the same time for the same
resource. All Projects are essential for the success ofthe program what can the resource do?
Task A
Project 1One Week
Task BProject 2
One Week
Task CProject 3
One Week
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
9/30
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
10/30
Collaboration has become impossible to achieve
Engineers
Team leaders Project managers Resource managers Program managers Business unit managers
Multiple decision points
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
11/30
Current feedback after surveying more than dozen cases
30% of projects cancelled before finished
75% of completed projects are late
Average cost overruns of 189% Average time overruns of 222%
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
12/30
How these issues are addressed
Multi - Project Management the TOC Way has five
main components:
1. Synchronization mechanism.
2. Planning processes
3. Scheduling processes
.4. Resource Behavior
5. Project Control & Visibility
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
13/30
KEY CONCEPTS
Buffers
Critical Chain
Critical Chain:
Longest chain
incorporates resourcedependencies/constraints
Buffers: Use available slack in
feeding chain to isolatecritical chain from delays
Remove buffer from critical
chain components, andinsert it in the end
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
14/30
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
15/30
Project Planning :
Have strategic protection times - Buffers
5 85
8 8
10 Project Buffer 28
FeedingBuffer 16
10
20
16 16
1610
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
16/30
Change in behaviours allows aggregated buffers to be smaller than the
individual safety.
ie There is less Multi-tasking!!!
5 85
8 8
10Project Buffer
14
FB 8
5 85
8 8
10 Project Buffer 28FeedingBuffer 16
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
17/30
Does it ever happen that a resource is needed in two places at
the same time?
A5 C 8B5
D8 C 8
E10Project Buffer
14
FB 8
What happens if the lower path experiences uncertainty beyond its durationtimes and the top doesnt? Wont we have a need for the C Resource at the
same time?
Solution: The Critical Chain
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
18/30
Identifying the Critical Chain
B5 C8
D8 C8
A5
E10
Resource dependencies are identified once resource contention is removed.
Finally, the longest path of dependent events - the Critical Chain - is identified.( We have already removed the safety from the task times, which was half oforiginal task estimate).
A5 B5
E10D8 C8 C8
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
19/30
A feasible and immune schedule
A5 B5
E10D8 C8 C8
A5 B5
E10D8 C8 C8 Project Buffer 17
FB5
Buffers - Strategic protection of the Due date
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
20/30
Buffers are used to provide focus and early warning to
protect the critical chain and due date
OKZone 3
WATCH& PLAN
Zone 2
ACTZone 1
RemainingProject Buffer:
BUFFER
MANAGEMENT
PB
100% 67% 67% 33% 33% 0%
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
21/30
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
22/30
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
23/30
Typical Benefits - Globally
Completing projects ahead of schedule
Increasing capacity - i.e. more projects (thru-put ) with the same number of
resources (typically 20 to 50%);
Competitive advantage - can guarantee customers when delivery will be
Increased revenue and profitability
Management has clearer view of project status and resource availability
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
24/30
Typical Benefits - Continued
Unified approach to managing, scheduling and synchronizing projects
Visibility and understanding of project requirements
Resources (internal and contractors) have one system for priority
More accurate forward planning of resources and projects
Less stress burnout at the Program Director / Project Manger level
Resource planning becomes logical and not emotional
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
25/30
Project Management the TOC Way - summary
Is both LOGISTICAL and CULTURAL.
Multi-Project Management the TOC Way has five main components:
1. A synchronization mechanism that allows projects to be started later, but finished sooner
and that clarifies resource assignment priorities.
2. Planning processes that account for the needed dependencies and completion criteria.
3. Scheduling processes that concentrate safety where it will provide the most protection.
4. Changes in behavior that support a world class relay team culture.
5. Mechanisms that create Project Control & Visibility to assist in global decision
making.
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
26/30
Results - June 1999 - Seabridge - Israel
Telecommunications start-up - with Multi-Service Access Platform (50 people - 35 inR&D)
Purchased by Siemens & NewBridge in November 1997
To deliver Release 2.0 by March 1998 - Bonus tied
Performance - 5 months late
CEO reads Critical Chain - decides to implement Sept 1998
1st project on schedule; 2nd project 2 months early; 3rd on track to meetUnrealistic time constraint;
Major review by Siemens on company turnaround
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
27/30
Results -
Harris Semiconductor - new $250m plant
New technology product - first 8-inch discrete power wafer fabNew raw material, new automated technologyNew facility, doubling capacityProject scope - construction, installation, ramp-up,Focus on actual delivery of production via the Critical Chain
Industry norm Groundbreaking to first silicon - 28-36 months
Time to ramp production - 18 months
Harris results with Critical Chain
Groundbreaking to first silicon - 13 months
Time to ramp production - 21 days
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
28/30
Results -
Balfour Beatty Civil Engineering (UK)
1st Project - By pass road (A13) 80 M GBP - 2.5 yr
Half way stage - well behind schedule
Handover 2 weeks early -
99% complete vs Industry norm of 80%
2nd Project - 8km highway (A50)- 35M GBP- 2.4 yr
Beat tender program by 9.5 weeks
45 weeks earlier than contract completion date.
Increased Project Profit Margin.
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
29/30
The change is both logistical and cultural!
Staggering the introduction of work to minimize the negative effects of badmultitasking.
Building and scrutinizing individual project networks in a way that significantlyreduces the opportunity for missing critical dependencies.
Constructing project schedules in a way that recognizes both resource and pathdependencies.
Placing safety strategically to protect the project, not the individual tasks.
Eliminating behaviors that waste safety.bad multi-tasking unreported early finishes
unclear task completion criteria delayed task starts (StudentSyndrome)
Managing resource assignments according to which project has the greatest need.
(Buffer Management) Managing project progress according to buffer depletion - taking corrective actions
when and only when required.
-
8/9/2019 Presentation of Critical Chain and Theory of Constraints
30/30
Thanks You