critical chain project scheduling. copyright © 2010 pearson education, inc. publishing as prentice...

14
Critical Chain Project Scheduling

Upload: clifford-nicholson

Post on 17-Dec-2015

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Critical Chain Project Scheduling. Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall11-2 Theory of Constraints (ToC) A constraint limits

Critical Chain Project Scheduling

Page 2: Critical Chain Project Scheduling. Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall11-2 Theory of Constraints (ToC) A constraint limits

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 11-2

Theory of Constraints (ToC)

A constraint limits any system’s output.

TOC Methodology1. Identify the constraint2. Exploit the constraint3. Subordinate the system4. Elevate the constraint5. Repeat the process

Page 3: Critical Chain Project Scheduling. Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall11-2 Theory of Constraints (ToC) A constraint limits

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 11-3

Variation

Common Cause

Inherent in the systemSpecial Cause

Due to a special circumstance

Managers should• Understand the difference between the two types

• Not adjust the process if variation is common cause

• Not include special cause variation in risk simulation

• But: not aggregate discrete project risks

Page 4: Critical Chain Project Scheduling. Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall11-2 Theory of Constraints (ToC) A constraint limits

CCPM and the Causes of Project Delay

How safety is added to project activities

1. Individual activities overestimated

2. Project manager safety margin

3. Anticipating expected cuts from management

time

25%

50%

80%90%

Galton (or lognormal) Distribution

Page 5: Critical Chain Project Scheduling. Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall11-2 Theory of Constraints (ToC) A constraint limits

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 11-5

Wasting Extra Safety Margin

1. The Student Syndromea. More immediate deadlinesb. Padded estimatesc. Personnel in high demand

2. Failure to pass along positive variationa. Working on other tasksb. „Early delivery penalty” on future estimatesc. Perfectionism

3. Multitasking4. Path Merging: losing positive slacks

Page 6: Critical Chain Project Scheduling. Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall11-2 Theory of Constraints (ToC) A constraint limits

Parkinson's law

• Work expands to fill the time available.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 11-6

Page 7: Critical Chain Project Scheduling. Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall11-2 Theory of Constraints (ToC) A constraint limits

Multitasking and task duration

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 11-7

Page 8: Critical Chain Project Scheduling. Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall11-2 Theory of Constraints (ToC) A constraint limits

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 11-8

Critical Chain Solutions

Central Limit Theorem

Activity durations estimated at 50% level

Buffer reapplied at project level– Goldratt rule of thumb (50%)– Newbold formula

Feeder buffers for non-critical paths

n

Page 9: Critical Chain Project Scheduling. Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall11-2 Theory of Constraints (ToC) A constraint limits

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 11-9

CCPM Changes

Due dates & milestones eliminated

Realistic estimates – 50% level not 90%

“No blame” culture

Subcontractor deliveries & work scheduled ES

Non critical activities scheduled LS

Factor the effects of resource contention

Critical chain usually NOT the critical path

Solve resource conflicts with minimal disruption

Page 10: Critical Chain Project Scheduling. Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall11-2 Theory of Constraints (ToC) A constraint limits

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 11-10

Critical Chain Solutions

Bob

Feeder Buffer

Feeder Buffer

Feeder Buffer

ProjectBufferBob

Bob

Buffers protect constraints and prevent delays

Page 11: Critical Chain Project Scheduling. Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall11-2 Theory of Constraints (ToC) A constraint limits

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 11-11

Critical Chain Project Portfolios

Drum – system-wide constraint that sets the beat for the firm’s throughput– company policy

–one person

–a department/work unit

–a resource

• Capacity constraint buffer – safety margin between projects

• Drum buffer – extra safety before the constraint

Page 12: Critical Chain Project Scheduling. Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall11-2 Theory of Constraints (ToC) A constraint limits

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 11-12

Applying CCPM to Project Portfolios

1. Identify the drum

2. Exploit the druma. Prepare a schedule for each project

b. Determine priority for the drum

c. Create the drum schedule

3. Subordinate the project schedules (next slide)

4. Elevate the capacity of the drum

5. Go back to step 2

Page 13: Critical Chain Project Scheduling. Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall11-2 Theory of Constraints (ToC) A constraint limits

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 11-13

Subordinating Project Schedules

• Schedule projects based on drum

• Designate critical chain

• Insert capacity constraint buffers

• Resolve any conflicts

• Insert drum buffers so the constraint is not starved

Page 14: Critical Chain Project Scheduling. Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall11-2 Theory of Constraints (ToC) A constraint limits

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 11-14

CCPM Critiques

No milestones used

Not significantly different from PERT

Unproven at the portfolio level

Anecdotal support only

Incomplete solution

Overestimation of activity duration padding

Cultural changes unattainable