presentation 4 - eia part 1.pdf

Upload: mohamedraahim

Post on 06-Jul-2018

228 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    1/36

    Environmental ImpactAssessment

    Dr. P. I. A. Gomes

    1

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    2/36

    Environmental Impacts

    What is pollution/what is an impact?

    Current

    (planning

    stage)

    Commencement

    of the project

       E   n   v   i   r   o   n   m

       e   n   t   a    l   p   a   r   a   m   e   t   e   r

    Time (years)

    No infrastructure

    development (no

    project)

    Project A

    Project B

    50 years after the

    commencement

    of the project

    2

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    3/36

    Pollution is a change in an environmental parameter (or an indicator)

    over time relative to the no project scenario (i.e. relative to the

    natural trend of the parameter).

    Environment

    Natural Social

    Pollution and Environmental impacts are not synonyms, but are

    correlated.

    Physical   Biological

    3

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    4/36

    Generally when the environment is been mentioned it obviously includes

    the social environment. However nowadays there is a trend, of separating

    these two: Instead of Environmental Impact Assessment, Environmental and

    Social Impact Assessment. Where the former includes the physical andbiological environments only.

    In many countries it is a statutory requirement to evaluate or assess the

    Environmental impact of large scale projects . As Infrastructure Projects are

    massive and large in size, technically almost all infrastructure projects needs

    to conduct an assessment of probable impacts on the environment in

    advance.

    Assessment of possible impacts (positive or negative), that a proposed

    project may have on the environment is called an Environmental Impact

    Assessment (EIA).EIAR: Environmental Impact Assessment Report.

    Due to statutory nature of the Environmental Impact Assessment Report, it

    can be considered as a decision making tool.

    4

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    5/36

    Development Projects/Anthropogenic

    activities

    Technical feasibility Economic feasibility Environmental feasibility

    To commence a project these three need to be satisfied

    The developer is very much interested of the technical and economic

    feasibilities, as these factors govern the return (profit) of the project. Its

    very rare to see a private developer (may be different if the developer is

    government) consider the impact on the environment. However

    nowadays any developer is compelled to check the impact on theenvironment as it is a statutory obligation.

    Importantly unlike in Technical and Economic feasibility studies, in the

    Environmental feasibility the public participation take place.

    5

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    6/36

    Environmental Impact Assessment (EIA) should be carried

    out for the stages; construction and operational and

    maintenance separately

    Impacts during the construction stage are relatively short

    term and in case of operational and maintenance are

    rather long term

    6

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    7/36

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    8/36

    8

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    9/36

    Environmental Impact Assessment- A case

    study-Havelock City Mixed Development

    Project, Sri Lanka

    9

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    10/36

    Site for the Havelock city

    project

    10

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    11/36

    11

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    12/36

    N12

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    13/36N 13

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    14/36

    Technical feasibility

    The 2004 master plan of the UDA (although not yet officially sanctioned) identifiedthe need for vertical development considering the space limitations of the Colombo

    City. Considering the large-scale vertical development that is proposed, the most

    important issue in technical evaluation is the capacity of the urban environmental

    infrastructure. This study shows that the prevailing infrastructure in the area is

    already over-stretched and in bad condition to meet even the present needs. Thus

    the project will invest significantly for the improvement of environmental

    infrastructure and services in the project area. These investments will benefit notonly the proposed project but also the entire project area and beyond.

    Economic feasibility

    Total investment will be in the range of 250 million US Dollars (USD). This will be a

    significant boost to the national economy. Also significant number of employment

    opportunities will be crested by this project both during design/construction and

    operation stages. In fact the long-term employment opportunities available as a

    result of this project will exceed 1000. This is considering the large work force

    required to operate and maintain the facilities created under this project consisting

    of over 1000 housing units, 300 rooms hotel, shopping complex etc. Other than the

    direct employment there will significant number of indirect employment

    opportunities by way of provision of ancillary services.

    Technical and Economical aspects

    14

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    15/36

    Skeleton road

    Proposed

    bridge

    Mayura Lane

    Old flatsReligious

    centers

    15

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    16/36

    Nature of the Project

    Havelock City is urban development project based on the

    concept of   “City  within a   City”. Accordingly it consists of allfacilities, such as shopping, marketing, recreation and

    pleasure, parking and other services required for modern

    living. Hotel mainly catering to the needs of businessmen is an

    added feature in this development.

    Project components and salient features

    Havelock City consists of two main components, namely a

    residential complex and commercial complex. In addition it will

    also include several other facilities to support the needs of the

    residents and visitors.

    16

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    17/36

    Residential (Apartment) Complex

     Number of Towers 8 (of each with 22-29 storey)

     Number of units 1080Car park 1360 slots (floor area: 42,960 m2)

    Gross floor area* 170,888 m2

    Commercial Complex

    Retail Mall 41,460 m2

    5-star Hotel 35,160 m2

    Cinema (6 Nos) 4,250 m2

    Car Park 810 slots (floor area: 27,537 m2)

    Gross floor area* 85,259 m2

    Other FacilitiesClub house including sports complex

    Internal road network including a bridge across the canal connecting to Skeleton

    Road (The access to the Skeleton Road is limited to permanent residents of the

    apartment complex only).

    Project components and salient features

    17

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    18/36

    Constructional Activities

    The construction methods will be typical to high rise building construction. In comparison to

     building works the other construction activities will be minor in nature. These will include

    internal road network, the bridge over the canal connecting the site to Skeleton Road, water and

    sewer pipe laying and finishing works. Landscaping is also a key component of the development plan.

    Earthwork will range from shallow to deep excavations for construction of apartment car parks

    and commercial complex basement. The site was previously used as an industrial site. Therefore

    it was fully developed and there is no need for clearing of vegetation.

    Project will also invest in upgrading/improvement of the infrastructural facilities in the site area.

    These include water supply, sewer network, electricity and roads. The construction work related

    to these activities will be carried out by the respective government agencies, such as the

     NWSDB. The project proponent) will meet the cost of upgrading.

    The project plans to construct a bridge over the canal to link with Skeleton Road. Also a newaccess road via Darmarama Road to Duplication Road is planned. However, the main access to

    the site will be through the Havelock Road. The project proponent envisages some improvement

    to the Havelock Road in order to facilitate the traffic and avoid congestion. However plan for this

    improvement has not yet being developed. The project proponent intends to consult the RDA and

    CMC in the future for this purpose.18

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    19/36

    The Construction Management System

    Initial capital Investment

    Land = Rs. 750 millionEquity = Rs. 1875 million

    Total = Rs. 2625 million

    Life time of equipment

     Not relevant

    Operating cost

     Not relevant. The construction costs are given below.

    Apartment = Rs. 17,198 million

    Commercial = Rs. 8,990 million

    Total = Rs. 26,188 million

    Method of financing

    Equity and Land/presales = Rs. 14729 million

    Equity contribution for commercial = Rs. 7260 million

    Loan facilities = Rs. 4200 million

    Total = Rs. 26189 million

    19

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    20/36

    Justification of the project

    An idling land of nearly 3000 perches will be put into productive use.

    Replacement houses for the occupants of five dilapidated apartment blocks in

    the adjoining land. (There is a significant opportunity cost1 in leaving these

     prime lands as it is).

    Furthermore proposed project will not compromise the environmental and

    social assets in the project area. Therefore the   “no action” alternative is not an

    acceptable option.

    1The opportunity cost includes all the forgone benefits of not using this

    economic space in the commercial capital, Colombo. Forgone benefits

    includes mainly:•Satisfying the housing demand by 1080 dwelling units

    • Provision of material and spatial support for investors

    •The probable impetus to the local economy

    •The foreign investment of US $ 250 million

    20

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    21/36

    Environmental Impacts of Havelock City Project

    Construction

    stage

    Operationalstage

    Flora and fauna

    Traffic , transport and parking

    Water and energy

    Waste generation and disposal

    Strom water managementRelocation

    Work force

    21

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    22/36

    Description of the Existing Environment

    Physical Biological Social

    •Hydrology and

    drainage/surface waterbodies and water quality

    • Land use

    • Air quality

    • Noise

    •Flora and Fauna

    •Locations of centers of

    populations and settlements•Population characteristics

    • Available infrastructure

    •Housing and sanitation

    •Economic activities

    •Land value

    •Religious and cultural centers

    22

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    23/36

    Physical Environment

    The project area falls into western lowlands. The average annual rainfall is

    around 2500mm. Most of the rainfall is received from Southwest Monsoon

    (May to September). The average annual temperature is about 270C.

    The only surface water body is the Wellawatte canal, which was built during

    the Dutch period. Canal connects to the Diyawanda Oya and drains to the

    sea at Wellawatta, and the water hardly has any use due excessive

    pollution.

    Storm water drains to canal

     Available ground water not good for drinking

    H o

    r  ol   o g y  e t   c 

    The project area is highly built up area consisting of residential, public,

    business and commercial buildings, road network and several

    playgrounds. The project site is in mixed commercial land-use zone.

    L  an d  u s  e

    23

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    24/36

    UDA Land-use (a) Zones for Colombo City (b) Building densities

    (a) (b)

    24

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    25/36

     According to these data the prevailing ambient noise levels

    already exceed the standards

    N oi   s 

     e

    25

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    26/36

    Biological Environment

    Few species of economically important trees were observed in project

    area. No endemic or threatened floral species were observed. All

    most all faunal species were commonly found in home gardens

    F l   or  a

     an d 

    f   a un a

    Water hyacinth26

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    27/36

    Social/socio-economic Environment

    The social investigation covered the area within half a kilometer from the

    project site boundary. Based on the reconnaissance survey carried out by the

    sociologist this was determined as the key impact area. Regional and nationalimpacts are positive in nature and thus not considered in detail.

    27

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    28/36

    Anticipated Environmental Impacts (selected)

    Construction stage

    The construction works that could obstruct the natural drainage pattern ofthe area are earthwork, which include excavation for basements, filling and

    excavations of trenches for pipe laying

    Dust levels in the ambient air can be raised by almost all construction

    activities.

    Noise due to construction machinery

    However, considering the busy traffic conditions it is possible that large

    trucks blocks could block the Havelock Road under following conditions

    causing significant congestion

    28

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    29/36

    Operational stage

    Impact of additional traffic and related

    29

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    30/36

    Proposed Mitigation methods

    Construction stage

    Drainage pattern: The project site was once a developed land thus there

    are no natural drainage. All man made drainage paths are directed towards the

    Wellawatta Canal. The site borders the Wellawatta canal thus existing drainage

    paths are very short as well. The construction plans include drainage

    management so that runoff will be directed to the canal. Where the construction

    work affect existing drains or storm water carrying pipes the contractor will

    reroute the storm water through temporary drains. Construction activities willnot upset the natural drainage pattern of the project site.

    Dust contro l : paved the internal roads and start spraying water to keep the

    exposed soil moist as measures to minimize dust problem

    Noise con trol : Quieter equipment, Barrier protection, Work activityscheduling and planning

    Traff ic issues: Only use Havelock Road access by construction vehicles,

    such as trucks, All construction vehicles shall enter the site coming from

    Kirulapona direction and leave in Tibirigasyaya direction

    30

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    31/36

    Operational stage

    Traff ic related is sues: Consultants recommend the implementation of four

    access points (north, south, west and east). This is vital to minimize the trafficload on Havelock Road.

    It is also recommended that walk through access to the apartments through the

    Skeleton Road access be available only for the residents. This is in order to

    prevent visitors to the apartments parking their vehicles along Skeleton Road.

    It is also recommend that the developer plan the Havelock Road access in

    consultation with the RDA and CMC taking into account the proposed widening

    of the Havelock Road

    Consultants recommend that MCL shall further discuss with the Skeleton Road

    Residents Association and obtain their confidence with regard to accessconnection to the said road.

    31

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    32/36

    Anticipated Environmental Impacts and Mitigation methods for the Social

    environment

    Positive Impacts

    The project area and the vicinity will have an attractive look and it will add

    to enhance the significance of land-use in the area.

    The project will induce further improvements in the area including

    improvements to environmental services and canal will be cleaner than what

    it is today.

    The improved systems for managing solid waste and wastewater may

    establish in the area as a whole.

    The access roads in the project impact area will be improved (at least few

    sub-roads those may be connected to proposed project site)

    The properties, especially land values will go up significantly in the project

    impact area.

    There will be economic gains to the area and shop keepers expect

    significant boom to trading and sales.32

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    33/36

    Negative impacts

    The negative social impacts of the project are rather minimal. The people

    have perception that the project will overload the existing urban services suchas water supply, wastewater disposal, drainage, solid waste disposal and

    electricity. This is mainly because their lack of knowledge about the

    improvements proposed for the infrastructure facilities under this project. Due

    to planned improvement overall improvement to urban services is expected

    for the entire area. It is important that developer carry out a public awareness

    building in the project impact area.

    33

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    34/36

    Terrestrial ecology of the proposed project area is already permanently

    disturbed. Wellawatta Canal is the main aquatic habitats present in the

     project area, which is highly polluted and highly disturbed. The land

    used for construction of Hotel and Housing Complex is an abandoned

    factory. There is no presence of endangered or threatened animalspecies or significantly important plants in the proposed project site.

    Therefore it can be concluded that the impact of the project on the fauna

    and flora as none. Furthermore, most of the faunal species recorded are

    highly mobile species with the ability to survive under disturbed

    conditions and thus it is unlikely that the proposed project will affecttheir populations in an adverse manner .

    Anticipated Environmental Impacts and Mitigation methods for the

    Biological environment

    34

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    35/36

    EIA reports not only assess environmental impacts and

    propose mitigation methods, also it gives an environmental

    monitoring program as well. It includes;

    System of Checking the anticipated impacts and how the

    developer addressing them in the context of mitigatory

    methods.Institutional arrangement

    Reporting procedure

    Expertise required etc

    35

  • 8/17/2019 Presentation 4 - EIA part 1.pdf

    36/36

    References:

    EIA report for the Havelock city mixed development project,

    prepared by EML consultants in September 2006.

    Team members of the EIA

    •Mr. A. Jayathilake

    •E. Sivasudhan

    •Dr V.K Siriwardhena (team leader)

    •Mr K Jinapala

    •Dr P.M.C Bandara

    •Dr K. Weerasekara

    •Eng. P.I.A. Gomes

    •Ms. Shanthi Dharmawardhana.

    36